Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Section 9
Spillway Gates
SECTION 9
SPILLWAY GATES
9.1
MATERIAL PROPERTIES
There are 11 tainter gates at the spillway, each 40 feet wide. The top
of the gates is at Elevation 173.00, which is 28 feet above the crest of
the weir. Conservation pool is at 172.0 ft MSL in the reservoir.
Releases are instigated when the reservoir level reaches 172.5 ft MSL.
b.
Vertical ribs
Skin plates
Girders
Struts
b.
Location and sizes of the above components are shown under the
relevant isometric view on Figure 9.1-1
c.
Rev. 0
12/31/2004
Trunnion Hub
Bushing
Trunnion Pin
Bearing Ring
Thrust Ring
Trunnion Yoke
Pin Cover Plate
Box Girder
Page 9-1
d.
Rev. 0
12/31/2004
Section 9
Spillway Gates
Page 9-2
Figure 9.1-01
TAINTER GATES
DESIGN ANALYSES
9.2
Section 9
Spillway Gates
Rev. 0
12/31/2004
Page 9-3
Figure 9.2-01
TAINTER GATES
LOAD AND REACTIONS
Sheet 1 of 2
Figure 9.2-02
TAINTER GATES LOAD
AND SHEER REACTIONS
Sheet 2 of 2
figure 9.2-03
TAINTER GATES - SHEAR
MOMENTS AND STRESSES
Sheet 1 of 2
Figure 9.2-04
TAINTER GATES
SHEAR MOMENTS AND STRESSES
Sheet 2 of 2
9.3
Section 9
Spillway Gates
Rev. 0
12/31/2004
Page 9-4
9.4
Section 9
Spillway Gates
Rev. 0
12/31/2004
Page 9-5
9.5
Section 9
Spillway Gates
4-05. It was noted that some leakage was occurring at all the tainter gates in
the spillway (photograph 3) with the greatest amount flowing from gates 2, 4, 5
and 7. The leakage in every case was found at the bottom seal near the corner of
the gate and was not considered to be excessive or serious.
9.5.2 September 1979 FERC Part 12D Inspection Report
3-06. It was noted that portions of the spillway gate hoist equipment required
painting and lubrication. It is proposed to establish a program for servicing and
maintaining this equipment on a periodic basis.
3-07. A study is planned to determine the feasibility of double circuiting the
spillway gate hoists.
2.7
The spillway gates were inspected for corrosion, and evidence of maintenance
and leaks around the seals on the sides and bottom of gates. The stoplogs were
inspected for corrosion, evidence of stress, damage, or any unusual condition.
The lifting machinery was inspected for evidence of maintenance, corrosion, and
general condition. The spillway gates, stoplogs, and lifting machinery appear to
be in good condition with no evidence of problems. The leakage from the
spillway gates is minimal. The gates, stoplogs, and machinery have been painted
in the recent past, as evidenced by photographs #32, #33, #34, and #35.
Rev. 0
12/31/2004
Page 9-6
Section 9
Spillway Gates
2.7
The spillway gates were inspected for corrosion, and evidence of maintenance and
leaks around the seals on the sides and bottom of gates. The stoplogs were
inspected for corrosion, evidence of stress, damage, or any unusual condition. The
lifting machinery was inspected for evidence of maintenance, corrosion, and
general condition. The spillway gates, stoplogs, and lifting machinery appear to
be in good condition but there is evidence of corrosion beginning to appear as seen
in photograph #57, #58 and #61. This is an unexpected happening because it is
understood that the gates and machinery were painted in 1984. There has been a
definite deterioration since the 1985 inspection.
One spillway gate was exercised during the inspection. The discharge is shown in
photograph #59. The leakage from the spillway gates is minimal.
6.2.5 Spillway Gates - Corrosion is evident at certain limited areas of the gates
and lifting machinery. The gates were painted in the not to distant past. Touchup
painting of areas evidencing corrosion could be touchup painted to delay the
date when full painting will be repaired. No completion date is assigned to this
recommended action. Delay will result in more touchup work being required.
Rev. 0
12/31/2004
Page 9-7
Section 9
Spillway Gates
C. Maintenance of Spillway
The gated concrete spillway has eleven steel taintor gates with each gate having an
individual electric motor to hoist it. The hoisting equipment, consisting of the
electric motor, gear reduces and drum, is located above the gates well above
expected PMF water levels. The gates and lifting equipment are now being
painted. During the painting process all the gates are being exercised with each
gate lifted to the maximum up position by the hoisting equipment. Both the gates
and hoisting equipment are maintained by cleaning, painting, lubricating and
exercising on an as needed or periodic basis.
E. Adequacy of Operation of Spillway Gates and Standby Power
A trained, experienced and diligent staff with an appreciation and understanding of
the spillway gate opening consequences is in charge of operating the spillway
gates. During flood release, the staff has available an abundant amount of
information and refined judgement for opening and closing the spillway gates.
The Owners actions in past major flood releases demonstrate their capability in
operating the spillway gates in the prescribed manner. The standby diesel power
generator is adequate for emergency use.
6.
The condition of the spillway gates and machinery is shown in photographs #65
through #73.
The spillway gates were inspected for corrosion, evidence of maintenance and
leaks around the seals on the sides and bottom of the gates. The lifting machinery
was inspected for evidence of maintenance and corrosion, and to assess general
condition. Photographs #72 and #73 show the gate lifting equipment.
The gates show corrosion stains with a particularly bad example in photograph #68.
The gates were painted in 1993 and cathodic protection was added in 1994. The
actual corrosion should be minimized by the cathodic protection. Future corrosion
will verify the effectiveness of the cathodic protection. Photograph #70 shows
corrosion in the top gate arm near the trunnion. This corrosion is caused by
standing water in the arm. A drain hole was undoubtedly supplied in the web of
the beam but the hole has probably become plugged and now should be cleared.
The Authority should continually check all gates and unplug holes to prevent this
condition, as shown in photograph #70.
Rev. 0
12/31/2004
Page 9-8
6.
Section 9
Spillway Gates
One spillway gate was exercised during the inspection and the machinery was
found to be performing properly.
One matter of concern is that the gate motors are drawing more amps and are
requiring more power to raise than should be needed. Investigations as to the
cause are being made and possible corrective actions are being taken including
lubrication of moving parts, adjusting the brakes and the use other meters to check
the amps. Results of these measures will indicate if the problem persists. If so the
Authority should take actions deemed necessary to correct the matter.
Standby power located in the right abutment transition section is automatically
started weekly and appears to be in good operating condition.
Page 9-9
Section 9
Spillway Gates
Rev. 0
12/31/2004
Page 9-10