Smoothly does it CSPC enjoys successful start-up of $4.3-billion petrochemicals complex
uilding a large and complex
petrochemicals plant is an enormous undertaking. But the greatest tests often come during the commissioning and start-up process. Passing this vital milestone without any serious problems represents a major achievement. CNOOC and Shell Petrochemicals Company Limited (referred to as CSPC) has done just that with its giant petrochemicals complex in Daya Bay, Guangdong Province, China. Developed in response to the rapidly growing demand for petrochemicals in China, the $4.3-billion project has involved one of the largest ever start-ups. The processing complex covers 2.6 km2 and is expected to yield around 2.3 million tonnes of products per year. CSPC needed a smooth start-up to meet product delivery commitments and to maintain operational safety. Any delay could have meant substantial lost revenues. The project is an integrated chemicals complex with steam and electricity generation, and storage, handling and shipping facilities. As well as an ethylene cracker, which can process feedstocks ranging from light naphtha to heavy condensate, the complex includes units to manufacture styrene monomer, propylene oxide, ethylene oxide, ethylene glycol,
12
impact
propylene glycol, polyols, polypropylene
and high- and low-density polyethylene. The huge size of the complex presented tremendous challenges for the commissioning team. Jean Louis Bilhou, manufacturing director, CSPC, explains, The transition from construction to commissioning is usually a difficult period, but the normal trials were magnified by the scale of the Daya Bay project. A total of 3000 systems needed to be tested and handed over while plants were still under construction and 20 000 workers were on-site. The project managers realised that detailed planning was essential for successful start-up and so commissioned Shell Global Solutions to help them put an operations implementation plan (OIP) in place. An OIP helps project developers and owners to arrive at a documented basis from which the facility can be developed and also helps the organisation to be ready to receive the facility by the end of the project. An OIP is modular. Each module addresses one or more stages of the project development, for example, scouting; front-end engineering and design; final investment decision; engineering, procurement and construction; and commissioning and
start-up. There can be as many OIPs as
there are project phases. In the Daya Bay project, there were three phases. The OIP for each phase contains the same elements, but these become more detailed as the project progresses. In the recruitment element for example, the OIP at the outset of the project identifies the need for a recruitment and training plan. In the next phase, information, such as the numbers of inexperienced and experienced staff required, is added. The final OIP specifies details such as the type of people to be hired, when to hire them, how to assess their skill levels and the training to be given. The principle is the same for each element of the OIP; the low-level definition is established in the first-phase OIP, and a detailed plan is produced by the end of the project. An assurance gate review process, whereby every phase is approved before the next is begun, facilitates the transition between the different phases. This review helps to keep the project aligned and to ensure that all processes are at the same stage of development before embarking on the next phase.
Issue 4, 2006 www.shell.com/globalsolutions
THE CONCEPT OF SYSTEM OWNERSHIP HAS
GREATLY HELPED IN ACHIEVING AN EXCELLENT LEVEL OF QUALITY DURING COMMISSIONING The OIP at Daya Bay has been key in contributing to the success of the start-up. A massive, highly integrated project such as this needs to be planned in great detail from an early stage, says Martin van Uden, lead coordinating process engineer, CSPC. The overall schedule was defined during the feasibility studies, and the key issues and the critical paths were addressed and set out in an integrated commissioning and start-up schedule. The site-wide process integration of the individual engineering, procurement and construction projects has been achieved by using site-integration management tools to plan the commissioning and start-up and to connect all the logical process interfaces. This process has been instrumental in helping to detect and solve schedule disconnects, says van Uden. The OIP encompasses Shell Global Solutions Flawless start-up initiative (FSI). The FSI process is based on early identification of potential flaws in plant and equipment during start-up and putting tools and activities in place to help mitigate the numbers and effects of those flaws. The OIP focuses on organisation, and the FSI focuses on the plant and the
equipment. The OIPFSI process has
been developed from successful practices and lessons learned from previous startups, and is based around several key quality areas. Because most flaws originate in the development phase, the objective of the OIPFSI process is to begin planning for start-up early on. Bilhou says, The OIPFSI process was introduced during the project implementation phase in 2002, and began with a series of workshops for the project teams and the engineering, procurement and construction contractors. An important aspect of the OIPFSI process was having a separate member of the CSPC staff to drive the implementation of agreed activities and to take responsibility for one of the key quality areas, for example, integrity, operability or safety. The concept of system ownership has greatly helped in achieving an excellent level of quality during commissioning, Bilhou concludes. One of the distinctive features of the project was the multicultural make-up of the staff, which included people from all parts of China and from other countries, cultures and technology backgrounds from
Issue 4, 2006 www.shell.com/globalsolutions
in- and outside Shell. Building on the
work of the experienced operating teams, Shell Global Solutions played an important role in introducing health, safety and environmental standards and international best practices for operating systems and management processes. Care was taken to accommodate the different work methods and to develop lines of communication to identify problems and work together to solve them. CSPC successfully started up the plant on time and on budget in January this year. Gerard de Nazelle, technology manager, CSPC, says, This success was due in part to the quality of the design and construction and the plants operational readiness, and in part to the skills and competence of the operational staff, who are extremely motivated. There has been an outstanding atmosphere of cooperation. We received excellent support in all areas from Shell Global Solutions that was based on its experience of previous challenges and successes in other large projects. Contact: Peilin Xu Email: peilin.xu@shell.com
Zadco'S Value Assurance Process ةق يرط لا ةع ب ت م لا ي ف ةكرش او كداز نامض ل ةظ فاحم لا ىل ع ةي مق لا ةب س ت ك م لا By Zaid Hashem Al Habshi Student ID number 110028