Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
DEPARTMENT OF DEFENSE and National Aeronautics and Space DATES: For effective dates and comment
Administration (NASA). dates, see separate documents which
GENERAL SERVICES ACTION: Summary presentation of final follow.
ADMINISTRATION and interim rules.
FOR FURTHER INFORMATION CONTACT: For
NATIONAL AERONAUTICS AND SUMMARY: This document summarizes clarification of content, contact the
SPACE ADMINISTRATION the Federal Acquisition Regulation analyst whose name appears in the table
(FAR) rules agreed to by the Civilian below in relation to each FAR case or
48 CFR Chapter 1 Agency Acquisition Council and the subject area. Please cite FAC 2005–11
Defense Acquisition Regulations and specific FAR case number(s).
[Docket FAR—2006–0023] Council in this Federal Acquisition Interested parties may also visit our
Federal Acquisition Regulation; Circular (FAC) 2005–11. A companion Web site at http://www.acquisition.gov/
Federal Acquisition Circular 2005–11; document, the Small Entity Compliance far. For information pertaining to status
Introduction Guide (SECG), follows this FAC. The or publication schedules, contact the
FAC, including the SECG, is available FAR Secretariat at (202) 501–4755.
AGENCIES: Department of Defense (DoD), via the Internet at http://
General Services Administration (GSA), www.acquisition.gov/far.
VerDate Aug<31>2005 19:49 Jul 03, 2006 Jkt 208001 PO 00000 Frm 00002 Fmt 4701 Sfmt 4700 E:\FR\FM\05JYR2.SGM 05JYR2
Federal Register / Vol. 71, No. 128 / Wednesday, July 5, 2006 / Rules and Regulations 38239
• Post-award IBRs. of the final rule. for prime contracts. In addition, any
• Modified IBRs. Comment: A number of commenters small business awarded a prime
• Reporting. stated that the requirement for EVMS for contract that exceeds this threshold
• EVMS Compliance, System contractors will impact the overall cost should be subject to the same EVMS
Surveillance and Approval of Changes. to the government of acquisitions. requirements.
VerDate Aug<31>2005 19:49 Jul 03, 2006 Jkt 208001 PO 00000 Frm 00003 Fmt 4701 Sfmt 4700 E:\FR\FM\05JYR2.SGM 05JYR2
38240 Federal Register / Vol. 71, No. 128 / Wednesday, July 5, 2006 / Rules and Regulations
Response: The Councils believe that Comment: The commenter submitted contract work. EVMS is one method
the FAR should not establish EVMS the following recommendations to used to manage that work.
thresholds. The final rule provides mitigate the impact that EVMS
Pre-award IBRs
individual agencies the authority to requirements will have on small
establish appropriate thresholds for business: Comment: A number of commenters
major acquisitions and EVMS • No validation on contracts less than state that the pre-award IBR process
applicability criteria in accordance with $50M. may cause undue cost and manpower
OMB Circular A–11, based on their • No EVM on contracts less than burdens on offerors and the
particular facts and circumstances. $20M without authorization by agency’s Government, and could result in delay
Comment: The commenter states that senior acquisition executive. of award, excessive B&P costs,
EVMS requirements should not flow- • Costs of complying with EVMS decreased competition, risks of
down to subcontractors, regardless of requirements should be directly technical leveling, increased protest
dollar value. There is no privity of chargeable to that contract. potential and the necessity for a follow-
Response: The Councils believe it is up IBR after award.
contract between the government and
preferable to provide individual Response: Pre-award IBRs are not
any subcontractor.
agencies with the authority to establish mandatory; however, if agencies
Response: The Councils believe that
appropriate thresholds for major determine that establishing a firm
EVMS requirements should apply to
acquisitions and EVMS applicability baseline prior to award is beneficial, the
subcontracts when the cost/benefits
criteria in accordance with OMB rule allows this flexibility. The Councils
support such application. However, the Circular A–11, based on their particular acknowledge that pre-award IBRs may
Councils also recognize that facts and circumstances rather than increase B&P costs and source selection
clarification of this requirement is specifying a threshold in the FAR. It is resources; however, EVM is designed to
necessary. As such, the rule has been also not appropriate for the EVMS save money in the long run. Agencies
revised to clarify language at FAR clause to specify whether the costs of have the flexibility of paying for pre-
52.234–4(g) and 34.201(d) to require complying with EVMS requirements award IBRs within the source selection
application of EVMS to subcontractors should be a direct or indirect cost. The process. As with any source selection
using the same rules as applied to the charging of costs as direct or indirect process, the Government must take all
prime contractor. The Councils note that costs (including the cost of complying necessary steps to protect against
the Government often requires with EVMS requirements) is determined disclosure of proprietary information or
contractors to flow certain clauses down by the Cost Accounting Standards and/ technical leveling during the proposal
to subcontractors. Such flow-downs do or the requirements of FAR Part 31. evaluation. The Government has
not require privity of contract between Furthermore, EVMS costs, like other flexibility for source-selection
the Government and the subcontractor, costs, must meet the allowability criteria procedures as currently prescribed in
i.e., the flow-down requirement in the in FAR 31.201–2(a). FAR Subpart 15.3.
clause is between the Government and Comment: The commenter stated that Comment: A number of commenters
the contractor. the flow-down requirements of EVMS to expressed concern that a pre-award
Comment: The commenter small business could have a negative budget baseline may not add value to
recommends that EVMS thresholds effect. This commenter asserted that the the source selection process since there
should be indexed to inflation. statistical value in assessing the impact is insufficient information to establish a
Response: The Councils believe that it to small business is understated. technical or cost baseline and it is too
is preferable to provide individual Response: The Councils note that an difficult to properly assess risk prior to
agencies with the authority to establish Initial Regulatory Flexibility Analysis award.
appropriate thresholds for major was performed and comments were Response: The Councils believe that
acquisitions and EVMS applicability solicited as to the effect of this rule on pre-award IBRs are designed to verify
criteria in accordance with OMB small business. Some comments were and establish the technical and cost
Circular A–11 based on their particular received that indicated that small baseline. If an Agency determines that a
facts and circumstances, rather than businesses may be affected. Therefore, pre-award IBR is appropriate for that
indexing the thresholds to inflation. to alleviate the possible burden on small procurement, then the proposal should
Comment: The commenter stated that businesses that do not have an EVM serve as a sufficient baseline to conduct
EVMS is not simple to implement. system, the rule is revised to make it an IBR prior to contract award.
Small businesses may find it difficult clear that offerors shall not be Comment: A number of commenters
and costly to implement EVMS. Flowing eliminated from consideration for stated that the only reason to conduct a
down EVMS requirements to several contract award because they do not have pre-award IBR for sole source
tiers of subcontractors compounds these an operational EVM system, provided acquisitions is to establish a
difficulties. they submit an EVMS implementation performance measurement baseline
Response: The Councils believe that plan with their proposal. Likewise, (PMB). However, this PMB will not be
application of EVMS should be done agencies have the flexibility of paying valid because pre-award IBR budget
only when the cost/benefits of such for initial baseline reviews in values will change from the PMB after
application is warranted. The Councils accordance with agency procedures. award, and the contractor will be
also recognize that some businesses may Comment: The commenter reluctant to disclose management
not have an operational EVMS when recommended that the rule provide for reserve before negotiations are
they submit their offer. As such, the an exception to allow the Government concluded.
language in FAR 34.201(b) has been to manage the EVMS while the Response: The Councils agree that the
revised to make it clear that offerors contractor is responsible for reporting purpose of a pre-award IBR is to verify
wwhite on PROD1PC61 with RULES2
who do not have an operational EVMS status. the technical content and the realism of
shall not be disqualified from contract Response: The Councils believe that the related performance budgets,
award if they submit an EVMS management of the EVMS is the resources and schedules. However, the
implementation plan with their contractor’s responsibility. The Councils do not agree that such
proposals. contractor is responsible for managing technical and cost baselines will
VerDate Aug<31>2005 19:49 Jul 03, 2006 Jkt 208001 PO 00000 Frm 00004 Fmt 4701 Sfmt 4700 E:\FR\FM\05JYR2.SGM 05JYR2
Federal Register / Vol. 71, No. 128 / Wednesday, July 5, 2006 / Rules and Regulations 38241
substantially change after award. A pre- agency may choose to perform a post- structured to guard against undermining
award IBR will help to verify the award IBR. an offeror’s commitment or a
realism of the proposal and therefore Comment: The commenter does not contractor’s obligation to perform–
facilitate negotiations. Additionally, agree that ‘‘IBRs will normally be especially under a fixed-price,
disclosure of cost information is subject scheduled before award’’ as stated in performance-based type arrangement.
to and available under the Truth in 52.234–X3(c). In certain agency Response: The Councils believe that
Negotiations Act (41 U.S.C. 254b and 10 acquisitions, M&O contractors are pre-award IBRs do not undermine the
U.S.C. 2306a). responsible for design and planning source selection process. Pre-award
Comment: The commenter states that activities necessary to establish the IBRs are not required; however, if
performance of a pre-award IBR would PMB, which must be in place prior to performed, the pre-award IBR would be
fall under FAR Subpart 15.3 Source IBR. The commenter suggests a tiered considered in the evaluation process.
Selection. Specifically, pre-award IBRs approach for the performance of IBRs. FAR 7.105(b)(3) has been added to
would fall under FAR 15.306(d), Response: The Councils believe that address how the results of the pre-award
exchanges with offerors after the rule allows the flexibility for the IBR will be considered in the source
establishment of the competitive range. timing and conduct of the IBR. Pre- selection.
The proposed rule does not refer to Part award IBRs are not mandatory. An Comment: A number of commenters
15. agency may choose to perform a post- requested a revision to 52.234–X2(d) to
Response: The Councils do not award IBR. If an Agency determines that define the procedures for determining
believe that it is necessary to address a pre-award IBR is appropriate for that the competitive range and/or
pre-award IBRs in FAR Part 15. procurement, then the proposal should determining the number of offerors that
However, FAR 7.105(b)(3) is revised to serve as a sufficient baseline to conduct remain in a competitive range prior to
include source selection procedures an IBR prior to contract award. The conducting a pre-award IBR.
when a pre-award IBR is contemplated. Councils do not believe a tiered Response: The Councils do not
While a pre-award IBR is not mandated, approach is necessary or beneficial. believe that language is necessary to
when one will be performed, the Comment: The Commenter stated that specify what constitutes the competitive
acquisition plan should address how the the only way an independent baseline range for the conducting of pre-award
IBR results will be considered in source could exist prior to award would be if IBRs. Pre-award IBRs will be conducted
selection. it were developed either privately or in accordance with the source selection
Comment: The commenter states that under a prior contract. Therefore, there plan set forth for that acquisition.
any company with an approved EVM is no need for provision 52.234–X2. Comment: A number of commenters
System should not be subjected to a pre- Response: The Councils believe that stated that the regulations should not
award IBR. For those companies the pre-award IBR provision is encourage the imposition of pre-award
without an existing or approved EVMS, necessary. If an agency determines that IBRs on smaller acquisitions or those
this should be considered as part of establishing a firm baseline prior to contractors with minimal EVMS
management risk of the source selection award is beneficial, the rule allows the experience.
evaluation based on their proposed flexibility of requiring a pre-award IBR. Response: Agencies have the
system implementation described in The IBR is meant to verify the technical authority to establish thresholds and
their proposal. It would be resource and content and the realism of the related EVMS applicability criteria. The
schedule prohibitive to perform an IBR performance budgets, resources and Councils have agreed to revise the
or sequential IBRs prior to award. schedules. FAR 52.234–X2 does not language in FAR 34.201(a) to make it
Response: The Councils disagree. The address an independent baseline, but clear that offerors who do not have an
determination that an offeror’s EVM rather an integrated baseline conducted operational EVMS shall not be
System is compliant with the ANSI/EAI as a joint effort between the offeror and disqualified from contract award if they
- 748 standard is an independent the Government. submit an EVMS implementation plan
assessment and is not related to the Comment: A number of commenters with their proposals.
timing of an IBR. Pre-award IBRs are stated that it often takes a number of
designed to verify and establish the weeks, after award, for the contractor to Post-award IBRs
technical and cost baseline. If an agency develop and refine their understanding Comment: The commenter noted that
determines it is beneficial to establish of the project and their work plans so when a post-award IBR may be required,
the IBR prior to award, they have the as to have the detailed information 34.X03 prescribes a solicitation
flexibility to conduct an IBR. The available necessary for a comprehensive provision (52.234–X1) that does not
language in FAR 34.201(b) has been IBR. If the ‘‘first IBR’’ is conducted prior mention IBR.
revised to make it clear that offerors to award ‘‘there is little likelihood that Response: The Councils agree that the
who do not have an operational EVMS the level of information available to the proposed rule should be clarified to
shall not be disqualified from contract contractor will be sufficient to allow a address the responder’s concern. As a
award if they submit an EVMS meaningful IBR...’’ result, FAR 34.202 in the final rule
implementation plan with their Response: The Councils believe that specifically states that when an EVMS is
proposals. In such case, a pre-award IBR the technical proposal should reflect the required, the Government will conduct
would utilize data from the offeror’s offerors’ understanding of the an Integrated Baseline Review (IBR). No
current cost/schedule control system. requirements at time of proposal change to the provision at FAR 52.234–
Comment: The commenter states that submission. Thus the proposal should 3 is therefore necessary since IBRs shall
if the requirement for a pre-award IBR serve as a sufficient baseline to conduct always be required when the post-award
is retained in the final rule, the an IBR prior to contract award. IBR language is in the contract in
requirement for a post-award IBR Comment: The commenter cautions accordance with the clause at 52.234–4.
wwhite on PROD1PC61 with RULES2
should be deleted. that a pre-award IBR may undermine Comment: The commenter
Response: The Councils believe that the normal source selection process of recommended revising 52.234–X3(c) to
the rule allows the flexibility for the technical evaluation. The IBR should be state ‘‘If a pre-award IBR has not been
timing and conduct of the IBR. Pre- considered as one aspect of the conducted, such a review shall be
award IBRs are not mandatory. An evaluation process. The IBR should be scheduled [and initiated] as early as
VerDate Aug<31>2005 19:49 Jul 03, 2006 Jkt 208001 PO 00000 Frm 00005 Fmt 4701 Sfmt 4700 E:\FR\FM\05JYR2.SGM 05JYR2
38242 Federal Register / Vol. 71, No. 128 / Wednesday, July 5, 2006 / Rules and Regulations
practicable after contract award...’’ since programs requiring only scaled back contractor’s EVM system is compliant
it is important to indicate that the IBR IBRs. Task order contracts and other with the contractual requirements.
should commence during the allotted contract types where scope is not well Comment: The commenter believes
timeframe. defined should be excluded from IBRs. that allowing contractors an unlimited
Response: The Councils do not agree Response: The Councils have amount of time to demonstrate
that the timing of post award IBRs provided that agencies have the compliance to the EVMS requirements
should be specified in the FAR. The flexibility to determine the application is counterproductive. Demonstration of
clause at FAR 52.234–4(c) has been and extent of IBRs. compliance should precede award fee
revised to state that a post award IBR determination or should happen within
shall be conducted as early as Reporting 90 days after award.
practicable after contract award. Comment: The commenter is Response: The Councils believe that
Agencies have the flexibility to establish concerned that FAR 42.1106, Reporting EVMS compliance is related to the
the timing and conduct of the post Requirements, will result in EVM overall EVMS review and is not
award IBRs. reports without the EVM System necessarily related to a contract award
Comment: The commenter requirement. fee determination. The contractor
recommended that Post-award IBRs for Response: The Councils agree that the should take the necessary actions to
options or major modifications should language should be revised to clarify the meet the negotiated milestones in their
have a numerical threshold - 50% of applicability of EVMS reporting. The EVMS plan. Whether these milestones
prior contract value. language is moved to FAR 34.201(c), are tied to an award fee determination
Response: The Councils believe it is and revised to specifically state that will be a subject for negotiation on an
preferable to provide flexibility in contractors shall ‘‘submit EVMS reports individual contract basis.
regard to whether there is a change to Comment: The commenter suggested
monthly for those contracts for which
the contract in terms of exercise of that in addition to specifying EIA
an EVMS applies.’’
significant option(s) or incorporation of Standard 748, the Government should
Comment: The commenter believes
major modification(s), rather than require that the evaluation process be
that EIA - 748 should govern reporting
applying a predetermined dollar or based on either the EMIR or the NADIA
requirements, and any additional
percentage threshold. EVM Intent Guide.
reporting requirements should require Response: The Councils believe that
Comment: The Commenter specific approval by the head of the
recommended changing the language in the FAR coverage is appropriate.
contracting activity. Agencies have the flexibility to develop
FAR 52.234–X3 from ‘‘not later than 180 Response: The Councils do not agree
days after award’’ to ‘‘in accordance implementation procedures to meet
that reporting requirements outside of their requirements.
with agency procedures.’’ ANSI/EIA - 748, which does not
Response: The Councils agree that the Comment: A number of commenters
mandate specific reports, formats, or stated that EVMS oversight should be
timing of post award IBRs should not be
timing, should be subject to mandatory clarified. In general, EVMS oversight
specified in the FAR. The clause at FAR
head of contracting activity approval, should be performed for the contractor’s
52.234–4(c) has been revised to state
but instead should be subject to Agency entire company or facility, surveillance
that a post award IBR shall be
procedures. should be performed jointly by the
conducted as early as practicable after
Comment: The commenter suggested contractor and a single cognizant
contract award. Agencies have the
that agencies should be required to Federal Agent for all contracts, and that
flexibility to establish the timing and
submit written comments within 10 certification resources and procedures
conduct of the post award IBRs.
Comment: A number of commenters days of monthly reports or waive the should be established.
requested clarification of 34.X03(a) as to right to require corrective action or to Response: The Councils agree that
whether post-award IBRs are optional, take adverse action. In addition, the EVMS surveillance should be performed
‘‘may require’’, while Paragraph (b) pre- commenter stated that variances of less on a business segment basis rather than
award is less optional, ‘‘will require’’. than 10% should not be grounds for on a contract-by-contract basis.
Response: The Councils have revised corrective action. Therefore, the Councils have provided
the language at FAR 34.202 to explicitly Response: The Councils believe that in the final rule that the Cognizant
state that an IBR is required regardless time allotted for review will be Federal Agency (CFA) will determine if
of whether it is performed pre-award or determined on a case-by-case basis. a contractor’s EVMS is compliant with
post-award. The requirement for the Failure to respond does not equate to the guidelines in ANSI/EIA Standard -
timing of an IBR will be determined by acceptance. The Councils further 748.
the agency. believe that variances should be subject Comment: A number of commenters
Comment: A number of commenters to review based on the particular facts questioned the effective date of the
suggested the language at 52.234–X3(c) and circumstances rather than a EVMS rule. One commenter questioned
be revised to change Agencies ‘‘may specified minimum percentage. whether modification of existing
conduct IBRs’’ to ‘‘shall conduct IBRs.’’ EVMS Compliance, System contracts will be required to comply
Response: The Councils agree that Surveillance and Approval of Changes with the new FAR EVMS requirements.
agencies are required to conduct the Another commenter suggested that the
IBR’s. As such, the Councils have Comment: The commenter believes rule should provide a suitable phase-in
revised the language at FAR 52.234–4(c) that third-party system certification or for the EVMS requirements.
to state that the Government ‘‘will self assessment, as the basis for Response: The Councils have
conduct an IBR.’’ acceptance of an EVMS system, does not determined that the rule will be
provide sufficient Government implemented within the standard
Modified IBRs
wwhite on PROD1PC61 with RULES2
VerDate Aug<31>2005 19:49 Jul 03, 2006 Jkt 208001 PO 00000 Frm 00006 Fmt 4701 Sfmt 4700 E:\FR\FM\05JYR2.SGM 05JYR2
Federal Register / Vol. 71, No. 128 / Wednesday, July 5, 2006 / Rules and Regulations 38243
existing contracts by mutual agreement be reviewed during those periodic Comment: The commenter refers to a
on a case-by-case basis. reviews. sentence in the Background Section of
Comment: The commenter states that Response: The Councils believe that the Federal Register notice of this
the proposed rule uses the term the rule provides the necessary proposed rule, noting that the intent of
‘‘responsible Federal department or Government oversight of a contractor’s the Clinger-Cohen Act of 1996 was to
agency’’ but does not provide a EVMS, and that approval of changes, include Construction of Building and
definition. The commenter requests that done on a case-by-case basis, should be Facilities, not just information systems.
the rule be clarified to clearly delineate obtained prior to their implementation Response: The Councils believe that
roles and responsibilities for approval in a contractor’s EVMS, not as a no change to the text is necessary
and oversight of Contractor’s EVMS. retroactive action. because the proposed language
Response: The Councils have revised Comment: A number of commenters addresses all types of capital
the language in the provisions at FAR have stated that the Government’s investments, including construction of
52.234–2 and 52.234–3, and clause at access to records, including audit rights, buildings.
52.234–4 to clarify that the Cognizant are too broad. 52.234–X3 requires the Comment: Some commenters suggest
Federal Agency (CFA) (definition in Contractor to provide access to: ‘‘...all removing references to OMB Circular
FAR 2.101 and 42.003) is responsible for pertinent records and data... to permit A–109 in FAR Part 34.000. No reason
determining if a contractor’s EVMS is Government surveillance to ensure that was provided.
compliant with the contractual the EVMS conforms... with the Response: The Councils believe that
requirements, i.e., the guidelines in performance criteria....’’ The OMB Circular A–109 continues to
ANSI/EIA Standard - 748. commenters request that this language apply. OMB Circular A–11, Part 7
Comment: A number of commenters be removed from the clause. supplements OMB Circular A–109,
stated that the rule needed to be Response: The Councils believe that which has not been rescinded by OMB,
clarified regarding the use of the term governmental oversight for EVMS and is still available. Therefore, a
‘‘recognized,’’ i.e., which agency has compliance is provided at FAR 52.234– reference to OMB Circular A–11 has
cognizance, who within an agency is 4(f) and is necessary. Audit rights are been added to FAR 34.000.
qualified, what constitutes a provided via FAR 52.215–2, Audit and Comment: The commenter suggested
‘‘recognized’’ system, what Records-Negotiation. FAR 52.234–4 that the definition in Paragraph 2.101
documentation is required to does not expand upon these audit which states ‘‘Earned value management
‘‘recognize’’, and is ‘‘recognition’’ by rights. If third party proprietary rights system means a project management
one agency binding on another agency? are marked with proper legends, the tool...’’ implies that EVMS is a single
Response: The Councils have clarified Government is prohibited from tool and not a methodology that can
the rule by changing the term disclosure. successfully be accomplished with a
‘‘recognize’’ to ‘‘determined to be in variety of existing tools.
Training Response: The Councils believe that
compliance with the ANSI/EIA
Comment: A number of commenters the proposed language in the definition
Standard - 748.’’ The Cognizant Federal
stated that sufficient training must be is consistent with the Capital Planning
Agency (CFA) will determine if a
received by program managers and Guide and therefore should remain as
contractor’s EVMS is compliant with the
contracting officers. In addition, the stated.
guidelines in ANSI/EIA Standard - 748 Comment: The commenter suggested
numbers of program managers and
on a contractor business segment basis, including additional references to sites
contracting officers sufficiently trained
not an individual contract basis. where authoritative guidance and policy
will be significant.
Comment: A number of commenters Response: The Councils recognize on EVMS may be found.
suggested that FAR 34.005–2(b)(6) be that the use of EVM will require Response: The Councils do not
revised to change the terminology resources and training. As such the believe that a change to the proposed
‘‘meets’’ to ‘‘complies with.’’ Councils are working with Federal language is appropriate. The Councils
Response: The Councils agree with Acquisition Institute and Defense believe that implementing guidance and
the recommendation and have revised Acquisition University to provide EVMS instructions provided by the agencies
the language in FAR 34.005–2(b)(6) to training. will be sufficient.
require the use of an EVM System that Comment: A number of commenters
‘‘complies with’’ the guidelines of Miscellaneous Comments recommended a public meeting prior to
ANSI/EIA Standard – 748. Comment: For construction of publication of a final rule, and/or a
Comment: The commenter suggested buildings and facilities, the commenter second proposed rule.
substituting the term ‘‘EVMS criteria’’ suggests revising FAR Part 7 to require Response: The Councils believe that
for ‘‘EVMS guidelines’’. that a notice to proceed should be based on comments received, no
Response: The Councils believe the contingent on approved EVMS WBS, substantial changes were necessary in
use of the term ‘‘EVMS Guidelines’’ is approved S Curve Baseline, and formation of the final rule. Therefore no
more appropriate because that term is schedule. public meeting is necessary, and it is
used in ANSI/EIA - 748. Response: The Councils believe that appropriate to issue this final rule.
Comment: The commenter the proposed revision is not appropriate Comment: For a joint venture, the
recommends that the proposed clause for FAR Part 7 Acquisition Planning. If commenter suggests that the joint
be revised to remove the requirements a contractor does not have an EVM venture should use a single, mutually
that the contractor obtain approval of system that complies with ANSI/EIA agreed on EVMS. The commenter also
proposed changes to their EVMS from standard – 748, FAR 52.234–4 requires suggests that for teaming arrangements,
the Government prior to the contractor to take necessary actions the prime contractor should be
wwhite on PROD1PC61 with RULES2
implementation of the proposed change. to meet the negotiated milestones in responsible for meeting the EVMS
The commenter recommends that their EVMS plan. Whether these requirements.
surveillance be performed only every milestones are tied to the notice to Response: The Councils believe that
six months, after seven calendar days proceed will be a subject for negotiation use of a single EVMS system is not, and
notice, and that changes to their EVMS on an individual contract basis. should not be, required for prime
VerDate Aug<31>2005 19:49 Jul 03, 2006 Jkt 208001 PO 00000 Frm 00007 Fmt 4701 Sfmt 4700 E:\FR\FM\05JYR2.SGM 05JYR2
38244 Federal Register / Vol. 71, No. 128 / Wednesday, July 5, 2006 / Rules and Regulations
contractors and their subcontractors. B. Regulatory Flexibility Act above $20 million. The qualification of
Likewise, it is not appropriate to require ‘‘development’’ was added to the final rule at
The Regulatory Flexibility Act, 5 34.201. The FAR could have made fewer
a single EVMS for joint ventures or team U.S.C. 601, et seq., applies to this final contracts subject to EVMS by setting a
members in a teaming agreement. While rule. The Councils prepared a Final Governmentwide threshold, and by setting it
EVMS systems may differ, the reporting Regulatory Flexibility Analysis (FRFA), high. But this would be contrary to OMB’s
elements remain constant, and that is and it is summarized as follows: purpose in initiating the EVMS rule, which
what’s needed for management and is to allow OMB flexibility to require EVMS
oversight purposes. Final Regulatory Flexibility AnalysisEarned when OMB feels the stricter budgetary
Value Management Systems, (EVMS) discipline is necessary for a particular
Unrelated to the Proposed Rule This Final Regulatory Flexibility Analysis acquisition.
has been prepared consistent with 5 U.S.C. • Small businesses may avoid all EVMS
Comment: The responder submitted a 604. costs by choosing not to participate in EVMS
comment concerning an application for 1. Succinct statement of the need for, and solicitations, or may offset such costs to
a Federal job. the objectives of, the rule. implement a compliant EVM System through
Response: The Councils believe the Title V of the Federal Acquisition cost reimbursement on resulting Government
comment is not applicable to this rule. Streamlining Act of 1994 (FASA) requires contracts.
agency heads to approve or define the cost, • EVMS system. The cost for a small
Summary of Changes. As a result of performance, and schedule goals for major business setting up an EVMS compliant
the comments, changes to the proposed acquisitions and achieve, on average, 90% of system should be a one-time cost. No public
rule include the following: the cost, performance and schedule goals commenter gave specifics about the actual
1. FAR 7.105(b)(3) is revised to clarify established. The Clinger-Cohen Act of 1996 costs. In adopting the industry standard,
source-selection procedures, related to requires the Director of OMB to develop, as contractors are already moving to set up
part of the budget process, a process for EVMS systems. The construction industry is
the Acquisition Plan, when an agency analyzing, tracking, and evaluating the risks familiar with the concept of EVMS. The IT
decides to perform a pre-award and results of all major capital investments industry is rapidly adapting this industry
Integrated Baseline Review (IBR). for information systems for the life of the standard.
2. FAR 34.X01(a) is designated as system. OMB Circular A–11, Part 7, Planning, • The FAR rule provides that agencies
34.201(a) and is revised to require Budgeting, Acquisition, and Management of should not eliminate a contractor’s proposal
Capital Assets and its supplement, Capital because that business does not have a
EVMS in major acquisitions for Programming Guide, were written to meet the
development and in other acquisitions compliant EVMS. This was added to the final
requirements of FASA and the Clinger-Cohen rule at 34.201.In such a case, agencies can
in accordance with agency procedures. Act. OMB Circular A–11, Part 7, sets forth the offset costs for a small business to implement
3. FAR 34.X02(a) is designated as policy, budget justification, and reporting a compliant EVM System through the
34.202(a)and is revised to clarify that an requirements that apply to all agencies of the resulting contract. Agencies can also help by
agency shall conduct an IBR when Executive Branch of the government that are
restricting flow-down of the EVMS clause
subject to Executive Branch review, for major
EVMS is required. capital acquisitions. The proposed FAR
only to certain named subcontractors.
4. FAR 34.X03 is designated as 34.203 • Pre-award IBR’s. We anticipate un-
changes are necessary to implement Earned
reimbursed pre-award IBR’s will be unusual.
and is revised to provide prescriptive Value Management Systems (EVMS)
OMB wants the flexibility of having the pre-
language to clearly state pre-award and requirements in OMB Circular A–11, Part 7,
Planning, Budgeting, Acquisition, and award IBR tool available to agencies, and
post-award EVMS IBR requirements. would be responsible for giving extra money
Management of Capital Assets, and the
5. FAR 52.234–X1, 52.234–X2 and supplement to Part 7, the Capital to the agencies to pay for pre-award IBRs.
52.234–X3 are designated as 52.234–3, Programming Guide. Although the FAR is not forcing agencies to
52.234–2, and 52.234–4 respectively. 2. Summary of the significant issues raised reimburse pre-award IBR costs either for
The clause and provisions are clarified by the public comments in response to the large or small businesses; we anticipate
Initial Regulatory Flexibility Analysis, a agencies that want pre-award IBR’s will pay
to provide that the Cognizant Federal for them, for example as separately funded
Agency (CFA) is responsible for the summary of the assessment of the agency of
such issues, and a statement of any changes cost reimbursement contracts. This was
approval and oversight of contractor’s added to the final rule at 34.202. We also
made in the proposed rule as a result of such
EVMS. comments. expect the agencies to reduce the number of
6. FAR 34.X01(b) is designated as Some comments were received that proposals in the competitive range to avoid
34.201(b) and is revised to clearly state indicated that small businesses were affected. unnecessarily imposing costs on more than a
that offerors shall not be eliminated The comments received covered the few offerors. Small businesses may avoid
following issues: Many small businesses do these IBR costs entirely by choosing not to
from consideration for contract award bid on solicitations with non-reimbursed pre-
because they do not have an EVMS that not have compliant EVMS systems. It will
cost them money to set up an EVMS, and if award IBR costs. Small businesses can
is compliant with the ANSI/EIA the small business is a subcontractor, it may partially recover un-reimbursed pre-award
standards, provided they submit an cost the prime money to coordinate the IBR costs by bidding only on cost-
EVMS implementation plan with their EVMS systems. If the small business delays reimbursement contracts, which would allow
proposal. setting up an EVMS system until a desirable the recovery as overhead on this and later
7. The provisions at FAR 52.234– business opportunity occurs, the time delay contracts if the business wins these contracts.
may discourage contracting officers from 3. Description of and an estimate of the
2(b)(4) and 52.234–3(b)(4) are revised to number of small entities to which the rule
selecting them as prime contractors, or
provide for negotiated milestones in discourage prime contractors from selecting will apply.
offerors’ EVMS plans that indicate when them as subcontractors. It will cost money for An analysis of data in the Federal
an offeror anticipates its EVMS system a small business to perform a pre-award IBR; Procurement Data System (FPDS) on actions
will be compliant. these would be part of the business’s bid and and dollars on contracts above $20 million
This is not a significant regulatory proposal costs. It is harder on small for supplies and equipments, IT services and
action and, therefore, was not subject to businesses than large businesses to absorb construction, areas where EVMS is likely to
bid and proposal costs on contracts they do be applied, indicated that small business
wwhite on PROD1PC61 with RULES2
review under Section 6(b) of Executive not win. only received 3.8 percent of the $36.8 billion
Order 12866, Regulatory Planning and The assessment of these issues is as and 5.8 percent of the 345 actions. Because
Review, dated September 30, 1993. This follows: FPDS does not collect data on EVMS use, the
rule is not a major rule under 5 U.S.C. • The Councils anticipate that EVMS will data above is only an approximation of the
804. be required mainly for development contracts effect on small business. These numbers
VerDate Aug<31>2005 19:49 Jul 03, 2006 Jkt 208001 PO 00000 Frm 00008 Fmt 4701 Sfmt 4700 E:\FR\FM\05JYR2.SGM 05JYR2
Federal Register / Vol. 71, No. 128 / Wednesday, July 5, 2006 / Rules and Regulations 38245
include more than just IT development Dated: June 28, 2006 (iii) Whether offerors will be directly
contracts. Ralph De Stefano, compensated for the costs of
4. Description of the projected reporting, participating in a pre-award IBR.
Director,Contract Policy Division.
recordkeeping and other compliance
requirements of the rule, including an ■ Therefore, DoD, GSA, and NASA * * * * *
estimate of the classes of small entities amend 48 CFR parts 2, 7, 34, and 52 as (10) * * * If an Earned Value
which will be subject to the requirement and
set forth below: Management System is to be used,
the type of professional skills necessary for discuss the methodology the
preparation of the report or record. ■ 1. The authority citation for 48 CFR Government will employ to analyze and
The net effect of the rule is unknown at parts 2, 7, 34, and 52 are revised to read use the earned value data to assess and
this time. The rule is expected to have some as follows:
effect on small business concerns that do not
monitor contract performance. In
have EVM systems. The final rule only affects Authority: 40 U.S.C. 121(c); 10 U.S.C. addition, discuss how the offeror’s/
those small businesses that receive a contract chapter 137; and 42 U.S.C. 2473(c). contractor’s EVMS will be verified for
designated as a major acquisition. To compliance with the American National
alleviate burden on those small businesses PART 2—DEFINITIONS OF WORDS Standards Institute/Electronics
that do not have an EVM system, the rule was AND TERMS Industries Alliance (ANSI/EIA)
revised to make it clear that offerors shall not Standard–748, Earned Value
be eliminated from consideration for contract ■ 2. Amend section 2.101 in paragraph
Management Systems, and the timing
award because they do not have an (b) by adding, in alphabetical order, the
operational EVMS, provided they submit an and conduct of integrated baseline
definition ‘‘Earned value management
EVMS implementation plan with their reviews (whether prior to or post
system’’ to read as follows:
proposal.Other compliance requirements of award). (See 34.202.)
the rule are covered in paragraph 2. 2.101 Definitions. * * * * *
5. Description of the steps the agency has * * * * *
taken to minimize the significant economic PART 34—MAJOR SYSTEM
impact on small entities consistent with the (b) * * *
ACQUISITION
stated objectives of applicable statutes, Earned value management system
including a statement of the factual, policy, means a project management tool that ■ 4. Revise section 34.000 to read as
and legal reasons for selecting the effectively integrates the project scope follows:
alternative adopted in the final rule and why
of work with cost, schedule and
each one of the other significant alternatives 34.000 Scope of part.
to the rule considered by the agency which performance elements for optimum
project planning and control. The This part describes acquisition
affect the impact on small entities was
qualities and operating characteristics of policies and procedures for use in
rejected.
The FAR rule provides that agencies an earned value management system are acquiring major systems consistent with
should not eliminate a contractor’s proposal described in American National OMB Circular No. A–109; and the use
because of that business not having a Standards Institute/Electronics of an Earned Value Management System
compliant EVMS. This was added to the final Industries Alliance (ANSI/EIA) in acquisitions designated as major
rule at 34.201. Agencies can also help by acquisitions consistent with OMB
Standard–748, Earned Value
restricting flow-down of the EVMS clause Circular A–11, Part 7.
only to certain named subcontractors. Management Systems. (See OMB
■ 5. Amend section 34.005–2 by adding
Agencies can reimburse pre-award IBR costs Circular A–11, Part 7.)
paragraph (b)(6) to read as follows:
if OMB requires them and furnishes the * * * * *
money for them. Other alternatives suggested 34.005–2 Mission-oriented solicitation.
by public commenters were discussed in the PART 7—ACQUISITION PLANS
preamble, such as having a Governmentwide * * * * *
threshold of $50,000,000. This alternative is ■ 3. Amend section 7.105 by revising (b) * * *
not feasible as the purpose of the EVMS rule paragraph (b)(3) and amending (6) Require the use of an Earned Value
is to give OMB the tool to require stricter paragraph (b)(10) by adding two Management System that complies with
budgetary discipline where it sees fit, even in
sentences to read as follows: the guidelines of ANSI/EIA Standard–
a lower dollar contract. Alternatives of 748 (current version at time of
excluding small businesses entirely from 7.105 Contents of written acquisition solicitation). See 34.201 for earned
EVMS, or to give them a lower threshold plans. value management systems and
Governmentwide, will not meet the purpose
of the rule. * * * * * reporting requirements.
Interested parties may obtain a copy (b) * * * * * * * *
of the FRFA from the FAR Secretariat. ■ 6. Add subpart 34.2 to read as follows:
(3) Source-selection procedures.
The FAR Secretariat has submitted a Discuss the source-selection procedures
copy of the FRFA to the Chief Counsel Subpart 34.2—Earned Value
for the acquisition, including the timing Management System
for Advocacy of the Small Business for submission and evaluation of
Administration. proposals, and the relationship of Sec.
C. Paperwork Reduction Act evaluation factors to the attainment of 34.201 Policy.
the acquisition objectives (see Subpart 34.202 Integrated Baseline Reviews.
The Paperwork Reduction Act does 15.3). When an EVMS is required (see 34.203 Solicitation provisions and contract
not apply because the changes to the FAR 34.202(a)) and a pre-award IBR is clause.
FAR do not impose information contemplated, the acquisition plan must
collection requirements that require the 34.201 Policy.
discuss— (a) An Earned Value Management
approval of the Office of Management
and Budget under 44 U.S.C. 3501, et (i) How the pre-award IBR will be System (EVMS) is required for major
wwhite on PROD1PC61 with RULES2
VerDate Aug<31>2005 19:49 Jul 03, 2006 Jkt 208001 PO 00000 Frm 00009 Fmt 4701 Sfmt 4700 E:\FR\FM\05JYR2.SGM 05JYR2
38246 Federal Register / Vol. 71, No. 128 / Wednesday, July 5, 2006 / Rules and Regulations
(b) If the offeror proposes to use a conducted, the solicitation must include (ii) Distinguish between the offeror’s
system that has not been determined to the procedures for conducting the IBR existing management system and
be in compliance with the American and address whether offerors will be modifications proposed to meet the
National Standards Institute/Electronics reimbursed for the associated costs. If guidelines;
Industries Alliance (ANSI/EIA) permitted, reimbursement of offerors’ (iii) Describe the management system
Standard–748, Earned Value pre-award IBR costs is governed by the and its application in terms of the
Management Systems, the offeror shall provisions of FAR Part 31. EVMS guidelines;
submit a comprehensive plan for (iv) Describe the proposed procedure
34.203 Solicitation provisions and
compliance with these EVMS standards. for administration of the guidelines, as
contract clause.
Offerors shall not be eliminated from applied to subcontractors; and
(a) The contracting officer shall insert (v) Provide documentation describing
consideration for contract award
a provision that is substantially the the process and results of any third-
because they do not have an EVMS that
same as the provision at FAR 52.234–2, party or self-evaluation of the system’s
complies with these standards.
(c) As a minimum, contracting officers Notice of Earned Value Management compliance with the EVMS guidelines.
System – Pre-Award IBR, in (2) The offeror shall provide
shall require contractors to submit
solicitations for contracts that require information and assistance as required
EVMS monthly reports for those
the contractor to use an Earned Value by the Contracting Officer to support
contracts for which an EVMS applies.
(d) EVMS requirements will be Management System (EVMS) and for
review of the plan.
applied to subcontractors using the which the Government requires an (3) The Government will review and
Integrated Baseline Review (IBR) prior
same rules as applied to the prime approve the offeror’s plan for an EVMS
to award.
contractor. before contract award.
(b) The contracting officer shall insert
(e) When an offeror is required to (4) The offeror’s EVMS plan must
a provision that is substantially the
provide an EVMS plan as part of its provide milestones that indicate when
same as the provision at 52.234–3,
proposal, the contracting officer will the offeror anticipates that the EVM
Notice of Earned Value Management
determine the adequacy of the proposed system will be compliant with the
System – Post Award IBR, in
EVMS plan prior to contract award. ANSI/EIA Standard - 748 guidelines.
solicitations for contracts that require
the contractor to use an Earned Value (c) Offerors shall identify the major
34.202 Integrated Baseline Reviews.
Management System (EVMS) and for subcontractors, or major subcontracted
(a) When an EVMS is required, the effort if major subcontractors have not
Government will conduct an Integrated which the Government requires an
Integrated Baseline Review (IBR) after been selected subject to the guidelines.
Baseline Review (IBR). The prime Contractor and the
(b) The purpose of the IBR is to verify contract award.
(c) The contracting officer shall insert Government shall agree to
the technical content and the realism of subcontractors selected for application
the related performance budgets, a clause that is substantially the same as
the clause at FAR 52.234–4, Earned of the EVMS guidelines.
resources, and schedules. It should (d) The Government will conduct an
provide a mutual understanding of the Value Management System, in
solicitations and contracts that require a Integrated Baseline Review (IBR), as
inherent risks in offerors’/contractors’ designated by the agency, prior to
performance plans and the underlying contractor to use an EVMS.
contract award. The objective of the IBR
management control systems, and it PART 52—SOLICITATION PROVISIONS is for the Government and the
should formulate a plan to handle these AND CONTRACT CLAUSES Contractor to jointly assess technical
risks. areas, such as the Contractor’s planning,
(c) The IBR is a joint assessment by ■ 7. Add sections 52.234–2, 52.234–3, to ensure complete coverage of the
the offeror or contractor, and the and 52.234–4 to read as follows: contract requirements, logical
Government, of the— scheduling of the work activities,
52.234–2 Notice of Earned Value
(1) Ability of the project’s technical Management System –Pre-Award IBR. adequate resources, methodologies for
plan to achieve the objectives of the earned value (budgeted cost for work
As prescribed in 34.203(a) use the
scope of work; performed (BCWP)), and identification
(2) Adequacy of the time allocated for following provision:
NOTICE OF EARNED VALUE of inherent risks.
performing the defined tasks to MANAGEMENT SYSTEM – PRE-AWARD (End of provision)
successfully achieve the project IBR (JUl 2006)
schedule objectives; (a) The offeror shall provide 52.234–3 Notice of Earned Value
(3) Ability of the Performance documentation that the Cognizant Management System – Post Award IBR.
Measurement Baseline (PMB) to Federal Agency has determined that the As prescribed in 34.203(b) use the
successfully execute the project and proposed earned value management following provision:
attain cost objectives, recognizing the system (EVMS) complies with the NOTICE OF EARNED VALUE
relationship between budget resources, EVMS guidelines in ANSI/EIA Standard MANAGEMENT SYSTEM –POST AWARD
funding, schedule, and scope of work; – 748 (current version at time of IBR (JUl 2006)
(4) Availability of personnel, solicitation). (a) The offeror shall provide
facilities, and equipment when (b) If the offeror proposes to use a documentation that the Cognizant
required, to perform the defined tasks system that has not been determined to Federal Agency has determined that the
needed to execute the program be in compliance with the requirements proposed earned value management
successfully; and of paragraph (a) of this provision, the system (EVMS) complies with the
(5) The degree to which the offeror shall submit a comprehensive EVMS guidelines in ANSI/EIA Standard
management process provides effective plan for compliance with the EVMS –748 (current version at time of
wwhite on PROD1PC61 with RULES2
VerDate Aug<31>2005 19:49 Jul 03, 2006 Jkt 208001 PO 00000 Frm 00010 Fmt 4701 Sfmt 4700 E:\FR\FM\05JYR2.SGM 05JYR2
Federal Register / Vol. 71, No. 128 / Wednesday, July 5, 2006 / Rules and Regulations 38247
offeror shall submit a comprehensive 748 (current version at time of award), DEPARTMENT OF DEFENSE
plan for compliance with the EVMS the Contractor shall—
guidelines. GENERAL SERVICES
(1) Apply the current system to the
(1) The plan shall— ADMINISTRATION
contract; and
(i) Describe the EVMS the offeror
intends to use in performance of the (2) Take necessary actions to meet the NATIONAL AERONAUTICS AND
contracts; milestones in the Contractor’s EVMS SPACE ADMINISTRATION
(ii) Distinguish between the offeror’s plan approved by the Contracting
existing management system and Officer. 48 CFR Part 18
modifications proposed to meet the (c) The Government will conduct an [FAC 2005–11; FAR Case 2005–038; Item
guidelines; Integrated Baseline Review (IBR). If a II;Docket 2006–0020, Sequence 5]
(iii) Describe the management system pre-award IBR has not been conducted,
and its application in terms of the RIN 9000–AK50
a post award IBR shall be conducted as
EVMS guidelines; early as practicable after contract award.
(iv) Describe the proposed procedure Federal Acquisition Regulation; FAR
for administration of the guidelines, as (d) The Contracting Officer may Case 2005–038, Emergency
applied to subcontractors; and require an IBR at— Acquisitions
(v) Provide documentation describing (1) Exercise of significant options; or AGENCIES: Department of Defense (DoD),
the process and results of any third- General Services Administration (GSA),
(2) Incorporation of major
party or self-evaluation of the system’s and National Aeronautics and Space
modifications.
compliance with the EVMS guidelines. Administration (NASA).
(2) The offeror shall provide (e) Unless a waiver is granted by the
ACTION: Interim rule with request for
information and assistance as required CFA, Contractor proposed EVMS
comments.
by the Contracting Officer to support changes require approval of the CFA
review of the plan. prior to implementation. The CFA will SUMMARY: The Civilian Agency
(3) The Government will review and advise the Contractor of the Acquisition Council and the Defense
approve the offeror’s plan for an EVMS acceptability of such changes within 30 Acquisition Regulations Council
before contract award. calendar days after receipt of the notice (Councils) have agreed on an interim
(4) The offeror’s EVMS plan must of proposed changes from the rule amending the Federal Acquisition
provide milestones that indicate when Contractor. If the advance approval Regulation (FAR) to provide a single
the offeror anticipates that the EVM requirements are waived by the CFA, reference to acquisition flexibilities that
system will be compliant with the the Contractor shall disclose EVMS may be used to facilitate and expedite
ANSI/EIA Standard -748 guidelines. changes to the CFA at least 14 calendar acquisitions of supplies and services
(c) Offerors shall identify the major days prior to the effective date of during emergency situations.
subcontractors, or major subcontracted implementation. DATES: Effective Date: July 5, 2006.
effort if major subcontractors have not Comment Date: Interested parties
been selected, planned for application (f) The Contractor shall provide access
should submit written comments to the
of the guidelines. The prime Contractor to all pertinent records and data
FAR Secretariat on or before September
and the Government shall agree to requested by the Contracting Officer or
5, 2006 to be considered in the
subcontractors selected for application a duly authorized representative as
formulation of a final rule.
of the EVMS guidelines. necessary to permit Government
ADDRESSES: Submit comments
(End of provision) surveillance to ensure that the EVMS
identified by FAC 2005–11, FAR case
conforms, and continues to conform,
52.234–4 Earned Value Management 2005–038, by any of the following
with the performance criteria referenced
System. methods:
in paragraph (a) of this clause. • Federal eRulemaking Portal: http://
As prescribed in 34.203(c), insert the
following clause: (g) The Contractor shall require the www.regulations.gov/far. Follow the
EARNED VALUE MANAGEMENT subcontractors specified below to instructions for submitting comments.
SYSTEM (JUl 2006) comply with the requirements of this • Agency Web Site: http://
(a) The Contractor shall use an earned clause: [Insert list of applicable www.acquisition.gov/comp/far/
value management system (EVMS) that subcontractors.] ProposedRules/comments.htm. Click on
has been determined by the Cognizant llllllllll the FAR case number to submit
Federal Agency (CFA) to be compliant comments.
with the guidelines in ANSI/EIA llllllllll • E-mail: farcase.2005–038@gsa.gov.
Standard - 748 (current version at the llllllllll Include FAC 2005–11, FAR case 2005–
time of award) to manage this contract. (End of clause) 038 in the subject line of the message.
If the Contractor’s current EVMS has not • Fax: 202–501–4067.
[FR Doc. 06–5966 Filed 7–3–06; 8:45 am]
been determined compliant at the time • Mail: General Services
BILLING CODE 6820–EP–S
of award, see paragraph (b) of this Administration, Regulatory Secretariat
clause. The Contractor shall submit (VIR), 1800 F Street, NW, Room 4035,
reports in accordance with the ATTN: Laurieann Duarte, Washington,
requirements of this contract. DC 20405.
(b) If, at the time of award, the Instructions: Please submit comments
Contractor’s EVM System has not been only and cite FAC 2005–11, FAR case
wwhite on PROD1PC61 with RULES2
VerDate Aug<31>2005 19:49 Jul 03, 2006 Jkt 208001 PO 00000 Frm 00011 Fmt 4701 Sfmt 4700 E:\FR\FM\05JYR2.SGM 05JYR2