M&DCPurchasing&SupplyChain:MaterialManagement
Master Scheduling
IntroductiontoMaterialManagement
MasterScheduling
Contents
MaterialRequirementsPlanning
CapacityManagement
1.
Introduction
2.
Definition
3.
Objectives
Purchasing
4.
PurposesofMPS
Forecasting
5.
6.
InputsforMPS
ProductionActivityControl
InventoryFundamentals
OrderQuantities
1.Introduction
IndependentDemandOrderingSystems
MasterproductionscheduleMPSisthenextstepinMPCthemanufacturingplanningandcontrol
PhysicalInventoryandWarehouseManagement process
PhysicalDistribution
MPSisameansofCommunication,aLinkorContractbetweenMarketingandManufacturing.
TheMPSreportincludesanATPAvailabletoPromisefiguretoenablerealistic,achievable
deliverypromisestobemadetocustomers.
Itisaplanofwhatistobeproducedandwhen
Itisanagreeduponplanbetweenmarketingandmanufacturing.
TheMPSisaPriorityPlanforManufacturing.
Itisnotmeanttoberigid.Itisthebasistomakechangesthatareconsistentwiththe
demandsofthemarketplaceandthecapacityofmanufacturing.
ItbreaksdownthePPintotheRequirementsforIndividualEndItems,ineachfamily,bydate
andquantity.
ThesumofallFamilyMPSitemsmustequaltheagreedSOPSalesandOperationsPlanforthat
Familyovereachplanningperiod(normallyamonthor4weekperiod).
MPSapplicationusuallydependsonproductionenvironment(MTS,ATO,andMTO)
TheMPSdrivestheMaterialRequirementsPlanMRP
ItemsplannedattheMPSlevelareexplodedbyMRPtoproducethedetailmaterialandcapacity
requirements.
Asascheduleofitemstobebuilt,theMPSandBOMBillsOfMaterialdeterminewhat
componentsareneededfrommanufacturingandpurchasing.
2.Definition
TheMPSisalineonthemasterschedulegrid(MPSMatrix)thatreflectstheanticipated
buildscheduleforthoseitemsassignedtothemasterscheduler.
Themasterschedulermaintainsthisschedule,andinturn,itbecomesasetofplanning
numbersthatdrivesMRPMaterialRequirementsPlanning.
Itrepresentswhatthecompanyplanstoproduceexpressedinspecificconfigurations,
quantities,anddates.
TheMPSisnotasalesitemforecastthatrepresentsastatementofdemand.
TheMPSmusttakeintoaccounttheforecast,theproductionplan,andotherimportant
considerationssuchasbacklog,availabilityofmaterial,availabilityofcapacity,and
managementpoliciesandgoals.(APICS)
3.Objectives
MPSObjectiveistoBalancetheDemand(Priorities)setbythemarketplacewiththeavailability
ofmaterials,labor,andequipment(Capacity)ofmanufacturing.
TheObjectiveindevelopinganMPSare:
toMaintainthedesiredlevelofCustomerServiceby
http://www.mdcegypt.com/Pages/Purchasing/Material%20Management/MPS.asp
1/8
9/1/2015
IntroductionMaterialManagement
maintainingfinishedgoodsInventoryLevelsor
bySchedulingtomeetcustomerdeliveryrequirements,
tomakethebestuseofmaterial,labor,andequipment,and
tomaintaininventoryinvestmentattherequiredlevels.
Constraintstheplanmustbewithinthecapacityofmanufacturing,andbewithintheguidelinesof
theproductionplan.
4.PurposesofMPS
DevelopmentofMasterProductionSchedule(MPS)
ProjectsInventory/Backloglevels
DrivesDetailedScheduling&planning
OrderPromising
AssistsinassigningjobPrioritiesonFacilityfloor
5.InputsforMPS
TheInformationNeededtodevelopanMPSisprovidedby:
TheProductionPlanPP,
Forecastsforindividualenditems,
ActualOrdersreceivedfromcustomersandforstockreplenishment,
InventoryLevelsforindividualenditems,and
CapacityRestraints
MoreDetailed
InventoryLevelandTargets(forMTS)
BacklogLevelsandTargets(forATO)
TimeFencepolicies
Interplantandintraplantorders
Servicepartsordersandforecasts
DistributionRequirements
PlanningBillsOfMaterialsBOM
Actualproductionandsupplylevels
6.Outputs
MasterProductionScheduleMPS
ProjectInventorylevelsPAB(forMTS)
ProjectedBackloglevels(forATO)
FutureavailabilityofproductsATP
Informationforpromisingfuturecustomerorders
7.Constraints
SumofMPSMasterProductionSchedulequantitiesequalsPPProductionPlan.
Efficientallocation,recognizing
SetupCostsand
InventoryHoldingCosts.
CapacityLimitations
8.RelationshiptoProductionPlanPP(AggregatePlanning)
MPSistheBridgebetweenthestrategicplanexpressedasthePPProductionPlan(aggregate
planningprocess)andtheexecutionofthatplanthroughdetailedmaterialandcapacityplans.
MPStakesInputfromPPProductionPlan.
MPSDisaggregatesthePPProductionPlan
http://www.mdcegypt.com/Pages/Purchasing/Material%20Management/MPS.asp
2/8
9/1/2015
IntroductionMaterialManagement
MPSisstatedinitems(enditem,enditemgroups,options)inordertofigureouttheMaterialsand
Capacityneeds.
AggregatePlan
MasterScheduling
Objective
SupplyRatebyProductFamily
AnticipateBuildSchedule
ItemPlanned
ProductFamily
EnditemorPlanningofBOM
PlanningHorizon
LongestleadtimeResource
LongestcumulativeleadtimeforEndItems
Constraints
Resourcecapacity
Criticalworkcenters
TimePeriods
Monthly
Weeklyormonthly
PlanningFocus
Productvolume
ProductMix
Processoutput
ProductionPlanPP
MasterProductionScheduleMPS
ExampleProblem
1.ProductionPlan:Familyoftwoproducts
Week
Forecast
Projected
Available
ProductionPlan
GivenData
500
1
300
2
350
3
300
4
250
Total
1200
450
250
350
250
300
250
300
250
1000
TotalProductionPlan=TotalForecast+EndingInventoryBeginningInventory
TotalProductionPlan=1200+300500=1000Unit
ProductionPlanperWeek=1000/4=250Unit
ProjectedAvailable=ProductionPlan+PreviousProjectedAvailableForecast
ProjectedAvailable1=250+500300=450Unit
ProjectedAvailable2=250+450350=350Unit
ProjectedAvailable3=250+350300=300Unit
ProjectedAvailable4=250+300250=300Unit
2.MasterSchedule:ProductA
Week
Forecast
Projected
Available
ProductionPlan
GivenData
200
1
200
2
300
3
100
4
100
Total
700
250
250
200
250
100
100
100
600
TotalProductionPlan=TotalForecast+EndingInventoryBeginningInventory
TotalProductionPlan=700+100200=600Unit
ProjectedAvailable=ProductionPlan+PreviousProjectedAvailableForecast
ProjectedAvailable1=250+200200=250Unit
ProjectedAvailable2=250+250300=200Unit
ProjectedAvailable3=0+200100=100Unit
ProjectedAvailable4=100+100100=100Unit
2.MasterSchedule:ProductB
Week
Forecast
Projected
Available
ProductionPlan
GivenData
300
1
100
2
50
3
200
4
150
Total
500
200
150
200
250
200
150
400
TotalProductionPlan=TotalForecast+EndingInventoryBeginningInventory
TotalProductionPlan=500+200300=400Unit
ProjectedAvailable=ProductionPlan+PreviousProjectedAvailableForecast
ProjectedAvailable1=0+300100=200Unit
ProjectedAvailable2=0+20050=150Unit
ProjectedAvailable3=250+150200=200Unit
ProjectedAvailable1=150+200150=200Unit
http://www.mdcegypt.com/Pages/Purchasing/Material%20Management/MPS.asp
3/8
9/1/2015
IntroductionMaterialManagement
9.DevelopingaMasterProductionSchedule
a.
DevelopaPreliminaryMPS.
b.
CheckthepreliminaryMPSagainstCriticalavailablecapacityinthePotentially
ConstrainingWorkCenter(RoughCutCapacityPlanning)RCCP
c.
ResolvedifferencesbetweenthepreliminaryMPSandcapacityavailability.
a.PreliminaryMasterProductionSchedule
Onhand=80units
Lotsize=100units
Period
Forecast
ProjectedAvailable
MPS
80
1
60
20
2
60
60
100
3
60
0
4
60
40
100
5
60
80
100
6
60
20
IfPreviousProjectedAvailableForecastThenMPS=0
IfPreviousProjectedAvailable<ForecastThenMPS=100
ProjectedAvailable=PreviousProjectedAvailable+MPSForecast
ProjectedAvailable1=80+060=20
ProjectedAvailable2=20+10060=60
ProjectedAvailable3=60+060=0
ProjectedAvailable4=0+10060=40
ProjectedAvailable5=40+10060=80
ProjectedAvailable6=80+060=20
b.RoughCutCapacityPlanningRCCP
CheckswhethercriticalresourcesareavailabletosupportthepreliminaryMPS
Criticalresourcesmayinclude:
Bottleneckoperations
Labor
Criticalmaterials
Itissimilartoresourcerequirementsplanningusedintheproductionplanningprocess,exceptwe
nowworkwithaproductandnotafamilyorproducts.
Theresourcebillisforasingleproduct
ExampleProblem
MasterProductionSchedule
Week
Total
ProductA
ProductB
40
25
40
15
120
20
10
30
20
80
4
7.5
24
31.5
Total
60
96
156
ResourcesBillforBottleneckWorkCenterWC20
workCenter
WC20
HoursperUnit
A
B
0.5
1.2
Answer:RequiredCapacityinworkinghoursonWC20
Week
A
B
TotalHours
1
20
24
44
2
12.5
12
24.5
3
20
36
56
c.ResolutionofDifferences
Comparethetotaltimerequiredtotheavailablecapacityoftheworkcenter.
Ifavailablecapacityisgreaterthantherequiredcapacity,theMPSisworkable.
Ifnot,methodsofincreasingcapacityhavetobeinvestigated
overtime,
additionalworkers,
routingthroughalternateworkcenters,or
subcontracting
Ifnot,revisetheMPSanddecreasedemand
http://www.mdcegypt.com/Pages/Purchasing/Material%20Management/MPS.asp
4/8
9/1/2015
IntroductionMaterialManagement
10.EvaluatingtheMPS
ResourceUse:
IstheMPSwithincapacityrestraintsineachperiod?
CustomerService:
Willduedatesbemet?
Willdeliveryperformancebeacceptable?
Cost
Istheplaneconomical?
Willexcesscostsbeincurred?
OT,subcontracting,expediting,transportation,etc.
11.MasterScheduleDecisions
a.MPSDecisionLevel
Iftoomanyitemsareincluded,itwillleadtodifficultiesinforecastingandmanagingtheMPS.
IneachoftheManufacturingEnvironmentsMakeToStockMTS,MakeToOrderMTO,and
AssembleToOrderATOMasterschedulingshouldtakeplacewherethesmallestnumberof
productoptionsexists
b.DifferentMPSenvironments
MTSMakeToStockproducts"A"Structure
Alimitednumberofstandarditemsareassembledfrommany
components.
Televisionsandotherconsumerproductsareexamples.
TheMPSisusuallyascheduleoffinishedgoodsitems.
FocusonForecasting,ServiceLevel,fillrate(unit,line,
ororderfillrate)andResourceUtilization.
UseManufacturingBasedMPSMatrix(finishedproductslevel)
Itemno:
Description:
20
OnHand
LeadTime:
2 periods
DemandTimeFenceDTF:
SafetyStock
PlanningTimeFencePTF:
50
LotSizing:
PTF
DTF
3
8
Period
10
11
Forecast
20
21
20
22
24
26
28
28
25
25
20
CustomerOrders
19
20
21
21
25
24
20
18
16
12
10
31
10
38
13
37
31
31
ProjectedAvailableBalancePAB
20
AvailableToPromise
CumulativeAvailabletoPromise
MasterProductionSchedule
10
50
14
50
16
20
50
36
50
11
28
64
50
MTSMakeToOrderproducts/ETOEngineerToOrder"V"Structure
Manydifferentenditemsaremadefromasmallnumberof
components.
Customtailoredclothesareanexample.
TheMPSisusuallyascheduleoftheactualcustomer
orders.
FocusonDeliveryTimeandProductOption
UseGrossRequirementsMPSMatrixisBasedonRaw
Material(SingleLevelMPSRecordProcessing)
ProductA
Grossrequirements
Scheduledreceipts
http://www.mdcegypt.com/Pages/Purchasing/Material%20Management/MPS.asp
Period
1
2
3
4
5
6
30 30 30 30 30 30
30
5/8
9/1/2015
IntroductionMaterialManagement
Projectedavailablebalance 50 50 20
Plannedorderrelease
Q=lotforlotLT=0SS=10
10
20
10
30
10
30
10
30
ATOAssembleToOrderproducts."X"Structure
Manyenditemscanbemadefromcombinationsof
basiccomponentsandsubassemblies.
Wehaveverysmallamountofmodulesenablealarge
amountofendproducts.
Insteadofendproducts,fewermodules(options)are
forecastedandcontrolled.
Throughthis,betterforecastaccuracyisachieved.
FocusonDeliveryTimeandProductOption,
Forecasting,ServiceLevel,fillrate(unit,line,or
orderfillrate)andResourceUtilization
UseTowLevelMPSMatrix
Examplecompanymanufacturespaintfromabasecolorandaddstintstoarrivetomanyfinal
colors.
Productionisplannedatthelevelofthebasecolorandthetentints.
Onceacustomer'sorderisreceived,thebasecolorandtherequiredtintscanbecombined
(assembled)accordingtotheorder.
Family
Week
S&OP
CustomerOrders
ATP
40
40
40
40
20
16
12
10
18
28
40
Itemno:
LeadTime:
Description:
Buffer:
DemandTimeFence
DTF:
PlanningTimeFenceDTF:
LotSizing:
LFL
Week
ItemForecast
ProductForecast=60%S&OP
ActualDemand=60%CarCO
TotalDemand
ProjectedAvailableBalance
PAB
0
AvailableToPromise
CumulativeAvailabletoPromise
MasterProductionSchedule
PTF
2
6
c.Finalassemblyschedule(FAS).
Thisisascheduleofwhatwillbeassembled.
It is used when there are many options and it is difficult to forecast which combination the
customerswillwant.
Masterproductionschedulingisdoneatthecomponentlevel
Thefinalassemblytakesplaceonlywhenacustomerorderisreceived.
TheFASschedulescustomerordersastheyarereceivedandisbasedonthecomponents planned
intheMPS.
ItisresponsibleforschedulingfromtheMPSthroughfinalassemblyandshipmenttothecustomer.
http://www.mdcegypt.com/Pages/Purchasing/Material%20Management/MPS.asp
6/8
9/1/2015
IntroductionMaterialManagement
Theplanninghorizonisthetimespanwhichcoversaperiodatleastequaltothetimerequiredto
accomplishtheplan(seefigure3.5).Theplanninghorizonisusuallylongerbecausethelongerthehorizon,
thegreaterthevisibilityandthebettermanagementsabilitytoavoidfutureproblemsortotakeadvantage
ofspecialcircumstances.Asaminimum,theplanninghorizonforafinalassemblyschedulemustinclude
timetoassembleacustomersorder.Itdoesnotneedtoincludethetimenecessarytomanufacturethe
components.ThattimewillbeincludedintheplanninghorizonoftheMPS.
8.PlanningHorizon
Theamountoftimethemasterscheduleextendsintothefuture.Thisisnormallysettocovera
minimumofcumulativeleadtimeplustimeforlotsizinglowlevelcomponentsandforcapacity
changesofprimaryworkcentersorofkeysuppliers.AIPCS
PlanningHorizon>MinimalCumulativeLeadPlanningHorizon>MinimalCumulative
LeadTime
Minimum=Manufacturingleadtime(=Cumulativeleadtime)
Planninghorizonisusuallylongertoallowvisibility
Insidethecumulativeleadtimeordersareconsideredasfirm,i.e.changescanonlybe
madeafterthoroughanalysis
ProductionPlanning,MasterScheduling,andSales
Theproductionplanreconcilestotalforecastdemandwithavailableresources.
TheMPSisbuiltfromforecastsandactualdemandsforindividualenditems.It
reconcilesdemandwiththeproductionplanandwithavailableresourcestoproducea
planthatmanufacturingcanfulfill.TheMPSisaplanforwhatproductioncanandwill
do.
Inamaketostockenvironment,customerordersaresatisfiedfrominventory.
However,inmaketoorderorassembletoorderenvironments,demandissatisfied
fromproductivecapacity.Salesanddistributionneedtoknowwhatisavailableto
satisfycustomerdemand.Asordersarereceived,theyconsumetheavailable
inventoryorcapacity.Anypartoftheplanthatisnotconsumedbyactualcustomer
ordersisavailabletopromisetocustomers.
Availabletopromise(ATP)isthatportionofafirmsinventoryandplanned
productionthatisnotalreadycommittedandisavailabletothecustomer(see
exampleson57,58&59).TheATPiscalculatedbyaddingscheduledreceiptsto
thebeginninginventoryandsubtractingactualordersscheduledbeforethenext
scheduledreceipt.
Ascheduledreceiptisanorderthathasbeenissuedeithertomanufacturingortoa
supplier.Ifcustomerordersaregreaterthanthescheduledreceipts,thenthe
previousATPisreducedbytheamountneeded.
http://www.mdcegypt.com/Pages/Purchasing/Material%20Management/MPS.asp
7/8
9/1/2015
IntroductionMaterialManagement
Projectedavailablebalance(PAB)iscalculatedbasedonthelargerofactual
customerordersandtheforecast.ThePABiscalculatedinoneoftwoways,
dependingonwhethertheperiodisbeforeorafterthedemandtimefence.For
periodsbeforethedemandtimefence:
PAB=priorperiodPABoronhandbalance+MPScustomerorders
Forperiodsafterthedemandtimefence,forecastwillinfluencethePABsoitis
calculatedusingthegreateroftheforecastorcustomerorders.
PAB=priorperiodPAB+MPSgreaterofcustomerordersorforecast
Thedemandtimefenceisthenumberofperiods,beginningwithperiod1,inwhich
changesarenotexceptedduetoexcessivecostcausedbyscheduledisruption.
Theplanninghorizonmustbeatleastaslongasthecumulativeleadtimeforthe
productstructure.Thecostofmakingachangeincreasesandthecompanys
flexibilitydecreasesasproductiongetsclosertothedeliverytime.Faroffchanges
canbemadewithminimalcostordisruptiontomanufacturing,butthenearerto
deliverydate,themoredisruptiveandcostlychangeswillbe.
ChangestotheMPSwilloccurduetocustomerordercancellationorchange,
changingcapacity,supplierproblems,andexcessiveprocessscrap.
Changestoproductionschedulescanresultincostincreasesduetorerouting,
rescheduling,extrasetups,expediting,andbuildupofWIPinventorydecreased
customerserviceandlossofcredibilityfortheMPSandtheplanningprocess.
ChangestotheMPSmustbemanagedanddecisionsmadewithfullknowledgeof
thecostsinvolved.
Frozenzonecapacityandmaterialsarecommittedtospecificorders,changes
resultinexcessivecosts,andsoseniormanagementapprovalisrequiredtomake
changes.Theextentofthefrozenzoneisdefinedbythedemandtimefence.
Slushyzonecapacityandmaterialsarecommittedtolessextent.Salesand
manufacturingnegotiatechanges.Theextentoftheslushyzoneisdefinedbythe
planningtimefence.
LiquidzoneAnychangecanbemadetotheMPSaslongasitiswithinthelimits
setbytheproductionplan.