ast in place concrete piles eliminate the need for
pile driving machinery which can cause dangerous vibrations and precipitate landslides and which is sometimes too costly for use on small jobs. Two simple new techniques for installing cast-in-place piles promise solutions to these problems.
CAST-IN-PLACE PILES WITH STEEL CORES
Steel-cored concrete piles cast in drilled shafts proved effective in preventing landslides on part of the new freeway construction in Seattle, Washington, where usual methods of driving piling were considered too hazardous because ground vibrations caused by the hammering might precipitate the slide. The method was developed by the Washington State highway department. The problem became apparent when hairline cracks developed in the area in which the contractor was proceeding with excavation pile driving, and footing and column construction for shoring to support an uphill retaining wall. Further investigation revealed some displacement at the 108-foot elevation in an adjacent pier footing excavation. Slope indicators were installed and correlated findings indicated that the area encompassed
by the slide extended to the south for approximately 400
feet on a line just west of the proposed retaining wall. The threatened hillside movement was particularly serious because it threatened closure of one of the citys main arterial streets and endangered a nearby apartment building. No movement had yet occurred in the main area of the proposed uphill retaining wall and the ancient fracture zone was 10 feet below the retaining wall footing elevation. The immediate danger was the possibility of the slide progression to the east beyond the limits of the wall, necessitating difficult remedial work in disturbed earth in a restricted right-of-way width. Also the prospect of heightening a 30- to 40-foot wall or increasing excavation depths in a critical area were disquieting. Quick action was imperative. The need to prevent ground vibrations such as those induced by a pile-driver led to the selection of a cast-in-place cylinder pile type of construction. This procedure required pre-drilling of holes, placing a steel beam in each hole, and back-filling voids with concrete. The upper zone would thus be pinned to the lower zone through the thin fractured layer prior to any movement, thus maintaining the stability of the earth in
Diagram of new piling system developed by a
British piling company. Workmen thread a precast section of the pile over central steel tube to form pile core.
both zones. Altogether 62 pilings were designed varying
in depth from 62 to 81 feet and requiring 4,410 lineal feet of boring excavation, 2,900 cubic yards of ready mixed concrete, 9,700 pounds of reinforcing steel and 1,453,000 pounds of high-strength, low-alloy structural steel I beams. Steel casings 1 1/4 inches thick and 4 feet 9 inches in diameter were used to case the holes to their full depths to retain the sandy clays. Excessive moisture in the borings required steady pumping prior to placing concrete and slough from a wet sand strata was not always avoidable. Consequently it was found desirable to drill and case to the upper limit of the sand zone, place the I beam and then drive it to position with an improvised mandrel and hammer. The contractor started out by using tremies down as far as 70 feet, but lost them so frequently because of hanging up on stud bolts that he finally placed the concrete directly into the cylinders. It was found that the crew could place a 60-foot head of concrete before pulling out the casing, so two casing lengths were placed before pulling up. Because the earth pressure came primarily from the overburden the holes in the top 25 feet were over-drilled regularly to 4 feet 4 inches and wider casings put down, the standard casings inserted, the interstices backfilled with sand, and then the outer casings removed before placing concrete. A cast-in-place face wall was hung on the front of the piles and fastened to the steel beams in the cylinders. To do this engineers placed a wood blockout on the front flange of the steel beam down to the wall footing elevation. The blockout was removed after excavation to subgrade, thereby permitting face wall dowels to be welded to the beam flange. The Washington State highway departments AX mix was used for the concrete in the piers. This mix is a refinement of the A class giving a minimum ultimate strength of 4,000 psi at 28 days. An admixture was used to give early curing because the drilling of adjacent piles would be necessary in two daysless than normal curing time. Experience on this project has shown the versatility of this type of design, and it appears certain that it will be used on other jobs where dangerous earth conditions exist.
CAST-IN-PLACE PILES WITH PRECAST CORES
A British piling company has introduced a system which uses precast sections for the core of the pile. The result is a better and simpler technique which has proved successful on several difficult projects. A hole is bored in the ground to the required depth and lined, as necessary, with a steel casing made up in convenient lengths. The precast sections are then threaded over a central steel tube to form the pile core. Support is by a special release gear fitted to the lower end of the steel tube; the tube is also made up in short lengths
screwed together as assembly proceeds. Lowering into
the borehole continues as each section is added. Main longitudinal reinforcement (4, 5 or 6 rods, 1/2 to 1 inch in diameter) is threaded through holes in the sections, and thus cannot be displaced. The steel lining of the borehole is withdrawn and a grout mix pumped in simultaneously through the central hole in the sections. The mix is under pressure to fill all voids both within the body of the pile and between the core and the sides of the hole. Subsoil water is forced out as the level of the mix rises. The result is a high-strength core grouted together and into the subsoil to form a solid pile encased in a thick skin of concrete firmly keyed to the substratum. The sections are usually cast in lengths of 1, 1 1/2, and 3 feet and diameters of 11 1/2, 14 1/2 and 23 1/2 inches for nominal pile sizes of 14, 18 and 26 inches (working loads up to 40, 60 and 150 tons). Each section has a ribbed annular surface to promote a good bond with the surrounding mix and is reinforced with 1/4-inch spiral binding at 6-inch pitch. The sections are cast of vibrated concrete with a nominal 1 : 1 1/2 : 3 mix by volume. Maximum resistance to attack by sulfates in the ground water or subsoils can be assured by the use of sulfate-resisting cements, but standard portland cement and other types of cement are often used.
All the equipment and components needed for the
piles are kept light and easy to handle. The vibration associated with pile driving is, of course, eliminated, a big advantage in built-up areas, and headroom and space problems are largely avoided. Piles up to 90 feet long are regularly being formed in this way without difficulty. Each stage of the assembly can be checked above ground. Main use of the system at present is on small jobs which do not justify the use of full-scale piling equipment. Inclined piles are also being formed with the system. Assembly through water, for such structures as bridge piers, is easily achieved by using concrete pipe sections as a permanent cofferdam. View of some of the 62 cast-in-place piles taken after the excavation had been completed but before the face wall was cast. Wood knockout blocks visible on the exposed side of the piles were removed to permit welding anchor bolts to the encased steel beams, the latter in turn providing for the fastening of the wall panels.
PUBLICATION #C630069 Copyright 1963, The Aberdeen Group All rights reserved