INSPECTION TEST PLAN (ITP)

:EQUIPMENT NAME
MOBILE FIRE EXTINGUISHER

MANUFACTURE NAME : NARFOAM KAR Co.

TABLE OF CONTENTS

1.

SCOPE

2.

LEGEND OF THE TECHNICAL SURVEILLANCE

3.

ABBREVIATION

4.

REFERENCE STANDARD

PRELIMINARY ACTIVITY

1. Scope
This inspection and test plan covers all activities that will be carried out in inspecting and testing
of mobile fire extinguisher.

2. LEGEND OF THE TECHNICAL SURVEILLANCE


Surveillance action by Manufacture, Third Parties
H: Hold Point = Hold on the production till TPI Inspector performs inspection and supervise the required test
W: Witness Point = Manufacture shall notify client and TPI Inspector but there is no hold on the production;
Client can waive this inspection based on his discretion and informs TPI Inspector accordingly.

R: Document Review = Review means Review document, which includes of material test certificates, WPS, PQR,
NDT Procedures and etc.

A: Approval
SW: Spot Witness = for items with spot witness manufacture shall notify TPI inspector as fulfilling the monitoring;
For example one random visit for whole UT tests or one or two visits for whole surface preparation works for
painting.

MOM: MINUTE OF MEETING


P.O: Purchase Order

3. Abbreviations
Manuf. Manufacture ( NARFOAMKAR )
TPI Third Party Inspector

4. Reference Standards
-

EN 288
EN ISO 15609-1
EN ISO 15614-1
EN 1866-2
EN 13445-2
EN 1866-1
EN 13445-4
EN 3
EN ISO 9017
EN 10204