Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
I. INTRODUCTION
Managing and running organizations is an evolutionary
process over the ages. Such processes have been under going
many structural changes. Organizations have shifted from
functional managed structures to project based organizational
structures. Consequently, project management in organizations
is becoming increasingly important. Indeed, it is critical for the
success of the company. Most of the above mentioned process
changes have occurred in the last three decades. Irrespective of
the type of industry or the domain, the need for managerial and
structural change is being observed.[1]
When it comes to a project, the entire project is divided into
many interdependent tasks. In this set of tasks, the sequence or
the order of the tasks is quite important.If the sequence is
wrong, the end result of the project might not be what the
management expected.Some tasks in the projects can safely be
performed parallel to other tasks. In a project activity diagram,
the sequence of the tasks is simply illustrated.[2]
PERT Steps[9]:
1. Identify activities and milestones;
2. Setting the sequence of activities;
3. Building the network diagram;
4. It is estimated the time required for the activities;
5. Determine the critical path;
6. During the project the PERT technique is
updating.
Implementation[6]
The first step to scheduling the project is to determine the
tasks that the project requires and the order in which they must
be completed. The order may be easy to record for some tasks
while difficult for others. Additionally, the time estimates
usually reflect the normal, non-rushed time. Many times, the
time required to execute the task can be reduced for an
additional cost or a reduction in the quality.
Some tasks can be done concurrently , while others cannot
be done until their predecessor task is complete. Additionally,
each task has three time estimates: the optimistic time estimateO (it appears in 1 of 20 ), the most likely or normal time
estimate M(uses a distribution), and the pessimistic time
estimate P (it appears also in 1 of 20). The expected time (TE)
is computed using the formula:
T E=
O+ 4 M + P
6
Advantages
Disadvantages
PATH METHOD
LS=LFD
Early Finish (EF) - In the critical path method, the earliest
possible point in time on which the uncompleted portions of a
schedule activity (or the project) can finish, based on the
schedule network logic, the data date, and any schedule
constraints.
EF =ES+ D
D-duration
Late Finish (LF) - In the critical path method, the latest
possible point in time that a schedule activity may be
completed based upon the schedule network logic, the project
completion date, and any constraints assigned to the schedule
activities without violating a schedule constraint or delaying
the project completion date.
Example:
Figure 1
TF=LS ES
TF=LFEF
Another important float in project scheduling is free float.
The free float is the amount of time an activity can be delayed
without delaying the early start date of its subsequent tasks.
Free Float = ES (successor task) - EF (predecessor task)
REFERENCES
Disadvantages
VI. CONCLUSIONS
Every successful project is characterized by sound project
analysis using some form of network diagram that breaks up
even very massive projects into small and manageable discrete
tasks that can be performed.
[1] http://www.iiuedu.eu/press/journals/sds/sds1_july_2008/05_SE
CC_01.pdf, Projects Analysis through CPM (Critical Path
Method), Peter Stelth (MSc)
[2] http://www.tutorialspoint.com/management_concepts/project_ac
tivity_diagram.htm.
[3] http://en.wikipedia.org/wiki/Arrow_diagramming_method
[4] https://www.scribd.com/doc/47657934/Managing-Projects.
[5] PROJECT MANAGEMENT, Steparies Martin, Zita Dewi
L.R.M Robert.
[6] http://en.wikipedia.org/wiki/Program_evaluation_and_review_te
chnique
[7] http://www.sce.carleton.ca/faculty/chinneck/po/Chapter11.pdf
[8] http://www.inc.com/encyclopedia/program-evaluation-andreview-technique-pert.html
[9] Laborator Tehnici de estimare, Prof Ioan Sacala, ACS.
[10] Critical Path Method, Shohreh Ghorbani
[11] http://www.tutorialspoint.com/management_concepts/critical_pa
th_method.htm