Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
PRINCE2 (an acronym for PRojects IN a Con1. 'Managing Successful Projects with PRINCE2 trolled Environment, version 2) is a project manage2009 Edition',[4]
ment methodology. The methodology encompasses the
2. 'Managing Successful Programmes 1999, fourth
high level management, control and organisation of a
edition in 2011.
project, but not lower level activities such as scheduling.
PRINCE2 is also used to refer to the training and accreditation of authorised practitioners of the methodology who Both the Foundation and Practitioner Examinations
must undertake accredited qualications to obtain certi- are based on the 2009 revision 'Managing Successful
cation.
Projects manual
History
means for capturing and assessing project issues is suggested together with the way in which corrective action
should be taken. It also lays down the method by which
certain project issues should be escalated to the project
Key activities include: Forming the project board; ap- board.
pointing an executive and a project manager; designing Key activities include: authorising work packages; asand appointing a project management team; preparing a sessing progress; capturing and examining project issues;
project brief; dening the project approach; preparing an monitoring and controlling risks; reviewing stage status;
outline business case, consulting the Lessons Logs of pre- reporting highlights; taking corrective action; escalating
vious projects; and planning the next stage (initiation).
project issues; and receiving completed work packages.
2.2
2.3
2.4
3.4
Issues register
The key activities are: Accept a work package, execute a have met their quality criteria and the agreed processes
work package and deliver a work package.
have been observed.
2.7
Key activities include: decommissioning a project; identifying follow-on actions; preparing a benets review plan
and project evaluation review. The benets review plan A set of notes of lessons learned (often the hard way)
indicates a time when the benets of the end product may which may be useful to future projects.
be measured, how and what resources will be required.
Management products
3.1
Project brief
4.1 Continued business justication
A short explanation of the need for the project, the management team, the structure and goals.
The Business Case is the most important document, and
is updated at every Stage of the project to ensure that the
project is still viable. Early termination can occur if this
3.2 Risk register
ceases to be the case. At lower levels, use of time and
resources should be justied, such as the need to have
See also: Risk register
expensive meetings. (e.g. it is good practice to begin each
meeting with a sentence about what its goal isand if
The risk register is a table which contains the risks that such a statement is hard to nd then the meeting may not
may threaten the goal of the project. Risks are catego- be necessary.)
rized, named and assigned a risk number. Then, each risk
gets a probability score and an impact score. The multiplication of these two results in the risk score. The risks 4.2 Manage by exception
are sorted on descending risk score in order to show the
priority of a risk. Each risk is also assigned an owner, a Regular meetings, especially the dreaded weekly team
precaution and a response-action in case the risk occurs. meetings are considered inecient and unnecessary. In-
3.3
Quality register
6 CERTIFICATIONS
4.3
4.4
4.5
Manage by stages
The project is planned and controlled on a stage by stage and in passing mentions as possible tools,
basis. This includes updating the Business Case, risks,
overall plan, and detailed next-stage plan after each stage
Gantt charts
in the light of new evidence.
PERT charts
4.6
Focus on products
4.7
Tailoring
6 Certications
PRINCE2 certication requires passing the requisite examinations or assessment.[8]
6.5
6.1
PRINCE2 Foundation
The lower level Foundation exam is a one-hour, multiple choice exam which tests candidates knowledge of the
method. The exam consists of 75 questions, 5 of which
are trial questions which do not carry a mark. Of the
remaining 70 questions which do carry a mark, the candidate needs to score 50% or more (i.e. 35 or more) to
pass.
6.2
PRINCE2 Practitioner
The higher level Practitioner exam lasts for 2.5 hours, and
is a more complex multiple choice exam which tests candidates ability to apply the method to a simple project
scenario. The paper consists of 8 topics, with 10 questions per topic making a total of 80 marks. The pass mark
is 55%, which is 44 marks or more. Passing the Foundation exam is a pre-requisite for sitting the Practitioner
exam.
Candidates who have passed the PRINCE2 Practitioner
exam may call themselves a Registered PRINCE2 Practitioner for 5 years after which they must pass a Reregistration examination every 5 years to maintain their
Registered Practitioner status. The Re-registration exam
is a one-hour exam with 3 topics each containing 10 questions. The pass mark is 55%, which means candidates
must score 17 marks or more to pass.
6.3
PRINCE2 Professional
6.4
6.6 Register
The APM Group publishes a successful candidate register which can be searched on the web.[9] The register
records the details of candidates who have sat PRINCE2
examinations.
6.7 Trainers
Trainers must be re-accredited every 3 years and undergo
a surveillance check (either in the form of a visit by an assessor to a training course or a telephone interview which
assesses their professional knowledge and training capability) every 12 months.[10]
6.8 Exemptions
Qualied PRINCE2 Practitioners who go on to study for
the APMP qualication of the Association for Project
Management are exempt from certain topics of the syllabus that are covered in the PRINCE2 Practitioner
qualication.[11]
7 Scalability
Project management is a complex discipline and it would
be wrong to assume that blind application of PRINCE2
will result in a successful project. By the same token, it
would be wrong to assume that every aspect of PRINCE2
will be applicable to every project. For this reason every process has a note on scalability. This provides guidance to the project manager (and others involved in the
project) as to how much of the process to apply. The positive aspect of this is that PRINCE2 can be tailored to
the needs of a particular project. The negative aspect is
that many of the essential elements of PRINCE2 can be
omitted sometimes resulting in a PINO project Prince
in Name Only. In order to counter this, APM Group have
dened the concept of a PRINCE2 Maturity Model.[12]
12
Adoption
EXTERNAL LINKS
11 References
[1] OGC - PRINCE2 - News
[2] OGC brings its shining quartet back into the limelight
(Press release). Oce of Government Commerce. 200512-14.
[3] Ocial PRINCE2 website
[4] OGC (Oce of Government Commerce) (2009). Managing Successful Projects with PRINCE2 (2009 ed.). TSO
(The Stationery Oce). ISBN 978-0-11-331059-3.
[5] About PRINCE2
10
See also
Ocial website
Guidelines for Managing Projects (fully consistent
with PRINCE2) from the UK Department for Business, Enterprise and Regulatory Reform (BERR)
PRINCE2 wiki
PRINCE2 Agile wiki
13
13.1
PRINCE2 Source: https://en.wikipedia.org/wiki/PRINCE2?oldid=681163925 Contributors: The Anome, Deb, Kku, Angela, Harry Wood,
Mkoval, Poor Yorick, Guaka, Boson, Dysprosia, Kaare, Topbanana, ChrisG, Michael Snow, Leonig Mig, Inter, Zigger, Binarygal,
Database~enwiki, Pinnecco, Marqoz, Rellis1067, Arnauldvm, Mike Rosoft, Rich Farmbrough, Vlipper~enwiki, Polymorp, ZeroOne, Sietse Snel, Vortexrealm, Notreadbyhumans, Haham hanuka, Mdd, Jumbuck, ProductBox, H2g2bob, Gene Nygaard, Drbreznjev, Bobrayner,
RHaworth, Syiem, Stuartroebuck, Hughcharlesparker, GraemeLeggett, FreplySpang, China Crisis, Rillian, Bhadani, Fred Bradstadt, Fish
and karate, Antidoter, StephenAshurst, Peter Grey, YurikBot, Fakelvis, NawlinWiki, Richard Allen, Wiki alf, Retired username, Ezeu,
Amakuha, Doncram, Lynbarn, Danus, Nelson50, SmackBot, Mark Tranchant, Reedy, Mauls, Gilliam, Thumperward, Hellre81, Oblomo, Freek Verkerk, Kolmigabrouil, Matt Whyndham, The undertow, Kuru, Jcamp, JHunterJ, Ehheh, MrTrev, Mgillett, Manifestation,
MTr~enwiki, Wizard191, Akbradford, Rkoster~enwiki, Wftbuts, Yaris678, Snarpel, Ccrichte, Dowm, Throxana, Ntitsuit, Sharkli, Dibbler5, Mattisse, Thijs!bot, Alynex, Faigl.ladislav, Colonel.jrd, Nick Number, Widefox, Ghettolave, Rajan52s, Lbk3918, MrKris, Andrew Swallow, Bethmanj, MaxPont, Magioladitis, Meredyth, Vernon39, Davidjcmorris, Speck-Made, Ash, Bonadea, VolkovBot, SueHay,
Mark Bush 29, Steve wiki ppc, Fionaspence, Jamelan, PorthosTyke, KimMarello, IILMarketing, PRINCE2Andy, Todo14, Malcolmxl5,
Alanpc1, Pmtoolbox, Sbrumpton, Ride the Hurricane, Pm master, Athirumurthi, Millstream3, Heesoyuy, Shruti14, Lonegroover, MarnixR,
Mnorse, Mike0001, Excirial, Eeekster, Technobadger, Iness it, Carriearchdale, Sean.sandys, IanNeville, Dwj7738, Nick in syd, XLinkBot,
Prof Wrong, Tthheeppaarrttyy, Addbot, Blethering Scot, MagnusA.Bot, Chilin, Thruxton, Itgov, Download, LaaknorBot, Erikko, Vasi,
Khyron2008, Luckas-bot, Yobot, Igniz ameheart, KamikazeBot, SwisterTwister, Nico Mannaerts, Georgebaily, AnomieBOT, Jakub.cz,
Xqbot, Tim Boothby, Wednesdaa, Alimozcan, Tianyx159, Fernandosantucci, Ernanims, JP du Preez, BKRathke, Pnaybour, Pmckeever,
MastiBot, Serols, Jandalhandler, Barinder hothi, Tony knowledge, Pothoc, WTF-tech, Thebluemanager, Bernd.Brincken, Sunilprabhale,
EmausBot, Fvanrenterghem, Tommy2010, F, Stephenog, JmRay, DanielV UK, Jimbo 1985, 28bot, Petrb, ClueBot NG, Invincible1984,
PRINCE2Coach, Helpful Pixie Bot, Parsley1972, Ultapultanikhil, BG19bot, MusikAnimal, BattyBot, Khorramirad, Calu2000, Khazar2,
Mariaannburton, Tonytowner, Mogism, SLP101, S.boilerhouse, Epicgenius, VernonD12, Lesser Cartographies, Ginsuloft, Lisapr1, Dexterous1802, Skr15081997, Davejones2004, Carlos.serra, Pboudr, Ranjanonline, Colin Bentley and Anonymous: 347
13.2
Images
File:Ambox_important.svg Source: https://upload.wikimedia.org/wikipedia/commons/b/b4/Ambox_important.svg License: Public domain Contributors: Own work, based o of Image:Ambox scales.svg Original artist: Dsmurat (talk contribs)
File:Commons-logo.svg Source: https://upload.wikimedia.org/wikipedia/en/4/4a/Commons-logo.svg License: ? Contributors: ? Original
artist: ?
File:Edit-clear.svg Source: https://upload.wikimedia.org/wikipedia/en/f/f2/Edit-clear.svg License: Public domain Contributors: The
Tango! Desktop Project. Original artist:
The people from the Tango! project. And according to the meta-data in the le, specically: Andreas Nilsson, and Jakub Steiner (although
minimally).
File:PRINCE2_-_Project_Management_Methodology.png Source:
https://upload.wikimedia.org/wikipedia/commons/a/a2/
PRINCE2_-_Project_Management_Methodology.png License: CC BY-SA 3.0 Contributors: Own work Original artist: Priya Ranjan
File:Question_book-new.svg Source: https://upload.wikimedia.org/wikipedia/en/9/99/Question_book-new.svg License: Cc-by-sa-3.0
Contributors:
Created from scratch in Adobe Illustrator. Based on Image:Question book.png created by User:Equazcion Original artist:
Tkgd2007
File:Unbalanced_scales.svg Source: https://upload.wikimedia.org/wikipedia/commons/f/fe/Unbalanced_scales.svg License: Public domain Contributors: ? Original artist: ?
File:Wiki_letter_w_cropped.svg Source: https://upload.wikimedia.org/wikipedia/commons/1/1c/Wiki_letter_w_cropped.svg License:
CC-BY-SA-3.0 Contributors:
Wiki_letter_w.svg Original artist: Wiki_letter_w.svg: Jarkko Piiroinen
13.3
Content license