Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Engineering
CONFIDENTIAL
doc. no.
2.187.735 -
page
0.1
doc. type
80
date
2005-06-30
dept
E-PX
author
F. Winkel/fwi
proj. no.
405.014
subject
abbr.
BOM
Distribution
book no.
address
Mr. Cleary
Mr. Balasundaran
Mr. Schouwenaars
Mr. Geuzebroek
File
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
0.2
date
2005-06-30
Revisions
rev.
description
Page
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Date
initials
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
0.3
date
2005-06-30
CONTENTS
1
2.1
2.2
2.2.1
2.2.2
2.3
2.4
3.1
3.1.1
3.1.2
3.2
3.2.1
3.2.2
Flocculant................................................................................................................. 3.3
3.2.3
Butane...................................................................................................................... 3.3
3.2.4
3.2.5
3.2.6
3.2.7
3.2.8
3.2.9
3.3
3.3.1
3.3.2
3.3.3
3.3.4
3.3.5
3.3.6
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
0.4
date
2005-06-30
3.3.7
3.3.8
3.3.9
3.3.10
3.3.11
3.3.12
4.1
Safety....................................................................................................................... 4.1
4.2
Environment............................................................................................................. 4.2
4.3
Health....................................................................................................................... 4.2
4.4
5.1
5.1.1
5.1.2
5.1.3
5.1.4
5.2
5.2.1
5.2.2
5.2.3
5.2.4
5.2.5
5.2.6
5.2.7
5.2.8
5.2.9
5.2.10
5.3
5.4
5.4.1
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
0.5
date
2005-06-30
5.4.2
5.4.3
5.5
5.5.1
5.5.2
5.5.3
5.6
5.6.1
5.6.2
5.6.3
5.6.4
5.6.5
5.7
5.7.1
5.7.2
5.7.3
5.7.4
5.7.5
Shut down in case of failure of liquor supply from the dredges.............................. 5.32
5.7.6
5.7.7
5.7.8
5.7.9
5.7.10
5.7.11
5.7.12
5.7.13
5.7.14
5.7.15
5.7.16
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
0.6
date
2005-06-30
6.1
6.2
6.2.1
6.2.2
6.3
6.4
6.4.1
6.4.2
6.5
6.5.1
6.5.2
6.5.3
6.5.4
6.6
6.7
6.7.1
6.7.2
6.7.3
6.7.4
6.8
Basic operating manual roller mill and calciner section ......................................... 6.10
6.9
7.1
7.1.1
7.1.2
7.1.3
7.1.4
7.1.5
7.2
7.2.1
7.2.2
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
0.7
date
2005-06-30
7.2.3
7.2.4
7.2.5
7.2.6
7.2.7
7.2.8
7.2.9
7.2.10
7.2.11
7.2.12
7.2.13
7.2.14
7.2.15
7.2.16
7.2.17
7.2.18
7.2.19
7.2.20
7.2.21
7.3
7.4
7.4.1
7.4.2
7.4.3
7.4.4
7.5
7.5.1
7.5.2
7.5.3
7.5.4
7.6
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
0.8
date
2005-06-30
7.6.1
7.6.2
7.6.3
7.7
7.7.1
Buffering of slurry in case of capacity variation of first and second stage.............. 7.53
7.7.2
7.7.3
7.7.4
7.7.5
7.7.6
7.7.7
7.7.8
7.7.9
Start-up and shut down of hot water tank 520-TK-091 .......................................... 7.60
7.7.10
7.7.11
7.7.12
7.7.13
7.7.14
7.7.15
7.7.16
7.7.17
8.1
8.2
8.2.1
Feed to static fluidbed dryer for pure soda ash plant (PID 600-01) ......................... 8.3
8.2.2
Static fluidbed dryer for pure soda ash plant (PID 600-02) ...................................... 8.3
8.2.3
Air supply and air heating for static fluidbed dryer for pure soda ash plant (PID 60003)............................................................................................................................ 8.4
8.2.4
Monohydrate dryer dust and condensate discharge (PID 600-04) .......................... 8.5
8.2.5
8.3
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
0.9
date
2005-06-30
8.4
8.4.1
8.4.2
8.4.3
8.4.4
8.5
8.5.1
8.5.2
8.6
8.6.1
8.6.2
8.7
8.7.1
8.7.2
8.7.3
8.8
8.8.1
8.8.2
8.8.3
8.8.4
8.8.5
9.1
9.1.1
9.1.2
9.1.3
9.1.4
9.1.5
9.1.6
9.1.7
9.2
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
0.10
date
2005-06-30
9.2.1
9.2.2
9.2.3
9.2.4
9.2.5
9.2.6
9.3
9.4
9.5
9.6
9.7
9.8
9.9
10
10.1
Washery................................................................................................................. 10.1
10.2
10.3
Crystallization......................................................................................................... 10.1
10.4
10.5
10.6
11
11.1
11.2
11.3
11.4
APPENDIX 1:
APPENDIX 2:
APPENDIX 3:
LIST OF ACRONYMS
APPENDIX 4:
UNIT SYSTEM
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
1.1
date
2005-06-30
rev
INTRODUCTION
This manual describes the basic principles of the start-up and operation of the Pure Soda
ash plant at Magadi Kenya.
The design of this plant is based on process development by Brunner Mond in
cooperation with package unit vendors and on the experience with other comparable units
(e.g. crystallization, drying).
These basic operating procedures have been compiled by Akzo Nobel Engineering and
are based on operating experience at Akzo Nobel and the basic design for Magadi pure
soda ash plant as reported in the Basic Engineering Package.
Furthermore, information from package unit vendors FFEM, HPD, L&T Niro (LTN) and
HDO and from some equipment vendors is also included.
In this manual, input from package unit vendors of mill&calciner, crystallization and drying
are included. This manual, together with the instructions of the different equipment
suppliers, will serve as a guideline for:
training of operating personnel
preparing detailed operating instruction
commissioning and first start-up of the plant
The manual is divided into 11 chapters:
Chapter 1: Introduction
Chapter 2 4: General information on plant operations, specifications of chemicals and
utilities appearing in the process, and safety provisions
Chapter 5 8: Process description, process characteristics and detailed information on
normal operation, start-up situations and deviation from normal operating conditions
Chapter 9: Emergency situations of the plant
Chapter 10: Information on first start-up and commissioning of the plant
Chapter 11: Basic information on maintenance of the plant; for detailed information
refer to information from vendors.
Operating manuals for section 100 (Dredging), Section 700 (Screening), Section 800
(Storage and load-out), Section 900 (Utilities) and Electrical Power Generation are
provided separately from this manual.
Other manuals relevant to this plant include:
Analytical Manual
Magadi Soda Company Safety Manual
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
2.1
date
2005-06-30
rev
PLANT OPERATION
2.1
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
2.2
date
2005-06-30
rev
Na2CO3.H2O. Fixed insolubles are again separated in an elutriation leg, and subsequently
the product is deliquored and washed on a centrifuge.
A liquor purge is provided in the first stage crystallization section. This purge serves to
keep sodiumsulfate concentration below 3 wt% to prevent contamination of the final
product. Sodiumsulfate is formed in small quantities in the calciner section.
In the fluid bed dryer the monohydrate is dried and subsequently dehydrated to anhydrous
Na2CO3 (dense soda ash), oversize is then removed in the screening section and the
product is then transferred to the storage section and rail load-out section.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
2.4
date
2005-06-30
rev
2.2
2.2.1
Location
The plant is located on the Eastern shore line of Lake Magadi, next to an existing plant of
Magadi Soda Company.
.
Elevation
m
596
Ambient pressure
kPa
94.9
Temperature max. (shade) C
41
min. (shade) C
16
Design dry bulb
C
36
Design wet bulb
C
22
Precipitation
mm/y
455
Days rainfall
d/y
73
Evaporation
mm/y
4105
Average design wind
km/h
3.6
Maximum wind
km/h
161
Seismic zone
2A
2.2.2
Plant structure
In principle all process equipment is located outside in steel structures.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
2.5
date
2005-06-30
rev
2.3
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
2.6
date
2005-06-30
rev
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
2.7
date
2005-06-30
rev
2.4
Operating philosophy
The dredge supplies trona slurry to the washery. In case the dredge does not supply trona
(unexpected failure or scheduled maintenance), the dredge pump will continue to supply
liquor. In this case trona will be supplied to the dredge product tank from the raw trona
stockpile, via the dry reclaim route.
There is a small buffer between washery (200 section) and the roller mill & calciner
(section 400) in the roller mill feed bin 200-BN-085. In case the washery is out of
operation, CRS can be supplied from the CRS stockpile by front end loader to this bin.
When the above route is used to feed the roller mill, the liquor feed to the washery has to
be maintained, because liquor is required for ESP dust recycle and for cooling of second
stage vent condenser.
Product from the calciner section is directly introduced to the first stage crystallizer. This
means that failure of either of these sections, results in a production stoppage of both
sections.
The product from the first stage crystallizer is collected in the second stage crystallizer
feed tank 520-TK-005. This tank provides the possibility to run the second stage for a
limited time without running the first stage crystallizer. When the first stage is running
without the second stage, then the solids concentration in the feed tank will increase. This
can only carried out be for a short duration in order give the operating team sufficient time
to put the first stage in stand-by mode. Also dilution with filtrate from the 1st stage
centrifuge is not desirable, which would lead to product quality issues.
Turndown of washery
The washery can be turned down to 50% of normal operating capacity in case one of the
centrifuges is not in operation. If required, additional feed to the mill can be supplied with
CRS from CRS stockpile.
As the product from the classifier can be partly diverted to intermediate stockpile 200-ZC030, the dredge feed can continue at 100% rate, but the operator has to remove product
from stockpile 200-ZC-030 whilst operating in this mode. As mentioned previously liquor
supply rate has to be maintained in order to supply liquor at the required flow rates to the
ESP dust recycle and second stage vent condenser.
Turndown of mill and calciner unit
The equipment within the Mill and calciner unit all run at the same capacity. In case the
first stage crystallizer operates with one centrifuge, then the unit will run at 50% capacity.
However, running the calciner unit below 70% can be problematic (decreased
conversion). If this situation occurs in practice, optimum condition will have to be found in
order to maximize rate in an effort to maintain product quality (increase feed over the one
running centrifuge as much as possible to keep the calciner running at as high possible
capacity).
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
2.8
date
2005-06-30
rev
Turndown of crystallizer
First stage crystallizer can be turned down to 50% of normal rate in case one centrifuge is
not running. The calciner has to reduce capacity as well (see above). Feed tank 200-TK005 provides time to decrease the second stage capacity to 50% also (stop one
centrifuge). If the second stage is running at 50%, the first stage will have to be reduced to
50% as well and in this case the tank provides time for the operators to respond. At
turndown the removal of impurities will be less efficient which lowers product quality.
Turndown of fluid bed dryer
The dryer has no real buffer capacity and it will be turned down to 50% if crystallizer is
turned down.
Buffering time of main buffer tanks of the process:
Tag number
200-TK-005
200-TK-030
Equipment name
Dredge product tank
CRS wash tank
Operating
Normal Operating
volume
capacity
1)
93 m
11 minutes
130 m
95 m
22 minutes
120 m
Buffering time
200-ZC-040
CRS stockpile
5000 ton
5000 ton
47 hours
200-BN-085
100 m3
50 m3
60 minutes
520-TK-005
269 m
800-BN-020
Product Silo
5000 ton in
A/B/C
190 m
total
1)
Normal operating capacity is defined as follows: from normal operating level to low level
2)
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
2 hours
4 days
2)
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
3.1
date
2005-06-30
rev
3.1
3.1.1
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
3.2
date
2005-06-30
rev
3.1.2
wt%
wt%
wt%
wt%
wt%
wt%
> 85
< 15
< 0.5
<5
25
< 10
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
3.3
date
2005-06-30
rev
3.2
3.2.1
Lake brine
Composition:
Na2CO3
NaHCO3
Na2SO4
NaCl
NaF
Specific gravity
pH
Temperature
Viscosity
3.2.2
wt%
wt%
wt%
wt%
wt%
C
mPas
wet
14.0
0.5
0.1
9.0
0.3
1.20
11
35
6
dry season
18.0
0.1
0.1
12.0
0.3
1.30
11
35
6
Flocculant
Solution of 0.5 wt% guar gum.
Viscosity
mPas
400
Supply of guar gum by 50 kg bags (HOLD).
3.2.3
Butane
Quality: LPG with 60 % butane and 40 % propane.
Used as oil burner ignition fuel.
Supplied in 22.5 kg gas bottles.
3.2.4
Trisodium phosphate
Used as antiscalant.
Supply by 50 kg bags
3.2.5
Morpholine/Ammonia
Added to boiler make-up water and condensate.
Supply by 20 liter bottles.
3.2.6
Biocide
Added to cooling tower water.
Supply by 20 liter bottles.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
3.4
date
2005-06-30
rev
3.2.7
Flocon 100
Added to boiler make-up water.
Supply by 20 liter bottles.
3.2.8
3.2.9
100
Diatomaceous earth
Type: Celite Hyflo Supercel
Density
< 100 m
Median cake pore size
pH
Supply by 20 kg bags.
kg/m3
wt%
m
-
160
95
7
10
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
3.5
date
2005-06-30
rev
3.3
Specification of utilities
3.3.1
3.3.2
MJ/kg
wt%
wt%
cSt
C
C
kg/m3
vol%
wt%
43
0.25
3.7
180
65
24
985
0.75
0.15
ppm wt
ppm wt
ppm wt
ppm wt
ppm wt
ppm wt
ppm wt
2.9
34
28
9
8
2
12
MJ/kg
wt%
cSt
C
C
kg/m3
vol%
wt%
wt%
wt%
mg KOH/g
mg KOH/g
wt%
44.8
1.8
10 (IP test method)
66
12
915
0.25
0.02
0.02
0.45
0.5
2.9
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
3.6
date
2005-06-30
rev
3.3.3
Steam 15 bar
Generated ISBL.
Process design temperature
Process design pressure
Mechanical
design temperature
design pressure
Supply by pipeline.
3.3.4
210
15.5
C
bar
236
18.5
C
bar
150
3
C
bar
210
6
Steam 3 bar
Generated ISBL.
Process design temperature
Process design pressure
Mechanical
design temperature
design pressure
Supply by pipeline.
3.3.5
C
bar
C
bar
bar
Mechanical
design temperature C
design pressure
bar
3.3.6
- 20
7
5.5
50
8
Electric power
24 V dc for instrument power
110 V 1 ph. 50 Hz
240 V 1 ph. 50 Hz
415 V 3 ph. 50 Hz
5.5 kV 3 ph. 50 Hz for > 150 kW.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
3.7
date
2005-06-30
rev
3.3.7
Process water
Quality: Fish-springs water
Composition:
wt%
Na2CO3
NaHCO3
wt%
Na2SO4
wt%
NaCl
wt%
NaF
wt%
SiO2
ppm
Suspended solids
ppm
pH
Temperature
C
Specific gravity
Supply by pipeline via pipeline.
3.3.8
0.83
0.66
0.011
0.63
0.014
200
270
9.4
30
1.012
3.3.9
Purge water
Generated ISBL.
Quality: Filtered process water.
Pressure
bar
Supply by pipeline.
3.3.10
10
Potable water
Quality: treated raw water.
Composition (analysis 2001-06-25 and 2001-07-25):
HCO3mg/l
49
SO42mg/l
11.54
CO2
mg/l
nil
CO32mg/l
< 6.00
Clmg/l
10.79
Fmg/l
0.34
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
3.8
date
2005-06-30
rev
PO43+
-P
Na
NH4+
NO3Mn
Cd
Cr
Pb
Cu
Zn
Fe
Mg
Ca
K
Total Si
Hg
Se
As
Ba
Total dissolved solids
Fixed suspended solids
Total alkalinity
pH
Conductivity
Total Coliforms
E. Coli
Pressure
Temperature
Supply by pipeline.
mg/l
0.62
mg/l
3.4
mg/l
0.28
mg/l
2.48
ppm
0.027
ppm
0.020
ppm
nil
ppm
nil
ppm
nil
ppm
0.336
ppm
0.193
ppm
2.783
ppm
4.759
ppm
2.798
ppm
15.0
ppm
< 0.001
ppm
<0.01
ppm
<0.05
ppm
<0.001
wt%
0.02
wt%
< 0.001
mg/l
0.049
7.24
S
200
MPN/100 ml
nil
MPN/100 ml
nil
bar
C
30
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
3.9
date
2005-06-30
rev
3.3.11
Raw water
Composition:
Composition (design conditions):
ppm
61
HCO32SO4
ppm
8.08
CO2
ppm
10
CO32ppm
< 6.0
Cl
ppm
600
Fppm
15
3PO4 -P
ppm
1.87
Na+
ppm
100
NH4+ as N
ppm
0.6
NO3- as N
ppm
0.6
Mn
ppm
0.1
Cd
ppm
0.015
Cr
ppm
nil
Pb
ppm
nil
Cu
ppm
nil
Zn
ppm
0.024
Fe
ppm
1.4
Mg
ppm
2.76
Ca
ppm
2.74
K
ppm
12
Total Si
ppm
15.0
Hg
ppm
< 0.001
Se
ppm
<0.01
As
ppm
<0.05
Ba
ppm
<0.001
Total dissolved solids
ppm
1500
Total suspended solids
ppm
56
Total hardness (as CaCO3) ppm
90
Total alkalinity
ppm
50
pH
7.35
Conductivity
S
230
Total Coliforms
MPN/100 ml 200
E. Coli
MPN/100 ml 60
Pressure
Temperature
Supply by pipeline.
bar
C
8
30
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
3.10
date
2005-06-30
rev
3.3.12
5.5
1
30
45
50
10
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
4.1
date
2005-06-30
rev
4.1
Safety
Storage of raw materials and finished products
There are no special requirements for the materials used in the plant. The storage of
fuel oil for the calciner is existing. However, new intermediate storage between the
existing storage and the plant will be provided.
Auxiliary materials (like filter aid or guar) in bags or other types of packaging have to be
stored in an ordered fashion. All materials have to be labeled clearly to prevent using in
the wrong application.
Lay out
The degree of hazards according the DOWs F&EI is in the range of light. For the
layout of the plant no special arrangements are foreseen in terms of safety distances.
Fire safety
No flammable/combustable materials, except for small amounts of fuel oil and LPG, are
present in the plant. There will be fire extinguishing provisions (hydrants).
Area classifications
Storage area of LPG will is a classified area. LPG is used in burner of steam boiler and
calciner burner. In the vicinity of the burner, area classification for instrumentation and
other equipment is not applicable.
No other flammable liquids or gases are used in the process area, therefore no area
classification is executed based on flammable vapors. The way of processing guar gum
and the limited amounts indicates that an area classification to prevent dust explosions
is not needed.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
4.2
date
2005-06-30
rev
4.2
Environment
The Plant is designed is in accordance with the requirements of the World Banks
Pollution Prevention & Abatement Handbook, 1998 Edition, the U.S Occupational Safety
and Health Administration and the American Conference of Governmental Industrial
Hygienists.
Emission limits for new sources are:
Particulates
mg/Nm3
SO2
mg/Nm3
NOx
mg/Nm3
50
2000
460
Health
Safety showers and eye-washers are placed at appropriate locations and a map is
included within the safety regulations identifying them.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
4.3
date
2005-06-30
rev
4.4
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
SODIUM CARBONATE
1. IDENTIFICATION OF THE SUBSTANCE AND COMPANY
Product Name
Chemical Name
Alternative Name
Chemical Formula
:
:
:
:
SODIUM CARBONATE
Sodium Carbonate
Soda Ash Light, Dense, Heavy, Granular
Na2CO3
Manufacturing Sites
Company Address
:
:
2. COMPOSITION/INFORMATION ON INGREDIENTS
Sodium Carbonate
CAS Number
EC Number
ID Number (Annex 1)
:
:
:
497 19 8
207 838 8
011 005 00 - 2
3. HAZARDS IDENTIFICATION
General
Inhalation
Skin Contact
Eye Contact
Irrigate eye thoroughly with eye wash solution or clean water for at least 10 minutes.
Eyelids should be held away from the eyeball to ensure thorough rinsing.
Obtain medical attention if necessary.
Ingestion
Brunner Mond PO Box 4 Winnington Northwich Cheshire CW8 4DT Tel +44(0)1606 724000 Fax +44 (0)1606 781353 www.brunnermond.com
5. FIRE-FIGHTING MEASURES
Flash Point
Not applicable
Extinguishing Media
Special Hazards
Non-combustible
Not applicable
Environmental Precautions
Prevent discharges into the environment (rivers, water courses, sewers etc.)
See Section 13 for disposal details
Storage
Store in a cool dry place ( in humid conditions the product will absorb moisture from the atmosphere and this
will eventually cause caking and loss of free flowing properties)
Do not store together with acids
Non-combustible
Brunner Mond PO Box 4 Winnington Northwich Cheshire CW8 4DT Tel +44(0)1606 724000 Fax +44 (0)1606 781353 www.brunnermond.com
Not listed by H&SE (Guidance Note EH40) or ACGIH (Ref.UK EH40 Limits for Nuisance Dust)
Recommended Limits: OES 10mg/m3 (total dust) (8hr TWA)
5mg/m3 (respirable dust) (8hr TWA)
Respiratory Protection
In the case of high dust levels wear suitable respiratory protective equipment, ie. dust mask or respirator
Hand Protection
Wear suitable chemical resistant protective gloves for frequent or prolonged operations
Eye Protection
Appearance
Colour
Odour
Melting Point
Powder, granules
White
Odourless
851 c
OxidisingProperties
Vapour Pressure
Specific Gravity
Bulk Density
Flash Point
Not applicable
Solubility in water
Flammability
Auto ignition temp.
Explosive properties
Non flammable
Not applicable
None known
Explosion Limits
Not applicable
None known
Not applicable
2.53
Light ash approx.
550kg/m3
Dense ash approx.
1000kg/m3
71 g/l @ 0 c
471 g/l @ 32 c
Not available
11.4 (1% w/w soln @20c
Not applicable
Not applicable
Not applicable
Conditions to avoid
Materials to avoid
Brunner Mond PO Box 4 Winnington Northwich Cheshire CW8 4DT Tel +44(0)1606 724000 Fax +44 (0)1606 781353 www.brunnermond.com
: 4090 mg/kg.
: Sodium carbonate is a permitted food additive, however in large doses
corrosion of the mucous membranes of the gastrointestinal tract may occur.
: 2300 mg/m3/2hr.
: High concentrations of dust may irritate the nasal membranes and respiratory
tract.
Eye Irritation
: Irritating to eyes
: May cause corneal damage, permanent damage is unlikely.
Skin Irritation
Prolonged or repeated inhalation of high dust concentrations may cause ulceration of the nasal septum,
which may in time progress to perforation or complete destruction of the nasal cartilage.
Not teratogenic
Bio-degradeability
Aerobic/Anaerobic degradation
Packaging
14.TRANSPORT INFORMATION
Brunner Mond PO Box 4 Winnington Northwich Cheshire CW8 4DT Tel +44(0)1606 724000 Fax +44 (0)1606 781353 www.brunnermond.com
Land Transport
Sea Transport
Air Transport
ADR Class
RID Class
TREM-card
Hazard identification number
Proper shipping name
IMO/IMDG
Packing group
EMS
Marine pollutant
Proper shipping name
ICAO-TI/IATA-DGR Class
Proper shipping name
Not restricted
Not restricted
Not relevant
None
None
Not relevant
Not relevant
None
None
Not restricted
None
Not relevant
No
Not relevant
Class
UN number
MFAG
Not relevant
None
Not relevant
Not restricted
None
UN number
Packing number
None
None
EC Labelling
Chemical description
207 838 8
Xi Irritant
R36 : Irritating to eyes
S22 : Do not breathe dust
S26 : In case of contact with eyes, rinse immediately
With plenty of water and seek medical advice
National Legislation/Regulations
: WGK 1,
: Listed
16.OTHER INFORMATION
The information only concerns the above mentioned product and is not necessarily valid if used with other
product(s) or in any process. It does not constitute a hazard assessment and should not be used in place of the
users own assessment of workplace risks as required by other health and safety legislation. The information is to
our best present knowledge correct and complete and is given in good faith but without warranty.
The following sections contain revisions or new statements: 1,2,3,4,5,6,7,8,9,10,11,12,13,14,15
Date of Issue : 21/10/2002
Revision: 03
Brunner Mond PO Box 4 Winnington Northwich Cheshire CW8 4DT Tel +44(0)1606 724000 Fax +44 (0)1606 781353 www.brunnermond.com
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.1
date
2005-06-30
rev
200 SECTION
5.1
Process description
5.1.1
Introduction
The washery serves to remove a large portion of impurities from the dredged trona,
resulting in crushed refined soda (CRS).
In this chapter the process of the washery is described. In order to have a complete
picture also the OSBL dredging is described in this chapter.
5.1.2
5.1.3
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.2
date
2005-06-30
rev
overflow liquor to ESP dust conveyor 400-CV-040 where it picks up the ESP dust. From
here the resulting slurry is returned to 200-TK-010.
In the event that the dredge is unable to meet the solid feed requirements, a dry handling
system will receive material from a front-end loader to allow feeding from a stockpile. The
dredge product tank can also receive fines bank material. Trona and fines bank material
will be reclaimed from the stockpiles by front-end loader with a maximum capacity of 115
t/h solids. The front-end loader discharges onto raw trona reclaim conveyor 200-CV-010
via the raw trona reclaim hopper 200-BN-010. Raw trona reclaim screen 200-SN-010
removes lumps >32 mm from the raw trona. The raw trona is further transported by raw
trona undersize conveyor 200-CV-015 and slurried in the dredge product tank. Metal
contamination is removed by magnet 200-MA-015, which is located on top of the
undersize conveyor. Lumps are transported via raw trona oversize chute 200-CH-010 to
the raw trona oversize bunker 200-ZC-015.
5.1.4
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.3
date
2005-06-30
rev
containing 0.7 t/h of solids at 20 wt% solids density, will be pumped by tailings settler
underflow pumps 200-PP-050/1 to the tailings tank 900-TK-250.
The tailings settler overflow brine will dilute the spiral classifier product from 75% to 30%
solids in the CRS wash tank. The tank, with a volume of 125 m3, will receive 110 t/h of
solids and will provide about 30 minutes of surge capacity to smooth fluctuations in solids
flow from the dredge. The CRS wash tank slurry will be pumped by CRS hydrocyclone
feed pumps 200-PP-030/1/2 to CRS hydro-cyclones 200-CY-065/6. The hydro-cyclones
provide further insolubles rejection, whilst pre-thickening the slurry to 60 wt% solids. The
overflow from the hydro-cyclones is fed together with the CRS centrifuge centrate to the
classifier by CRS centrate pump 200-PP-070/1.
The underflow from the CRS hydro-cyclones is directed to the CRS centrifuges
200-CF-070/1. The centrifuges are designed to provide a 93 wt% solids cake. The cake
will be washed with 2-4 displacements of process water to reduce the sodium chloride and
insolubles. Centrate liquor will be pumped via the CRS centrate tank 200-TK-070 to the
spiral classifier. The product CRS cake product will contain 5 to 6 wt% moisture with the
following solids analysis: 97.5% trona, 2% sodium fluoride, up to 0.45% insolubles, and
about 0.05% sodium chloride.
The washery is sized to produce 104.3 ton/h dry base CRS. This will generate more CRS
than the downstream equipment can process. It will therefore be necessary to
continuously divert a portion of the CRS by CRS stockpile conveyor 200-CV-090 to
Intermediate CRS stockpile 200-ZC-090. From this stockpile CRS is transported to CRS
stockpile 200-ZC-040 by front end loader. CRS will be reclaimed from the stockpile as
required.
From conveyor 200-CV-090 running in opposite direction, CRS is transported via CRS
conveyor 200-CV-075 to CRS conveyor 200-CV-080. CRS conveyor belt 200-CV-080 will
transfer the CRS to the roller mill feed bin 200-BN-085. From this bin the CRS is fed to the
roller mill (section 400) via roller mill belt weigh feeder 200-FD-085.
Any metal contamination is removed by magnet 200-MA-080, which is located at the top
of CRS conveyor 200-CV-080.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.4
date
2005-06-30
rev
5.2
Normal operation
5.2.1
5.2.2
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.5
date
2005-06-30
rev
5.2.4
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.6
date
2005-06-30
rev
5.2.6
5.2.7
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.7
date
2005-06-30
rev
Centrate is pumped from 200-TK-070 to the washery sieve bend feed chute 200-CH-020
by CRS centrate pump 200-PP-070/1. The flow is controlled by the level of the CRS
centrate tank 200-LICSA-0701. At low low level the CRS centrate pumps are
automatically tripped.
In case the feed to both centrifuges is diverted back to the CRS wash tank 200-TK-030,
pump 200-PP-070/071 has to be stopped, to prevent pumping against a closed head.
Stopping the feed to both centrifuges has therefore to be avoided.
5.2.8
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.8
date
2005-06-30
rev
5.2.9
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
5.9
date
2005-06-30
rev
5.2.10
Setting list
Instrument
Unit
200-DIA-0101
kg/m
200-DICSA-0401
kg/m
Normal
Alarm
1380
L 1330
1440
L 1390
Trip/Switch
H 1430
H 1490
HH 1550
200-EIA-I-0101
kW
65
H 75
200-EISA-I-0301
kW
TBD
HH TBD
200-EI-I-0306
kW
TBD
200-EIA-I-0401
kW
73
H 85
200-EISA-I-0601/02
kW
50
H 63
200-EISA-I-0901
kW
check
HH 1550
HHTBD
HH 70
H TBD
HH TBD
200-FICA-0401/0402
m3/h
130
145 (check)
200-FICA-0601/02
m3/h
5.4
L 2.5
200-FI-0704
l/h
0.5
200-FICA-0801
kg/h
106700
200-HIC-0201
TBD
200-HIC-0301/02
RPM
TBD
200-HIC-0901/02
RPM
TBD
200-KIS-0601/0606
TBD
TBD
200-LICSA-0101
90
HH TBD
101000
LL 15
LL 15
L 35
H 95
200-LSA-0102
200-LICSA-0201
90
HH 100
HH 100
LL 15
LL 15
L 25
H 95
200-LISA-0401
85
LL 15
LL 15
L 60 (check)
H 95
HH 100
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
5.10
date
2005-06-30
rev
Instrument
Unit
Normal
Alarm
200-LICA0501
90
L 15
Trip/Switch
H 95
200-LSA-0603/0604
TBD
TBD
200-LICSA-0701
90
L TBD
LL 15
LL 15
L 25
H 95
200-LISA-0801
mm 1)
LLL -1000
LLL -1000
LL -500
LL -500
L 1000
H 3100
HH 4000 (check)
200-LSA-0802
mm
200-LICSA-0902
2)
HH 1600-3200
90
LL 15
2)
LL 15
L 25
H 95
200-LI-0901
mm
3)
2000 (4 discs
visible)
200-SSA-0001
L TBD
L TBD
200-SSA-0002
L TBD
L TBD
200-SSA-0301
L TBD
L TBD
200-SSA-0303
L TBD
L TBD
200-SSA-0801
L TBD
L TBD
200-SSA-0802
L TBD
L TBD
200-SSA-0803
L TBD
L TBD
200-SSA-0807
L TBD
L TBD
200-TISA-0601/0602
55
H 60
HH 65
200-XISA-0601/0602
mm/s
H 9
HH 14
g/ton solids
100
Purgerators on instrument
l/h
20
l/h
50
connections
Purgerators on pump seals
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
5.11
date
2005-06-30
rev
5.3
Logic functions
In this section the logic functions that act on equipment and the automatic actions of
valves are described.
Logical functions that act on equipment are for example:
Start conditions and running conditions
Process switches
Safety switches (dry run protection on pumps, speed alarm on conveyors)
Also the way equipment can be started and stopped is provided in this table. This is apart
from a thermal overload which is provided on all motors. The thermal overload shuts off
the motor directly (hardwired from MCC).
Logic functions acting on equipment:
Equipment/Action
Start
Stop
Signal description
Type
Start/
Switch/
Running
Interlock
condition
200-CV-010
Locally by
Locally by
hand
hand and
automatic
200-SN-010 in operation
time delayed 200-SSA-0001
X
Stop
activated
Stop
0001 activated
200-SN-010
Locally by
Locally by
hand
hand and
Misalignment 200-GA-0001
200-CV-015 running
Alarm
X
automatic
200-CV-015
HH current on 200-EISA-I-
Locally by
Locally by
hand
hand and
0101 of 200-AG-005
automatic
activated
Stop
Stop
activated
Stop
0002 activated
200-AG-005
Misalignment 200-GA-0002
Alarm
Alarm
Locally by
Locally by
HH current 200-EIA-I-0101
hand
hand
activated
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
5.12
date
2005-06-30
rev
Equipment/Action
Start
Stop
Signal description
Type
Start/
Switch/
Running
Interlock
condition
200-PP-005/006
Locally by
Locally by
LL level of 200-LICSA-0101
hand
hand and
activated
Stop
automatic
Dregde feed to
HH level of 200-LSA-0102
Divert to
200-TK-005
activated
wash-out
paddock
200-PP-
Locally by
Locally by
LL level of 200-LICSA-0201
010/011/012
hand
hand and
activated
Stop
automatic
200-CR-025
200-CI-030
Locally by
Locally by
hand
hand
Locally by
Locally by
hand
hand and
automatic
density 200-DICSA-0401 is
high high
By hand
By hand on
Drive to direction
on DCS
DCS and
of 200-TK-030
and
automatic
automatic
density 200-DICSA-0401 is
high
agitator 200-AG-030 is in
operation
density 200-DICSA-0401 is
Start
low
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Start
Stop
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
5.13
date
2005-06-30
rev
Equipment/Action
Start
Stop
Signal description
Type
Start/
Switch/
Running
Interlock
condition
200-GA-030
By hand
By hand on
Drive to direction
on DCS
DCS and
of 200-ZC-030
and
automatic
200-CV-030 in operation
automatic
density 200-DICSA-0401 is
Start
high high
Start
Start
of operation
Stop
activated
200-CV-030
Locally by
Locally by
hand
hand and
automatic
Stop
activated
Stop
0301 activated
200-PP-
Locally by
Locally by
030/031/032
hand
hand and
Misalignment 200-GA-0302
LL level of 200-LISA-0401
Alarm
Stop
activated
automatic
200-PP-040/041
Locally by
Locally by
hand
hand
200-CF-070./071
Locally by
Locally by
hand
hand and
automatic
200-PP-070/071
Locally by
Locally by
hand
hand and
200-CV-090 running
HH current on 200-EISA-I-
Switch feed
0601/0604
to bypass
LL level of 200-LISA-0701
Stop
activated
automatic
200-CV-070
Locally by
Locally by
hand
hand and
automatic
200-CV-090 in operation
time delayed 200-SSA-0801
X
Stop
activated
Stop
0801 activated
Misalignment 200-GA-0802
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Alarm
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
5.14
date
2005-06-30
rev
Equipment/Action
Start
Stop
Signal description
Type
Start/
Switch/
Running
Interlock
condition
200-CV-090
By hand
By hand on
Drive to direction
on DCS
DCS and
of 200-CV-075
and
automatic
automatic
200-CV-075 in operation
Start
Stop
Stop
activated
Stop
0807 activated
200-CV-090
By hand
By hand on
Drive to direction
on DCS
DCS and
of 200-ZC-090
and
automatic
Misalignment 200-GA-0807
Alarm
Start
Stop
Stop
activated
automatic
Stop
0807 activated
200-CV-075
Locally by
Locally by
hand
hand and
automatic
Misalignment 200-GA-0807
time delayed 200-SSA-0803
Alarm
Stop
activated
Stop
0803 activated
200-CV-080
Locally by
Locally by
hand
hand and
automatic
Misalignment 200-GA-0803
time delayed 200-SSA-0802
Alarm
Stop
activated
Stop
0802 activated
200-FD-085
Locally by
Locally by
hand
hand and
automatic
Misalignment 200-GA-0804
400-AL-010 in operation
feed release signal from
Alarm
X
X
Stop
activated
Stop
0806 activated
200-PP-050/051
200-TM-050
Locally by
Locally by
hand
hand
Locally by
Locally by
hand
hand
HH torque on 200-EISA-I0901
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Lift rake
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
5.15
date
2005-06-30
rev
Equipment/Action
Start
Stop
Signal description
Type
Start/
Switch/
Running
Interlock
condition
200-PP-060/061
Locally by
Locally by
hand
hand and
LL level of 200-LICSA-0902
activated
automatic
Action
Cause
200-LCV-0501
Close
200-XSV0601
Close
On
On
200-XSV-0602
200-XSV-0604
200-XSV-0605
Open
Close
Open
HH level of 200-LSA-0102
200-CF-070 out of operation
flushing of 200-CF-070
200-CV-070 out of operation
200-CF-070 out of operation
flushing of 200-CF-070
200-CV-070 out of operation
200-CF-071 out of operation
flushing of 200-CF-071
200-CV-070 out of operation
200-CF-071 out of operation
flushing of 200-CF-071
200-CV-070 out of operation
200-LISA-0801 high switch is not activated
BN-080
Red light at 200BN-080
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Stop
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.16
date
2005-06-30
rev
5.4
Start up
5.4.1
Check free rotation of all pumps. Check that all pump suction lines are closed.
Check that the discharge line of each pump is open, in order to keep purging with
purge water and to prevent pressurizing the system and line damage. Pumps should
be lined up as follows:
200-PP-005/06: flow to 200-CY-005
200-PP-010/11/12: flow to 200-TK-250 (check that bypass of 200-LCV-0201 is
closed), lines to 520-HX-010 and 400-CV-040 remain closed
200-PP-030/31: flow to 200-TK-030 (via CRS slurry return)
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.17
date
2005-06-30
rev
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.18
date
2005-06-30
rev
16
17
18
19
20
21
22
At this moment the washery section is filled with liquid completely and liquor circulation is
running. The next procedure can now be followed in order to deliver trona slurry from the
dredge.
23
24
25
26
27
28
29
30
Control liquor flow to sieve bend 200-SN-020 and crusher 200-CR-025 with manual
regulator valves. Start crusher 200-CR-025.
Open up feed to 200-CH-020 and 200-CI-030 from 200-PP-060/061
Start classifier screw. See supplier information for exact procedure. Check that 200GA-030 is directed towards 200-ZC-030 (GBS-0301B active).
Start 200-CV-075, direct 200-CV-090 to 200-ZC-090, start 200-CV-070
Provide washing water to centrifuges 200-CF-070/071. By adjusting the set point of
200-FICA-0601/02.
Start 200-PP-050.
Start taking in slurry from the dredge.
When classifier operates stable, divert 200-GA-030 towards 200-TK-030
(200-GBS-0301A active)
Now slurry is flowing to the centrifuges, and the centrifuge cake is being diverted to
intermediate stockpile 200-ZC-090.
31
32
Make sure roller mill feed bin 200-BN-085 is ready for use.
If CRS from centrifuge is of good quality, start 200-CV-080 and 200-CV-075. Set
direction of 200-CV-090 towards 200-CV-075
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.19
date
2005-06-30
rev
33
Weigh feeder 200-FD-085 to the roller mill section can be activated, when there is
sufficient CRS in bin 200-BN-085 (200-LISA-0801 > L) and when there is a feed
release signal from the roller mill section. When high level switch 200-LISA-0801 is
activated, 200-CV-090 is set back into the direction of 200-ZC-090 again.
Before the mill and calciner section comes into operation, the following start-up sequence
for the dust conveyor system applies.
40 Place setpoint of 200-LICSA-0201 to a high value. Check suction valve of spare
pump is closed 200-PP-010/011/012. Open suction valve and close discharge valve,
start up 200-PP-011/012 and open discharge valve. Open flow to 400-CV-040 as
fast as possible considering the level in 200-TK-010. ESP dust conveyor 400-CV040 requires pressure, otherwise backflow can occur in ESP Dust Hopper 400-BN040. (Note: The line volume is significant compared to the tank volume of 200-TK010).
41 As soon as circulation line is filled, (return flow to 200 TK-010), put level control on
normal setpoint and let system transport air for some time before adding dust.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.20
date
2005-06-30
rev
5.4.2
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.21
date
2005-06-30
rev
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
are open at the same time. Specifically for installed spare pumps: check that purge
water can be drained to a process connection.
Make sure all flushing connections are closed
Start 200-PP-060/61. Adjust flow to 200-CH-020 manually.
Start pump of 200-PP-040/041. Adjust flow to 200-DE-050 manually (200-LICSA0902).
Start guar dosing (510-MP-070/71) and check guar dosing rate (refer to setting list).
Start 200-AG-005 and 200-AG-030 if stopped
Check slurry discharge from 200-PP-030/031/032 is directed via cyclone bypass
(200-XSV-0601 and 0604 closed and 200-XSV-0602 and 0605 open). Start 2 pumps
of 200-PP-030/031/032. Check that flow is present at 200-FI-0401/02 and outlet of
CRS recycle. Adjust flow with 200-HIC-0402/03/04 in such a way that a constant
level can be maintained in 200-TK-030
Start 200-PP-070/71. Adjust level in 200-TK-070 by hand (200-LICSA -0701).
Start 200-CV-090 in the direction of intermediate stockpile 200-ZC-090
Start-up centrifuge (oil system, main drive etc.; info from vendor)
Direct slurry to cyclone inlet (open 200-XSV-0601 and 200-XSV-0604 and close
200-XSV-0602 and 200-XSV-0605)
Open 200-DCV-0401 and adjust flow. Close supply from 200-PP-060/61 to 200-CH020.
Start pump 200-PP-010/11. Adjust level (200-LICSA 0201), so that a constant level
is maintained in 200-TK-010. Check that cyclone bottom outlet (200-HCV-0201) is
fully open.
Start 200-PP-005/006.
Start lake liquor brine intake from No5. dredger.
Check bypass valve of 200-LCV-0501 is closed. Adjust flow from 200-PP-040/41 to
200-TK-005 (200-LICA-0501).
Now No5. dredger can start delivering trona slurry as described in procedure for initial
start-up (see step 23 in section 5.4.1).
5.4.3
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.22
date
2005-06-30
rev
3
4
5
6
7
8
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.23
date
2005-06-30
rev
5.5
Shut down
5.5.1
Going to standby
Solids supply from No5. dredger is stopped and liquor supply continues in order to keep
the rest of the plant in operation.
1
2
3
4
5
5.5.2
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.24
date
2005-06-30
rev
At the end of this procedure, the shut down of dredge product tank and overflow tank is
described.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
Stop solids supply from the dredge and or dry reclaim and maintain liquor supply.
After approx. 10 minutes only liquor is fed to 200-TK-005 (time will change with
position of dredge). Reduce position of 200-HIC-0201.
Switch 200-DCV-0401 to manual control and keep level in 200-TK-030 constant
When classifier 200-CI-030 is empty of trona, stop screw drive.
Start feeding CRS from stockpile to 200-BN-080 (see CRS reclaim, section 5.7.3)
When 200-TK-030 is empty of trona, stop centrifuges 200-CF-070/71 (procedure
from vendor) and stop process water supply (200-FICA-0601/02)
Underflow valve 200-HIC-0201 of 200-CY-005 closes automatically when no more
solids are supplied to the cyclone.
Stop 200-PP-050/51.
Stop 200-PP-030/31/32 and 200-AG-030 if required.
Stop 200-PP-070/071.
Stop 200-CR-025.
Stop 200-PP-060/061 when low level in 200-TK-060 (this will stop liquor supply to
boiler scrubber).
Stop Guar supply (510-MP-070/71).
Stop 200-PP-040/041.
Stop 200-CV-070, 200-CV-090, 200-CV-075.
Start flushing lines (particularly slurry lines) as soon as possible after stopping a
pump.
If settler remains full, keep rake mechanism 200-TM-050 running.
When done, keep all purgewater to instrument connections open and running.
If the rest of the plant (section 400 to 800) remains in operation and 200-TK-005, 200-AG005, 200-PP-005/006 or 200-CY-005 has to be taken out of operation, than the liquor
bypass to 200-TK-010 can be used:
19 Open bypass line to 200-TK-010
20 Close liquor feed to 200-TK-005
When the rest of the plant is shut down, liquor flow from dredge can be stopped and the
intake part of the washery can be stopped:
21 Calciner section and other down stream units are stopped. Stop 200-CV-080 and
roller mill belt weigh feeder 200-FD-085
22 Stop dust supply to 400-BN-040 (400 section) and stop 200-PP-011/012
23 Stop liquor supply from dredge to 200-TK-005
24 Stop 200-PP-005/006 (and 200-AG-005 if required)
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.25
date
2005-06-30
rev
25
Stop 200-PP-010/11
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.26
date
2005-06-30
rev
5.5.3
Stop solids supply from the dredge and or dry reclaim system and maintain liquor
supply.
After approx. 10 minutes only liquor is fed to 200-TK-005. Reduce position of 200HIC-0201
Switch 200-DCV-0401 to manual control and keep level in 200-TK-030 constant
Divert 200-GA-030 to 200-ZC-030
When classifier 200-CI-030 is empty of trona, stop screw drives.
When 200-TK-030 is empty of trona, stop centrifuges 200-CF-070/71(procedure
from vendor) and stop process water supply (200-FICA-0601/02)
Reduce level in 200-TK-005 (set point 200-LICSA-0101)
The opening of 200-HIC-0201 reduces automatically, which reduces the level in the
washery.
Stop roller mill belt weigh feeder 200-FD-085
Stop dust supply to 400-BN-040 (400 section)
Stop 200-PP-060/061 (stop liquor supply to boiler scrubber)
Stop liquor supply from dredge.
Stop 200-PP-005/006 and 200-AG-005
Stop 200-PP-010/11/12
Stop 200-PP-050/51
Stop 200-PP-030/31/32 and 200-AG-030
Stop 200-PP-070/071
Stop 200-CR-025
Stop Guar supply (510-MP-070/71)
Stop 200-PP-040/041
Stop 200-CV-070 , 200-CV-090, 200-CV-075, 200-CV-080
Start flushing lines as soon as possible after stopping a pump
Settler remains full. Keep rake mechanism 200-TM-050 running.
Tanks can be drained as required. Drained liquor is collected in the sump
200-SU-090. Pump capacity of 200-PP-090 is 35 m3/h.
Keep purgewater to instrument connections open and running as far as possible.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.27
date
2005-06-30
rev
5.6
5.6.1
5.6.2
5.6.3
Checks
Check purge flow rates instruments are set according to the required setting (see
setting list).
Check centrifuge cake visually on 200-CV-070 for high moisture
Check pump seals:
Purge flow rate is set according to setting list
Check that water is dripping from the seal. If no dripping is visible or if a continuous
flow is visible, maintenance attention by a qualified person is required.
Check liquor flow to sieve bend 200-SN-020 and crusher 200-CR-025 are right
Check sump 200-SU-090 (e.g. automatic level switch 200-LSA-0402)
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
5.28
date
2005-06-30
rev
5.6.4
Parameter
Tag or analysis
Target / setpoint
200-PP-005/006
Pump speed
200-HIC-0001/0002
TBD
200-TK-005
Density
200-DIA-0101
20 wt%)
200-CY-005
Sample (SC207)
60 wt%
concentration
200-CY-005
200-CI-030
Sample (SC206)
3 4 wt%
size
Sample (SC208)
25 wt%
concentration
200-CI-030
200-CI-030
Sample (SC209)
75 wt%
insolubles (organics)
0 wt%
Sample (SC211)
2 wt%
D90 cut size 175 m
size
200-TK-030
Density
200-DICSA-0401
200-PP-030/031/032
Pump speed
200-HIC-0402/0403/0404
TBD
200-TK-050
200-LI-0901
4 discs visible
510-MP-070/071
Calibration tube
200-TK-050
Sample (SC216)
200-TK-050
Sample (SC217)
20 wt%
concentration
clean
concentration
200-CF-070/071
Cake moisture
< 6 wt%
200-CF-070/071
200-FICA-0601/0602
5 m3/h
rate
5.6.5
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.29
date
2005-06-30
rev
5.7
5.7.1
3
4
Adjust slurry flow through washery feed cyclone underflow control 200-HCV-0201
Keep one centrifuge operating. Stop one feed pump (200-PP-030 or 031 or 032)
Stop one centrifuge and flush the centrifuge. After flushing: stop process water flow
to the centrifuge. Flush the discharge line to the cyclone that has been stopped.
Adjust flow of antifoam and guar (depending on the expected duration of the turn
down situation)
Adjust the speed of settler underflow pump 200-PP-050/51 in such a way that the
sludge level stays correct.
5.7.2
Dry reclaim
5.7.2.1
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.30
date
2005-06-30
rev
Above raw trona undersize conveyor 200-CV-015 a magnet 200-MA-015 is installed. This
magnet has to be inspected periodically and cleaned.
If the magnet has to be removed for cleaning, then raw trona / fines bank supply MUST be
stopped until the magnet is back in place. Make sure the magnet is positioned correctly,
otherwise it will not effectively catch metal parts in the raw / trona fines bank feed.
Raw trona reclaim conveyor 200-CV-010 transports the dry feed, which is delivered by
front-end loader to raw trona reclaim hopper 200-BN-010, to raw trona reclaim screen
200-SN-010.
Raw trona reclaim screen 200-SN-010 rejects lumps larger than 32 mm to raw trona
oversize chute 200-CH-010. Smaller particles are allowed to pass the screen to raw trona
undersize conveyor 200-CV-015.
Raw trona undersize conveyor 200-CV-015 transports the smaller particles to dredge
product tank 200-TK-005.
5.7.2.2
Operating procedure
In the dry reclaim case, the liquor inlet from the dredge into dredge product tank
200-TK-005 remains open. There is no solids supply from the dredge, therefore trona
supply will be started from stockpile 200-ZC-010.
For starting solids supply via the dry reclaim route the following steps are required:
1
Raw trona undersize conveyor 200-CV-015 is started.
2
Raw trona reclaim screen 200-SN-010 is started.
3
Raw trona reclaim conveyor 200-CV-010 is started.
4
Raw trona from stockpile 200-ZC-010 is supplied by front loader to reclaim hopper
200-BN-010. The rate at which solids are added is to be controlled by the front end
loaders.
The speed of the conveyors is fixed and is designed for 115 ton/h. The manual gate of the
raw trona reclaim hopper has to be opened sufficiently to have the bin emptied in between
front end loader loadings.
The output flow of the washery is measured on 200-FICA-0801. The density in the dredge
product tank 200-TK-005 as read on 200-DIA-0101 has to be checked to ensure the
correct amounts of liquor and solid are being added, see setting list.
When returning to the normal operating situation, execute by stopping the equipment in
step 1 to 4 in reverse order.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.31
date
2005-06-30
rev
If high level switch 200-LSA-0102 HH in 200-TK-005 is activated, then stop dry reclaim
route.
5.7.3
CRS reclaim
CRS conveyor 200-CV-080 transports the CRS centrifuge cake to roller mill feed bin
200-BN-085. 200-CV-080 can also be fed by front end loader with CRS from the CRS
stockpile 200-ZC-040 to CRS chute 200-BN-080.
For a feed of 107 ton/h of CRS, front end loadings are required once per minute for the
1.7 m3 front end loader, and once per two minutes for the 3.5 m3 front end loader.
Check position of manual gate in order to empty BN-080 sufficiently fast.
Two colored lights at 200-BN-080 inform the operator when to load CRS into 200-BN-080:
Green light: 200-LISA-0801 H(S) is not activated: start supplying CRS
Red light: 200-LISA-0801 H(S) is activated: stop supplying CRS
5.7.4
Centrifuge flushing
During normal operation, the flushing of the centrifuges with process water is necessary at
a certain frequency. Centrifuge flushing is activated via a timer switch (200-KIS-0601 and
0606), which activates flush water supply (open 200-KSV-0603 or 200-KSV-0606).
Flushing is stopped again by the same switch. Only one centrifuge can be flushed at a
time.
When flushing centrifuge 200-CF-070 the slurry flow to hydrocyclone 200-CY-065 is
redirected to the CRS wash tank by opening 200-XSV-0602 and closing 200-XSV-0601
(pump remains in operation). When the slurry is redirected the flush valve 200-KSV-0603
is opened. When flushing is complete 200-KSV-0603 is closed, 200-XSV-0601 is opened
and 200-XSV-0602 is closed.
In the same way when flushing centrifuge 200-CF-071 the slurry flow to hydrocyclone
200-CY-066 is redirected to the CRS wash tank by opening 200-XSV-0605 and closing
200-XSV-0604 (pump remains in operation). When the slurry is redirected the flush valve
200-KSV-0606 is opened. When flushing is complete 200-KSV-0606 is closed,
200-XSV-0604 is opened and 200-XSV-0605 is closed.
If the density in 200-TK-030 becomes too high, the classified slurry is diverted to
200-CV-030 automatically. If the slurry is diluted sufficiently again, 200-GA-030 is set in
the direction of 200-TK-030 automatically (see section 2.3.3).
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.32
date
2005-06-30
rev
If the level in 200-TK-030 becomes too high, 200-DCV-0401 is closed. Control valve
200-DCV-0401 is automatically opened when the level has reduced (see section 2.3.4).
5.7.5
Put calciner on standby (unit 400) and stop weigh feeder 200-FD-085.
Other units further down stream go to standby
Stop ESP fines supply to 400-BN-040 (unit 400)
When level in 200-TK-005 is low, stop 200-PP-005/006 and 200-PP-010/11/12
Put washery on standby (see section 5.5.1)
When level in 200-TK-060 is low, provide additional process water to the system to
keep feeding the boiler scrubber, or stop 200-PP-060/061
This is the stage where the washery runs in stand-by mode: i.e. full circulation, no feed
and no CRS delivery. Slurry from CRS wash tank is gradually washed out towards the
centrifuge. The liquid loss has been minimized.
In case of a longer failure, the washery can be shut down (see section 5.5.2).
5.7.6
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.33
date
2005-06-30
rev
1
2
3
4
5
6
7
8
9
10
11
This is the stage where the washery operates in stand-by mode: i.e. full circulation, no
feed and no CRS delivery. Slurry from CRS wash tank is gradually washed out towards
the centrifuge. The liquid loss has been minimized.
In case of a longer failure, the washery can be shut down (see section 5.5.2).
5.7.7
5.7.8
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.34
date
2005-06-30
rev
3
4
5
6
7
8
9
10
5.7.9
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.35
date
2005-06-30
rev
5.7.10
5.7.11
5.7.12
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.36
date
2005-06-30
rev
10
11
12
13
14
Open flush valve on discharge line upstream of discharge valve, open discharge
valve and flush through discharge valve.
Close discharge valve and open suction valve and flush through suction valve.
Close suction valve, open drain valve and close flush water valve.
Drain pump and leave drain valve open.
Close purge water shut-off valve.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.37
date
2005-06-30
rev
5.7.13
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.38
date
2005-06-30
rev
Backflow does not occur when the running pump is stopped for positive
displacement pumps
Close the purge water supply before the pump is isolated to prevent high
pressure in pump and piping.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.39
date
2005-06-30
rev
5.7.14
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
5.40
date
2005-06-30
rev
5.7.15
Event
Automated action
Cause
Recovery action
200-LISA-0401 H(S)
too slow
ZC-030
Pump failure
One cyclone/centrifuge
out of operation
Valve 200-DCV-0401
fails open
200-LISA-0401 L(S)
200-LISA-
Pump stop
0401LLL(S)
200-DICSA-0401
HH (SA)
200-ZC-030
(200-DCV-0401 fully
open)
200-DICSA-0401 L
(S)
200-TK-030
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
5.41
date
2005-06-30
rev
5.7.16
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
6.1
date
2005-06-30
rev
6.1
Process description
To produce soda ash the CRS cake must be dried and calcined. The complete chemical
reaction is shown below.
2 Na2CO3. NaHCO3.2H2O(Trona) 3 Na2CO3(Calcine) + 5 H2O (g) + CO2(g)
A two stage calcination system is included in the process. The CRS cake is
simultaneously ground and dried in roller mill 400-ML-010. A roller mill is the preferred
grinding device because of energy efficiency, close control of particle size (reduced
generation of super fines), and reduced iron contamination of the product. Grinding is
essential to the process because the subsequent recrystallization process physically
separates impurities based upon their particle size.
The roller mill is the first stage of calcination. The wet CRS is heated to about 100C, fully
drying and partially calcining it. The hot air used for conveying and drying is supplied from
the flash calciner cyclone. The roller mill grinds the product between hydraulically
activated vertical rollers and a horizontal rotating table. The ground material falls off the
table and into a louvered section, in which it contacts the mill air. The solids are
pneumatically conveyed to variable speed impact classifier 400-CI-015 that rejects
oversized material back to the center of the table for regrinding. The fine material (less
than 105 micron) is carried to roller mill cyclone 400-CY-020 that collects about 85 - 90%
of the solids in the underflow. The roller mill cyclone gases are blown by roller mill fan
400-FN-020 to ESP cyclone 400-CY-025 to be combined with the mill bypass gas and the
roller mill dust cyclone underflow. The mill gas flow is controlled by roller mill fan damper
400-DA-010. Damper 400-DA-020 is positioned in the mill bypass gas line to provide
additional flow balancing capability. The gas leaving the ESP cyclone will be at a
temperature of about 130C. It is estimated that the solids leaving the ESP cyclone will be
> 30% calcined.
The ESP cyclone and roller mill fan appear to add complication to the system, but provide
significant cost and operational benefits. The roller mill size is significantly impacted by
airflow. To match the mill size with the grinding requirements, it is necessary to bypass
about 45% of the hot gas around the mill. The higher temperature of the combined gas
stream supports additional calcination in the ESP cyclone. In addition, the ESP cyclone
provides dust recovery that reduces the load on the electrostatic precipitator (ESP). The
roller mill fan provides two important functions. The fan balances the pressure between
the mill discharge and the bypassed gas. In addition, the fan reduces the vacuum on the
ESP, reducing cost and air in-leakage.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
6.2
date
2005-06-30
rev
The ESP cyclone underflow is discharged into flash calciner 400-FD-050 just above the
air-cooled grid plate 400-CK-050. There the hot combustion gases from the flash calciner
burner 400-BU-050, mixed with the colder gas (recycled from the ESP exit) to produce a
mixed gas at 700 to 730C, are introduced. This gas and the solids react almost
instantaneously, quenching the temperature to 400 to 450C. The flash calciner conveying
velocity is near 15 m/s, and the retention is about 2 seconds. This contact time is sufficient
to fully calcine the solids and to heat them to 400C. The high temperature ensures > 99%
calcination, while eliminating organics that can be detrimental in the crystallization
process. Calcined product is separated from the hot gases in flash calciner cyclone 400CY-060 and transported by gravity via crystallizer feed airlocks 400-AL-060 and 400-AL065 to calcined feed chamber 510-CH-010. During washouts and off-spec conditions the
product stream can be diverted to dump tank 400-TK-060, where it is mixed with water for
discharge to the lake.
ESP 400-EP-030 consists of four high voltage electrical fields. Static charge is induced on
the surface of the particles allowing their collection on charged plates. The accumulated
dust is periodically removed from the plates by a rapping system. The ESP will reduce the
exhaust gas dust loading to below 50 mg/Nm3. Dust losses will be less than 10 kg/h.
Sulfur dioxide generated during the combustion of the heavy fuel oil reacts with the roller
mill product in the calciner to produce sodium sulfate. More than 98% of the sulfur dioxide
will be removed during calcination. The chemical reaction is shown below.
SO2 (g) + O2 (g) + Na2CO3(s) Na2SO4(s) + CO2 (g)
3 SO2 (g)+3/2 O2 (g)+2 Na2CO3.NaHCO3.2H2O(s) 3Na2SO4(s)+3 CO2(g) + 5 H2O (g)
The sodium sulfate generated will dissolve in the crystallization process and will ultimately
be purged to the lake.
Cleaned air with a temperature of about 125 C is transported by ESP ID fan 400-FN-030
to stack 400-ST-030, where the air is checked for particulates. Part of the air is
recirculated by dilution air fan 400-FN-035 to be mixed with the calciner burner gases.
When the ESP has a misoperation, the air can contain too much particulate material to be
used for dilution and the dilution air fan suction will change to outside air
Dust collected in the ESP is transported by ESP collection screw conveyor to roller mill
ESP airlock 400-AL-040 and ESP dust bleed airlock 400-AL-030. Via the roller mill ESP
airlock the dust is discharged into a pneumatic transport system, which brings the dust
back to the flash calciner. The pneumatic transport system consists of ESP dust
pneumatic conveyor blower 400-GB-040, ESP dust pneumatic conveyor 400-PN-040,
ESP dust bin 400-BN-010, ESP dust collector 400-DC-010 and ESP dust collector airlock
400-AL-045. Remaining dust, which is not discharged into the pneumatic conveying
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
6.3
date
2005-06-30
rev
system, is discharged via the ESP bleed dust airlock 400-AL-030 into ESP dust hopper
400-BN-040, where it is mixed with air and sucked into ESP dust conveyor 400-CV-040.
The ESP dust conveyor is driven by washery feed cyclone overflow liquor and transports
the dust to the washery feed cyclone overflow tank, from which it is ultimately discharged
to the lake.
All cyclones are equipped with 2 air cannons (400-AC-020/1, 400-AC-025/6 and
400-AC-060/1). In addition vibrators are mounted on the cyclones and the cyclone
discharge lines (400-VB-020/1/2/3/4, 400-VB-025/6/7/8/9 and 400-VB-060/1/2).
6.2
Normal operation
6.2.1
6.2.2
Setting list
Instrument
Unit
Normal
Alarm
Trip/Switch
400-FISA-1401
m3/h
100
L 90
L 90
400-QIA-1401
mg/m3
<18
1)
mg/Nm3
<50
2)
H 18
H 50
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
6.4
date
2005-06-30
rev
6.3
Logic functions
In this section the logic functions describing automatic actions of valves are described.
Logical functions that act on equipment are for example:
Start conditions and running conditions
Process switches
Safety switches (dry run protection on pumps, speed alarm on conveyors)
Thermal overload is provided on all electric motors. The thermal overload shuts off the
motor directly (hardwired from MCC).
Table: automatic actions of valves
Valve
Action
Cause
400-GA-041
Close
400-XSV-1401
Open
400-XSV-1402
Open
400-LSA-1401 H activated
200-PP-011 or 200-PP-012 out of operation
200-PP-011 or 200-PP-012 out of operation
Signal from 400 section, prior to divert soda ash to
the dump tank
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
6.5
date
2005-06-30
rev
6.4
6.4.1
Normal start-up
1
2
3
4
5
6
7
8
6.4.2
The Calciner is not yet running, or is not supplying ESP dust to 400-BN-040.
Check 400-GA-041 is closed
Check manual drain valve upstream of 400-CV-040 is closed. The automated drain
valve 400-XSV-1401 has to be closed by the operator (reset on DCS).
Check 200-TK-010 has sufficient level and that No.5 dredger supplies sufficient
liquor.
Check automated drain 400-XSV-1401 valve is closed (reset on DCS)
Start selected pump (200-PP-011 or 200-PP-012)
If pump is running well, then 400-GA-041 can be opened.
Now ESP dust can be supplied to 400-BN-040 by starting 400-AL-030
Normal shut-down
1
2
3
4
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
6.6
date
2005-06-30
rev
6.5
6.5.1
Initial start-up
1
2
6.5.2
Normal start-up
1
6.5.3
Open 400-XSV-1402 and read flow rate on FISA 1401. Check the recorded amount
with the setting list.
Verify the sprayers provide an even water curtain.
Check that 400-TK-060 does not contain solids from previous dumpings. Liquid level
(rain water) should be at nozzle N2 (1 m level). If water level is below nozzle N2,
add water via manual valve.
Check that manual valve in process water supply line upstream of 400-FISA-1401 is
open and manual valve in bypass line of 400-XSV-1402 is closed.
6.5.4
Normal shutdown
No real actions for shutdown. Manual valve upstream of 400-FISA-1401 can be closed.
Tank can be emptied via nozzle N1 or drain nozzle.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
6.7
date
2005-06-30
rev
6.6
2
3
Dump tank level: when not in use, the dump tank level should be at nozzle N2. If too
low, then supply water to fill to this level. If too high, then line 100-SLS1-102,
connected nozzle N2, is plugged, or sump or ditch is flooded.
ESP Dust Hopper: check air inlet opening is free
Sampling and analyses: see Analytical Manual.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
6.8
date
2005-06-30
rev
6.7
6.7.1
6.7.2
6.7.3
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
6.9
date
2005-06-30
rev
Valve 400-XSV-1401 has to be closed by the operator (reset action on the DCS).
6.7.4
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
6.10
date
2005-06-30
rev
6.8
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Document Information
Document Number
Title
Contract Number
Originating Author
8.500933
Functional Specification for a Roller Mill and Flash Calciner System
03-51573-727
Michael Prokesch, FFE Minerals USA
Date
Designed
30Nov04
MEP
05May05
MEP
Checked:
Approved
Description
General Revisions as per Oct04 Hazop
Revisions as per P&IDs Rev 10, FLS Mill Control
Review, Airtek ESP Review, and Vendor
Documents Received to Date
Reference Documents
FFE Doc./ Dwg. #
8.500742 Sheet 4
8.500742 Sheet 5
8.500742 Sheet 6
8.500742 Sheet 7
8.500742 Sheet 8
8.500742 Sheet 9
8.500742 Sheet 10
8.500742 Sheet 11
8.500742 Sheet 12
8.500742 Sheet 13
8.500742 Sheet 14
8.500742 Sheet 15
ii
Document Format
This document begins with a description of the overall process. The entire process is then divided into groups
and each is described in a separate section. The following table provides an overview of the document
structure. Each group section includes a functional description of operation, equipment/instrument
summary, control loop descriptions, alarm table and interlock table.
Group Name
Description
Process Overview
Calciner Group
The equipment that performs the high temperature calcination work and delivers product to the
crystallizer circuit. The main components in the group include the fuel skid, valve stand, air
heater, flash calciner and calciner collection cyclone.
Burner
Management
System
The stand-alone PLC-based system that controls the safety interlocks for the air heater burner
system.
The equipment that receives the wet CRS feed and produces a fine, dry, pre-calcined feed for the
Calciner Group.
All fans and dampers utilized for combustion and process air flow control.
ESP Group
The equipment that removes particulate from the calciner system off gas stream.
Cleaning Group
This group includes equipment utilized to promote stable material flow through cyclones and
material transfer ducts (air cannons, rappers and vibrators).
Dust Handling
Group
Water Spray
Group
Provides water to the roller mill for the purpose of bed stabilization and temperature control.
Roller Mill
Hydraulics Group
Lubrication Group
Table of Contents
DOCUMENT INFORMATION ..................................................................................ii
Document Revision History ............................................................................................................................................. ii
Reference Documents........................................................................................................................................................ ii
Document Format ............................................................................................................................................................. iii
iv
vi
1 PROCESS OVERVIEW
The roller mill and flash calciner circuit serves to convert Crushed Refined Soda (CRS) supplied from the
washery to a calcined soda ash product in a form suitable for further processing in the crystallizer circuit. The
CRS is composed primarily of sesquicarbonate (97.4%) with minor amounts of sodium fluoride, sodium
chloride and other inerts. The calciner process supports drying to remove 6% free water, grinding to reduce
the particle top size to approximately 105 microns, and calcining the CRS at a maximum temperature of
400C to convert the sesquicarbonate to an intermediate decimite phase followed by final conversion to
sodium carbonate (soda ash). In addition to the chemical decomposition supported by the flash calciner, the
temperature supports a partial decomposition of organic carbon present in the feed material. Minimizing the
product residual bicarbonate level is important to maximizing the efficiency of the crystallizer circuit, and the
organic carbon reduction is required to improve the color of the final pure ash product.
The CRS is supplied by a transport system from the washery to a weigh feed system. This feed system (200FD-085) meters the wet CRS to the roller mill system (400-ML-010) through a rotary airlock (400-AL-010).
The feed chute between the rotary airlock and the mill body is heated utilizing mill inlet gas passed through a
heating jacket in order to minimize the potential for material flow problems. The CRS drops onto the mill
table where it is crushed between the rotating table and the three vertical rolls. A hydraulic system exerts a
force onto the roll support arms to generate the pressure between the vertical rolls and horizontal table
required to support the communition process. The centrifugal force exerted on the particles by the rotating
table forces the particles to the periphery of the mill housing where they are entrained by the hot process gas
from the calciner (400-FD-050) entering the mill housing through the louver section. The louvers serve to
develop a gas velocity sufficient to limit CRS particles from falling below the table level and into the mill
plenum. Particles that do enter the plenum are discharged from the bottom of the mill through manual gate
valves. Coarse particles disengage from the gas stream and fall back onto the mill table while finer particles
are carried to dynamic classifier 400-CI-015 located in the top section of the mill. The speed of the classifier
is adjusted via a variable-frequency drive to permit the minus 105 micron particles to pass through the
classifier rotor and exit the mill while deflecting the >105 micron particles back onto the mill table.
Energy from the process gas stream supports the vaporization of all free water in the CRS and supports
about 25% calcination of the sesquicarbonate in the roller mill. Additional water may be added onto the mill
table delivered from 900-PP-060 to improve the dynamics of the material load on the table in order to limit
instabilities that create mill vibration. Water may also be delivered to the mill freeboard section in a finely
atomized form via water spray system 400-PP-010. The purpose of this spray is for the control of the mill off
gas temperature, particularly during operation at reduced system capacities due to the need to maintain a level
of process gas flow at the mill exit equivalent to 90% of the normal operating level. Maintaining this flow
level at a reduced system capacity results in an excess of energy in the mill that will damage the classifier if the
gas temperature is not limited to 110C.
Off gas from the roller mill system enters the mill cyclone (400-CY-020). The bulk of the particulate is
disengaged from the process gas stream and discharged from the bottom cyclone cone through a rotary
airlock (400-AL-020). Calciner off gas is pulled through the roller mill and mill cyclone by the roller mill fan
(400-FN-020). Fan inlet damper 400-DA-010 is adjusted to maintain a target pressure drop across the mill
cyclone to ensure sufficient gas flow through the mill.
Vibrators (400-VB-020/021/022) and air cannons (400-AC-020/021) are positioned on the cyclone cone to
prevent material from bridging across the cone and provide a smooth, continuous flow of solids to the next
stage of the process. Additional vibrators (400-VB-023/024) are mounted on the underflow duct to
minimize the potential for solids flow problems.
Lake Magadi Functional Specification Rev 2
Off gas from the roller mill fan is combined with the calciner off gas bypassed around the mill, and then the
roller mill cyclone underflow stream is introduced to this combined gas stream. This reintroduction of the
milled solids into the off gas stream makes effective use of the energy in the mill bypass stream by supporting
about 50% calcination of the sesquicarbonate still present and about 25% calcination of the decimite. This
stream is directed to the ESP cyclone (400-CY-025) for particulate separation. The particulate underflow
passes through the ESP cyclone rotary airlock (400-AL-025) and then enters flash calciner 400-FD-050 via a
splash plate to promote good solids distribution into the calciner gas stream. The ESP cyclone and
underflow ducting include vibrators (400-VB-025/026/027/028/029) and air cannons (400-AC-025/026) to
promote stable solids flow as described for the mill cyclone.
The ESP cyclone underflow material is entrained by calciner gas at a temperature of 730C. The rapid
decomposition of the sesquicarbonate and decimite components quenches the calciner gas to a temperature
below 550C. The stainless steel calciner section provides for a total gas residence time of about 2.5 seconds
in order to support a reduction in the bicarbonate content to <0.4% and heat the solids to a temperature of
400C. It is critical to the availability of the calciner to minimize the contact between solids and the hot
calciner walls in the feed inlet zone in order to limit the potential for coating formation.
The soda ash product is disengaged from the calciner process gas stream in the calciner collection cyclone
400-CY-060, and discharged through the actuated double tipping valve 400-AL-060. Crystallizer feed diverter
400-GA-060 is positioned below the airlock to direct cyclone cleanout material away from the crystallizer
circuit during cleaning operations or when feed to the crystallizer must be stopped immediately. During
normal operation, calciner product passes vertically downward through the diverter valve and is then
discharged through rotary valve 400-AL-065. This rotary valve is utilized to stabilize the flow of material into
the calciner and dampen material slugs generated by the action of the double tipping valve. The ducting
below the feed airlock is maintained at a negative pressure by the crystallizer vent fan to prevent saturated gas
from the crystallizer from condensing in the ducting and creating buildup problems.
Air cannons (400-AC-060-061) and vibrators (400-VB-060/061/062) are included on the calciner cyclone
cone to promote stable material flow if required.
Hot gas for the calciner operation is generated using flash calciner burner 400-BU-050 and the combustion of
heated heavy fuel oil. The fuel rate is adjusted to control the calciner collection cyclone process gas overflow
temperature at 425C, and the ratio of fuel to the air supplied by primary combustion air fan 400-FN-050 is
controlled by the Process Control System to generate a maximum gas temperature of 1600C. This gas exits
the calciner burner and enters a mixing chamber where it is combined with stack gas supplied by dilution fan
400-FN-035 to yield a final mix temperature of 730C. The design of the refractory-lined mix chamber is
such that the tangential entry of the relatively cool stack gas limits the refractory surface temperature to
reduce the potential for the deposition of fine soda ash that is present in the stack gas. The stack gas first
passes through a jacket on the calciner burner to provide cooling of the chamber prior to be introduced into
the mix chamber. The velocity in the jacket is such that particulate present in the dilution air stream will
remain suspended as opposed to settling out and accumulating in the jacket.
The 730C calciner inlet gas passes through air-cooled grid plate 400-CK-050 supplied with cooling air from
grid plate cooling fan 400-FN-055. The primary function of the grid plate is to distribute the calciner inlet
gas across the full cross section of the calciner below the feed inlet location. This even distribution eliminates
gas recirculation zones that would draw the calciner feed material down into the hottest zone of the calciner
and promote buildup formation. The air cooling serves to limit the temperature of the top surface of the
plate in order to prevent sticking of material that does come in contact with the plate. The cooling air exiting
the grid plate is vented into the calciner above the feed inlet location.
The off gas from the calciner system (overflow stream from the ESP cyclone) is cleaned using a 4-field
electrostatic precipitator (400-EP-030). The cleaned off gas passes through roller mill ESP ID fan 400-FN030. The ID fan damper 400-DA-030 is adjusted to maintain a neutral gas pressure in the top of the flash
calciner vessel. A portion of the ID fan outlet gas is directed to the stack while the balance is pulled by
dilution air fan 400-FN-035 for use in the calciner. In the event that a problem with the ESP results in a
stack particulate concentration >50 mg/Nm3, tempering tee 400-DA-034 is opened to introduce ambient air
to the calciner inlet and prevent high concentrations of particulate from entering the high-temperature
calciner inlet.
Dust collected in the ESP is discharged through screw conveyor 400-SC-040. The discharge from the screw
is normally passed through rotary valve 400-AL-030 and conveyed to a dust recovery circuit (provided by
others). In the event that dust is to be reprocessed in the flash calciner, rotary valve 400-AL-040 is activated
and the dust output is conveyed to dust bin 400-BN-010 using blower 400-GB-040. A manual valve
positioned above 400-AL-040 controls the flow of dust into this circuit while the balance of the dust is
discharged through 400-AL-030. All material collected in the dust bin is discharged through rotary valve 400AL-045 and into the calciner.
Pilot Only is selected, no further action will be performed. If Oil Firing is selected, ignition of
the main oil burner will proceed immediately following pilot ignition.
8. The PCS will make adjustments to the fuel rate and air/fuel ratio to preheat the air heater chamber.
This sequence will ensure proper preheating of the chamber refractory lining and establish a calciner
off gas temperature of 300C (System Idle condition).
9. Start the ESP dust purge rotary valve and hopper discharge screw conveyor.
10. Select Start All ESP Fields in the PCS. The PCS will send a command to the local ESP PLC to
energize all fields.
11. Start all cyclone discharge valves (3 rotary valves and 1 tipping valve). Set the product diverter valve
to direct calciner product to the crystallizer circuit.
12. Approximately one hour before the CRS feed start target, start the following mill system
components:
a.
Start the roller mill main drive lubrication system. This will start the circulating lube pump.
b. Start the roller mill hydraulic group. The hydraulic pump will run until the rollers are moved
to there upper position and then de-energize.
c.
Set the classifier speed to 50% and then initiate a start command. Once started, adjust the
classifier speed to the normal level. The classifier grease system is energized by the PCS
once the classifier drive is started.
13. Open the mill inlet damper and then open the mill fan inlet damper to a position of 3%. Hold this
setting while the mill is preheated to a freeboard temperature of 80C. Once 80C is obtained, either
close the damper to hold or immediately proceed with a feed start.
14. Initiate a Start CRS Feed command. Upon receiving this command, the Process Control System
will perform the following actions:
a.
Activate the mill off gas temperature control loop (105C set point).
b. The PCS will issue the prompt Mill Pre-charge Required. If the mill table is void of
material (inspect if necessary), select Yes. The PCS will proceed to start the CRS feed
system and deliver CRS to the mill table for a period of approximately 30 seconds (time
TBD during commissioning).
c.
The mill fan damper is opened to a preset position to develop the required process gas flow
to the mill.
d. The mill main drive is started at the specified speed set point. The roller mill grease system
is started automatically.
e.
f.
g. The hydraulic pump is started if necessary to obtain the target grinding system pressure.
h. Increase the ID fan damper opening.
i.
j.
15. The mill table water spray may now be started if required to stabilize the mill operation and reduce
vibration.
The calciner system is now in a Feed Start mode. This mode of operation can be continued or
proceed to the next step to increase capacity.
16. Allow the system to stabilize (1-2 minutes). Engage the following control loops allowing for
appropriate system response and stabilization before initiating the subsequent control loop:
a.
Mill flow
f.
g. Move the tempering tee to the fresh air intake position and adjust the system for System Idle
conditions,
h. De-energize air cannons, rappers and vibrators,
2. If the stop sequence is initiated due to a failure of the crystallizer vent fan, the diverter on the
calciner cyclone discharge duct will be repositioned to divert solids to the soda ash dump bin. If
safety interlocks prevent access to this bin, the calciner will proceed with an emergency shutdown
sequence.
3. The system can be idled at these conditions until a feed start is required. If a full shutdown is
required, initiate a burner stop command. This command will stop fuel flow to the air heater and
place the system in a cool down mode. Once the air heater chamber refractory temperature
decreases to <150C, all fans can be stopped. The Process Control System will send a stop
command to the ESP to de-energize all fields and stop the screw conveyor five minutes after the last
process fan has been stopped, or the ESP may be de-energized by the operator. Calciner discharge
valves will continue to operate until manually stopped by the operator.
2 CALCINER GROUP
The Calciner Group consists of the Fuel Skid (400-BU-050-F1), Valve Stand (400-BU-050-V1), Burner (400BU-050), Air Heater Chamber (400-FU-050), Flash Calciner (400-FD-050), Air-cooled Grid Plate (400-CK050), Calciner Collection Cyclone (400-CY-060), Calciner Cyclone Dual Tipping Valve (400-AL-060),
Calciner Cyclone Discharge Diverter Valve (400-GA-060), Calciner Cyclone Discharge Rotary Valve (400AL-065) and Burner Cooling Air Fan Circuit (400-FN-054). These components are referenced on the
following C&ID drawings:
soda ash to the crystallizer . Select components on the fuel skid and valve stand are controlled by the Burner
Management System to satisfy safety protocols during purge and ignition sequences once a start command is
received from the Process Control System. After the burner ignition sequence is complete and a flame is
successfully detected, control of components in the Calciner Group resides in the Process Control System
until a burner stop is initiated by the Burner Management System as a result of a safety or process interlock
action. A description of the Burner Management System logic is included in Section 3.
7.
8.
9.
10.
11.
12.
13.
6.5.2. If not satisfied within 10 minutes, alarm in BMS and display in PCS
6.5.3. If not satisfied within 60 minutes, alarm in BMS, reset sequence in PCS and reset BMS
BMS oil flow control valve 400-TCV-0131 Low Fire position check: (position switch 400-GB-0414)
7.1. If valve in position, proceed and lock out PCS control
7.2. If valve out of position, alarm to PCS and recheck position:
7.2.1.
The PCS repositions valve and satisfies limit within 10 minutes, proceed with sequence
and lock out PCS control
7.2.2.
Limit not satisfied within 10 minutes, reset sequence in the PCS and BMS
Purge interval timing in BMS. Ready signal sent to PCS following purge completion,
PCS will re-position dampers in sequence for Low Fire until the following position switches are
closed (the mill bypass damper remains in its full open position):
9.1. ID Fan Damper (400-DA-030), position switch 400-GBS-0310C
9.2. Combustion Fan Damper (400-DA-050), position switch 400-GBS-0460C
9.3. Dilution Air Fan Damper (400-DA-035), position switch 400-GBS-0302C
9.4. Mill Fan Damper (400-DA-010), position switch 400-GBS-0261B
9.5. Mill Inlet Damper (400-DA-015) fully closed, position switch 400-GBS-0165.
PCS Low Fire damper position check:
10.1. All switches closed send a ready signal to the BMS
10.2. All switches not closed alarm and wait for resolution before proceeding
10.3. Stop command from operator reset sequence in PCS and send reset command to the BMS
PCS combustion air flow rate check (400-FFIC-0460):
11.1. If within +/-10% of target set in PCS (TBD during commissioning), send ready signal to the
BMS
11.2. If flow is outside this range, display Combustion Air Flow Out of Range and check flow
indication every 30 seconds and compare to target:
11.2.1. If within +/-10% tolerance, send ready signal to the BMS
11.2.2. If outside tolerance, wait 30 seconds and then recheck
11.3. Stop command from operator reset sequence in PCS and send reset command to the BMS
BMS pilot ignition sequence:
12.1. Start igniter,
12.2. Open pilot gas valves 400-XSV-0440 and 400-XSV-0441,
12.3. Stop igniter,
12.4. Scanner detection of pilot,
12.4.1. If Pilot Only selected at start of sequence, stop sequence and hold
12.4.2. If Oil Firing selected at start of sequence, proceed
12.5. No pilot detection by scanner Burner Start sequence reset in the BMS and PCS
BMS main burner ignition sequence
13.1. Open steam shutoff valve 400-XSV-0422,
13.2. Open oil shutoff valve 400-XSV-0442,
13.3. Close oil bypass shutoff valve 400-XSV-0444,
13.4. Stop pilot gas flow,
13.5. Scanner detection of main burner, Burner Start sequence complete. Proceed to Preheat
sequence
13.6. No main burner detection by scanner Burner Start sequence reset in the BMS and PCS
If ignition sequences are successful, the BMS sends a Burner On signal to the PCS and releases its interlock
on fuel control valve 400-TCV-0131 for PCS control during the Preheat and/or System Idle sequences. If
the ignition sequence is not successful, the BMS will issue an alarm to the PCS and reset. The operator must
now issue a Start Purge command in the PCS.
10
2. Adjust the dilution air fan damper position (400-DA-035) during the preheat cycle to limit the
calciner inlet temperature (400-TISCA-0140) to 325C.
3. Adjust the ID fan inlet damper (400-DA-030) to maintain a pressure of -25 mm WG at the calciner
exit (400-PICA-0130).
If the refractory temperature (400-TI-0469) is greater than 815C at the time that the main burner is ignited,
no preheat sequence is performed. The PCS will proceed with a System Idle sequence.
The system preheat sequences may proceed as long as the following conditions are satisfied:
1. Emergency Stops are not engaged
2. No high temperature states existing:
a. Calciner inlet (400-TICSA-0140)
b. Calciner outlet (400-TICSA-0131,400-TIZA-0161)
c. Roller mill outlet (400-TICSA-0004)
d. ESP outlet (400-TISA-0302)
3. ESP ID Fan running (400-FN-030)
4. Combustion Air Fan running (400-FN-050)
5. Dilution Air Fan running (400-FN-035)
6. Grid Cooling Air Fan running (400-FN-055)
7. Tempering Tee in full open position (400-GIS-0328) for ambient air intake
8. No high CO at the ESP inlet (400-QISZA-0301)
If conditions 2, 6 and 8 are not satisfied, the preheat sequence will be held at current conditions until the
problems are resolved. The remaining conditions will result in a main burner shutdown.
If a failure occurs with the operation of the combustion air fan or dilution air fan after the system is hot, the
PCS will perform the functions described in Section 2.1.6.
3.
4.
5.
6.
7.
If a condition in the above list is not satisfied, the main burner will be shutdown by the BMS.
12
400-CTL-01:
400-CTL-02:
400-CTL-03:
400-CTL-04:
In addition, the BMS will detect this loss of contact and/or pressure switch status change and immediately
stop fuel flow to the main burner.
The automatic response by the PCS will supply cooling air to the burner to protect it from high temperature
damage. If the Combustion Air Fan is re-energized successfully or a manual shutdown command is issued by
the operator (400-TI-0469 <150C), valve 400-XVS-0471 will be closed and then the cooling air fan stopped.
1.
2.
3.
4.
5.
These actions will supply cooling air to the air heater cooling jacket to protect the inner air heater shell from
high temperature damage. If the Dilution Air Fan is re-energized successfully or a manual shutdown
command is issued by the operator (400-TI-0469<150C), valve 400-XVS-0470 will be closed and the cooling
air fan stopped.
The valve timing sequence is set in the PCS as per supplier specifications and cannot be changed by the
operator.
The following sequence is performed during normal start, run and stop cycles for the dual tipping valve unit:
1. Check for emergency stop and maintenance lock out. If not present, continue to step 2,
2. Check that the upper and lower valves are in their closed positions. If either closed limit is not
satisfied (400-GS-0151 and 400-GS-0152), issue an alarm indicating position limits not satisfied. If
limits are satisfied, display a start permissive on the PCS screen,
3. The operator manual selects the tipping valve icon and selects Start,
4. The PCS energizes Solenoid A to direct instrument air to the low side of the cylinder and open the
high side to ambient. This extends Cylinder A and moves the upper valve into its open position. If
the open limit switch (400-GS-0151) is not satisfied within 2 seconds after energizing Solenoid A,
issue an alarm indicating position limit not satisfied and remove the start permissive.
5. Energize Solenoid A for a total period of 6 seconds after the open limit is satisfied and then deenergize Solenoid A. This will open the low side of the cylinder to ambient and pressurize the high
side. This retracts Cylinder A and moves the upper valve to its closed position. If the closed limit
switch is not satisfied within 2 seconds after de-energizing Solenoid A, issue an alarm indicating
position limit not satisfied and remove the start permissive.
6. Three seconds after the upper valve reaches its closed position, energize Solenoid B to direct
instrument air to the low side of the cylinder and open the high side to ambient. This extends
Cylinder B and moves the lower valve into its open position. If the open limit switch (400-GS-0152)
is not satisfied within 2 seconds after energizing Solenoid B, issue an alarm indicating position limit
not satisfied and remove the start permissive.
7. Energize Solenoid B for a total period of 6 seconds after the open limit is satisfied and then deenergize Solenoid B. This will open the low side of the cylinder to ambient and pressurize the high
side. This retracts Cylinder B and moves the lower valve to its closed position. If the closed limit
switch is not satisfied within 2 seconds after de-energizing Solenoid A, issue an alarm indicating
position limit not satisfied and remove the start permissive.
8. Three seconds after the lower valve reaches its closed position limit, repeat the cycle until a stop
command is received from the operator, an emergency stop is activated or the local maintenance
switch is engaged.
9. When the valve is stopped for whatever reason, de-energize both solenoids so that the upper and
lower valves return to their closed positions.
Description
PCS Display
Fuel Skid
Reference Tag
400-BU-050-F1
400-PC-0400
400-PI-0401
400-PSA-0402
400-PSA-0403
400-FP-0404
400-PI-0407
400-PI-0408
400-PI-0404
400-PSA-0405
400-PC-0409
400-PI-0410
400-PSA-0411
400-PSA-0412
400-TIS-0413
400-TC-0401
X
400-EA-0401
400-FIT-0401
400-TCV-0131
400-GBS-0414
400-PI-0415
400-PC-0416
400-PI-0417
400-PI-0419
400-XSV-0426
400-XSV-0425
400-GBS-0425
400-XSV-0424
400-GBS-0424
400-FI-0418
400-XSV-0422
400-GBS-0422
Valve Stand
400-BU-050-V1
400-XSV-0440
X
400-XSV-0441
X
400-GBS-0441
400-XSV-0442
400-GBS-0442
400-PI-0443
400-XSV-0444
400-GBS-0444
400-XSV-0445
400-GBS-0445
400-PC-0446
400-PSA-0420
Burner
400-BU-050
400-XISA-0463
400-XISA-0469
Air Heater
400-FU-050
400-TISA-0468
400-TIA-0467
400-TIS-0469
400-XSV-0472
X
400-GBS-0472
400-FN-054
400-XSV-0471
400-GBS-0471
400-XSV-0470
400-GBS-0470
400-PI-0454
400-CK-050
X
400-FIA-0137
400-PI-152A-F
Flash Calciner
18
400-GBS-0440
400-TIA-A-F
400-FD-050
400-TISCA-0140
400-PIA-0139
400-PDA-0138
400-TI-0101
400-TI-0102
400-TI-0103
400-TI-0104
400-PICA-0130
400-QISZA-0180
400-WIA-0135
400-CI-060
400-TI-0131A
400-TI-0131B
400-TI-0131C
400-TI-0131D
400-TICSA-0131
400-TIZA-0162
400-PISA-0161
400-WIA-0148
400-TIA-0150
400-PIA-0147
400-AL-060
400-KSV-0151
400-KSV-0152
400-GS-0151
400-GS-0152
Diverter Valve
400-GA-060
400-XSV-0154
400-GBS-0154A/B
400-PA-0156
Rotary Valve
Rotary Valve Motion Switch
400-AL-065
X
400-SSA-0101
400-TCV-0157
400-TICS-0157
This control loop is automatically deactivated if the Calciner Group is moved into Low Fire or System Idle
modes, or the system is shutdown.
2.4 ALARMS
Alarm Condition
Burner Management System Fault
Alarm Trigger
Device
Analog Set
Point
Debounce
Value
See Section 3
High
400-EA-0401
10 sec
High
400-TIA-0468
>1650C
0 sec
High
400-TIA-0467
>300C
0 sec
High
400-QISZA-0180
0.5%
0 sec
High High
400-QISZA-0180
1.2%
0 sec
High
400-TISCA-0140
>750C
0 sec
High High
400-TISCA-0140
800C
2 sec
High
400-TIA-0152A-F
>435C
5 sec
High
400-PICA-0130
>25mm WG
10 sec
Low
400-PICA-0130
<-50mm WG
10 sec
High
400-TICSA-0131
>435C
0 sec
High High
400-TICSA-0131
450C
15 sec
High High
400-TZA-0162
455C
0 sec
Low
400-PISA-0161
<-200mm WG
5 sec
High
400-PISA-0161
>0mm WG
5 sec
High High
400-PISA-0161
200mm WG
5 sec
High
400-PIA-0147
-25mm WG
10 sec
High High
400-PIA-0147
0mm WG
10 sec
High
400-TIA-0150
405C
15 sec
Low
400-TIA-0150
390C
15 sec
Low
400-PA-0156
-50mm WG
10 sec
High
400-WIA-0135
TBD
TBD
High
400-WIA-0148
TBD
TBD
400-EM-0461
400-GBS-0460A
400-GBS-0460B
400-GBS-0460C
400-GBS-0302A
400-GBS-0302B
400-GBS-0302C
400-GBS-0130A
400-GBS-0130B
400-GBS-0130C
400-GBS-0261A
400-GBS-0261B
400-GBS-0165
400-EM-0452
400-GB-0472
400-GB-0472
Software
Software
400-EM-0124
Low
400-FI-0137
1000 m3/h
0 sec
Low Low
400-FI-0137
500 m3/h
0 sec
400-PIA-0139
400-PDA-0138
>305mm WG
5 sec
>250mm WG
2 sec
400-GS-0151
5 sec
400-GS-0151
5 sec
400-GS-0152
5 sec
400-GS-0152
5 sec
400-GBS-0154B
2 sec
400-GBS-0154A
2 sec
400-EM-0125
400-SSA-0101
5 sec
High
High
22
2.5 INTERLOCKS
All interlocks required for the system are listed in tabular format. The output device is listed in the left-hand
column. Interlock Conditions are listed in the middle column as AND Boolean top to bottom, OR
Boolean left to right. The Interlock Type is listed in the right column.
In local control mode devices are operated locally using start/stop, open/close push buttons. In Manual
control each device is started and stopped from the HMI, using device manual control pop-up screen. In
group control mode all the devices in a particular group start and stop, based on sequential start and stop
logic. In Individual group control all devices in a group are started and stopped individually by the operator;
when their start and stop logic is satisfied.
Safety Interlock will shutdown device in local, manual, or group control mode. The failure of a Start interlock
will not allow the device to be started in group control mode or in individual group control mode. The
failure of a Process interlock will cause the system to stop after the system has been started in group control
mode or in individual group control mode. The failure of an interlock will cause the equipment to shut-down
or execute other interlock related actions.
Equipment/Action
Signals
Sample:
(X AND Y AND Z); Z to start, X
AND Y to run, X for safety shutdown
Safety
Start
X
X
X
X
X
Process
Z
BMS Burner On Signal
Preheat Sequence
Interlock Type
Equipment/Action
Interlock Type
Signals
Safety
Start
Process
24
Air Fan
(400-EM-
No System Power
No System Power
OPERATOR INTERFACE
SYSTEM OPERATION
Notes:
The burner management system is designed to be operated from either the local panel or the PCS; however, the PCS must enable local
operation. This procedure assumes that the operator is at the local panel and that the local operation has been enabled. All
pushbuttons referred to n this document have parallel commands fro the PCS. See PCS documentation for information on enabling
local control from the PCS.
NORMAL BURNER STARTUP
1.0
1.0
2.0
2.0
OPERATOR INTERFACE
3.0
SYSTEM OPERATION
3.0
ID Fan
Combustion Air Fan
Dilution Air Fan
Mill Fan
Other fans as may be required
by the process
The fan limits for each fan will be satisfied and the
BMS will indicate:
ID Fan On
CA Fan On
DA Fan On
Mill Fan On
4.0
4.0
5.0
5.0
6.0
7.0
7.0
26
OPERATOR INTERFACE
SYSTEM OPERATION
8.0
8.1
8.1
8.2
8.2
9.0
OPERATOR INTERFACE
9.1
SYSTEM OPERATION
9.1
9.2
9.2
10.0
10.0
10.1
10.1
28
OPERATOR INTERFACE
11.0
SYSTEM OPERATION
11.0
11.1
11.1
OPERATOR INTERFACE
12.0
SYSTEM OPERATION
12.0
12.1
12.1
13.0
13.0
30
OPERATOR INTERFACE
SYSTEM OPERATION
13.1
13.1
13.2
13.2
14.0
Common Limits
Low Fire Limits
Pilot Limits
Oil Limits
Pilot Valve Open Limits
Flame On
Atomizing Steam Limits
If any of these limits fails, all ignition and valve
outputs will go off and the system will go to
Alarm.
14.1
14.1
OPERATOR INTERFACE
15.0
SYSTEM OPERATION
15.0
15.1
15.1
16.0
16.0
16.1
32
16.1
OPERATOR INTERFACE
SYSTEM OPERATION
Note: The operator should observe the burner firing and
flame shape to insure that the burning characteristics have not
changed. Defects such as plugged nozzles, worn nozzle ports,
broken burner tile, and wet steam can cause flame instability.
Corrective action should be taken when abnormal conditions
are observed.
17.0
17.0
17.1
17.1
17.2
17.2
17.3
17.3
OPERATOR INTERFACE
17.4
SYSTEM OPERATION
17.4
18.0
18.0
18.1
18.1
18.2
18.2
STEAM PURGE
34
OPERATOR INTERFACE
SYSTEM OPERATION
19.0
19.0
19.1
19.1
19.2
19.2
19.3
19.3
CHANGING ATOMIZERS
20.0
20.0
20.1
20.1
The BMS will relight the pilot and shutoff the oil.
OPERATOR INTERFACE
20.2
SYSTEM OPERATION
20.2
The BMS will relight the main fuel and shutoff the
pilot.
BURNER STOP
21.0
21.0
22.0
22.1
22.1
22.3
22.3
36
23.0
3.2 DEFINITIONS
DEFINITION OF ACRONYMS
BMS
CA
Combustion Air
DA
Dilution Air
ID
Induced Draft
MTFI
PCS
PTFI
POC
Proof of Closure
VCS
VOS
AII.1
AII.1
E-Stop #1 is closed
E-Stop #2 is closed
E-Stop #3 is closed
AII.2
AII.2
AII.2
AII.3
AII.3
AII.2
AII.4
AII.4
AII.3
AII.5
AII.5
AII.6
AII.6
AII.7
AII.7
AII.8
AII.8
AII.9
AII.9
AII.10
AII.1
0
ID Fan On
Vent Stack Damper Closed (400-GBS-0472)
Mill Fan On
Mill By-Pass Damper Open Switch (400-GBS-0163A)
AII.11
AII.11
E-Stop Limits OK
ID Fan On (400-EM-0321)
CA On (400-EM-0461)
DA Fan On (400-EM-0323)
Exhaust Gas Path Clear
Instrument Air Low Pressure OK (400-PSA-0405)
Process Interlocks (from PCS)
Process temperature not high (400-TSIA-0468)
Flame Signal Processor is not in fault (400-XSIA-0469)
PLC not faulted
AII.12
AII.13
AII.14
38
AII.13
AII.16
AII.16
AII.17
AII.17
Pump Limits
Oil Low Pressure Switch (400-PSA-0411)
Oil High Pressure Switch (400-PSA-0412)
Oil Low Temperature Switch (400-TIS-0413)
Oil High Temperature (400-TIS-0413)
Low Steam Pressure Switch (400-PSA-0420)
AII.18
AII.18
Setting
Oil MTFI
15 sec
7 sec
15 sec
Purge Start
10 min
Purge Time
15 min
MTFI
15 sec
Pre-Ignition Timer
10 min
Pre-Purge Time
10 min
PRIT
10 sec
PTFI Time
10 sec
Purge Time
15 min
10 min
30 sec
1. Calciner Group has successfully entered a System Idle mode of operation to remove the interlock on
the mill fan inlet damper closed position (400-GIS-0261). System Idle mode is confirmed by the
position of the oil control valve 400-TCV-0131.
2. The rollers are in their raised position as indicated by position switches 400-GBS-0007, 400-GBS0009 and 400-GBS-0011 (mill hydraulic system must be activated),
3. The Table Water Spray control valve (400-FCV-0001) closed limit switch is satisfied (400-GBS0001),
4. The Upper Mill Water Spray control valve (400-TCV-0004) closed limit switch is satisfied (400-GBS0002).
The mill preheat process interlock on the mill fan damper is then removed and the operator can manually
position the mill fan inlet damper valve at an opening of 3% to supply gas for the mill preheat after the
mill inlet damper (400-DA-015) is opened. Once a temperature of 77C is detected at 400-TICSA-0004,
the interlock on mill start associated with the preheat requirement is removed. If a temperature >90C is
detected before the start of the CRS feed system, the PCS will force the mill fan inlet damper and mill
inlet damper to a closed position. In the event of a hot mill restart, the temperature at 400-TICSA-0004
may already be >77C and will satisfy the interlock requirement.
40
9.
10.
11.
12.
13.
14.
15.
50 mm WG the interlock is removed on mill drive 400-EU-0009 and the upper roller mill spray
temperature control loop (400-CTL-05).
Immediately start mill drive 400-EU-0009 and ramp to the set point level at the maximum rate
permitted by the drive (RPM set point can be adjusted by operator):
9.1. Drive at target set point continue sequence
9.2. Drive not at target set point after 30 seconds (may be adjusted during commissioning) alarm,
stop sequence, close mill inlet damper (400-DA-015) and close mill fan inlet damper (400-DA010).
De-energize Solenoid 6S (400-XSV-1103) in mill Hydraulic Spring System 400-HP-010 as soon as the
mill drive is activated to lower the three rolls onto the material bed (this solenoid remains deenergized during normal mill operation). The rate at which the rollers are lowered is adjusted during
commissioning such that the rolls engage the material load on the bed as soon as the mill drive
reaches the set point speed.
10.1. No high roller indication after 10 seconds - continue sequence.
10.2. High roller indication after 10 seconds - alarm, stop sequence, raise mill rollers (see Section
10.1.2), stop mill main drive (400-EU-0009), close mill inlet damper (400-DA-015) and close
mill fan inlet damper (400-DA-010).
After a delay of approximately 30 seconds (exact timing TBD during commissioning), start the CRS
feed weigh belt 200-FD-085 at a rate of 75 mtph.
11.1. Feed weight belt motor running continue sequence
11.2. No motor operation detected alarm, stop sequence, raise mill rollers (see Section 10.1.2), stop
mill main drive (400-EU-0009), close mill inlet damper (400-DA-015) and close mill fan inlet
damper (400-DA-010).
Remove interlock on the Mill Table water spray.
After a delay of 10 seconds (exact delay time TBD during commissioning) following de-energizing of
Solenoid 6S (400-XSV-1103), energize Solenoid 8s (400-XSV-1102) in mill Hydraulic Spring System
400-HP-010 for normal operation. This solenoid remains energized during normal mill operation.
Check circuit hydraulic pressure (400-PISA-1107) this initial adjustment develops a soft grinding
mode of operation to minimize the potential for grinding instability during initial startup:
14.1. If less than 0.8 x accumulator pressure, start hydraulic pump motor 400-EM-1107 in Hydraulic
Spring System 400-HP-010. Stop motor 400-EM-1107 when the target pressure at 400-PISA1107 is obtained.
14.2. If greater than 0.8 x accumulator pressure, de-energize Solenoid 5S (400-XSV-1101) until the
target pressure at 400-PISA-1107 is obtained.
Following a mill operating period of 5 minutes (exact interval TBD during commissioning), adjust
the hydraulic pressure to the operator specified set point.
Following a mill operating period of 20 minutes the roller lube system pump (400-LU-011A, 400-LU-011B
and 400-LU-011C) motors (400-EM-0605, 400-EM-0612, 400-EM-0704, 400-EM-0708, 400-EM-0804, 400EM-0808) are started automatically.
Roller Mill Group operation under Feed Start conditions may continue as long as the following conditions
are satisfied:
1. The pressure differential across cyclone 400-CY-020 as measured by transducer 400-PDISCA-0200 is
greater than 75 mm WG,
2. Mill vibration is below the high-high limit of 15 mm/s as indicated by 400-XISA-0005,
3. The rollers do not reach their low limits indicated by 400-GBSA-0006, 400-GBSA-0008 and 400GBSA-0010,
42
4.
5.
6.
7.
Mill motor winding and bearing temperatures are below high-high levels (400-TISA-0020-27),
Mill motor power draw is below the high-high level (400-EISA-I-0009),
Classifier motor power draw is below the high-high level (400-EISA-I-0010),
Classifier bearing temperatures are below high-high levels (400-TISA-0001 and 400-TISA-0002).
If any of these limits are exceeded, the Roller Mill Group is shutdown and the Calciner Group is returned to a
System Idle mode and the operator is prompted with the option for a complete system shutdown.
400-CTL-01:
400-CTL-02:
400-CTL-03:
400-CTL-04:
The CRS rate may be increased in increments selected by the operator, up to a maximum rate of 106 mtph.
This maximum rate is password protected in the PCS and provides protection against over-feeding the
system. An over-feeding situation will result in low temperature alarm conditions, instability and an eventual
feed stop condition. PCS will prevent increases to the CRS feed rate if a low temperature condition of <90C
is encountered at the mill outlet (400-TICSA-0004).
b. Motor fault,
c. Emergency shutdown action,
d. The local maintenance switch is engaged.
7.
8.
9.
10.
When one or more of these conditions occur, the following actions are taken by the PCS:
1. Close Upper Mill Water Spray valve (400-TCV-0004) and Mill Table Water Spray valve (400-FCV0001),
2. De-energize the mill fan motor 400-EM-0223 and close mill fan inlet damper 400-DA-010,
3. Close the mill inlet damper 400-DA-085,
4. Stop the CRS feed system 200-FD-085 and mill feed rotary valve 400-AL-010,
5. Raise the mill rollers:
a. De-energize Solenoid 8S (400-XSV-1102),
b. Energize Solenoid 6S (400-XSV-1103),
c. Energize Solenoid 4S (400-XSV-1104),
d. Start pump motor 400-EM-1107,
e. Stop motor 400-EM-1107when roller hit their high limit switches 400-GBS-0007, 400-GBS0009 and 400-GBS-0011,
f. De-energize Solenoid 4S (400-XSV-1104).
6. Stop the main mill drive motor 400-EM-0009,
7. Stop main drive lube pump motor 400-EM-0524 one minute after stopping the main mill drive
motor 400-EM-0009.
8. Stop the classifier drive motor 400-EM-0010,
9. Stop the classifier drive lube pump motor 400-EM-0015 one minute after stopping the classifier
drive motor 400-EM-0010,
10. Stop roller lube system pump (400-LU-011A, 400-LU-011B and 400-LU-011C) motors (400-EM0605, 400-EM-0612, 400-EM-0704, 400-EM-0708, 400-EM-0804, 400-EM-0808).
PCS Display
Roller Mill
Reference Tag
400-ML-010
400-EM-0009
400-EU-0009
400-EISA-I-0009
400-TISA-0022-27
400-TISA-0020-21
400-PDICA-0035
400-GBS-0007
400-GBS-0009
400-GBS-0011
400-GBSA-0006
400-GBSA-0008
400-GBSA-0010
400-XISA-0005
400-PDIA-0001
400-EM-0003
400-SSA-0003
400-TICSA-0004
400-TSA-0005
Dynamic Classifier
400-CI-015
Drive Motor
400-EM-0010
400-EISA-I-0010
400-EU-0010
Rotor Speed
400-SI-0010
400-TISA-0001-02
Mill Cyclone
400-CY-020
400-PDICSA-0200
Cone Temperature
400-TI-0203
Cone Pressure
400-PIA-0201
400-AL-020
400-EM-0222
400-SSA-0260
ESP Cyclone
400-CY-025
400-PDIA-0249
Cone Temperature
400-TI-0243
Cone Pressure
400-PIA-0244
46
400-AL-025
400-EM-0224
400-SSA-0250
400-TISA-0250
a. Increase the mill table speed via variable frequency drive 400-EU-0009.
2. If the roller mill louver differential pressure 400-PDICA-0035 is less than the operator set point:
b. Decrease the mill table speed via variable frequency drive 400-EU-0009.
This control loop can be deactivated at the discretion of the operator.
48
4.4 ALARMS
Alarm Trigger
Device
Alarm Condition
Low Low
Mill Off Gas Temperature
Low
High
400-TICSA-0004
High High
Mill Off Gas Temperature
Debounce Value
66C
0 sec
77C
0 sec
100C
0 sec
115C
0 sec
High High
400-TSA-0005
115C
0 sec
High
400-XISA-0005
12 mm/s
0 sec
High High
400-XISA-0005
15 mm/s
1 sec
Roller #1 Position
Low
400-GBSA-0006
5 sec
Roller #2 Position
Low
400-GBSA-0008
5 sec
Roller #3 Position
Low
5 sec
Low Low
400-GBSA-0010
400-PDICA-0035
<200mm WG
0 sec
Low
400-PDICA-0035
<400mm WG
0 sec
High
400-PDICA-0035
>700mm WG
0 sec
High High
400-PDICA-0035
>800mm WG
0 sec
Low
400-PDIA-0001
<300mm WG
0 sec
High
400-PDIA-0001
>800mm WG
0 sec
High
400-TISA-0022-27
>120C
0 sec
High High
400-TISA-0022-27
160C
0 sec
High
400-TISA-0020-21
>85C
0 sec
High High
400-TISA-0020-21
90C
0 sec
High
400-EISA-I-0009
>TBD kW
5 sec
High High
400-EISA-I-0009
TBD kW
5 sec
High
400-EISA-I-0010
>TBD kW
5 sec
High High
400-EISA-I-0010
TBD kW
5 sec
High
400-TISA-0001-02
93C
0 sec
High High
400-TISA-0001-02
99C
0 sec
Low
400-SSA-0003
5 sec
High
400-PDICSA-0200
>150mm WG
0 sec
Low
<75mm WG
0 sec
Low Low
400-PDICSA-0200
400-PDICSA-0200
<50mm WG
5 sec
High
400-PIA-0201
>(-700)mm WG
0 sec
Mill Vibration
Pressure
High High
400-PIA-0201
>(-500)mm WG
0 sec
Low
400-SSA-0260
5 sec
ESP Cyclone
Differential Pressure
High
400-PDIA-0249
>200mm WG
5 sec
Low
400-TISA-0250
<100C
0 sec
High
400-TISA-0250
>310C
0 sec
High High
400-TISA-0250
325C
2 sec
Low
400-SSA-0250
5 sec
High
400-PIA-0244
>(-75)mm WG
0 sec
High High
400-PIA-0244
>(-25)mm WG
0 sec
ESP Cyclone
Overflow
Temperature
ESP Cyclone Rotary
Valve Speed
ESP Cyclone Cone
Pressure
4.5 INTERLOCKS
Equipment
Signals
Sample:
(X AND Y AND Z); Z to start, X
AND Y to run, X for safety
shutdown
Interlock Type
Safety
Process
50
Start
Equipment
Signals
Interlock Type
Safety
Process
Start
1. Close dampers 400-DA-050, 400-DA-010, 400-DA-030, and 400-DA-035. Check closed contacts at
switches 400-GIS-0261, 400-GBS-0130B, 400-GBS-0302B, and 400-GBS-0460B.
2. Move tempering tee 400-DA-034 in its full open position such that switch 400-GIS-0328 is closed.
3. Move mill bypass damper 400-DA-020 to its full open position as indicated by 400-GI-0163.
4. Start ESP ID fan 400-FN-030 motor 400-EM-0321. Wait 60 seconds after contact is proved.
5. Move the ESP ID fan damper 400-DA-030 to 5% open.
6. Start dilution air fan 400-FN-035 motor 400-EM-0323. Wait 60 seconds after contact is proved.
7. Start mill fan 400-FN-020 motor 400-EM-0223. Wait 60 seconds after contact is proved.
8. Start combustion air fan 400-FN-050 motor 400-EM-0461. Wait 60 seconds after contact is proved.
9. Start grid cooling air fan 400-FN-055 motor 400-EM-0124.
This arrangement supplies required cooling air to the burner and air heater jacket at the minimum allowable
air flow rate.
52
PCS Display
Reference Tag
400-FN-050
Fan Motor
400-EM-0461
400-TISA-0482-87
400-TISA-0480-81
400-SS-0401
Modulating Damper
400-DA-050
400-EM-0460
400-FCV-0460
400-GIS-0460
400-GBS-0460A
400-GBS-0460B
400-GBS-0460C
400-FFIC-0460
400-PSA-0462
400-FN-035
Fan Motor
400-EM-0323
400-EIA-I-0323
400-TISA-0335-40
400-TISA-0333-34
400-TISA-0331-32
400-PS-0302
400-SS-0302
Modulating Damper
400-DA-035
400-EM-0322
400-GIS-0140
400-TCV-0140
400-GBS-0302A
400-GBS-0302B
400-GBS-0302C
400-FIA-0301
Tempering Tee
Motor Actuator
400-DA-034
X
400-HIC-0328
Motor
400-EM-0328
Position Indication
400-GIS-0328
400-GBS-0328A/B
ESP ID Fan
400-FN-030
Fan Motor
400-EM-0321
400-EIA-I-0321
400-TISA-0316-21
400-TISA-0314-15
Fan Vibration
400-XISA-0312-13
400-TISA-0312-13
400-SS-0301
400-PS-0301
Modulating Damper
400-DA-030
400-GIS-0130
400-PCV-0130
400-GBS-0130A
400-GBS-0130B
400-GBS-0130C
400-FN-020
Fan Motor
400-EM-0223
400-EIA-I-0223
400-TISA-0229-34
400-TISA-0227-28
Fan Vibration
400-XISA-0221-22
400-TISA-0225-26
400-SS-0201
400-PS-0202
Modulating Damper
54
400-DA-010
400-GIS-0261
400-PDCV-0200
400-GBS-0200A
400-GBS-0200B
400-PDIA-0262
400-DA-020
400-EM-0121
Lake Magadi Functional Specification Rev 2
400-HIC-0163
400-GI-0163
400-GBS-0163A
400-TI-0160
400-DA-015
400-EM-0118
X
400-FN-055
X
400-GBS-0165
400-EM-0124
400-DA-055
400-FI-0137
This control loop is deactivated only by the PCS when the roller mill is shutdown or by the operator.
5.4 ALARMS
Alarm Trigger
Device
Debounce Value
400-PDIA-0262
500 mm WG
5 sec
High
400-XISA-0221-22
>12 mm/s
0 sec
High High
400-XISA-0221-22
15 mm/s
1 sec
High
400-TISA-0225-26
100C
0 sec
High High
400-TISA-0225-26
110C
0 sec
High
400-TISA-0227-28
85C
0 sec
High High
400-TISA-0227-28
90C
0 sec
High
400-TISA-0229-34
120C
0 sec
High High
400-TISA-0229-34
160C
0 sec
High
400-EIA-I-0223
870 kW
2 sec
High
400-TISA-0480-81
85C
0 sec
High High
400-TISA-0480-81
90C
0 sec
Alarm Condition
Mill Fan Damper Pressure
Differential
Mill Fan Vibration
Mill Fan Bearing
Temperature
Mill Fan Motor Bearing
Temperature
Mill Fan Motor Winding
Temperature
Mill Fan Motor Power
Draw
Combustion Air Fan Motor
Bearing Temperature
High (400-CTL-03
Activated)
High
400-TISA-0482-87
120C
0 sec
High High
400-TISA-0482-87
160C
0 sec
400-PSA-0461
5 sec
High
400-XISA-0312-13
>12 mm/s
0 sec
High High
400-XISA-0312-13
15 mm/s
1 sec
High
400-TISA-0312-13
100C
0 sec
High High
400-TISA-0312-13
110C
0 sec
High
400-TISA-0314-15
85C
0 sec
High High
400-TISA-0314-15
90C
0 sec
High
400-TISA-0316-21
120C
0 sec
High High
400-TISA-0316-21
160C
0 sec
High
400-EIA-I-0321
825 kW
2 sec
Low
400-PIA-0326
<-100mm WG
5 sec
High
400-PIA-0326
>100mm WG
5 sec
High
400-TISA-0327
140C
2 sec
High High
400-TISA-0327
150C
5 sec
56
High
400-TISA-0331-32
100C
0 sec
High High
400-TISA-0331-32
110C
0 sec
High
400-TISA-0333-34
85C
0 sec
High High
400-TISA-0333-34
90C
0 sec
High
400-TISA-0335-40
120C
0 sec
High High
400-TISA-0335-40
160C
0 sec
400-EIA-I-0323
350 kW
2 sec
High
5.5 INTERLOCKS
Equipment
Signals
Sample:
(X AND Y AND Z); Z to start, X AND
Y to run, X for safety shutdown
Interlock Type
Safety
Start
X
X
Process
6 ESP GROUP
The ESP Group consists of a 4-compartment Electrostatic Precipitator (400-EP-030), ESP Dust Screw (400SC-040) and ESP Dust Purge Valve (400-AL-030). These components are referenced on the following
C&ID drawings:
performed by the PIACS local PLC upon receiving a single Start command from the PCS. The local
PIACS controller will energize all fields simultaneously at a reduced current and ramp to the target power
settings as per the specified ramp function (required to minimize inrush current). The PIACS will return a
confirmation signal as each field is successfully energized. The field shall be highlighted in the PCS display
once this confirmation is received to give the operator a clear indicator of which fields are active. Once
started, the PIACS controller will adjust field conditions and rapper operation to optimize the overall
performance of the ESP.
Once the PCS receives conformation that all fields are energized, the PCS sends a start command to the
PIACS system to activate the electrode cleaning rappers. The actual rapper operation is then controlled by
the PIACS.
1. Check for emergency stop or maintenance setting at the PIACS. If not present, display a start
permissive on the PCS screen,
2. Check for operation of Dust Purge Rotary Valve 400-AL-030:
a. If 400-SSA-0330 indicates operation, continue sequence.
b. If 400-SSA-0330 indicates that 400-AL-030 is not active, stop sequence and alarm.
3. The operator manually selects the ESP Dust Screw and selects start,
4. The PCS sends a start signal to the motor starter for 400-EM-0306,
5. The PCS checks for screw shaft motion confirmation from 400-SSA-0305:
a. If received in <5 seconds, confirm operation and highlight screw icon on PCS display to
denote operation.
b. If not received in 5 seconds, the motor is de-energized and an alarm is displayed.
6. Once a successful start is achieved, the screw is de-energized via:
a. Stop command from the operator,
b. A loss of shaft motion detection at 400-SSA-0305,
c. Motor fault signal from motor starter (400-EM-0306),
d. Emergency shutdown action,
e. Dust Purge Rotary Valve 400-AL-030 is stopped.
60
PCS Display
Electrostatic Precipitator
Reference Tag
400-EP-030
400-HS-1014,30,67,87
N/A
400-EE-1001,31,51,71,91
400-TE-1017,46,64,84,89
400-LSA-1016,45,65,85,90
400-KSV-1001,02,03,04,
05,06,07,08
Purge Fan
400-GB-030
400-EM-1030
400-FSA-1099
PIACS-DC PLC
N/A
Inlet Pressure
400-PI-0300
Outlet Temperature
400-TISA-0302
400-SC-040
400-SSA-0305
Screw Motor
400-EM-0306
400-AL-030
400-SSA-0330
Valve Motor
400-EM-0330
400-GA-040
Solenoid Valve
400-KSV-0301
400-GS-0301
400-QIA-1401
6.4 ALARMS
Alarm Trigger
Device
Debounce
Value
High
400-QIA-1401
0 sec
High High
400-QIA-1401
>50mg Nm3
equivalent
0 sec
High
400-TISA-0302
300C
0 sec
High High
400-TISA-0302
315C
0 sec
Low
400-SSA-0305
5 sec
Low
400-PIA-0300
-600 mm WG
2 sec
Low
400-SSA-0329
5 sec
Low
400-SSA-0330
5 sec
High
400-LSA-1016,
45,65,85
10 sec
Alarm Condition
ESP Outlet Opacity Level
6.5 INTERLOCKS
Equipment
62
Signals
Interlock Type
Lake Magadi Functional Specification Rev 2
Safety
Sample:
(X AND Y AND Z); Z to start, X AND Y
to run, X for safety shutdown
Process
X
Start
Electrode Rappers On
ESP Rappers
7 CLEANING GROUP
The Cleaning Group includes the Air Cannons (400-AC-020/021/025/026/060/061) and Rappers (400-VB020/021/022/023/024/025/026/027/028/029/060/061/062) mounted on the cyclone cones and discharge
ducts for the purpose of maintaining stable solids flow through the system. Several modes of operation are
available for these devices. Components are referenced on the following C&ID drawings:
evaluations. The cannons remain charged with compressed air at all times unless the manual air supply valves
are closed. The PCS highlights the air cannon icon on the display at the time that the solenoid is being
energized. If set for automatic timed firing, the active cannon icons are highlighted appropriately. The air
cannons may be operated in several different modes as determined by the operator.
This specification does not require the operation of the ESP ID fan to enable air cannon firing. This
interlock should be considered as the operation of the ESP ID fan will place the system under
suction and minimize the potential for nuisance dust emissions when an air cannon is fired.
64
5. The manual firing sequence may be repeated after 10 seconds has elapsed from the firing of
the last cannon in the selected sequence.
6. The selected air cannons in the group may be changed after the sequence has been completed.
7.1.2 RAPPERS
Rappers are utilized to promote material flow via high amplitude/low frequency vibrations. Thirteen rappers
are installed for initial system startup, but provisions must be made to accommodate the control of 9
additional units should they be required based on commissioning evaluations. The PCS highlights the rapper
icon on the display at the time that the solenoid is being energized. If set for automatic timed firing, the
active devices are highlighted appropriately. The rappers may be operated in several different modes as
determined by the operator:
1.
The device remains active until a Stop command is received from the operator or an emergency stop action
occurs.
Cleaning Group
Description
Air Cannons on 400-CY-060 Cone
PCS Display
Reference Tag
400-AC-060/061
Solenoid Valves
Vibrators/Rappers on 400-CY-060 Cone
400-XSV-0144/45
X
Solenoid Valves
Air Cannons on 400-CY-020 Cone
400-XSV-0141/42/43
X
Solenoid Valves
Vibrators/Rappers on 400-CY-020 Cone
66
400-VB-060/061/062
400-AC-020/021
400-XSV-0204/05
400-VB-020/021/022
Solenoid Valves
400-XSV-0206/07/08
Solenoid Valves
400-VB-023/024
400-XSV-0271/72
Solenoid Valves
400-AC-025/026
400-XSV-0241/42
Solenoid Valves
400-VB-025/026/027
400-XSV-0245/46/47
Solenoid Valves
400-VB-028/029
400-XSV-0171/72
7.4 ALARMS
There are no alarms associated with the operation of the Cleaning Group.
7.5 INTERLOCKS
Equipment
Signals
Sample:
(X AND Y AND Z); Z to start, X AND Y to run,
X for safety shutdown
X
Y
No Emergency Stop
Activate Vibrators/Rappers
No Emergency Stop
Interlock Type
Safety
Start
Process
X
X
X
X
PCS Display
Reference Tag
400-AL-040
Motor
400-EM-0329
400-EU-0329
Motion Switch
400-SSA-0329
400-GA-040
Solenoid Valve
Position Indicating Switches O/C
400-KSV-0301
X
400-GS-0301
400-GB-040
Motor
400-EM-0313
400-PSA-0341
400-PI-0342
X
400-TSA-0343
400-SV-0344
400-PN-040
400-BN-010
400-LS-0104
400-LS-0105
400-SV-0101
400-DC-010
400-PDIS-0101
400-PC-0103
400-PI-0102
Pulse Timer
400-KIS-0101
400-KSV-0101
400-AL-045
Motor
400-EM-0103
400-EU-0103
Motion Switch
400-SSA-0105
400-SI-0106
8.4 ALARMS
Alarm Condition
Alarm Trigger
Device
Debounce Value
No Motion
400-SSA-0329
5 sec
High
400-PSA-0341
0.5 bar
2 sec
High
400-TSA-0343
80C
0 sec
No Motion
400-SSA-0105
5 sec
8.5 INTERLOCKS
Equipment
Signals
Sample:
(X AND Y AND Z); Z to start, X AND Y
to run, X for safety shutdown
Safety
Start
Process
70
Interlock Type
PCS Display
Reference Tag
n/a
400-FCV-0001
400-FICA-0001
400-GBS-0001
400-FSV-0040
n/a
400-PDA-0901/02
400-PDI-0901/02
Water Tank
400-PP-010-A
Pump
400-LSA-0903
400-PP-010
Pump Motor
400-EM-0905
400-PI-0906
400-SV-0902
400-FIA-0002
400-TCV-0004
400-GBS-0002A
400-GIS-0002
400-PI-0002
9.4 ALARMS
Alarm Condition
Alarm Trigger
Device
Debounce Value
High
400-PDA-0901/02
5 sec
Low
400-LSA-0903
5 sec
High/Low
400-FICA-0002
+/-25%
5 sec
High/Low
400-FIA-0002
+/-25%
5 sec
9.5 INTERLOCKS
72
Equipment
Signals
Sample:
(X AND Y AND Z); Z to start, X AND Y to
run, X for safety shutdown
Interlock Type
Safety
Start
Process
400-CTL-05 Activated
c.
The pump is stopped by the PCS once the rollers are in their raised positions as indicated by
position switches 400-GBS-0007, 400-GBS-0009 and 400-GBS-0011 and 400-PS-1103
closes.
d. Solenoid 400-XSV-1104 (4S) is de-energized to hold the rollers in the raised position.
e. If a high position indication from any of the three high position switches is lost (400-GBS0007, 400-GBS-0009 and 400-GBS-0011) or switch 400-PS-1103 opens, the hydraulic pump
will be started by the PCS and Solenoid 400-XSV-1104 (4S) energized until high level
indication is obtained and the pressure switch is closed. The PCS will then de-energize 400XSV-1104.
2. The CRS Feed Belt 200-FD-085 is stopped as a result of a normal stop, interlock action or
emergency action:
a. If hydraulic pump motor is not running, a start command is sent to the starter for hydraulic
pump motor 400-EM-1107.
b. Solenoids 400-XSV-1104 (4S), 4000-XSV-1101 (5S) and 400-XSV-1103 (6S) are energized.
Solenoid 400-XSV-1102 (8S) is de-energized.
c. The pump is stopped by the PCS once the rollers are in their raised positions as indicated by
position switches 400-GBS-0007, 400-GBS-0009 and 400-GBS-0011 and closure of pressure
switch 400-PS-1103..
d. Solenoid 400-XSV-1104 (4S) is de-energized to hold the rollers in the raised position.
e. If a high position indication from any of the three high position switches is lost (400-GBS0007, 400-GBS-0009 and 400-GBS-0011), the hydraulic pump will be started by the PCS and
Solenoid 400-XSV-1104 (4S) energized until high level indication is obtained and the
pressure switch closes. The PCS will then de-energize 400-XSV-1104.
This sequence can also be performed manually by the operator by selecting Raise Rollers from the Roller
Mill Start menu. Starting of the main mill drive cannot be performed unless the rollers are in their raised
position.
74
operation and then increases the pressure to the set point value. This initial operation at a lower pressure
improves mill stability and reduces the potential for a low roller position fault.
The pressure control sequence performed by the PCS is as follows:
1. Following a delay of 10 seconds after the PCS initiates lowering of the rollers, energize Solenoid 400XSV-1102 (8S). This solenoid remains energized during normal mill operation.
2. Check circuit hydraulic pressure (400-PISA-1107):
2.1. If >1.75 bar below 0.8 x Set Point, start hydraulic pump motor 400-EM-1107. Stop motor 400-EM1107 when the target pressure at 400-PISA-1107 is obtained.
2.2. If >3.5 bar above 0.8 x Set Point, de-energize Solenoid 5S (400-XSV-1101) until the target pressure
at 400-PISA-1107 is obtained and then re-energize.
3. After 10 minutes, adjust the hydraulic pressure (400-PISA-1107) to the set point and maintain:
3.1. If >1.75 bar below the set point, start hydraulic pump motor 400-EM-1107. Stop motor 400-EM1107 when the target pressure at 400-PISA-1107 is obtained.
3.2. If >3.5 bar above the set point, de-energize Solenoid 5S (400-XSV-1101) until the target pressure at
400-PISA-1107 is obtained and then re-energize.
PCS Display
Hydraulic Reservoir
Reservoir Level Switch
Reference Tag
400-HP-010A
400-LSA-1110
400-LI-1111A/B
Hydraulic Pump
400-HP-010B
400-EM-1107
400-PI-1102
400-PDA-1101
400-SV-1102
400-SV-1103
400-SV-1101
400-PDA-1100
400-PDI-1100
400-PS-1103
400-PS-1104
400-PI-1105
400-PI-1106
400-PISA-1107
Solenoid 5S
400-XSV-1101
Solenoid 8S
400-XSV-1102
Solenoid 6S
400-XSV-1103
Solenoid 4S
400-XSV-1104
10.4 ALARMS
Alarm Trigger
Analog Set
point
Debounce Value
400-EM-1107 Starter
400-EM-1107 Contact
5 min
400-PDA-1101
1.7 bar
5 sec
400-PDA-1100
1.7 bar
5 sec
High
400-PISA-1107
>3.5 bar
Above Set
Point
5 sec
Low
400-PISA-1107
5 sec
Low Low
400-PISA-1107
5 sec
Alarm Condition
Cylinder Pressure
10.5 INTERLOCKS
Equipment
Interlock
Type
Signals
Safety
Sample:
(X AND Y AND
Z); Z to start, X
AND Y to run, X
for safety shutdown
Raise Rollers
Solenoids 400XSV-1104 & 400XSV-1103
76
Start
Process
X
Equipment
Interlock
Type
Signals
Safety
Start
Process
Lower Rollers
Solenoid 400XSV-1103
Hydraulic Pump
Start (400-HP010B)
11 LUBRICATION GROUP
11.1 FUNCTIONAL DESCRIPTION
The Lubrication Group consists of the Roller Mill Main Drive Lubrication System (400-LU-010), the Roller
Mill Roller Lubrication System (400-LU-011A, 400-LU-011B, and 400-LU-011C), the Roller Mill Grease
System (400-ML-010A), the Classifier Drive Lubrication System (400-LU-015), and the Classifier Grease
System (400-CI-015A).
Lubrication Group components are referenced on the following C&ID drawings:
Lubrication Group
Description
PCS Display
400-LU-010
Fluid Reservoir
Reservoir Temperature Switch
78
Reference Tag
n/a
400-TI-0527
400-TI-0528
400-LI-0526
400-LSA-0525
400-EM-0524
400-SV-0523
400-PI-0524
400-PI-0522
400-PI-0520
400-PDA-0521
400-TI-0519
400-TCV-0501
400-TI-0506
400-PI-0506
400-TI-0504
400-PI-0504
Pressure Indicator
400-PI-0503
400-TISA-0507
400-PS-0501
400-PSA-0502
400-PI-0503
400-PI-0505
400-TISA-0510
400-TISA-0508
400-LU-011A/011B/011C
Lube Reservoir
n/a
400-EE-0601/0701/0801
400-TIS-0605/0705/0805
400-TSA-0604/0704/0804
400-LI-0605/0705/0805
400-LSA-0601/0701/0801
400-LSA-0611/0711/0811
400-EM-0605/0704/0804
400-EM-0612/0708/0808
400-PI-0602/0702/0802
X
400-FIA-0602/0702/0802
400-PDI-0600/0700/0800
X
400-PDI-0610
X
400-FISA0607/0707/0807
400-PDI-0606/0706/0806
400-PDA-0606/0706/0806
400-PI-0609/0709/0809
400-ML-010A
Grease Reservoir
n/a
400-EM-0030
400-LA-0030
400-GA-0030
400-SV-0030
400-LU-015
Lube Reservoir
Reservoir Level Indicator
n/a
X
400-LI-0005
400-EM-0015
400-SV-0016
n/a
400-PDA-0012
400-PI-0012
Heat Exchanger
400-LU-015-H2
400-TS-0014A
400-TA-0014B
400-TI-0016
400-TS-0018
400-PSA-0017
400-PI-0018
400-TI-0020
400-PA-0601
400-TCV-0603/0703/0803
400-PDA-0600/0700/0800
400-FZA-0019
400-CI-015A
n/a
400-EM-0020
400-LA-0020
400-GA-0020
400-SV-0020
11.4 ALARMS
Alarm Trigger
Device
Alarm Condition
High
400-LSA-0525
>2200 liters
5 sec
Low
400-LSA-0525
<1200 liters
5 sec
High
400-PDA-0521
>2.5 bar
5 sec
Low
Motor Starter
400-TISA-0507
18C
0 sec
High
400-TISA-0507
47C
0 sec
High High
400-TISA-0507
49C
0 sec
Low
400-TISA-0510
18C
0 sec
High
400-TISA-0510
75C
0 sec
High High
400-TISA-0510
85C
0 sec
400-PA-0501
<2.8 bar
5 sec
<2.5 bar
5 sec
High
400-PSA-0502
400-TISA-0508
56C
0 sec
High High
400-TISA-0508
60C
0 sec
Fluid Temperature
Low
Low Low
400-LSA0601/0701/0801
5 min
High
400-LSA0611/0711/0811
5 min
2.3 lpm
30 sec
1.7 bar
TBD
Low
High
400-FSA0607/0707/0807
400-PDA0606/0706/0806
High
400-PDA0600/0700/0800
1.7 bar
TBD
Low
400-FA0602/0702/0802
2.3 lpm
30 sec
Reservoir Fluid
Temperature
400-TSA0604/0704/0804
27C
30 sec
Motor Starter
Motor Starter
400-PA-0601
TBD
Low
Low
Low
400-LA-0030
0 sec
Distribution Block
Sequence
Not Complete
400-GA-0030
2 min
Motor Starter
82
Low
400-FZA-0019
4 lpm
2 sec
Low Low
400-PSA-0017
0.35 bar
2 sec
400-TA-0014
90C
2 sec
400-TSA-0018
100C
2 sec
High
400-PDA-0012
0.35 bar
2 sec
High
400-EISA-I-0010
TBD
TBD
High High
400-EISA-I-0010
TBD
TBD
Low
400-LA-0020
0 sec
Not Complete
400-GA-0020
2 min
Motor Starter
11.5 INTERLOCKS
Equipment
Signals
Sample:
(X AND Y AND Z); Z to start, X AND
Y to run, X for safety shutdown
X
Y
Interlock Type
Safety
Start
X
X
X
Process
Signals
Sample:
(X AND Y AND Z); Z to start, X
AND Y to run, X for safety shutdown
Interlock Type
Safety
Start
84
Process
X
X
Equipment
Signals
Interlock Type
Start
Process
Safety
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
6.11
date
2005-06-30
rev
6.9
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
DATE: FEB,28,2005
REV. 0
Calciner:
1. Stop feed, shutdown and cool system as per the Operating Instructions.
2. Shutdown all fans except the ID fan and prepare system for access as per
the Operating Instructions. Adjust the ID fan inlet damper to obtain 2550mm suction in the calciner plenum.
3. Open one access hatch on the calciner plenum to permit the discharge of
wash water. Exercise caution when opening this hatch as hot material
may have accumulated behind the hatch. Personnel should be positioned
such that the discharge of hot material through the hatch will not result in
personnel injury.
4. Once the hatch is open, clear material away and setup a containment area
to collect wash water discharging through the hatch.
5. Open the uppermost inspection port on the calciner. Perform cleaning as
required, close port and proceed to the next lowest port. Repeat this
procedure until the calciner has been cleaned at all levels above the grid
plate.
6. Open one or more hatches above the grid plate level. Clean the lower
calciner area, feed inlet splash box, and upper grid surface. Close
hatches and secure. This cleaning should be performed without entering
the calciner. If entry is required, follow plant procedures for confined
space entry and ensure that there are no coatings in the calciner that
could break free from the calciner walls and injure personnel.
7. Open the inspection port below the grid plate. Perform a wash down of
the lower plate surface if required and then close the port.
8. Open the remaining hatches on the calciner plenum section while
exercising caution against hot material that may be accumulated on the
back side of the hatch. Wash down the plenum inventory and direct it to
the hatch opening where the containment area has been setup. Use tools
as required to pull sludge and free standing water from the plenum. Once
complete close and secure all hatches.
Calciner Collection Cyclone:
1. Stop feed, shutdown and cool system as per the Operating Instructions.
2. Shutdown all fans except the ID fan and prepare system for access as per
the Operating Instructions. Adjust the ID fan inlet damper to obtain 2550mm suction at the calciner exit.
3. Position the diverter gate to direct cyclone discharge to the dump tank.
4. Activate cycling of the discharge tipping gates.
5. Open an inspection hatch on the cyclone body. Utilize a high intensity
light source to inspect the cyclone interior.
6. If material is observed above the tipping gates and there is no material
flow to the dump tank, close the inspection hatch and activate the cyclone
cone rappers. If this does not initiate material flow, activate the air
cannons. Once it is confirmed that all ports on the calciner system are
closed and no one is working inside the system, fire the air cannons.
7. Once the cone inventory has been discharged and the cone area has
been allowed to cool, proceed with the final wash down.
8. Following completion of the wash down, close and seal all hatches.
Calciner Off Gas Ducting:
1. There are no provisions for wash down of this ducting.
Roller Mill:
1. Stop feed, shutdown and cool system as per the Operating Instructions.
2. Shutdown all fans except the ID fan and prepare system for access as per
the Operating Instructions. Close the mill inlet shutoff damper (if not
already closed) and adjust the ID fan inlet damper to obtain 25-50mm
suction at the mill inlet. Close down the mill bypass damper if required to
generate the necessary mill inlet suction.
3. Ensure that the mill rollers and table are cool before adding water to the
mill as these large castings may crack due to thermal shock.
4. Open the mill body inspection hatch. Wash down the classifier louvers,
mill body and upper inlet louver area as required. Once complete, close
the hatch.
5. Open the mill plenum inspection hatch. Wash down the plenum area and
underside of the louvers as required. Close hatch.
Roller Mill Cyclone:
1. Stop feed, shutdown and cool system as per the Operating Instructions.
2. Shutdown all fans except the ID fan and prepare system for access as per
the Operating Instructions. Adjust the ID fan inlet damper to obtain 2550mm suction at the roller mill exit.
3. Blank off the material discharge duct and remove the blank to the dump
line. Position a collection hopper under the line.
4. Activate the discharge rotary valve.
5. Open an inspection hatch on the cyclone body. Utilize a high intensity
light source to inspect the cyclone interior.
6. If material is observed above the rotary valve and there is no material flow
to the dump bin, close the inspection hatch and activate the cyclone cone
rappers. If this does not initiate material flow, activate the air cannons.
Once it is confirmed that all ports on the calciner system are closed and
no one is working inside the system, fire the air cannons.
7. Once the cone inventory has been discharged and the cone area has
been allowed to cool, proceed with the wash down.
8. Following completion of the wash down, close and seal all hatches.
ESP Cyclone:
1. Stop feed, shutdown and cool system as per the Operating Instructions.
2. Shutdown all fans except the ID fan and prepare system for access as per
the Operating Instructions. Adjust the ID fan inlet damper to obtain 2550mm suction at the ESP cyclone inlet.
3. Blank off the material discharge duct and remove the blank to the dump
line. Position a collection hopper under the line.
4. Activate the discharge rotary valve.
5. Open an inspection hatch on the cyclone body. Utilize a high intensity
light source to inspect the cyclone interior.
6. If material is observed above the rotary valve and there is no material flow
to the dump bin, close the inspection hatch and activate the cyclone cone
rappers. If this does not initiate material flow, activate the air cannons.
Once it is confirmed that all ports on the calciner system are closed and
no one is working inside the system, fire the air cannons.
7. Once the cone inventory has been discharged and the cone area has
been allowed to cool, proceed with the wash down.
8. Following completion of the wash down, close and seal all hatches.
ESP Plates/Hopper:
1. Stop feed, shutdown and cool system as per the Operating Instructions.
2. Shutdown all fans except the ID fan and prepare system for access as per
the Operating Instructions. Adjust the ID fan inlet damper to obtain 2550mm suction at the ESP inlet.
3. Activate the ESP fines purge rotary valve and ESP screw.
NOTE: The ESP is a source of extremely high electrical voltage capable of
severely injuring or killing personnel. The voltage cannot be seen or detected
in any way without instrumentation. Only properly trained individuals
following all plant and ESP manufactures recommendations for safety shall
clean the ESP.
4. Open an inspection hatch on the ESP body. Utilize a high intensity light
source to inspect the ESP interior.
5. If material is observed above the screw and there is no material flow to the
ESP fines purge circuit, close the inspection hatch and activate the hopper
rappers.
6. Inspect the collection plates. If heavy coatings are observed, close the
unit and activate the plate rappers. Permit several rapping cycles, deenergize and then inspect.
7. Once the hopper inventory has been discharged proceed with the wash
down.
8. Following completion of the wash down, close and seal all hatches.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.1
date
2005-06-30
rev
CRYSTALLIZATION
7.1
Process description
7.1.1
Introduction
The crystallization section serves to remove impurities from milled calcined soda ash.
The ground calcine is expected to contain 95.4% sodium carbonate, 3.0% sodium
fluoride, 0.26% sodium chloride, 0.84% sodium sulfate, and 0.5% insoluble material.
The re-crystallization process will include two stages. Both stages are necessary to
achieve the required product purity. In the first stage hot, dry anhydrous soda ash is
slurried with near-saturated sodium carbonate solution to produce sodium carbonate
monohydrate. The anhydrous sodium carbonate dissolves as sodium carbonate
monohydrate crystallizes. The operating conditions provide for the growth of well formed
sodium carbonate monohydrate crystals while the other impurities either dissolve or
remain as very small solid particles. The resulting slurry is then transferred to the first
stage elutriator where the fine impurities are flush out the top while the larger
monohydrate crystals settle and are separated on the first stage centrifuges.
In the second stage process, the sodium carbonate monohydrate crystals from the first
stage are combined with saturated liquor and this slurry is transferred to the anhydrous
reactor, where it is heated above the transition temperature. The monohydrate crystals
dissolve while anhydrous sodium carbonate crystallizes. The anhydrous slurry is then
transferred to the second stage crystallizer where it is cooled below the transition
temperature, causing the anhydrous crystals to dissolve while monohydrate crystals form.
The second stage elutriator separates the fines from the coarse product and the second
stage centrifuges recover the monohydrate product.
Each time the re-crystallization is performed, insoluble impurities are liberated and
separated, resulting in a purer product.
7.1.2
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.2
date
2005-06-30
rev
through first stage scrubber 510-DC-015 to recover entrained dust and liquor. 510-EV-010
is provided with a wall wash to periodically wash and dissolve any wall accretions.
The scrubber sprayers are fed directly with cold process water. In this way water
condensation in the scrubber is increased which improves the scrubber efficiency for dust
removal.
The scrubber liquor discharge is cooled with process water feed to the hot process water
tank 520-TK-091. In this way heat is removed from the first stage crystallization system:
less water vapor is emitted to atmosphere, and process water feed to the hot process
water tank 520-TK-091 is preheated.
The first-stage crystallizer is circulated by a bottom entry draft tube agitator 510-AG-010.
The agitator induces an internal circulation of slurry up the draft tube and down the
annular region outside the draft tube. The incoming ground calcine is sluiced with slurry in
the hydrator and combined with the bulk circulating slurry in the crystallizer. The calcine
(anhydrous sodium carbonate) dissolves and re-crystallizes as sodium carbonate
monohydrate. Control of supersaturation levels through retention time, recirculation rate,
and crystal slurry density control allows the crystals to grow to the desired average size of
350 microns. The first stage crystallizer will operate at about 97 to 98C and 35% solids
and will provide two hours of retention time. The crystallization chemistry is shown below.
Na2CO3 (calcine) Na2CO3 (aq)
Na2CO3 (aq) + H2O Na2CO3.H2O (monohydrate)
The magma withdrawn from the first-stage crystallizer is pumped to the top of the first
stage elutriator 510-SP-025. Overflow liquor from the first stage settler 510-TK-050 is
pumped to the bottom of the first stage elutriator by first stage settler overflow pumps 510PP-060/1. The coarse crystals descend through the elutriator. A net upward velocity of
about 6 mm/s is required to remove the fine (less than 105 micron) sodium fluoride and
insoluble particles. Some fine (less than 125 micron) sodium carbonate monohydrate will
also be lost. The rejected fines overflow the elutriator to the first stage deaerator 510-DE050. The elutriator will reject approximately 90% of the solid sodium fluoride and 80% of
the insolubles.
The deaerator separates entrained air that would interfere with liquor clarification. Process
water, first-stage elutriated solids, centrate, guar gum and first-stage settler underflow
solids combine and gravity flow to the first stage settler feedwell. Guar is added at a
dosage of 80 g/t solids. The settler underflow at about 20% solids will be pumped by 510PP-050/1 to the paddock slurry tank 900-TK-260. It is predicted that the solids in the
settler underflow will contain about 80% by weight of sodium fluoride, representing
approximately 70% of the quantity entering the process. The first stage settler underflow is
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.3
date
2005-06-30
rev
the main purge of impurities from the first and second stage crystallizer circuit. The high
fluoride slurry will be combined with other waste streams in the fluoride slurry tank. The
slurry will then be pumped back to a separate isolated area on the lake, where the slurry
will be placed in the bottom of the paddock to keep the fluoride containing solids
submerged. Water is lost from the first stage crystallizer by evaporation, monohydrate
formation, discharge of the first settler underflow and discharge of the settler overflow. To
maintain the solution balance it is necessary to replace the lost water with process water.
Some of the required water is added to the deaerator to dissolve fine soda ash that would
otherwise be lost with the settler underflow.
The first stage settler overflows to the first stage settler overflow tank 510-TK-060, where
it will combine with liquor pumped from the second stage filter. The volume of liquor
pumped from the second stage settler to the first stage is controlled by the liquor inventory
in the second stage. Liquor collected in the settler overflow tank is used for density control
in the first stage crystallizer, for flushing in the elutriator and for discharge to the tailings
tank. The sodium sulfate concentration in the crystallizer liquor must be controlled below
about 3% to avoid product contamination. The discharge rate to the tailings tank controls
the sodium sulfate concentration in the first stage crystallizer.
Crystal slurry at 50 to 60% solids density is withdrawn from the bottom of the elutriator
and flows by gravity to the first stage centrifuges 510-CF-035/6. The first stage centrifuges
are an important purification step in the process. The removal of soluble impurities
achieved during centrifuging and washing allows the second stage crystallization to
operate at lower impurity levels than the first stage. The first stage centrifuges will produce
70 t/h of wet crystals at 4% to 5% moisture with an expected analysis of 99.5% sodium
carbonate monohydrate, 0.2% sodium fluoride, and 0.08% insolubles. The crystals will be
collected in the second stage crystallization feed tank 520-TK-005.
Guar is delivered in bags of 50 kg. For the preparation of a guar solution an automated
system is used. Guar is brought into powder storage hopper 510-TK-071, from which it is
dosed on demand by screw feeder 510-SC-070.
Guar solution is prepared by dissolving guar in process water to about 0.3 wt% solution in
guar make-up tank 510-TK-070 with the aid of guar make-up agitator 510-AG-070. The
resulting viscous solution is transferred to the guar storage tank 510-TK-071 by guar
transfer pump 510-PP-070/1. Guar metering pumps 510-MP-070/1 dose the guar solution
to tailings settler deaerator 200-DE-050. Guar metering pumps 510-MP-072/3 dose the
guar solution to first stage settler deaerator 510-DE-050 and guar metering pumps 510MP-074/5 dose the guar solution to second stage settler deaerator 520-DE-050.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.4
date
2005-06-30
rev
7.1.3
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.5
date
2005-06-30
rev
The magma withdrawn from the second-stage crystallizer is pumped to the top of the
second stage elutriator 520-SP-025. The monohydrate crystal slurry is elutriated with
filtrate from a polishing filter (PFD 500-04). The coarse crystals descend through the
elutriator. A net upward velocity of about 6 mm/s is required to remove the fine (less than
105 micron) sodium fluoride and insoluble particles. Some fine (less than 125 micron)
sodium carbonate monohydrate will also be lost. The rejected fines overflow the elutriator
to the second stage deaerator 520-DE-050. The elutriator will reject approximately 90% of
the solid sodium fluoride and 80% of the insolubles.
Magma at 50 to 60% density is transferred by gravity from elutriator 520-SP-025 to the
second stage centrifuges 520-CF-035/6 (PFD 500-03).
7.1.4
7.1.5
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.6
date
2005-06-30
rev
Two pre-coat filters 520-FL-060/1 are included in the crystallizer train to achieve maximum
clarity of recycle liquor. The filters each provide 124 m2 of filtration area and reduce the
suspended solids to less than 10 mg/l. The filter elements are vertical leafs consisting of a
stainless steel backing cloth that supports a polypropylene media. The actual filter media
is, however, fine diatomaceous earth. In operation the filter leafs are initially coated with a
thin layer, 3 mm thick, of diatomaceous earth (precoat). Once precoated, the filters are
continuously fed with clarified solution by polishing filter feed pump 520-PP-060/1. A small
flow of diatomaceous earth slurry at 10% solids is metered into the filter to provide a
continuous diatomaceous earth membrane. This addition, termed "filter aid" or "body mix",
maintains filtration rates by preventing the fine suspended solids from blinding the filter
surface. The filters operate until a pre-determined differential pressure is reached,
typically 2.0 bar(a). At that time the filter enters a blowdown and backflush cycle in which
the filter chamber drains and collected solids are sluiced off the leaves. The filter cake
slurry is pumped to the fluoride slurry tank 900-TK-260 for disposal to the lake. The filters
are automated and operate on a batch cycle. The estimated cycle time is 2 to 3 days. This
will be controlled by the clarity of the second stage settler overflow. The diatomaceous
earth consumption will be determined by the clarity of the filter feed solution.
Plate and frame heat exchanger 520-HX-065 will be used to heat the filtered liquor during
start-up. The condensate from this start-up heater will flow to the condensate tank 520
TK-045 (500-02). Condensate from all sources will be pumped from the condensate tank
to the boiler feed water tank.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.7
date
2005-06-30
rev
7.2
Normal operation
7.2.1
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.8
date
2005-06-30
rev
below 2.5 wt% (check), then the amount of water can be decreased in order to reduce
product loss and water consumption.
Most of the water that comes into the process should be added to the second stage
deaerator. This will maximize the dissolution of impurities from the final product. The
water addition to the first stage deaerator is adjusted to dissolve sodium carbonate
monohydrate solids that come from the first stage elutriator overflow and the first stage
centrifuge.
The first stage scrubber serves to wash out solids from the vapor stream. The scrubber
should typically be operated once through. Process water is added (510-FICQA-0003) at
a typical rate of 20 m3/h. If the process water addition rate needs to be reduced below 20
m3/h, scrubber effluent should be partially recirculated to maintain the flow to the spray
nozzles.
Cold process water is added to the scrubber for the following purposes:
To keep the saturation in the scrubber system below 50%
To dissolve sodium monohydrate crystals in the elutriator overflow, which takes place
in the deaerator 510-DE-050.
As the required amount of the above purposes fits the circulation rate of the scrubber
liquor, cold process water is fed at a fixed rate (510-FICQA-0003), without circulation of
liquor. In this way the scrubber is washed with cold water which is beneficial for dust
removal.
The scrubber effluent liquor is cooled using plate heat exchanger 520-HX-015. Cooling is
provided by process water which is feed to the hot process water tank. The process water
flow rate through the cooler is fixed. During normal operation more process water is
needed for the hot process water tank and is added to 520-TK-091 directly.
7.2.2
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.9
date
2005-06-30
rev
7.2.4
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.10
date
2005-06-30
rev
The overflow from the tailings settler is collected in the first stage settler overflow tank
510-TK-060.
7.2.5
7.2.6
7.2.7
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.11
date
2005-06-30
rev
The normal slurry level to be operated at should provide a buffer time for unexpected
interruption of production of both first and second stages. If the tank is operated at 70%75%, then a buffer capacity of 1 - 1.5 hours is provided for both cases. In case a stand-by
mode is scheduled for first or second stage, then the tank can be operated at max or min
level, depending on which section will be put on stand-by. A maximum buffer capacity for
failure of the first stage of 2.4 hours is created with a full tank (90%). The maximum buffer
capacity for adding cake from first stage crystallization of about 2.5 hours is created at a
starting level of 55 60%.
7.2.8
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.12
date
2005-06-30
rev
7.2.10
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.13
date
2005-06-30
rev
The wash liquor flows upward through the elutriator, until the overflow rim at the top. It
flows by gravity to the deaerator. The overflow rim fixes the liquid level in the elutriator.
7.2.11
7.2.12
7.2.13
7.2.14
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.14
date
2005-06-30
rev
overflow is introduced and finally the guar gum and recycle sludge are added. For a
proper distribution the guar gum is sprayed. All streams to the deaerator are introduced at
the inlet section in order to provide some residence time.
The overflow of the settler is a clear liquid.
High solids concentration in overflow causes high cake growth on the polishing filters and
therefore a shorter operating time. If the overflow liquor is not clear, the following items
should be checked:
Sludge level not too high (520-LI-0701)
Check guar dosing rate
Consider an increase of guar supply and/or underflow recycle
High level (small number of discs can be seen) can mean a high sludge level in the
settler, or poor separation (high turbidity). When turbidity is high, several vague discs are
seen. When the level is high the operator has to check the turbidity by sample and
analysis.
The second stage settler is provided with a rake mechanism 520-TM-050. At high torque,
the rake arms are lifted automatically.
Sludge from the settler is pumped by 520-PP-050/051. The speed of these pumps is
manually controlled by 520-HIC-0701/2. Operator adjustment of the speed is based on the
sludge level of the settler, given by 520-LI-0701. Setpoint for 520-LI-0701 is provided on
the setting list.
The content of the sump 520-SU-095 can be transferred to the first stage settler deaerator
510-DE-050. This is allowed only if the sump contains useable clean liquor or product and
is not contaminated with non-product materials like filter aid, guar, mud etc.
At high level 520-LS-0702 in sump 520-SU-095 sump pump 520-PP-095, is started
automatically and at low level 520-LS-0702 this pump is stopped automatically.
Sump agitator 520-AG-095 is started and stopped by hand locally. The agitator is normally
kept running.
7.2.15
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.15
date
2005-06-30
rev
When regeneration is completed, the tank will be brought back to a low level with
increased flow rate. The capacity of this system is sized for the crystallization unit running
at 100% capacity, one filter being regenerated, and one in operation. It is not possible to
regenerate both filters at the same time, and keeping operating capacity at 100%.
Flow rate over the filter has to be constant in order to reduce damage of filter cake. If flow
is stopped, then the cake may start to fall off.
Therefore, filter feed pumps 520-PP-060/1 are provided with automatic changeover.
The content of the sump 520-SU-100 can be transferred to the first stage settler deaerator
510-DE-050. This is allowed only if the sump contains useable clean liquor or product and
is not contaminated with non-product materials like filter aid, guar, mud etc.
At high level 520-LS-0803 sump pump 520-PP-100 is started and at low level 520-LS0803 this pump is stopped automatically.
7.2.16
7.2.17
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.16
date
2005-06-30
rev
7.2.18
7.2.19
7.2.20
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
7.17
date
2005-06-30
rev
The hot process water pressure is controlled by 520-PICA-1301. Hot water is transported
via a header. The (discontinuous) users are connected to the header with short
connecting lines to prevent a lot of cold water being forwarded from stagnant lines.
7.2.21
Setting list
Instrument
510-DICA-0001
Unit
kg/m
Normal
Alarm
1530
H 1600
Trip/Switch
L 1400
510-EIA-0001
kW
75
H 105
510-EIA-0002/0003
kW
15
H 18
510-EIA-0004/0005
kW
11
H 14
510-EIA-0008
kW
130
H 200
510-EICSA-0201/0204
kW
50
H 63
510-ES-0202/0205
510-EISA-I-0301
HH 70
Local control
kW
TBD
H TBD
HH TBD
510-FICA-0001
m /h
140
L 50
510-FIA-0002
m /h
150
L 80
HHTBD
H 200
H TBD
3
510-FICQA-0003
m /h
22
L 90% of normal
510-FIA-0004
l/min
L 0.5
510-FA-0005..0010
l/min
510-FIC-0011..0016
l/h
30
510-FI-0017
m3/h
22
510-FI-0018
m /h
22
510-FICA-0101
m /h
160
m /h
10
510-FIC-0103/0104
l/h
30
510-FICA-0201/0202
m /h
3.5
510-FI-0203/0204 (PW)
l/h
510-FI-0102
L 100
L 1
510-FICA-0301
m /h
L 90% of normal
510-HIC-0301/02
RPM
TBD
TBD
510-KIS-0001
min; n/h
1; 1
510-KIS-0002
min; n/h
1; 4
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
TBD
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
7.18
date
2005-06-30
rev
Instrument
Unit
Normal
510-KIS-0201/0202
min; n/h
1; 4
510-LICSA-0001
60
Alarm
Trip/Switch
L 35
H 85
510-LICSA-0002
50
HH 90
HH 90
LL TBD
LL TBD
L 35
H 85
510-LI-0003
TBD
510-LICSA-0101
50
L 35
H 80
HH 90
510-LI-0201/0202
TBD
TBD
510-LSA-0203/0204
TBD
TBD
HH 90
L TBD
(corresponds with 1
m clear liquor;3 to 4
discs visible)
510-LICSA-0401
80
L5
L5
H 95
510-PIA-0001
barg
-0.07
L -0.2
H 0.05
510-PI-0002
barg
510-PDIA-0003
mm wc
510-PI-0201/0202
barg
5)
H TBD
TBD
510-PI-0401
barg
510-TICA-0001
97
L 90
H 100
510-TIA-0002
97
L 90
H 100
510-TI-0003
85
510-TI-0004
35
510-TI-0101
93
510-TISA-0201/0202
55
510-TI-0203/0204
55
510-TI-0401
90
510-TI-0402
90
H 60
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
HH 65
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
7.19
date
2005-06-30
rev
Instrument
Unit
Normal
Alarm
Trip/Switch
H 9
HH 14
510-XISA-0201/0202
mm/s
Guar dosing
g/ton solids
80
Capacity 510-MP-072/073
m /h
0.1
kg/m3
1500
520-DIA-0001
L 1400
H 1600
kg/m
520-DI-0101
kg/m
520-EIA-0001
kW
170
H 200
520-EIA-0002/0003
kW
27
H 36
520-EIA-0101
kW
75
H 105
520-EIA-0102/0103
kW
11
H 14
520-EICSA-0301/0304
kW
50
H 63
520-DICA-0002
1500
L 1400
H 1600
520-ES-0302/0305
1500
HH 70
Local control
520-EIA-0307
kW
TBD
H TBD
520-EIA-0501
kW
TBD
L TBD
520-EISA-I-0701
kW
TBD
H TBD
HH TBD
HH TBD
520-EIA-I-1201
kW
TBD
TBD
TBD
520-EIA-I-1203
kW
TBD
TBD
TBD
520-FICA-0001
m /h
150
L 50
520-FIA-0002
l/min
L 1
520-FIA-0003/0004
l/min
520-FI-0011
m3/h
64
H TBD
520-FIA-0101
m /h
140
520-FI-0102/0103
l/min
10
520-FI-0104..0106
l/min
520-FIC-0107..0110
l/h
30
520-FICA-0201
m /h
160
520-FI-0202
m3/h
10
520-FIC-0203/0204
l/h
30
520-FICA-0301/0302
m /h
3.5
520-FI-0303/0304 (PW)
l/h
L 70
L 0.5
L 100
L 1
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
7.20
date
2005-06-30
rev
Instrument
Unit
Normal
Alarm
520-FIQ-0401
ton/h
7.5
520-FIA-0402
kg/h
120
520-FIC-0601
NNF
520-FI-0605
m /h
93
520-FICA-0701
m3/h
8.2
L 90% of normal
104
L 80% of normal
520-FICA-0901/02
m /h
m /h
Trip/Switch
30
H 120% of normal
520-FIC-1001
m3/h
520-FI-1101
m /h
520-FIA-1201
m /h
NNF
16
2 (Check)
L 80% of normal
H 120% of normal
520-HIC-0601/02
RPM
TBD
TBD
TBD
520-HIC-0701/02
RPM
TBD
TBD
TBD
mg/l
concentration in deaerator
liquor flow rate
Capacity 510-MP-074/075
m /h
0.35
520-KIS-0101
min; n/h
1; 0.25
520-KIS-0102
min; n/h
0.5; 0.25
520-KIS-0103
min; n/h
0.5; 0.25
520-KIS-0301/0302
min; n/h
1; 4
520-LICSA-0001
60
L 35
H 85
HH 90
520-LICA-0002
60
HH 90
L 35
H 85
520-LI-0003
520-LICSA-0101
60
L 35
H 85
HH 90
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
HH 90
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
7.21
date
2005-06-30
rev
Instrument
Unit
Normal
Alarm
520-LICSA-0201
50
L 35
Trip/Switch
H 80
HH 90
520-LI-0301/0302
TBD
HH 90
TBD
520-LSA-0303/0304
TBD
TBD
520-LISA-0501
Variable
L TBD
LL 20
LL 20
L 23
H 95
520-LA-0502
520-LICSA-0601
64
L 47
L 47
H 77
2
(corresponds with 1
m clear liquor;3 to 4
discs visible)
520-LICSA-0802
1)
28
2)
L L14
85
3)
L 20
28
3)
L 20
85
2)
LL 24
LL 14
H 95
520-LICSA-1001
LL 24
H 35
HH 95
520-LISA-1002
(L 24)
L 24
H 95
520-LICSA-1101
4)
80
LL 0
LL 0
L 15
H 95
520-LISA-1201
85
L 30
H 90
HH 95
520-LISA-1202
85
L 30
H 85
HH 95
520-LICSA-1301
4)
60
L9
L 15
H 77
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
L9
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
7.22
date
2005-06-30
rev
Instrument
Unit
Normal
520-PIA-0001
barg
Alarm
Trip/Switch
H 1.5
HH 1.8
520-PI-0002
barg
1.2
520-PDIA-0003
mbar
300
H 400
520-PICA-0101
barg
-0.16
L -0.25
520-PDIA-0102
mbar
2.5
H 20
520-PI-0103
mbarg
520-PI-0104/0106
mbarg
-160
520-PI-0105/0107
barg
520-PI-0301/0302
barg
TBD
520-PICA-0401
barg
14.5 ??
520-PI-0402
barg
-0.16
520-PI-0403
barg
1.2
520-PDIA-0902/0908
bar
H -0.05
L 14 ??
H 2.5
barg
520-PIC-1101
barg
0.15
520-PI-1102
barg
0.15
520-PICA-1301
barg
4.5
L3
520-QIA-1101
S/cm
20
40
520-SSA-0301
TBD
TBD
520-TICA-0001
120
L 110
H 130
520-TIA-0002
120
L TBD
H TBD
520-TI-0003
121
520-TI-0004
124
520-TDIA-0005
0.7
H 1.0
520-TDIA-0006
H 5
520-TIA-0101
97
H 100
L 90
520-TI-0102
37
520-TIC-0103
55
520-TI-0201
93
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
7.23
date
2005-06-30
rev
Instrument
Unit
Normal
Alarm
Trip/Switch
H 60
HH 65
520-TISA-0301/0302
55
520-TI-0303/0304
55
520-TI-0401
143
520-TICA-0402
125
520-TI-0501
98
520-TIA-0601
99
520-TI-0901/02
96
520-TI-1001
Ambient to 96
520-TI-1002
80 - 96
520-TI-1003
96
520-TICA-1301
90
520-TISA-1302
520-XISA-0301/0302
mm/s
Timer 520-XSV-1201/1202
520-XSV-1201
H 135
H 102
L 85
H 95
H 95
H 9
HH 14
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
7.24
date
2005-06-30
rev
7.3
Logic functions
In this section the logic functions describing automatic actions of valves are described.
The guar make-up sequence is described in section 7.7.2 and the filter regeneration
sequence is described in section 7.7.11.
Logical functions that act on equipment are for example:
Start conditions and running conditions
Process switches
Safety switches (dry run protection on pumps, speed alarm on conveyors)
Thermal overload is provided on all electric motors. The thermal overload shuts off the
motor directly (hardwired from MCC).
In the table below logic functions acting on equipment are presented.
Equipment/Action
Start
Stop
Signal
Type
Start/
Switch/
Running
Interlock
condition
400-GA-060
Manual on
Manual on
DCS
DCS (check)
(check)
and
and
automatic
Direct
0001
calcined
feed to
running
dump tank
If Pump 510-PP-010/011 is
automatic
not running
Locally by
Locally by
hand
hand and
510-PP-015/016
Locally by
Locally by
hand
hand
Locally by
Locally by
hand
hand and
Stop
automatic
510-AG-010
Stop
0002
automatic
510-PP-020/021
510-FN-010
Locally by
Locally by
hand
hand
Locally by
Locally by
hand
hand
Stop
510-LICSA-0101
-
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
7.25
date
2005-06-30
rev
Equipment/Action
Start
Stop
Signal
Type
Start/
Switch/
Running
Interlock
condition
510-CF-035/036
Locally by
Locally by
hand
hand and
automatic
0203/0206) is running
Stop
0203/0204 activated
Stop
TISA-0201/0202
510-PP-050/051
510-TM-050
Locally by
Locally by
hand
hand
Locally by
Locally by
hand
hand
510-XISA-0201/0202
HH torque on 510-EISA-I0301
Stop
-
Lift rake
(local
control)
510-PP-060/061
LL level of 510-LICSA-0401
Locally by
Locally by
hand
hand and
Stop
510-AG-070
Automatic
automatic
Automatic
LL level of 510-LI-001
Stop
510-MP-070 to
Locally by
Locally by
LL level of 510-LI-002
Stop
075
hand
hand and
510-PP-070/071
Automatic
Automatic
LL level of 510-LI-001
Stop
Locally by
Locally by
Stop
hand
hand and
activated
automatic
520-PP-005/006
automatic
0001 is activated
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
7.26
date
2005-06-30
rev
Equipment/Action
Start
Stop
Signal
Type
Start/
Switch/
Running
Interlock
condition
520-PP-020/021
Locally by
Locally by
hand
hand and
Stop
0201
automatic
520-CF-035/036
Locally by
Locally by
hand
hand and
automatic
0308/0309) is running
0303/0306) is running
Stop
0303/0304 activated
Stop
TISA-0301/0302
520-CV-040
Locally by
Locally by
hand
hand and
automatic
520-XISA-0301/0302
Emergency switch 520-EM-
Stop
Stop
0307 is activated
520-AG-005
520-PP-040/041
Locally by
Locally by
hand
hand
Locally by
Locally by
hand
hand and
LL level of 520-LICSA-0601
Stop
automatic
520-TM-050
Locally by
Locally by
hand
hand and
0701
(local
automatic
520-PP-050/051
520-PP-095
520-AG-095
Locally by
Locally by
hand
hand
Automatic
Automatic
Locally by
Locally by
hand
hand and
Lift rake
control)
520-LS-0702 Low
520-LS-0702 High
-
automatic
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Stop
Start
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
7.27
date
2005-06-30
rev
Equipment/Action
Start
Stop
Signal
Type
Start/
Switch/
Running
Interlock
condition
520-PP-060/061
Locally
Locally and
and on
on DCS by
DCS by
hand and
hand and
automatic
520-PP-065/066
Automatic
pump
X
automatic
520-PP-100
Start spare
Automatic
Locally by
Locally by
hand
hand and
520-LICSA-0802 LL level
Stop
520-LS-0803 Low
Stop
520-LS-0803 High
Start
520-LICSA-1001 LL level
Stop
Start
automatic
520-PP-070/071
Locally
Locally and
and on
on DCS by
DCS by
hand and
hand and
automatic
Stop
LL
automatic
520-PP-045/046
Locally
Locally and
and on
on DCS by
DCS by
hand and
hand and
automatic
Start spare
pump
Stop
LL
automatic
520-PP-080
Locally by
Locally by
hand
hand and
automatic
520-AG-080
Locally by
Locally by
hand
hand and
automatic
520-PP-085
Locally by
Locally by
hand
hand and
automatic
520-AG-085
Locally by
Locally by
hand
hand and
automatic
520-PP-091/092
Locally by
Locally by
hand
hand and
automatic
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Stop
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
7.28
date
2005-06-30
rev
Action
Cause
510-FCV-0001
Close
510-KIS-0001/0002
Close
510-ECV-
Close
0201/0204
520-DCV-0002
Close
520-PCV-0401
Close
520-XSV-
Open
0001/0002
Close
Open
520-PP-022/023 is running
Close
Close
Close
520-KIS0101/0102/0103
520-XSV0101/0102
520-ECV-
Close
0301/0304
520-LCV-0601
Close
520-XSV-1001
Open
520-XSV-1201
Open
Close
520-XSV-1202
Open
Close
520-TCV-1301
Close
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.29
date
2005-06-30
rev
7.4
7.4.1
Instrument air
Electrical power
Instruments are working and calibrated
1
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.30
date
2005-06-30
rev
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.31
date
2005-06-30
rev
10
11
o Scrubber pump can be started once the scrubber is filled to the proper operating
level. The pumps are interlocked with low low level of 510-LICSA-0002 so the
level indication must be working properly prior to operating the scrubber pumps.
o Ensure the manual recycle valve to the scrubber spray nozzles is open and the
level control valve 510-LCV-0002 is closed.
o When not in use, the pumps should have the suction and discharge valves closed
and the drain valve open.
o To start a pump, first ensure the seal purge water is flowing at 1 l/m.
o Close the drain valve and open the suction valve.
o Start pump and then open the discharge valve.
o Only one pump should operate at a time.
o The scrubber level control can then be put in automatic.
Start first stage scrubber fan 510-FN-010
o Before starting the fan, water should be added to the overflow lutes of both the
first stage crystallizer and the first stage scrubber. This is done by attaching a
hose to the drain valves on the lute and then adding water until water comes out
the overflow. The water in the lutes prevents air from being drawn through the
overflow lines.
o The fan should be started in manual mode at the minimum speed.
Start first stage slurry pump 510-PP-020/021
o When not in use, the pumps should have the suction and discharge valves closed
and the drain valve open.
o To start a pump, first ensure the seal purge water is flowing at 1 l/m.
o Close the drain valve and open the suction valve.
o Start pump and then open the discharge valve.
o Only one pump should operate at a time.
o Set pump speed manually through 510-LICSA-0001 to show ~40 m3/h flow rate
on 510-FIA-0002.
o Set feed to crystallizer through 510-FICA-0001 to ~70 m3/h (~half of design rate).
o Put first stage crystallizer level control 510-LICSA-0001 to automatic and select a
level setpoint that maintains the level between the upper and lower level sight
glasses on the crystallizer wall.
o If the level in the first stage settler overflow tank is low, additional water can be
added to the circuit by starting the process water addition to the first stage
scrubber through 510-FICQA-0003 (make sure bypass over 510-FCV-0003 is
closed).
o If the level in the first stage settler overflow tank is high, the level controller 510LICSA-0401 can be put in automatic and the transfer to 900-TK-250 can be
opened (ensure bypass valve over 510-LCV-0401 is closed).
Start first stage centrifuge 510-CF-035/036
o First ensure that the seal purge water is flowing at ~8 l/h.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.32
date
2005-06-30
rev
12
13
14
15
o Ensure the oil level is adequate and then start the hydraulic pump motor
o Verify that the oil cooler fan and oil circulation pump have started (these motors
are wired in the MCC to start and stop with the hydraulic pump motor).
o After the hydraulic pump has been running for at least one minute, start the main
rotor motor.
o During normal operation, both centrifuges will operate at the same time.
However, during start-up or at reduced rates it is only necessary to operate one
centrifuge.
o If desired, water can be fed through the running centrifuge and into the first stage
settler deaerator. However, since the first stage elutriator overflows to the same
place, it is not necessary to run the first stage centrifuges on water.
o To stop the centrifuge, first stop the main rotor motor. After the centrifuge comes
to a complete stop the hydraulic pump motor can be stopped.
Start first stage settler rake mechanism
Filling of anhydrous reactor 520-EV-010
o Bottom valves have to be closed.
o Manual 25 mm vent valve on top of the reactor is opened.
o Open 150 mm process water valve located on the recirculation pipe and fill the
anhydrous reactor to a level that is approximately 1 meter above the recirculation
inlet nozzle. (The level indicator is calibrated for process slurry so the level
indication will not be correct on water). The level can be viewed through the top
sight glasses.
Start the anhydrous reactor pump 520-PP-010
o The anhydrous reactor pump can be started once the anhydrous reactor is filled
to the proper operating level. The allowable operating level ranges from the
center line of the recirculation inlet nozzle (N1) to the top of straight side of the
vessel.
o First ensure the seal purge water is flowing at ~2 l/m.
o Start the pump
Filling of second stage crystallizer 520-EV-020
o Bottom valves have to be closed.
o Manual 25 mm vent on line from second stage vent condenser is opened to vent
the second stage crystallizer through the condenser.
o Fill the second stage crystallizer through anhydrous slurry transfer lines by
opening 520-LCV-0001A/0001B, along with the block valves in these lines.
o Only one transfer line is in use at a time.
o Put anhydrous reactor level controller 520-LICSA-0001 in automatic and adjust
the level setpoint.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.33
date
2005-06-30
rev
16
17
18
19
20
21
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.34
date
2005-06-30
rev
22
23
24
25
26
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.35
date
2005-06-30
rev
27
28
29
30
31
32
o Belt conveyor motor is interlocked with second stage centrifuge feed valves 520ECV-0301/0304 such that valves can only be opened if motor is running.
Filling of second stage centrate tank 520-TK-040
o Water can be fed through the running centrifuge and into the centrate tank
o First ensure second stage centrifuge is running
o Open the block valve in the centrifuge feed line
o Set 520-EICSA-0301/0304 to manual and gradually open 520-ECV-0301/0303
(control valves are interlocked to the respective centrifuge rotor motors such that
valves will only open if the motor is running and will close if the motor is stopped).
Start second stage centrate pump 520-PP-040/041
o Check dust system of 600 section can receive liquor
o When not in use, the pumps should have the suction and discharge valves closed
and the drain valve open.
o To start a pump, first ensure the seal purge water is flowing at ~1 l/m.
o Close the drain valve and open the suction valve
o Ensure valve on tank is open
o Start pump and then open the discharge valve
o Only one pump should operate at a time
o Set 520-LICSA-0601 to 40% in automatic. 520-LCV-0601 will open flow to 520TK-005.
Filling of second stage crystallization feed tank 520-TK-005
o Bottom valves have to be closed.
o Filling can be accomplished either by pumping water from the filtrate tank or by
running the second stage centrifuge 520-CF-035/036 and opening the centrifuge
feed valve 520-ECV-0301/0304 from the second stage elutriator and then
pumping out of the second stage centrate tank 520-TK-040 with second stage
centrate pump 520-PP-040/041.
o Fill the tank to 50% level (this corresponds to 30% level on 520-LISA-0501 when
on water).
Start second stage crystallization feed pump 520-PP-005/006
o When not in use, the pumps should have the suction and discharge valves closed
and the drain valve open.
o To start a pump, first ensure the seal purge water is flowing at ~1 l/m.
o Close the drain valve and open the suction valve
o Start pump (discharge valve will automatically open when pump is started).
o Only one pump should operate at a time
o Set flow setpoint of 520-FICA-0001 to ~2500 l/m.
o Stop adding process water to anhydrous reactor through 150mm water
connection once operating levels in all second stage vessels is adequate.
Start second stage crystallization feed tank agitator.
Start second stage vacuum pump 520-PP-022/023
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.36
date
2005-06-30
rev
33
34
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.37
date
2005-06-30
rev
o Stop second stage slurry pump 520-PP-020/021, close the valve at the
crystallizer, flush the line with water for several minutes, stop the flush water,
close the discharge valve and open the drain valve.
o Stop the flow to the second stage centrifuge by closing the valve at the elutriator
and flushing the line with water for several minutes. It may be necessary to set
520-EICSA-0301/0304 to manual to keep the control valve open while flushing.
o Stop the second stage centrifuges.
o Stop the second stage belt conveyor 520-CV-040.
At this point, the anhydrous reactor and second stage crystallizer vessels are isolated and
the following function on:
Anhydrous reactor pump 520-PP-010 running
Crystallizer agitator 520-AG-020 running
Vacuum pump 520-PP-022/023 running with automatic pressure control enabled
Cooling liquor flow through condenser with automatic temperature control enabled
Filtrate flow to second stage elutriator
Centrate pump 520-PP-040/041 running
Second stage settler rake mechanism running
Polishing filter feed pump 520-PP-060/061 running with automatic level control on
polishing filter feed tank 520-TK-060
Filtrate pump 520-PP-065/066 running
Condensate pump 520-PP 045/046 running
7.4.2
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.38
date
2005-06-30
rev
2
3
4
Open water supply to scrubber and set flow rate via 510-FIC-0003 to ~5 m /h (25%
of design rate) with recirculation valve throttled to obtain ~20 m3/h flow rate on 510FI-0017 (ensure bypass over 510-FCV-0003 is closed).
Open manual valves in process water supply for wall wash and enable wash timers
510-KIS-0001/0002.
Put scrubber fan speed control in automatic 510-TICA-0001.
Start adding calcined feed from calciner unit
The hot (400 C) calcined feed will start increasing the temperature of the first stage
crystallization circuit as well as the liquor concentration and density. As the crystallizer
temperature approaches the operating setpoint of 97 C, the vent fan will automatically
increase speed via temperature controller 510-TICA-0001.
5
6
7
8
When the crystallizer density increases above 1.30, monohydrate crystals will begin to be
produced. These crystals will then start to be transferred to the elutriator. The elutriator
level indicator 510-LICSA-0101 would be negative when the liquor is below saturation and
give a positive reading when crystals begin to accumulate. As the level indication
increases above 10%, one of the centrifuges should be started.
9
10
Check crystal size and shape. If too many fine crystals are formed, then a portion of
the slurry will be discharged via the elutriator overflow.
Start first stage centrifuge 510-CF-035/036
o First ensure that the seal purge water is flowing at ~8 l/h.
o Ensure the oil level is adequate and then start the hydraulic pump motor
o Verify that the oil cooler fan and oil circulation pump have started (these motors
are wired in the MCC to start and stop with the hydraulic pump motor).
o After the hydraulic pump has been running for at least one minute, start the main
rotor motor.
o During normal operation, both centrifuges will operate at the same time.
However, during start-up or at reduced rates it is only necessary to operate one
centrifuge.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.39
date
2005-06-30
rev
11
12
13
14
15
16
17
18
19
7.4.3
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.40
date
2005-06-30
rev
2
3
o Gradually close vent valves on heater to reduce the amount of steam vent to a
small continuous amount.
Open water to thermo compressor desuperheater 520-DS-010 and put control valve
via 520-TICA-0402 in automatic.
When the anhydrous reactor temperature rises above 100 C, steam will vent
through the manual vent valve at the top. Gradually close this vent valve in a similar
manner to the heater vent valves, leaving a small continuous vent to avoid
accumulating non-condensable gasses.
When the operating temperature reaches 120 C, start second stage crystallization
feed pump 520-PP-005/006
o When not in use, the pumps should have the suction and discharge valves closed
and the drain valve open.
o To start a pump, first ensure the seal purge water is flowing at ~1 l/m.
o Close the drain valve and open the suction valve
o Start pump (discharge valve will automatically open when pump is started).
o Only one pump should operate at a time
o Set flow setpoint of 520-FICA-0001 to ~150 m3/h.
o Adjust flow setpoint as necessary to maintain level in 520-TK-005.
Start automatic density control of feed to anhydrous reactor by opening filtrate flow
to suction of pump 520-PP-005/006 and putting 520-DICA-0002 in automatic at the
design setpoint of 1.50.
Start transferring to the second stage crystallizer via 520-LICSA-0001. First open
the manual valve at the anhydrous reactor, then open the valve at the second stage
crystallizer and finally open 520-LCV-0001 and set to automatic control at the
current operating level indication. As the density in the anhydrous reactor
increases, the actual level will decrease for the same level indication. The desired
operating level is ~1 meter above the recirculation inlet nozzle. The level setpoint
should be adjusted to obtain this.
NB: the density of water is not sufficient to prevent boiling in the transfer line.
Start the second stage slurry pump 520-PP-020/021
o When not in use, the pumps should have the suction and discharge valves closed
and the drain valve open.
o To start a pump, first ensure the seal purge water is flowing at 1 l/m.
o Close the drain valve and open the suction valve.
o Start pump and then open the discharge valve.
o Only one pump should operate at a time.
o Set the second stage crystallizer level control 520-LICSA-0101 to automatic.
As 120 C slurry is transferred to the second stage crystallizer, the operating
temperature will rise to ~97 C, where the crystallizer contents will begin boiling.
Usually, the operating pressure in the second stage crystallizer will increase when
boiling first occurs until the vacuum system is able to draw out all the air. When the
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.41
date
2005-06-30
rev
10
11
12
proper operating pressure is reestablished after boiling commences, the block valve
at the suction of the thermo compressor is opened slowly.
The manual valves in the bypass line around the thermo compressor are opened
and the control valve via 520-TICA-0001 is put in automatic control at the design
operating temperature (120 C).
Start the automatic wall wash and demister wash 520-KIS-0101/0102/0103.
Ensure fluid bed dryer is on standby
Start second stage belt conveyor 520-CV-040
When the crystallizer density increases above 1.30, monohydrate crystals will begin to be
produced. These crystals will then start to be transferred to the elutriator. The elutriator
level indicator 520-LICSA-0201 would be negative when the liquor is below saturation and
give a positive reading when crystals begin to accumulate. As the level indication
increases above 10%, one of the centrifuges should be started.
13
14
15
16
17
18
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.42
date
2005-06-30
rev
19
20
21
22
23
24
7.4.4
Shut-down
Purpose of this procedure is to shut down for a longer period of time or for maintenance.
Most of the sodium carbonate solids in the crystallization circuits are removed and
recovered and the remaining solids are dissolved.
7.4.4.1
3
4
5
6
7
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.43
date
2005-06-30
rev
9
10
11
12
13
14
Stop first stage centrifuge and close hot water supply via 510-FCV-0201/0202.
Close process water supply to deaerator via 510-FCV-0301.
Stop guar pump 510-MP-072/073
Stop first stage settler overflow pump 510-PP-060/061 (close discharge valve, keep
suction valve open for seal purging).
Stop first stage settler underflow pump 510-PP-050/051.
Ensure all lines are flushed.
2
3
4
5
6
Maintain flows through second stage crystallization circuit after first stage circuit has
been stopped. Objective is to process the remaining sodium carbonate solids in the
circuit. The suspended solids concentration in the feed tank 520-TK-005, the
anhydrous reactor 520-EV-010 and the crystallizer 520-EV-020 will gradually be
reduced as product is recovered on the second stage centrifuges and centrate is
recycled to the feed tank.
When the density in the anhydrous reactor has dropped below 1.35, close 15 bar
steam supply to thermo compressor 520-SJ-010
Prior to stopping pump 520-PP-005/006, flush line (because otherwise 520-XSV0001/0002 is closed). Stop second stage crystallization feed pump 520-PP-005/006,
flush both sides of the automated on/off valve 520-XSV-0001/0002 with hot water for
several minutes (this valve closes automatically when the pump stops), close the
valve at the feed tank and open the drain valve.
Stop filtrate supply from filtrate tank 520-TK-065 to slurry feed line (close 520-DCV0002).
Continue slurry transfer from anhydrous reactor 520-EV-010 to 520-EV-020, by
putting 520-LICSA-0001 in manual.
When level indicator 520-LICSA-0001 shows ~20% or level is below N1 nozzle,
stop slurry transfer from anhydrous reactor by closing valve at reactor, flushing line
with hot water for several minutes, closing valve at crystallizer, stop flush water and
open drain valve of S2 connection.
Open DN 150 process water connection to anhydrous reactor and fill to high level
(top of vessel straight side) or until density indication 520-DIA-0001 shows <1.30.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.44
date
2005-06-30
rev
9
10
11
12
13
14
15
Stop second stage slurry pump 520-PP-020/021, close the valve at the crystallizer,
flush the line with water for several minutes, stop the flush water, close the
discharge valve and open the drain valve.
When elutriator is empty of crystals, (having level control 520-LICSA-0201 in
manual) close elutriator outlet valves 520-ECV-0301/0304.
Flush front-side of centrifuge screen with hot process water until all solids are
dissolved.
Stop centrifuge and close hot water supply via 520-FCV-0301/0302.
Stop second stage belt conveyor 520-CV-040
Close 520-FCV-0701 ( hot process water supply to deaerator 520-DE-050)
Stop guar pump 520-MP-074/075
Stop settler underflow pump 520-PP-050/051
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.45
date
2005-06-30
rev
7.5
7.5.1
7.5.2
Close 15 bar steam supply to thermo compressor 520-SJ-010. Keep reactor above
115C.
Prior to stopping pump 520-PP-005/006, flush line(because otherwise 520-XSV0001/0002 is closed). Stop second stage crystallization feed pump 520-PP-005/006,
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.46
date
2005-06-30
rev
3
4
6
7
8
9
10
11
12
flush both sides of the automated on/off valve 520-XSV-0001/0002 with hot water for
several minutes (this valve closes automatically when the pump stops), close the
valve at the feed tank and open the drain valve.
Stop filtrate supply from filtrate tank 520-TK-065 to slurry feed line (close 520-DCV0002).
Stop slurry transfer from anhydrous reactor 520-EV-010 to 520-EV-020 by closing
valve at reactor, flushing line with hot water for several minutes (always flush in two
directions), closing valve at crystallizer, stop flush water and open drain valve of
S2 connection. It may be necessary to set 520-LICSA-0001 to manual to keep the
control valve open while flushing.
Stop second stage slurry pump 520-PP-020/021, close the valve at the crystallizer,
flush the line with water for several minutes, stop the flush water, close the
discharge valve and open the drain valve.
When elutriator is empty of crystals, (having level control 520-LICSA-0201 in
manual) close elutriator outlet valves 520-ECV-0301/0304.
Flush front-side of centrifuge screen with hot process water until all solids are
dissolved.
Stop centrifuge and close hot water supply via 520-FCV-0301/0302.
Stop second stage belt conveyor 520-CV-040
Close 520-FCV-0701 ( hot process water supply to deaerator 520-DE-050)
Stop guar pump 520-PP-074/075
Stop settler underflow pump 520-PP-050/051
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.47
date
2005-06-30
rev
7.5.3
7.5.4
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.48
date
2005-06-30
rev
12
7.6
Open 520-FCV-0701 ( hot process water supply to deaerator 520-DE-050) and set
flow rate according setting list (ensure bypass over 520-FCV-0701 is closed)
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.49
date
2005-06-30
rev
7.6.1
Water balance
The water balance of the first and second stage have to be monitored carefully. Too much
water will result in product loss. Not enough water will result in too high a sulfate content
in the first stage crystallizer and also product loss when monohydrate in the deaerators is
not dissolved. Set points for flows are on the setting list. The settings have to be taken
proportional to the actual operating capacity of the unit.
Water input:
Process water supply on first stage scrubber (510-FIC-0003) (not proportional but fixed
flow rate)
Process water on first stage deaerator (510-FIC-0301)
Hot process water on first stage and second stage centrifuge (510-FIC-0201/0202,
520-FIC-0301/0302).
Hot process water on second stage deaerator (520-FIC-0701)
Process water on wall wash for crystallizers
Process water to second stage vacuum system (520-FI-0102/0103)
Process water via guar supply; negligible
Hot process water on second stage centrate tank (520-FI-0601); normally not in use
Process water on filtrate tank (520-FI-1001); normally not in use
Purge water on pumps and seals (not proportional but fixed flow rate)
Flushing of lines (not proportional)
Wash-out of crystallizers (incidental, not proportional)
Sight glass flush water
Water output:
Evaporation from first stage crystallizer via scrubber to air
Evaporation from second stage crystallizer to condensate
Free moisture and monohydrate water in centrifuge cake
First stage settler underflow (510-HIC-0301/0302) to 900-TK-260
Second stage settler underflow (520-HIC-0701/0702) to 900-TK-260
First stage liquor blowdown to 900-TK-250 (via 510-LCV-0401)
Emptying of filter content to 900-TK-260
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
7.50
date
2005-06-30
rev
7.6.2
Parameter
Tag or analysis
510-EV-010
Density
510-DICA-0001
Product quality;
3
Temperature
510-TICA-0001
Operating parameter;
97C
510-DC-015
510-FICQA-0003
22 m /h
510-HX-015
510-FI-0018
FN-010; 20 m /h
510-SP-025
Underflow solids
Sample
concentration
Content of insolubles in
Centrifuge performance;
50 wt%
Sample
Sample
Sample
Product loss;
monohydrate crystals
Content of NaF in
monohydrate crystals
510-SP-025
Overflow solids
(510-CF-035/036
Cake moisture
Product quality;
510-CF-035/036
510-FICA-0201/0202
Product quality;
concentration
2 wt%
5 wt%)
3.5 m3/h per centrifuge
flow rate
510-DE-050
510-FIC-0301
510-TK-050
510-LI-0301
level
510-MP-072/073
Settler performance;
4 discs visible
510-LI-0604
supply
510-DE-050
deaerator
Settler performance;
80 g/ton solids
Sample / Visual
overflow
Monohydrate in solids
indicates bad performance of
crystallizer/elutriator, or too
small water supply (510-FIC0301)
510-TK-050
Sample / Visual
solids concentration
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Product quality;
< 0.1 wt%
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
7.51
date
2005-06-30
rev
Location
510-TK-050
Parameter
Tag or analysis
Sample
Settler performance;
underflow solids
20 wt%
concentration
520-TK-005
Level
520-LISA-0501
520-EV-010
Density
520-DICA-0001
Product quality;
3
Temperature
520-TICA-0001
Operating parameter;
120C
520-HX-010
Temperature difference of
520-HX-010
Temperature difference of
520-TDIA-0006
520-TDIA-0005
520-PICA-0101
Pressure
Solids concentration
Sample
Product quality;
3
Underflow solids
Sample
concentration
Content of insolubles in
Centrifuge performance;
50 wt%
Sample
Sample
Sample
Product loss;
monohydrate crystals
Content of NaF in
monohydrate crystals
520-SP-025
Overflow solids
concentration
520-CF-035/036
Cake moisture
1.5 wt%
Sample
Product quality;
5 wt%
520-CF-035/036
520-FICA-0301/0302
520-FL-060/061
Product quality;
3.5 m3/h per centrifuge
flow rate
520-PDIA-0902/0908
520-DE-050
520-FIC-0701
520-TK-050
addition on deaerator
520-LI-0701
sludge level
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Settler performance;
4 discs visible
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
7.52
date
2005-06-30
rev
Location
Parameter
Tag or analysis
510-MP-074/075
510-LI-0603
supply
520-DE-050
Sample / Visual
overflow
Monohydrate in solids
indicates bad performance of
crystallizer/elutriator, or too
small water supply (520-FIC0701)
520-TK-050
Sample / Visual
overflow solids
concentration
520-TK-050
Sample
underflow solids
concentration
7.6.3
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Settler performance;
15 wt%
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.53
date
2005-06-30
rev
7.7
7.7.1
7.7.2
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.54
date
2005-06-30
rev
A third timer is set to provide time for ripening of the guar solution. The timer is
started when guar addition is completed. When the preset time is past, transfer of
solution from preparation tank 510-TK-070 to day tank 510-TK-075 is released.
Transfer of guar solution from preparation tank 510-TK-070 to day tank 510-TK-075.
1
At low level in the day tank 510-TK-075 transfer from preparation tank 510-TK-070
is started (start of 510-PP-070/071). The pump can only start if the guar preparation
process is completed (time for ripening is completed and level in 510-TK-070 is not
low).
2
Transfer pump 510-PP-070/071 is stopped when low level in preparation tank is
reached (preferred operation) or when high level in day tank 510-TK-075 is reached
7.7.3
7.7.4
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.55
date
2005-06-30
rev
Section 520
Liquor can be pumped through second stage mother liquor heater 520-HX-065 for heating
up during start-up. During normal operation the flow is bypassing the exchanger. The bypass valve has to be throttled when the heater is used. Open up supply and return liquor
valve of the exchanger always completely to prevent overheating of liquor and scaling.
The liquor is heated to approx 90C with 3 bar steam. Steam supply can be adjusted
locally by reading the local liquor outlet temperature 520-TI-1002. The recirculation flow
rate through the exchanger is significantly smaller than normal circulation rate
(respectively 50 and 300 m3/h).
If the 520-HX-065 is used for heating during normal operation, then open supply and
return liquor valve completely, and throttle bypass slightly, while checking that valve
position 520-DCV-0002, 520-FCV-0201 and 520-LCV-1001 remain within control range.
After usage of 510-HX-060 the line section has to be flushed to prevent plugging.
7.7.5
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.56
date
2005-06-30
rev
7.7.6
7.7.6.1
7.7.6.2
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.57
date
2005-06-30
rev
4
5
Check discharge valve is closed, start spare pump and open discharge valve
For maintenance, flush and drain pump that failed as described in section 7.7.6.1.
7.7.7.1
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.58
date
2005-06-30
rev
The pump has to be filled to provide lubrication of the stator (not for priming purpose).
When the pump is stopped, sufficient liquid is normally trapped between the pumping
elements to provide the necessary lubrication for restarting. However, if the pump has
been left standing for a long time or has been dismantled, it must be refilled and given a
few turns before starting, to get sufficient lubrication between the rotor and the stator.
Start of pump
If line and pump are empty:
1
Fill up suction line (open bottom valve of settler and drain valve at pump suction)
2
Fill up pump with water hose via plug on top of the pump and give it a few turns with
tool provided
If line and pump are full, proceed with:
3
Check purge water supply is open and check flow rate (discharge or suction valve
has to be open to have flow of purge water)
4
Check the valves in the discharge line of the pump is set up for the correct
destination
5
Check discharge valve of spare pump is closed.
6
Open suction and discharge valves
7
Start pump
Stop pump
1
Keep pump running during flushing. Open suction flushing connection and open
flush valve.
2
Close valve in suction line and flush through pump and discharge valve.
3
Stop pump and close discharge valve.
4
Open suction valve and flush through suction valve.
5
Close flush valve and keep suction valve open to allow purge water to flow through
the seal.
Note 1: Never run the pump dry, not even for a few revolutions.
Note 2: Never run pump with a closed suction or discharge valve.
Note 3: Do not vary the flow rate by throttling suction or discharge valve
7.7.7.2
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.59
date
2005-06-30
rev
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.60
date
2005-06-30
rev
When sufficient level has built up inside 520-TK-045, start pump 520-PP-045/046
and open discharge valve.
Shutdown
1
Stop pump 520-PP-045.
2
Close suction valve of 520-TK-045
3
Close the incoming condensate lines and destination lines.
4
Close 520-PCV-1101.
5
Tank will pull vacuum when cooling down which is not a problem as it is designed
for full vacuum.
Note: This pump has automatic changeover in case the running pump fails: when not in
use, the pump suction and discharge valves are open and the drains closed. A check
valve prevents back flow via the standby pump.
7.7.9
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.61
date
2005-06-30
rev
7.7.10
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.62
date
2005-06-30
rev
normal value of the LMTD is rather high, a fair amount of tubes may be plugged by the
time it is detected by a change in LMTD.
7.7.11
Filter regeneration
Filter regeneration refers to 4 P&IDs:
520-09
Filtrate feed
520-10
Liquor polishing
520-11
Polishing filter filtrate storage & distribution
520-13
Precoat and filter aid
A break down of the filtration and regeneration cycle is given below:
Description
Applying precoat
Filtration
Emptying filter vessel and
cake discharge
Sluicing
Backwash
Total regeneration time
Unit
min
h
min
Value
15
47
10
min
min
min
10
10
45
The precoat system has to be ready to use (see section 7.7.12). Check the availability of
process water.
In the description below filter 520-FL-060 will be regenerated, filter 520-FL-061 is in
operation. The following actions take place:
If 520-PDI-0902/0908 reaches its alarm point (2 bar), the operator starts the regeneration
cycle when precoat tanks is ready and there is no conflict in operation (other filter
regenerating or other large process water consumer taking water).
1
Disconnect 520-FIC-0902 (feed rate of running filter 520-FL-061) from 520-LICSA0802. (Level in 520-TK-060 will rise because one filter is regenerating)
2
Freeze valve position of 520-LCV-1001 on 520-PID 520-11. (Level in 520-TK-065
will fall because one filter is regenerating.)
3
Close filter feed and filtrate discharge (valve 520-XSV-0904 and 520-XSV-0913)
4
Open 520-XSV-0924 for draining to 520-TK-070, and if 520-XSV-0924 is open, open
vent/deaeration 520-XSV-0903
5
Waiting time. Duration to be set with timer. (few minutes)
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.63
date
2005-06-30
rev
7
8
9
10
11
12
13
14
15
16
17
Supply process water for sluicing (open 520-XSV-0907). (Second process water
pump will start automatically based on header pressure.) Duration to be set with
timer (approx. 10 minutes). Close 520-XSV-0907.
Supply process water for backwashing (520-XSV-0908). Duration to be set with
timer (approx. 10 minutes)
Waiting time for draining. Duration to be set with timer.
Close vent 520-XSV-0903 and 520-XSV-0924.
Open precoat feed line 520-XSV-0905 and overflow 520-XSV-0906.
Field operator to start precoat pump 520-PP-080 locally.
When filter is full (set time interval, also visible at tundish), open 520-XSV0925 and
close 520-XSV-0906.
Field operator adds 3 bags of diatomaceous earth to 520-TK-080.
Precoating to proceed for approx 15 minutes.
When precoating is done, following actions to take place:
open line to filtrate tank 520-TK-065 520-XSV-0913
close line to precoat tank 520-TK-080 520-XSV-0925
open filter feed line 520-XSV-0904
open 520-FCV-0901 20%
close precoat feed 520-XSV0905 and stop 520-PP-080
ramp setpoint 520-FIC-0901 to 120 m3/h
When liquid level in feed tank 520-TK-060 reaches its normal low setpoint, set 520FIC-0901 to automatic. Reconnect 520-LICSA-0802 (level of 520-TK-060) to 520FIC-0901 and 0902.
When liquid level in filtrate tank TK-065 is at its normal setpoint, unfreeze valve
position of 520-LCV-1001.
The total amount of slurry and water as drained to 520-TK-070 is more then the capacity
of 520-TK-070. Therefore, filter backflush pump 520-PP-070/071 will be started
automatically via level switch 520-LISA-1002 H(S). Agitator 520-AG-070 is kept running
continuously.
If the regeneration process is disturbed for some reason the filter feed tank 520-TK-060
will become full and the filtrate tank 520-TK-065 will run empty. As a consequence, the
production rate of the second stage crystallization section has to be decreased to 50%.
In this case liquor supply to the elutriator is reduced to 50% as well, leading to off-spec
product.
Note: Ensure the bypass over 520-FCV-0901/0902 is closed.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.64
date
2005-06-30
rev
7.7.12
Precoat preparation
Precoat tank 520-TK-080 is filled with filtrate and process water via 520-XSV-1201.
520-XSV-1201 is opened manually on the DCS and closed automatically, when 520-LISA1201 reaches target level of 90% (high level switch).
When starting with precoat application, the filter and the lines are empty. In total an
amount of approx. 25 m3 is required for filling up and the tank level will be reduced from
90% to 30%.
The filter hold-up of approx. 21.5 m3 is the actual loss of precoat liquor, which is approx.
28 ton. The filter aid concentration is 0.5 wt%. On a total of 28 ton loss, 140 kg has to be
added. Precoat filter aid is added manually from bags.
The precoat liquor can be diluted with 10% water to prevent scaling (to be determined
during first start-up).
The field operator is in attendance when filter regeneration has started. When
backwashing is complete, precoat will be applied. There is no waiting time available in the
regeneration time. If the precoat is not started at the right time, or if there is any other
delay in the filter regeneration, the second stage filtration operating capacity has to be
decreased.
Following procedure:
1
Manual valves of filtrate and process water are closed
2
Suction valve of precoat pump is open
3
Open 520-XSV-1201 (by desk operator)
4
Read tank level on 520-LISA-1201
5
Open process water supply and add the required amount (set by timer)
6
Close process water valve and open filtrate valve
7
When target level is reached, 520-XSV-1201 will automatically be closed
8
Close manual valve in filtrate feed line.
9
Start agitator locally by hand
10 Add diatomaceous earth through funnel
11 Flush funnel if needed with water hose.
12 Wait for instruction from the DCS operator to start the precoat pump (520-XSV-0905
or 0919 has to be open).
13 Start pump 520-PP-080
14 The pump is stopped when precoating is completed
15 Stop agitator
Note: Purge water is supplied to 520-PP-080. To maintain a continuous flow, keep suction
valve open and close discharge valve of the pump if pump is not running.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.65
date
2005-06-30
rev
7.7.13
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.66
date
2005-06-30
rev
4
5
Flushing of centrifuge
During normal operation, flushing of centrifuges with process water is necessary once
every 8 hours. Flush time is 5 minutes.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.67
date
2005-06-30
rev
Note: Flushing of line is required after pumping slurries and near saturated liquor.
7.7.16
Make sure deaerator 510-DE-050 and settler 510-TK-050 are ready for receiving
liquor or slurry from the sump.
Open valve towards 510-DE-050 and close valve towards 900-TK-250.
If the slurry is contaminated, then close towards 510-DE-050 and open valve
towards 900-TK-250
Set pump operating switch in automatic (check)
Note: Flushing of line is required after pumping slurries and near saturated liquor.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
7.68
date
2005-06-30
rev
7.7.17
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
HPD, LLC
23562 West Main Street, Route 126
Plainfield, Illinois 60544 USA
Tel: 1 (815) 609-2000 Fax: 1 (815) 609-0490
Web site: www.hpdsystems.com
1.2
Emergency Wash-Out
In the case where it is not possible to perform the Planned Wash-Out procedure due to equipment or
power failure, the crystallizer contents can be dumped through the drain valve. The drain nozzle will
usually require flushing with hot process water for several minutes in order to dissolve settled solids.
The crystallizer contents are hot (97C) and there is a large volume to drain (300 m3) so the disposition
of this material must be thought through before draining is performed. The crystallizer agitator cannot
suspend solids once the level is below the top of the draft tube so usually the entire contents must be
removed when draining is used. The level transmitter is not able to detect the level below the top of the
draft tube so the only indication of level for the remaining 70% of the crystallizer contents is when the
vessel is empty and slurry is no longer draining. However, the drain nozzle can become plugged and
give a false empty indication so this must be kept in mind when draining and the nozzle should be
flushed with hot process water to ensure the crystallizer is empty.
Once empty, the equipment repairs can be made and when ready, the crystallizer can be refilled to the
operating level with either water or solids-free liquor.
2
2.1
Anhydrous Reactor
Planned Wash-out
This wash procedure is used for routine cleaning of heat transfer surfaces of the Anhydrous Reactor
Heater. Once refined with operating experience, this procedure should take ~3 hours to perform. The
intent is to perform this Quick Wash at frequent enough intervals to prevent complete plugging of any
heat exchanger tubes. If tube plugging does occur, the plugged tubes will most likely remain out of
service until a complete shutdown is performed with draining the vessel, opening the manways and
performing high-pressure water cleaning of the tubes.
The initial frequency for performing a Quick Wash is once per week. The frequency can be adjusted
based on operating experience.
First stop the slurry feed by closing the isolation valve at the Second Stage Crystallization Feed Tank,
flushing the line with hot process water and then stopping the slurry feed pump.
Stop supplying steam to the Anhydrous Reactor Heater by putting the pressure control valve for the 15
bar steam in manual and closing (520-PCV-0401).
Put level control valve in manual so that slurry withdrawal is continued as the level decreases in the
Anhydrous Reactor (520-LCV-0001A/B).
Monitor the level in the Second Stage Crystallization Feed Tank. The level will increase in the feed
tank as the level decreases in the Anhydrous Reactor. If necessary, stop feeds to the First Stage
Crystallizer, flush the slurry transfer lines and recover the remaining product out of the First Stage
Elutriator through the First Stage Centrifuges and then allow the First Stage Crystallizer to idle. Brine
will also likely need to be purged from the circuit during this time.
Continue to draw down the level in the Anhydrous Reactor at normal operating flow rate for ~ one hour
or until the level transmitter indicates 20% level (~1 meter below RI nozzle). At this point the DN150
process water line to the Anhydrous Reactor should be opened and the vessel should be filled to a high
level. The objective is to reduce the density in the vessel below 1300. Care must be taken to avoid
over-filling the vessel and the pressure should also be closely monitored. The vessel should be
manually vented from the top vent valve if the pressure increases above 1.5 bar-g.
The temperature in the Anhydrous Reactor will decline as the process water is added. When the
temperature goes below 115 C, the slurry transfer to the Second Stage Crystallizer must be stopped and
the line flushed. If the density is still above 1300 when the vessel is nearly full, it will be necessary to
purge material through the drain valve.
Once the density is below 1300, the Anhydrous Reactor is allowed to circulate for at least one hour and
the density is monitored to ensure that the liquor remains below saturation. After one hour below 1300
density is obtained, the system can be restarted by first applying the steam and heating the contents to
120 C, then begin transferring material to the Second Stage Crystallizer and finally restarting the slurry
feed from the Second Stage Crystallization Feed Tank.
2.2
Emergency Wash-Out
Whenever possible, the Quick Wash procedure should be used prior to draining the Anhydrous Reactor.
This dilutes and dissolves the anhydrous sodium carbonate crystals and reduces the temperature.
Attempting to drain anhydrous slurry will result in the instant formation of sodium carbonate
monohydrate solids in addition to steam and hot liquor. If equipment failures prevent a Quick Wash
from being performed, the next best thing would be to first dilute the anhydrous slurry by opening the
DN150 process water connection and filling the Anhydrous Reactor to a high level. Then slurry can be
drained through the drain valve.
When possible, the Anhydrous Reactor can then be filled with process water to the normal operating
level and circulated for at least one hour to dissolve any solid build-up. If significant tube plugging has
occurred, the system will need to be drained of wash water and the high pressure water cleaning system
will need to be used to manually clear the plugged tubes.
2.3
3
3.1
3.2
Emergency Wash-Out
The emergency wash-out procedure, which is primarily and emergency drain procedure, is the same as
the First Stage Crystallizer.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
8.1
date
2005-06-30
rev
8.1
Process description
Monohydrate crystals leaving the second stage centrifuges are fed with belt conveyor
520-CV-040 to dryer feed screw conveyor 600-SC-010. In this conveyor the damp crystals
are mixed with dry crystals from the drying section of the fluid bed, supplied via dried
product recycle airlock 600-AL-010 and bucket elevator 600-BE-010. The mixed crystals
are further transported by dryer feed screw conveyor 600-SC-020 to dryer feed distributor
600-FD-010.
Fluid bed dryer 600-FB-010 comprises three baffled compartments containing heat
exchanger tube bundles. In the first compartment surface moisture is removed, and the
monohydrate is heated to about 85 to 90C. The first section is a well mixed deep bed for
receiving and drying the wet feed material. Dehydration is not desired in this first
compartment, as it results in a fragile, low hardness final product and can lead to
excessive heat bundle scaling.
In the second compartment the solids temperature is increased to 150C, and dehydration
is performed. The second section is for dehydration and has a plug flow design.
In the third compartment ambient temperature fluidizing air and circulating water supplied
from a cooling tower are used to reduce the product temperature to 80C. Anhydrous
product containing less than 0.1 % moisture will discharge through airlock 600-AL-040 to
the dryer product conveyor 700-CV-010 feeding the screening.
Fluidizing air will be indirectly steam heated to 180C prior to delivery to the first two dryer
compartments. Air for the first compartment is supplied by dryer air fan 600-FN-010,
preheated with condensate in dryer air preheater 600-HX-010 and heated with steam in
dryer air heater 600-HX-011. Air for the second compartment is supplied by dryer air fan
600-FN-020, preheated with condensate in dryer air preheater 600-HX-020 and heated
with steam in dryer air heater 600-HX-021. The majority of the heat for drying and
dehydration is supplied by the steam heated pipe bundles inside the fluid bed.
The third compartment will receive ambient air from cooling air fan 600-FN-025. The
majority of the cooling capacity is supplied by cooling water that flows through a pipe
bundle in the cooling section.
The dryer includes the integral baghouse 600-DC-010. The dust that originates from the
drying and dehydration section is recovered in the baghouse and is returned directly to the
dryer. About 3.5 t/h of dust removed from the cooling section end of the fluid bed dryer is
removed separately from the dryer, transported by dryer fines discharge screw 600-SC030 and recycled to the second stage centrate tank and to the second stage feed tank.
This dust is discharged via dryer fines airlock 600-AL-030 to dryer dust hopper 600-BN-
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
8.2
date
2005-06-30
rev
030. In this hopper the dust is mixed with air and sucked into dryer dust conveyor
600-CV-030, which is driven by second stage centrate.
Dedusting air from the inlet of conveyor 700-CV-010 is connected to the dryer dust
collector 600-DC-010.
Induced draft fan 600-FN-030 will pull the exhaust air from the dryer through the
baghouse for discharge to atmosphere.
Condensate from the air heaters and the heat exchanger tube bundles is collected in fluid
bed dryer condensate tank 600-TK-010, where it flashes to a pressure between 3 and 6
bar absolute. The resulting vapor is discharged into the low pressure steam header. The
condensate is discharged via the air preheaters to the boiler feed water tank 900-TK-040,
by means of the pressure inside 600-TK-010.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
8.3
date
2005-06-30
rev
8.2
Normal operation
8.2.1
Feed to static fluidbed dryer for pure soda ash plant (PID 600-01)
Via a chute, centrifuge cake from the crystallization section is fed to dryer feed screw
conveyor1 600-SC-010. Part of the dried light ash is recycled from the drying section to
this screw conveyor to lower the feed moisture content and to prevent fouling of the screw
conveyors and the feed distributor 600-FD-010. The dry ash recycle is provided by airlock
600-AL-010 and bucket elevator 600-BE-010 that run at a fixed speed. Therefore the
amount of recycle is fixed, and the ratio of dry crystals to the feed varies with the feed
capacity.
The mixed crystals are fed to dryer feed screw conveyor2 600-SC-020 that feeds the
crystals to the dryer feed distributor 600-FD-010, which distributes the feed evenly over
the width of the dryer. The speed of the feed distributor can be adjusted. After testing
during commissioning and start-up this is set at an optimal value.
8.2.2
Static fluidbed dryer for pure soda ash plant (PID 600-02)
The mixed crystals are fed to the drying section of the fluid bed dryer. The temperature of
the drying section is controlled by 600-TICSA-0101 which controls the steam flow to the
steam tube bundles.
The air flow through the distributor plate is essential for proper fluidization. The air flow
rate is controlled (see P&ID 600-03). In the dehydration section the air flow rate is
distributed over 2 segments. The air flow distribution can be adjusted with manual valves.
The flow rate for each segment can be determined by use of the pressure drop indicators
(600-PDI-0103/0104 and 600-PDI-0105/0106). The total pressure drop across the (clean)
distribution plate and the bed is measured and this is a coarse indicator for the bed height
and air flow rate in that section.
A good indication for the performance of the first two sections of the fluid bed dryer, is the
temperature of the soda ash leaving the dehydration section (600-TICSA-0102). Therefore
this temperature is an important quality parameter.
Cooling of dense soda ash is done partly by the ambient air (from cooling air fan 600-FN025) required for fluidization and for the major part by circulating cooling water through the
tube bundles in the third section of the unit. A correct air flow rate is important for proper
fluidization and for proper de-dusting. The amount of air can be controlled with a manual
valve, and the pressure drop of the bed (600-PDI-0107/0108) can be used as a measure
for the flow rate.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
8.4
date
2005-06-30
rev
This cooler section is also used for separation of dust. Dust is entrained in the air to the
filter bags and thus carried over beyond the fluid bed part of the unit. The hood of the
dryer is operated at a pressure slightly below atmospheric. This is done for dust control
(both from the dryer itself and for the rest of the plant). To maintain the required negative
pressure in the hood of the dryer, a pressure control valve 600-PCV-0110 is installed in
the suction line of dryer ID fan 600-FN-030. The dust entrained in the fluidization air is
separated in dust collector 600-DC-010. Dust from the dryer and dehydration section is
returned directly from where they are collected. Dust from cooling section is separately
discharged by means of dryer fines screw conveyor 600-SC-030 and dryer fines airlock
600-AL-030 to the dryer dust hopper 600-BN-030. This dust discharge system runs at a
fixed speed.
The filter bags clean the air from the dryer to below the dust level allowed for
environmental release to atmosphere. The dust level in the clean air is monitored with a
dust detector (opacity measurement) and a broken bag detector is installed.
To maintain an acceptable pressure drop across the filter the bags are automatically
cleaned by pulsing with compressed air. This is carried out in cycles, a few rows at a time,
triggered by a timer. The pressure drop is also monitored and at high pressure drop an
alarm is generated so that the operator can start an additional cleaning cycle.
Cooled dense ash is discharged from the dryer through dryer product discharge airlock
600-AL-040 to conveyor belt 700-CV-010. The airlock and conveyor run at fixed speed.
8.2.3
Air supply and air heating for static fluidbed dryer for pure soda ash plant (PID 60003)
Steam (15 bar) is supplied to to air heaters 600-HX-011 and 600-HX-021 for heating
fluidization air for drying and dehydration sections. The temperature of the hot air is
controlled by the steam flow to the air heaters (600-TCV-0201/0202).
The air heaters consist of of a preheating section and a heating section. In the preheating
section cold air is heated with the condensate discharge from condensate tank 600-TK010. Using this condensate air is heated to about 100C and the condensate is cooled to
about 80C. In the heating section the preheated air is heated with steam to 180C.
The flow distribution of condensate to both preheaters can be adjusted with manual
valves, in order to achieve equal the outlet condensate temperatures (600-TI-0203/0204).
One of these manual valves should be fully opened.
Fluizidization air for drying and dehydration sections is supplied by dryer air fans
600-FN-010 and 600-FN-020. The speed of these fans is controlled by flow meters
downstream of the heater (600-FIC-0201/0202).
Fluidization air for the cooling section is supplied by cooling air fan 600-FN-025 which
runs at fixed speed. The amount of air can be adjusted with a manual valve, and the
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
8.5
date
2005-06-30
rev
pressure drop of the bed (600-PDI-0107/0108) can be used as a measure for the flow
rate.
8.2.4
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
8.6
date
2005-06-30
rev
8.2.5
Setting list
Instrument
Unit
Normal
Alarm
Trip/Switch
600-FISA-0101
ton/h
24
LL TBD
LL TBD
L TBD
600-FI-0102
ton/h
14
600-FI-0103
ton/h
600-FI-0104
75
m /h
600-FIC-0201
m /h
30800
600-FIC-0202
m /h
50500
600-HIC-0001
600-KIS-0101
600-LICSA-0301
50
H 90
L 20
600-LA-0101
H TBD
600-LA-0102
H TBD
600-LICSA-0301
50
LL 5
LL 5
LL 5
L 20
H 90
600-LI-0302
50
600-LSA-0303
mm
600-PIC-0110
mm H2O-g
-10
600-PISA-0111
barg
14.5
600-PI-0112
barg
14.5
600-PI-0113
barg
14.5
H 200
LL TBD
L TBD
600-PI-0114
barg
4.5
600-PCV-0115
barg
4.5
600-PDI-0101
mm H2O
900 - 1050
600-PDI-0102
mm H2O
250 -300
600-PDI-0103
mm H2O
900 - 1050
600-PDI-0104
mm H2O
250 - 300
600-PDI-0105
mm H2O
900 - 1050
600-PDI-0106
mm H2O
250 - 300
600-PDI-0107
mm H2O
900 - 1050
3)
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
H 200
3)
LL TBD
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
8.7
date
2005-06-30
rev
Instrument
Unit
Normal
600-PDI-0108
mm H2O
250 - 300
600-PDISA-0109
mm H2O
125 - 150
600-PI-0201
barg
14.5
600-PI-0202
barg
14.5
600-PI-0203
mm H2O-g
1285
600-PI-0204
mm H2O-g
1285
600-PI-0205
Barg
600-PDI-0201 (0206?)
mm H2O
20
600-PDI-0202 (0207)?)
mm H2O
20
600-PDI-0203 (0208?)
mm H2O
20
600-PI-0301
Barg
600-PIC-0302
Barg
600-QIA-0101
mg/m
Trip/Switch
H TBD
H TBD
<35
1)
H 35 (Check)
mg/Nm
<50
2)
H 50
mg/m3
<35
5)
H 35 (Check)
<50
2)
H 50
600-QIA-0104
Alarm
600-SSA-0001
TBD
TBD
L TBD
600-TICSA-0101
90
H TBD
600-TICSA-0102
150
600-TIC-0103
80
600-TISA-0104
210
600-TIA-0105
90
600-TIA-0106
80
600-TI-0107
30
600-TI-0108
45
600-TIC-0201
180
600-TIC-0202
180
600-TI-0203
85
600-TI-0204
85
600-TI-0301
200
600-TIA-0302
99
HH TBD
L TBD
HH TBD
H TBD
HH TBD
HH TBD
LL TBD
LL TBD
L TBD
H TBD
L TBD
H TBD
H 101
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
8.8
date
2005-06-30
rev
Instrument
Instrument air purgerators
Unit
l/h
4)
Normal
Alarm
10
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Trip/Switch
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
8.9
date
2005-06-30
rev
8.3
Logic functions
The following table shows logic functions acting on equipment.
Equipment/Action
Start
Stop
Signal description
Type
Start/
Switch/
Running
Interlock
condition
600-AL-040
Locally by
Locally by
hand
hand and
700-CV-010
automatic
600-AL-030
Locally by
Locally by
hand
hand and
600-GA-030 is open
automatic
600-SC-030
Locally by
Locally by
hand
hand and
automatic
running
600-GA-030 is open
520-CV-040
Locally by
Locally by
hand
hand and
automatic
AL-040 running
SC-030 running
running
SC-020 running
SC-010 running
Stop
LL switch activated
Stop
TISA-0104 LL switch
activated
Stop
Locally by
Locally by
hand
hand and
automatic
running
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Stop
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
8.10
date
2005-06-30
rev
Equipment/Action
Start
Stop
Signal description
Type
Start/
Switch/
Running
Interlock
condition
600-AL-010
Locally by
Locally by
hand
hand and
automatic
running
SC-020 running
SC-010 running
running
600-SC-010
Locally by
Locally by
hand
hand and
SC-020 running
automatic
600-SC-020
Locally by
Locally by
hand
hand and
running
automatic
600-FD-010
Locally by
Locally by
hand
hand and
None
automatic
600-FN-010
Automatic
Automatic
600-FN-020
Automatic
Automatic
600-FN-025
Automatic
Automatic
600-FN-030
Automatic
Automatic
Dryer-FN-030 running
Dryer-FN-030 running
Dryer-FN-030 running
None
Action
Cause
600-TCV-0101
Close
600-TCV-0102
Close
600-TCV-0201
Close
600-TCV-0202
Close
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
8.11
date
2005-06-30
rev
8.4
8.4.1
7
8
Open all manual dampers at air inlet of drying, dehydration and cooling section of
the fluid bed.
Close valves 600-TCV-0101/0102 at steam supply to heating coils
Close manual flaps between drying section and dehydration section
Close product outlet powder gate in the fluid bed outlet section
Start dryer ID fan 600-FN-030 with closed inlet damper and put 600-PIC-0110 on
automatic.
(Overpressure on the dryer and dust collector must be avoided in order to prevent
dust emission. Therefore, Dryer ID Fan 600-FN-030 has to be running before other
fans are started)
Directly when 600-FN-030 is running, start dryer air fans 600-FN-010 and 020 at low
speed and cooling air fan 600-FN-025 and put flow controllers 600-FICA-0201/0202
on automatic. Gradually increase the setpoint to the value according to the setting
list.
Open instrument purgerators and set flowrate according to setting list
Open valve 600-PCV-0115 of plant air supply and activate air pulsation for cleaning
of dust filter
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
8.12
date
2005-06-30
rev
9
10
11
12
13
14
15
16
17
18
19
20
Now unit is ready to receive wet feed and the calciner and crystallization section can be
started.
21
22
23
24
25
26
27
Start 520-CV-040.
Adjust temperature setpoint of 600-TICSA-0201 as needed to keep the bed
temperature at 90C.
Monitor bed height, and when 600-PDI-0101 exceeds 900 mmWC, the intermediate
powder gate between drying and dehydration section shall be manually opened. In
this way the dry monohydrate enters the dehydration section of the bed
Put steam to dehydration section steam panel and air heater (600-TICSA-0102 and
600-TIC-0202) to automatic with setpoint of 180C (ensure bypass over 600-TCV0102/0202 is closed).
Monitor bed height, and when 600-PDI-0103 exceeds 900 mmWC, the intermediate
powder gate between dehydration and cooling section shall be manually opened. In
this way the dry soda ash enters the cooling section of the bed
Open isolation valves of cooling water and put 600-TIC-0103 in automatic mode with
a setpoint of 80C (ensure bypass over 600-TCV-0103 is closed).
Check temperature of the sections. The product temperature after the dehydration
section (600-TICSA-0102) has to be above 150C for required conversion. The
product outlet temperature has to be 80C or less.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
8.13
date
2005-06-30
rev
28
29
8.4.2
4
5
8.4.3
Check air flow rate in relation to bed height (600-PDI-0107/0108) Adjust with manual
control valve if needed (information provided by vendor)
Take sample of product to check fluid bed dryer performance (moisture content,
particle size distribution and bulk density)
When bed, hoppers, screw conveyors etc. are empty, the unit can be stopped.
3
Close steam supply to the tube bundles (600-TCV-0101/0102) and to air heaters
(600-TCV-0201/0202)
4
Close cooling water supply to tube bundle (600-TCV-0103)
5
Stop 600-AL-010, 600-BE-010, 600-SC-010, 600-SC-020, 600-FD-010
6
Stop dust recycle system (see procedure in section 8.5.2)
7
Stop 600-AL-040 and 700-CV-010
8
Stop liquor supply from crystallization section (see second stage crystallization)
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
8.14
date
2005-06-30
rev
9
10
11
12
13
8.4.4
Going to standby
1
2
3
8.5
8.5.1
Normal start-up
1
2
3
4
5
6
7
8
9
8.5.2
Normal shut-down
1
2
3
4
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
8.15
date
2005-06-30
rev
8.6
8.6.1
Normal start-up
1
2
3
4
5
8.6.2
8.7
8.7.1
Periodic checks
1
3
4
5
6
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
8.16
date
2005-06-30
rev
8.7.2
Parameter
Tag or sample
Purpose; target or
setpoint
520-CV-040
Sample
from crystallization
600-FB-010,
Bed temperature
600-TICSA-0101
drying section
600-FB-010,
Bed temperature
600-TICSA-0102
dehydration
Dehydration process;
135-150C
section
600-FB-010,
Bed temperature
600-TIC-0103
cooling section
600-FB-010,
80C
Bed height
600-PDI-0101/0102
drying section
600-FB-010,
Cooling process;
Drying process;
See setting list
Bed height
dehydration
600-PDI-
Dehydration process;
0103/0104/0105/0106
600-PDI-0107/0108
section
600-FB-010,
Bed height
cooling section
700-CV-010
setting list
Product moisture content,
Sample
Quality parameter;
< 0.1 wt%
bulk density
250 < D50 < 350 m
> 1000 kg/m3
8.7.3
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
8.17
date
2005-06-30
rev
8.8
8.8.1
Cleaning of dryer
If the pressure drop over the fluid bed increases too much, the fluid bed has to be cleaned
with water. Fouling is expected to occur mainly in the first section (drying section),
especially in case the feed moisture content is too high. It is expected that this section will
need to be cleaned every 3 months, depending on the control of the process.
Before cleaning, the dryer has to be empty so must be shut down in accordance with
procedure 8.4.3.
1
2
3
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
8.18
date
2005-06-30
rev
8.8.3
8.8.4
Dust transport
600-GA-030 is closed when 600-LSA-0303 detects high level and when 520-PP-040 and
520-PP-041 are out of operation (so when flow to 600-CV-030 stops). 600-GA-030 can be
opened by the operator when:
high level 600-LSA-0303 not activated
520-PP-040 or 520-PP-041 in operation
When both 520-PP-040 and 520-PP-041 are out of operation 600-GA-030 is closed and at
the same time 600-XSV-0301 is opened. Valve 600-XSV-0301 has to be closed by the
operator (reset action on DCS required).
Supplying hot dryer dust to the liquor stream causes the liquor temperature to increase
due to the sensible heat increase by introduction of hot dryer dust and the heat of
dissolution.
Supplying hot dryer dust to the liquor stream causes the liquor temperature to increase
due to the sensible heat increase by introduction of hot dryer dust and the heat of
dissolution. Therefore the return temperature of the liquor is monitored with 600-TIA-0302.
When the temperature is too high (see setting list), an alarm is generated, and the cause
of the high temperature has to be investigated or otherwise dust bleed has to be stopped.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
8.19
date
2005-06-30
rev
8.8.5
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Operation procedure for Fluid Bed Dryer Cooler for Pure Soda ash plant
Document No. MSC/CL/002, Rev.0
Customer:
Magadi Soda Company Limited, Kenya
DT: 22-2-2005
WASHING PROCEDURE
Wash-up of the fluid bed plant
It is expected that the fluid bed can be operated continuously for a longer
period. However it is recommended to make some short inspections during the
operation period while feed & fans are stopped.
After a running period of approximately 3 months the fluid bed should be
evacuated for product and inspected. Washing of steam tubes may be
necessary. In practice this stop typical have duration of 3 shifts.
Once in a year long overhaul shut down should be performed. In addition to
periodic inspection and washing we advice to pull out 1 or 2 stream bundles in
the drying as well as the calcining section. This will allow a walk in on the gill
plate for a closer look of this as well as inspection of the steam tubes.
For the pulling of steam bundles a set of mobile trolley to be placed in
extension to the internal rail in order to support the bundle in the outside
position.
Inspection of the plant is mainly a question of inspecting the plant interior due
to possible problems with the performance of the plant. It is absolutely
essential to have prior permission from concerned in-charge.
Note: Never enter the plant interior in case there is no person
available to supervise from the outside.
After washing it is recommended to let the system dry out before feeding is
started.
Page 1 of 2
Operation procedure for Fluid Bed Dryer Cooler for Pure Soda ash plant
Document No. MSC/CL/002, Rev.0
Customer:
Magadi Soda Company Limited, Kenya
DT: 22-2-2005
Washing procedure
1. Shut-down the plant as described the steps in the operation procedure
(document No. MSC/CL/001, Rev.0)
2. Open the blind flange provided at the bottom of plenum chamber of drying,
dehydrating & cooling section of fluid bed.
3. Open all manholes & inspection covers of fluid bed & dust collector
manually.
4. All manual valves in the cooling water line of cooling coils for cooling
section of fluid bed are closed.
5. The manual isolation valve at compressed air header at bag filter should be
closed.
6. Steam supply line to the fluid bed drying & dehydration section of fluid bed
are isolated by providing blind at the header.
7. Close valves TCV 0101 & TCV 0102 in manual mode at steam supply line to
heating coils of drying section & dehydration section. All isolation & bypass
valves of steam line supplied to the heating coils of drying & dehydration
section are manually closed.
8. The upstream & downstream system of the fluid bed drying system is
isolated.
9. All air dampers at air inlet of drying, dehydrating & cooling section of fluid
bed are manually closed.
Page 2 of 2
Operation procedure for Fluid Bed Dryer Cooler for Pure Soda ash plant
Document No. MSC/CL/002, Rev.0
Customer:
Magadi Soda Company Limited, Kenya
DT: 22-2-2005
10.Open intermediate powder gate in the fluid bed from drying to dehydration
section & from dehydration to cooling section.
11.Keep open the slide gate valve above AL-010.
12.Disconnect the heating coils with steam & condensate piping. Place mobile
trolley for the pulling of steam bundles, in extension to the internal rail in
order to support the bundle in the outside position.
13.Pull out heating coil & clean it manually by water jet. Clean all other
heating coils in same manner.
14.Connect flexible water hose at the screw feed (SC-010) & wash the screw
feed. Water should flow through the rotary distributor (SC-020). The feed
screw & rotary distributor (SC-020) may be started during washing.
15.Washing of fines screw (SC-030) & product outlet box can be done by
spraying water from the manhole provided at the product outlet hopper.
Page 3 of 2
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
9.1
date
2005-06-30
rev
EMERGENCY SITUATIONS
9.1
Power Failure
During limited power being available to the plant, the power management system (PMS)
automatically shuts down certain sections to allow sections with a higher priority to
continue operation, depending on the severity of the power failure. The order of priority
(highest first) is as follows:
Critical drives: items of equipment that need to be maintained in a safe mode of
operation and to ensure ease of start up after failure of the electrical power supply.
Essential drives: All other items of the pure ash plant that are needed for continuous
operation, excluding the majority of the washery area
Non essential drives: Majority of the new washery area
Applying the above logics provides the following response upon different levels of power
failure:
Level 1 failure: all non-essential drives are stopped, essential drives and critical drives
remain running
Level 2 failure: all non-essential drives and essential drives are stopped, critical drives
remain running
Level 3 failure (total power failure): all drives are stopped, incl. all utilities
The segregation of power supply gives the following general shut-down sequence:
In case of level 1 failure, the washery will be shut down (non essential drives). The roller
mill can be fed from CRS stockpile and so the calciner, crystallization and drying sections
can continue at normal operating capacity (essential drives).
In case of larger shortage of power (level 2), the essential drives are stopped as well, so
the whole plant is basically shut down however, critical drives remain running. This is
especially important to prevent long recovery time because of solids settling and plugging
in critical vessels. Therefore the agitators in tanks (incl. settlers and crystallizers) with high
concentrated slurries are critical drives. Furthermore the utility supply is classified critical
for purge water on seals, steam tracing of anhydrous lines and hot water for flushing.
In case of total power failure (level 3), all electrical drives including utilities are stopped.
A list of the classification of the drives is provided under separate cover.
9.1.1
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
9.2
date
2005-06-30
rev
Only non-essential drives are stopped and the plant continues to run (with some
disturbances, see section 5.7.6), except the washery section. CRS is supplied to the mill
from the CRS stockpile. Liquor from the dredge continues to be supplied to the ESP
conveying system and crystallization vent condenser after an interruption to make the
supply line from the dredge free of solids. When the supply line is free of solids the liquor
will be diverted to 200-TK-010 (pumps 200-PP-010/011/012 keep running). The liquor
supply to the boiler scrubber is stopped (200-PP-060/061 is stopped).
Level 2:
Essential drives are shut-down as well and the whole plant is shut down. For the washery
now the liquor supply to 400 and 500 section is stopped, as well as the CRS conveying to
the mill. Only the critical drives remain running.
Level 3:
Critical drives (agitators) are stopped.
Note: Of the sections that are stopped as a consequence of an electrical power failure, the
signals to the solenoid valves of all air operated control valves and on/off valves is
removed, so all valves go to the fail safe position.
9.1.2
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
9.3
date
2005-06-30
rev
9.1.4
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
9.4
date
2005-06-30
rev
9.1.5
9.1.6
9.1.7
Steam boiler
Level 1 failure:
Soda ash Plant remains in operation, however, no more liquor supply from washery to
boiler scrubber. The hold-up in the scrubber tank is sufficient for 1 hour of operation.
Provide make-up to boiler scrubber from other source.
9.2
9.2.1
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
9.5
date
2005-06-30
rev
stockpile and the washery has to be put on standby. In principal solids from the dredgeing
section can continue.
9.2.2
9.2.3
9.2.4
9.2.5
9.2.6
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
9.6
date
2005-06-30
rev
9.3
9.4
9.5
Steam failure
Steam failure has the following consequences:
the calciner section has to be shut down (Emergency shutdown, see FFEM section 1.3)
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
9.7
date
2005-06-30
rev
second stage anhydrous reactor has to shutdown so this section goes on standby
fluid bed dryer has to stop and be put on standby
Close manual isolation valves of steam supply to users.
In most cases steam hold-up in boiler and headers will provide heat tracing on anhydrous
slurry lines.
9.6
9.7
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
9.8
date
2005-06-30
rev
9.9
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
10.1
date
2005-06-30
rev
10
10.1
Washery
During commissioning and 1st startup a number of process characteristics have to be
learned.
At several positions in the washery section foaming can potentially occur. Antifoam supply
is provided on the CRS centrate tank 200-TK-070 and is transferred from there to other
parts of the washery.
10.2
10.3
Crystallization
Amount of process water needed in precoat liquor.
10.4
Dryer
The speed of the feed distributor can be adjusted (600-HIC-0001). During commissioning
and start-up this value is set at an optimal value.
During start-up the underflow outlet is kept shut to ensure that the first section remains full
during build-up of the bed in the rest of the unit.
The operating value for the temperature has to be established in practice. By varying the
setpoint for 600-TICSA-0102 and plotting the corresponding moisture content of the final
dense ash product, the required bed temperature can be established for the final product
moisture specification. In advance, a set value for 600-TICSA-0102 of between 130 and
140C is to be expected.
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
10.2
date
2005-06-30
rev
10.5
10.6
Safety valve 600-SV-0301 will blow-off in case the dryer produces more LP steam
than is used by low pressure steam consumers
Check condensate discharge capacity
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
11.1
date
2005-06-30
rev
11
MAINTENANCE
11.1
Maintenance inspection
Maintenance inspection is required for a number of critical items. The frequency of this
inspection is once a day. Below a list of items that have to be checked on each routine
tour:
1
Pumps and agitators (vibration, noise)
2
Belt conveyors (tension, vibration, noise)
If a spare pump remains idle for a long period of time, it is recommended that the shaft be
rotated by a quarter turn on a weekly basis. This ensures that static loads and vibrations
are shared equally over all rolling elements, thus avoiding localized deterioration.
11.2
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
2.187.735 -
page
11.2
date
2005-06-30
rev
11.3
11.4
Inspection of tanks
Periodic inspections of tanks are required:
Items to check are wind and water line scaling on wall and agitator shaft and scaling in
vent outlets which will have to be cleaned as required.
Corrosion
Fixation of internals
Instrument connections and probes
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
Appendix 1
Basic Operating Manual
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
A.1
date
2005-03-24
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
rev
Engineering
Appendix 2
Basic Operating Manual
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
doc. no.
2.187.735 -
page
A.2
date
2005-03-24
rev
Engineering
Appendix 3
Basic Operating Manual
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
A.3
date
2005-06-30
rev
Explanation
CRS
DCS
ESP
Electrostatic Precipitator
FLD
MCC
PFD
P&ID
PMS
UPS
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
Engineering
Appendix 4
Basic Operating Manual
CONFIDENTIAL
project no.
405.014
project name
BOM Magadi
doc. no.
2.187.735 -
page
A.4
date
2005-06-30
= micro = 10-6
m = milli = 10-3
k = kilo = 103
M = mega = 106
G = giga = 109
word 10.0
This document and the copyright is owned by Akzo Nobel Engineering bv Arnhem The Netherlands. It may neither be copied
nor submitted to third parties for copying, without permission of the company.
rev