Sei sulla pagina 1di 3

Federal Register / Vol. 72, No.

131 / Tuesday, July 10, 2007 / Notices 37525

Act of 1973. For accessibility powered, electrical generation resource. impacts of the Project. Western
accommodations please send an e-mail The Applicant has identified the Project considered proposed mitigation
to accessibility@ferc.gov or call toll free Area, near the White Substation, as measures as part of the proposed Project
(866) 208–3372 (voice) or 202–502–8659 suitable to meet the required criteria for to determine impacts.
(TTY), or send a fax to 202–208–2106 developing a large, utility-scale wind
Alternatives
with the required accommodations. energy project and has applied to
All interested parties and staff are Western for interconnection there. The Western analyzed the Proposed
permitted to attend. For further White Substation is located near Action and No Action alternatives in the
information please contact Katie Brookings, South Dakota. The Project EIS. Western considered alternative
Williams at (202) 502–8246 or e-mail Area encompasses approximately 28 sites for the Project but dismissed them
kathleen.williams@ferc.gov. square miles (17,920 acres). It is from consideration, as no viable
bisected by a 345-kilovolt (kV) alternative locations were identified.
Kimberly D. Bose,
transmission line owned by Western. Therefore, Western limited its analysis
Secretary. to the proposal the Applicant submitted
The location and land availability
[FR Doc. E7–13307 Filed 7–9–07; 8:45 am] would enable the economic viability of for approval.
BILLING CODE 6717–01–P the proposed Project. The Applicant Proposed Action
expects the proposed Project to meet a
portion of the projected regional Under the Proposed Action, the
DEPARTMENT OF ENERGY demand for electricity produced from Applicant would construct up to 103 2–
wind resources. MW WTGs with a net capacity of 200
Western Area Power Administration MW. The Applicant would also
The Federal action associated with
White Wind Farm Project (DOE/ EIS– the proposed Project is approval or construct underground and overhead
0376) denial of the Applicant’s electrical collector lines; a new Project
interconnection request. Western needs substation; a line interconnecting its
AGENCY: Western Area Power to respond to the interconnection Project substation to Western’s White
Administration, DOE. request, provide transmission service Substation; and associated facilities.
ACTION: Record of decision. under its Notice of Final Open Access The Applicant proposes to construct or
Transmission Service Tariff, protect improve approximately 22 miles of
SUMMARY: White Wind Farm, LLC roads for access to the WTGs and
transmission system reliability and
(Applicant), a wholly-owned subsidiary electrical collector lines.
service to its customers, ensure
of Navitas Energy, Inc., has applied to The Project would temporarily disturb
compliance with applicable
the U.S. Department of Energy (DOE), approximately 626 acres of land during
environmental laws, and consider the
Western Area Power Administration construction of the proposed Project. It
Applicant’s objective.
(Western), to interconnect its proposed A Notice of Intent to prepare an would permanently disturb about 93
White Wind Farm Project (Project) to environmental impact statement (EIS) acres for installation of Project
Western’s transmission system at the was published in the Federal Register components (access roads, turbine and
existing White Substation, near on February 18, 2005. Western held a crane pads, overhead poles, and new
Brookings, South Dakota. The project scoping meeting to solicit public substation). The disturbed areas would
would involve building up to 103 2- comments on the proposed Project in be dispersed throughout the Project
megawatt (MW) wind turbine generators Hendricks, Minnesota, on March 1, Area.
(WTG or Turbine) with a net capacity of 2005. In addition, the Applicant has The Applicant would mount each
up to 200 MW. Western considered the been communicating and meeting with WTG on a single steel self-supporting
environmental impacts of the Project area landowners throughout tower, approximately 255 feet high. The
and has decided to grant the Applicant’s development of the proposed Project, as towers would be approximately 16 feet
request to interconnect to the White part of lease negotiations. On August 18, in diameter at the base and secured to
Substation. Taking into consideration 2006, the U.S. Environmental Protection concrete foundations. The housing,
the mitigation measures the Applicant Agency published a notice in the mounted at the top of each tower, would
has incorporated into the Project, Federal Register, announcing the enclose the electric generator, a voltage
Western expects no significant long- availability of the Draft EIS. Western step-up transformer, and a gearbox.
term or short-term impacts to resources held an Open House and Public Hearing Each WTG rotor would have three
from construction, operation, and on September 14, 2006, to solicit public blades made of laminated glass and
maintenance of the proposed Project. comments on the Draft EIS. For both the carbon fiber. The full WTG height at its
FOR FURTHER INFORMATION CONTACT: Ms. initial scoping meeting and subsequent tallest point would be approximately
Catherine Cunningham, Western Area Open House/Public Hearing, Western 400 feet from the ground to the tip of the
Power Administration, P.O. Box 281213, provided notice of the meetings to turbine blade. The Applicant would
Lakewood, CO 80228, telephone (720) Federal, State, and local agencies, paint the towers a flat neutral color to
962–7000, e-mail cunningh@wapa.gov. Tribes, and the public, with print blend into the natural environment.
For information about DOE’s National media, local newspapers The Applicant proposes to construct
Environmental Policy Act (NEPA) announcements, and direct mailings. the new Project substation adjacent to
process, contact Ms. Carol M. Western accepted public comments on Western’s existing White Substation.
Borgstrom, Director, NEPA Policy and the Draft EIS August 18 through October The substation would have a footprint
Compliance, GC–20, U.S. Department of 2, 2006. The Notice of Availability of of no more than 1 acre. The Applicant
Energy, 1000 Independence Avenue the Final EIS was published in the would construct the substation on
SW., Washington, DC 20585, telephone Federal Register on April 13, 2007. private land immediately north of White
jlentini on PROD1PC65 with NOTICES

(202) 586–4600 or (800) 472–2756. Western decided to grant the Substation.


SUPPLEMENTARY INFORMATION: The Applicant’s request to interconnect to The network of underground and
Applicant’s objective for the proposed its transmission system at the White overhead 34.5-kV collector lines would
Project is to develop a technically Substation. This decision is based on a interconnect the WTGs. Approximately
feasible and economically viable, wind- review of the potential environmental 45 miles of underground 34.5-kV sub-

VerDate Aug<31>2005 16:17 Jul 09, 2007 Jkt 211001 PO 00000 Frm 00022 Fmt 4703 Sfmt 4703 E:\FR\FM\10JYN1.SGM 10JYN1
37526 Federal Register / Vol. 72, No. 131 / Tuesday, July 10, 2007 / Notices

transmission collection line and permanent facilities to their prior land general and permit-specific mitigation
approximately nine miles of overhead use. The Applicant would reseed conditions for areas where the proposed
34.5-kV collector line would be needed. disturbed vegetation in non-agricultural access roads and utility lines would
The Applicant would bury the areas in accordance with landowner impact jurisdictional waters of the
underground electric collection line at agreements or local county extension United States. The Applicant would
least four feet below grade. The service protocols. employ directional boring techniques
underground collection line would link During operation and maintenance, where underground collector systems
each turbine to the next one or to the the Applicant would continuously would require a stream or wetland
overhead lines, which would in turn, monitor the WTGs for any crossing. The use of directional boring
connect to the substation. The abnormalities. If required, maintenance would reduce erosion and/or
Applicant would construct the overhead staff would be dispatched to repair sedimentation impacts. The Applicant
lines within public road rights-of-way. WTGs. The Applicant would conduct would use Best Management Practices
The overhead lines would be supported routine maintenance of the WTGs every such as installing silt fencing to ensure
on wooden single-pole structures, six months. Maintenance activities that sediment or fill material does not
approximately 25 to 30 feet tall and include lubrication and inspection of impact adjacent waterways.
spaced approximately 150 feet apart WTG components and fasteners. The
WTGs have a design life of 20 years. No Action Alternative
along road rights of way.
A temporary staging area would be Occasionally, a crane may be necessary Under the No Action Alternative,
developed on approximately eight acres to remove and replace turbine Western would not grant the
of tilled farmland. While the location of components. In this event, the Applicant’s request to interconnect to
the staging area is not final, the Applicant would conduct all Western’s transmission system, and the
Applicant expects that it would be construction activity within previously Applicant would not build the Project.
located near the proposed Project disturbed areas. Without the Project, existing
substation. This staging area would be During operation of the proposed environmental conditions would remain
used by the Applicant for construction Project substation, authorized personnel unchanged.
safety meetings, office trailers, parking would conduct periodic inspections and
service and repair equipment as needed. Environmentally Preferred Alternative
for equipment and vehicles, and staging
for some project components. Substation equipment would include a Western evaluated the alternatives to
To accommodate interconnection of step-up transformer, SF6 circuit determine which is environmentally
the proposed Project to Western’s breakers, switchgears, and other preferred, as required under 40 CFR
substation, the Applicant would electrical equipment. Project personnel 1505.2(b). The No Action Alternative is
construct a 345-kV overhead connection would monitor the use, storage, and the environmentally preferred
line from the proposed Project replacement of SF6 to minimize releases alternative, because no new disturbance
substation to the White Substation. The to the environment. would result. No impacts to
new overhead line would terminate on Within 120 days of the completion of environmental or social resources
a steel structure inside the White Project construction, the Applicant would occur. The No Action Alternative
Substation. Western would install a would submit a Decommissioning Plan would not, however, meet the
sulfur hexafluoride (SF6), gas-insulated to the Brookings County Planning and Applicant’s objective.
power circuit breaker; two high-voltage Zoning Department. The
Decommissioning Plan would outline Mitigation Measures
disconnect switches; and other
miscellaneous equipment at the White the manner in which decommissioning The Applicant has committed to
Substation. Western would monitor the activities would be conducted. Upon minimize potential short-term and long-
use, storage, and replacement of SF6 to termination of operations, and if the term environmental and social impacts
minimize releases to the environment. WTGs are not updated, the Applicant of the Proposed Action through project
The Applicant anticipates an 8-month would be obligated to dismantle and design, which includes implementation
construction schedule. This schedule is remove all Project components. Unless of mitigation measures. These measures
subject to negotiations with regulatory written approval is given by the affected are consolidated in Appendix B of the
agencies and utilities and may change. landowner, all Project components Final EIS.
With the exception of the overhead lines would be removed to a depth of 48 The Applicant, in consultation with
within public road right of way, the inches below grade and the soil would Western, developed a monitoring plan
Applicant would construct the proposed be restored to a condition reasonably to collect data on avian collisions with
Project on privately-owned lands, similar to the condition of the WTGs. Western and the Applicant
according to landowner agreements and surrounding soil. would continue to coordinate with the
in compliance with county, State, and Western completed wetland surveys U.S. Fish and Wildlife Service (USFWS)
Federal requirements. The Applicant to determine the presence of to ensure adequacy of the plan. Through
has obtained all necessary leases from jurisdictional and non-jurisdictional such monitoring, the Applicant and
private landowners to construct and wetlands in the Project Area. The U.S. Western would be able to identify and
operate the proposed Project up to 20 Army Corps of Engineers has implement reasonable operational
years. The Applicant would have the determined that the majority of streams changes or additional mitigation
option to renew leases at the end of the and wetlands in the Project Area are measures to further reduce avian and
20-year agreements. Depending on wind jurisdictional waters of the United bat mortality. Western and the
turbine technology and market States. The Applicant’s final site design Applicant are working with the USFWS
conditions at the end of the lease would avoid all wetlands, both to identify thresholds for making
period, the Applicant may jurisdictional and non-jurisdictional. appropriate changes. Surveys associated
jlentini on PROD1PC65 with NOTICES

decommission the project or update it The Applicant would apply for with the monitoring plan include 1 year
with more efficient components and appropriate permits for utility line prior to construction to establish
renew lease agreements. activities, including access roads baseline data and 2 years following
Following construction, the Applicant administered under section 404 of the operational start-up. The Applicant
would reclaim areas not maintained as Clean Water Act. These would contain would develop additional mitigation

VerDate Aug<31>2005 16:17 Jul 09, 2007 Jkt 211001 PO 00000 Frm 00023 Fmt 4703 Sfmt 4703 E:\FR\FM\10JYN1.SGM 10JYN1
Federal Register / Vol. 72, No. 131 / Tuesday, July 10, 2007 / Notices 37527

measures in consultation with the maps. The Federal Emergency SUMMARY: Under the Federal Advisory
appropriate regulatory agency, if Management Agency has not updated Committee Act (Pub. L. 92–463), EPA
needed. the Flood Insurance Rate Maps for this gives notice of a public meeting of the
Western will develop a Mitigation portion of South Dakota to reflect 500- Coastal Elevations and Sea Level Rise
Action Plan (MAP) to provide year floodplains. One-hundred-year Advisory Committee (CESLAC).
additional information on how floodplains occur along Deer Creek and DATE AND TIME: The meeting will be held
mitigation measures, associated with the along several unnamed streams in the on Friday, July 27, 2007, from 12:30
proposed Project, would be Project Area. The floodplains are p.m. until 3:30 p.m.
implemented. The MAP would be generally confined to the streambed and ADDRESSES: The meeting will take place
developed and made available prior to immediately adjacent, low-lying areas. via teleconference. Interested parties
any project activities directed by this The floodplains associated with the can access the teleconference as follows.
Record of Decision (ROD) that are ephemeral streams generally range from First, dial the following toll free
subject to a mitigation commitment. 200 to 500 feet in width. The Deer Creek number: (866) 299–3188. Second, enter
Consultation floodplain ranges from approximately the following conference code:
400 to 1,500 feet in width. On-site or 2023439719#. The leader will begin the
Western is the lead Federal agency for off-site flooding would not result from conference call.
compliance with Section 106 of the construction and operation of the
National Historic Preservation Act FOR FURTHER INFORMATION CONTACT: Jack
proposed Project. The Applicant would Fitzgerald, Designated Federal Officer,
(NHPA) and Tribal consultation for all not construct WTGs in floodplains.
components of the Project. The Climate Change Division, Mail Code
Implementation of county-approved 6207J, Office of Atmospheric Programs,
Applicant would avoid all design standards for areas of
archaeological and traditional cultural Environmental Protection Agency, 1200
concentrated flow would ensure that on- Pennsylvania Avenue, NW.,
properties determined significant in
site or off-site flooding does not occur. Washington, DC 20460; e-mail address:
consultation with the South Dakota
State Historic Preservation Officer Decision Fitzgerald.jack@epa.gov, telephone
(SHPO) and interested Tribes. Western number (202) 343–9336, fax: (202) 343–
Western decided to grant the 2337.
prepared a Programmatic Agreement Applicant’s request to interconnect with
(PA) in coordination with the South SUPPLEMENTARY INFORMATION: The
Western’s transmission system at the purpose of CESLAC is to provide advice
Dakota SHPO. The PA was executed on White Substation. The Proposed Action
December 18, 2006. It establishes the on the conduct of a study titled Coastal
would meet the Applicant’s objectives Elevations and Sensitivity to Sea Level
Area of Potential Effect for the proposed for the Project. Construction, operation,
Project, proposes a treatment plan for Rise which is being conducted as part
and maintenance of the proposed of the U.S. Climate Change Science
identified resources, describes Project would not result in significant,
procedures for unanticipated Program (CCSP). The study pays
short-or long-term environmental particular attention to the coastal area of
discoveries, sets forth procedures for impacts. The Applicant would employ
Tribal consultation, and suggests the U.S. from the state of New York
all practical means to avoid or minimize through North Carolina. A copy of the
general mitigation measures. The PA environmental harm as a result of the
ensures that there would be no study prospectus is available at: http://
proposed Project. www.climatescience.gov/Library/sap/
‘‘unmitigatable’’ adverse effects on This ROD meets the requirements of
historic properties as defined under the sap4–1/default.php. A copy of the
NEPA as well as the Council on Committee Charter is available at
NHPA. The Applicant would avoid Environmental Quality and DOE’s
areas containing identified resources. http://www.fido.gov/facadatabase/. This
NEPA implementing regulations. is the third meeting of CESLAC. The
Western is also the lead for
Additional analyses may affect this meeting will focus on consideration of
compliance with Section 7 of the
decision and result in subsequent a draft of the study. Draft materials that
Endangered Species Act. Western
analysis or decisions. Western will will be considered in the meeting can be
prepared a biological assessment and
notify the public of any additional found at: http://
submitted it to the USFWS. Western
activities necessary to meet Western’s www.environmentalinformation.net/
determined that the project may affect
NEPA and other public involvement CESLAC/ as of Friday, July 13, 2007. If
but is not likely to adversely affect the
requirements. a printed copy of the material is needed,
western prairie fringed orchid, the
Topeka shiner, and the bald eagle and Dated: June 22, 2007. please contact Ms. Beth Scherer by: (1)
is not likely to affect the Dakota skipper. Timothy J. Meeks, E-mail at
The USFWS responded with a letter of Administrator. BScherer@stratusconsulting.com; (2)
concurrence on May 30, 2006, and an e- [FR Doc. E7–13328 Filed 7–9–07; 8:45 am] phone at (202) 466–3731, ext. 20; (3)
mail on May 31, 2007. Western BILLING CODE 6450–01–P
mail at Stratus Consulting, 1920 L St.,
reviewed additional literature and NW., Suite 420, Washington, DC 20036.
conducted field reconnaissance to Based on the extent of public
supplement this analysis. Western may participation in the first two meetings of
conduct further field studies prior to ENVIRONMENTAL PROTECTION CESLAC, thirty minutes of this third
construction as a component of the AGENCY meeting will be allocated for statements
Applicant’s monitoring study. Western by members of the public. Individuals
will continue to consult informally with [FRL–8337–7] who are interested in making statements
the USFWS. should inform Jack Fitzgerald of their
Coastal Elevations and Sea Level Rise interest by Tuesday, July 24, and
jlentini on PROD1PC65 with NOTICES

Floodplain Statement of Findings Advisory Committee Meeting provide a copy of their statements for
Western prepared a floodplain AGENCY: Environmental Protection the record. Individuals will be
assessment in the EIS according to 10 Agency (EPA). scheduled in the order that their
CFR part 1022. The assessment can be statements of intent to present are
ACTION: Notice of meeting.
found in the Draft EIS along with project received. A minimum of three minutes

VerDate Aug<31>2005 16:17 Jul 09, 2007 Jkt 211001 PO 00000 Frm 00024 Fmt 4703 Sfmt 4703 E:\FR\FM\10JYN1.SGM 10JYN1

Potrebbero piacerti anche