Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
-+-Mixed
--o- Average
--o- Unmixed
~ 6
.,
::::>
E s
::::>
0
~
E
::>
10
11
12
13
Sequence Position
FIGURE 1:
more formal and rigorous approach to sequencing vehicles on the line. Also, while earlier sequencing approaches were more concerned with leveling the work
load at each station on the line, as the company became
more involved in JIT production methods, the focus
shifted towards the impact of the final assembly sequence on the rate of demand for component parts.
These issues led to the development and adoption of
a heuristic procedure-a simplified version of Goal
Chasing I (GCl) used at Toyota (see [5]).
The basic logic behind Hyundai's heuristic procedure is that if the deviation between the expected use
of components (based on a constant usage rate) and
the actual use can be minimized, then the goals of minimizing the balance delays and smoothing the part usage rate can be realized. Smoothing or leveling the demand for component parts is essential to the pull
system of JIT production. If the final assembly sequence groups vehicles together which require common components, then the corresponding demand for
the components will be lumpy over the course of the
day. For example, Figures 1 and 2 provide illustrations
of relatively smooth consumption patterns and very
non-smooth consumption patterns for two component
parts.
A flowchart summarizing Hyundai's heuristic sequencing approach is presented in Figure 3. Starting
with the first position in the sequence list, an overall
measure of deviation is computed for each model type,
-+-Mixed
--o- Average
--o- Unmixed
3.5
-g
::3
2.5
c:J!l
::::>
:;;
.0
E 1.5
::>
0.5
10
11
12
13
Sequence Position
FIGURE 2:
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
21
TABLE 1:
Condition
Choices
1. Door Type:
2.
3.
4.
5.
Engine:
Trim Level:
Transmission (T/M):
Drive Type
6.
7.
8.
9.
10.
11 .
12.
Region:
Air Bag System:
Power Steering:
Anti-Lock Brakes
Rear Spoiler:
Delivery Wrapping:
Driving Instruction
Vehicle:
No
where
No
FIGURE 3:
Ri = average quantity of option j required per vehicle when averaged over the daily production schedule
= NJQ (Ni = total quantity of option j to produce all Q vehicles in the daily production
schedule)
Xi<k-l> =actual usage of option j for assembling the first
k-1 vehicles in the sequence
S;i = required quantity of option j for assembling
one unit of model type i.
The term (Xi<k-Jl + S;i) is equal to the actual usage of
option j for assembling the first k vehicles in the sequence if model type i is selected for the kth position
in the sequence list. On the other hand, the determination of the expected usage is based on achieving a
constant speed in consuming each component. The expected usage rate is an average units of that particular
option per vehicle. For example, if 600 of a total 860
units of the Accent model to be produced for the day
TABLE 2:
Model
Type
Door
Type
Engine
Trim
Level
TIM
Drive
Type
Air
Bag
Units
Required
A
B
4DR
3DR
3DR
4DR
5DR
13
13
13
15
15
GLS
GLS
GL
L
GL
A4
5
A4
5
A4
LH
RH
LH
LH
RH
0
0
4
2
3
3
c
D
E
22
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
require an air conditioner, the average or expected usage rate would be 600/860 or .70 unit per vehicle (i.e.,
R). Then, up to the kth vehicle in the sequence, k (0.70)
represents the total expected usage of air conditioners.
The expected usages for the other options are determined in a similar manner.
While Toyota's Goal Chasing Method I computes
the deviation Dik over all components feeding the
line, Hyundai's modified version does not calculate
the overall measure of deviation for the usage rates
for all parts. For example, if a given option, such as
transmission, has two possible choices (e.g., manual
or automatic), the calculation of Dik only includes
one of the two option choices. Hyundai reasons that
if each vehicle assembled requires a transmission,
and attention is focused on leveling the usage of one
type of transmission, then the usage rate of the other
transmission type will automatically be leveled.
Hyundai's approach was developed to provide a
reasonable sequence that approximates the result
produced by GC1 while reducing the computations
required.
1300 cc
3 Door
4 Door
AutoT/M
GLS Trim
GL Trim
Air Bag
LH Drive
1
1
1
1
1
1
1
1
X
X
9/ 13 - 0- 1
10/13 - 0 - 1
=
=
-4/13
5/ 13
-6 / 13
-5/13
-7/13
4/ 13
-4/13
-3 / 13
DAl = J(-4/13? + (5 / 13? + (-6/13? + (-5/13) 2 + (-7 /13) 2 + (4/13) 2 + (-4 / 13)2 + (-3/13?
= 1.066
To measure the impact of model type B being selected as the first vehicle in the sequence, 0 81 is calculated using
the same set of option choices from the previous calculation.
0 81
= 1.488
1.462, 0 01
1.294, DE1
1.682
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
23
TABLE 3:
Model Type
3-Door
4-Door
5-Door
1300 cc Engine
1500 cc Engine
L Trim
GL Trim
GLS Trim
Automatic T/M
Manual T/M
RH Drive
LH Drive
Air Bag
2
2
2
1300 cc
3 Door
4 Door
DA2
X
X
9/13 - 1 - 1 = - 8/13
5/13 - 0 - 0 = 10/13
7/13 - 1 - 1 = -12/13
2
2
2
2
2
X
X
X
X
8/ 13
6/13
4/13
9/13
10/13
1
1
0
1
1
1
1
0
1
1
=
=
=
=
=
-10 / 13
-14/13
8/13
- 8/ 13
- 6/13
2.132
1.243,
DE2 = 1.389
Auto TIM
GLS Trim
GL Trim
Air Bag
LH Drive
Finally, Table 4 shows a portion of an actual sequence list containing 860 Accent models to be produced by the line for a given day after the sequencing
procedure is completed considering all 12 factors currently used by Hyundai (see Table 1). This list is used
to specify the assembly sequence of vehicles.
CONCLUSION
By using the heuristic procedure, Hyundai generates six daily sequence lists for all of its passenger car
assembly lines. However, it must be pointed out that
the sequence lists do not get executed exactly as originally developed for a variety of reasons. In some
cases, the painted body storage area may not have
enough capacity to support the developed sequence
list and may force changes to the sequence. Also, during the actual assembly operations, the sequence often
must be changed at the line due to defective parts or
the discovery of unacceptable workmanship. In fact,
due to shop floor conditions, Hyundai may experience
up to a 15% change in the sequence list.
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
N
0
0
>
UJ
LL
N
MNMlOOOOlOOI'-NlO
cnw~ocnoocnlO<DN
M<D<:I"OlMI'-<OOl<O<O
0000000000
00
00
1'-
ACKNOWLEDGMENT
The authors wish to acknowledge the valuable comments and assistance of H. M. Koo, Executive Managing Director of Hyundai Motor Company.
<O<OMlOlOMNM<OM
C')l!)<:j"C')l!)C')<:f"C')lO<:t
0000000000
C')
0
C')
<1i
::0
OO<:I"N<DI'-OO<OOO<:I"N
T"""T"'""Q0T"""C\.10C'\JT"""Q
()()<(()()!ll!ll!ll()<(
00
:s.!:
"0
Ill
1--
a:
0
z
....J....J!I:....J....J....J....J....J....J!I:
....1
(/)
<(
IIIIIIIIII
REFERENCES
2.
C])
(/)
:::1
(/)
c:
0
3.
0c:
"0
c:
.c
"'
4.
t::
0
<:!"
<:!"
<:!"
lOlO<ClOlO<(lOIOlO<(
C/)C/)
C/)
.c
(/)
lO
C/)C/)
....J....J....J....J....J
....1
....1....1
(!J(!J(!J(!J<!J....J<!J....J<!J<!J
lOC')lOC')lOlOlOlOC')lO
....1
lO
T"'""T"'""T"'""T"'""T"""T"'""T"""T"""T"""T"""
C])
0
(ij
6.
7.
(/)
a:a:a:a:a:a:a:a:a:a:
a:
.E
C')l!)<:f"C')lOC')<:f"C')lO<:f"
C')
c:
0
E
c:
0000000000
lO~<O(ONI'-t--00<')00
C\IT"""<OC\JT"""C\J<.ON.,-<0
C')
0
<:tw<Dv<Dvw<:tw<D
00
00
=>::>=>::>=>=>::>=>::>=>
::>
oocnr--oocnoor--oocnt-,....r-NT"""T"""T"'""C\JT"'""T"'""N
o 0 T"'""oooT"'""o 0 .,....
(/)
';
"0
(/)
C])
C/)
-~
Z....JZ....IZZZZ....JZ
zv
0..
T"'""T"""T"'""T"""T"""VT"'""'VT"'""T"""
C\JC")("'')C\J('I')T"""C\JT"'""('I')("'J
0-J:LLO<I:OU:.O<CU.
>>=>>>>>>>=>
~NM<:I"IO<DI'-OOOlO
en
8.
"0
CIJC/)CIJ(fJCIJCIJC/)CIJC/)CIJ
ll.(l_ll.ll_ll.l'-t--Ol(l_ll.
5.
Line Sequencing Heuristic for Just-in-Time Production Systems." Journal of Operations Management 11, no. 1 (1993): 45-50 .
Hahn, C. K., E. A. Duplaga, and K. Y. Kim. "Production/Sales
Interface: MPS at Hyundai Motor." International Journal of Production Economics 37, no. 1 (1994): 5-17.
Kilbridge, M., and L. Wester. "The Assembly Line Model-Mix
Sequencing Problem." Proceedings of the Third International Conference on Operations Research, Oslo. Paris: English University
Press, 1963: 247.
Miltenburg, J. "Level Schedules for Mixed-Model Assembly
Lines in Just-in-Time Production Systems." Management Science
35, no. 2 (1989): 192-207.
Monden, Y. Toyota Production System. Norcross, GA: Industrial
Engineering and Management Press, 1983.
- - . "What Makes the Toyota Production System Really
Tick?" Industrial Engineering 13, no. 1 (1981 ): 36-46.
Okamura, K., and H. Yamashina. "A Heuristic Algorithm for the
Assembly Line Model-Mix Sequencing Problem to Minimize the
Risk of Stopping the Conveyor." International Journal of Production Research 17, no. 3 (1979): 233-247.
Thomopoulos, N. T. "Line Balancing-Sequencing for MixedModel Assembly." Management Science 14, no. 2 (1967): 59-75.
>
0
<D
00
C])
::0
"'Qi
1--
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
25
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.