Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1.1INTRODUCTION
A stable and reliable electric power supply system is an inevitable pre-requisite
for the technological and economic growth of any nation. Due to this, utilities must strive
and ensure that the customers reliability requirements are met and the regulators
requirements satisfied at the lowest possible cost. It is known fact around the world that
90% of the customer service interruptions are caused due to failure in distribution system.
Therefore, it is worth considering reliability worth assessments as it provides an
opportunity to incorporate the cost or losses incurred by the utilities customer as a result
of power failure and this must be considered in planning and operating practices.
The power system basically consists of generation, transmission and distribution,
regulated either by a single entity or by the number of entities. Hence, the responsibility
of maintaining reliability at different levels falls with different entities and should be the
common goals of the custodians of the various systems at different levels. Also
Regulators require most of investor owned utilities to report their reliability indices and
the regulator trend is moving towards performance based rates where performance is
rewarded and penalized based as quantified by regulator indices.
1.2 PROBLEM FORMULATION
Electricity networks are, and will continue to be a critical part of our energy
infrastructure,and we have the responsibility to ensure that they are developed
consistently and in a mannerthat meets future demands of society and customers. The
process of network developmentshould be directed towards a long term vision aligned
with the expectations of the present andfuture customers. After corporatization and
forming as utility company, BPCL`s mission is to transmit, distribute and supply
adequate electricity in a safe, reliable and efficient manner andthis has to be
accomplished.
The main problem facing by electric power utilities in developing countries today is that
thepower demand is increasingly rapidly where supply growth is constrained by scarce
1
resources,environmental problems and other societal concerns. This has resulted in a need
for moreextensive justifications of the new system facilities, and improvements in
production and useof electricity. System planning and operation based on reliability
cost/worth evaluationapproach provides an opportunity to justify one of the scrutinized
and vulnerable economicsectors in Bhutan. It is with this objective to conduct customer
surveys to find out the outagecost of interruptions.
The analysis of the customer failure statistics reveal that the distribution system
makeshighest individual contribution to the unavailability of supply to the customer. With
the existing system, the customer interruptions is as high as 20-30 hours per year. Withthe
vision of electricity to all within 2017, the interruptions per customer may
furtherdeteriorate due to rapid expansion of the distribution systems. As of now, no
sufficient technical research have been carried out in the distribution network, it may be
due to lack oftechnical expertise in the Utility and most of the interruption has been
caused due to thefailure in the distribution systems.Comparing with other utilities around
the world,reliability standards are very low in distribution system. Hence, it is felt
necessaryto improve the reliability of the system in order to improve the utilitys
performance and tokeep our valued customers satisfied. The reliability improvement
should be based mostprobably upon the consideration of reliability worth and to find the
reliability worth, which is suitable to our context is being formulated.
Intelligent placement of Distributed Generation units, protection devices,
sectionalizers and switches in the distribution feeders has significant impact in reliability
improvement and this will be further assessed along with the capacity outage probability
table(COPT) for the distribution system.
1.3 OBJECTIVE OF THE THESIS
The goal of the power system is to supply electricity to its customers in an
economical and reliable manner. Reliability assessment of distribution system has
became very important in recent years in designing and planning distribution systems that
operate in an economical manner with minimal interruption of load demands. Distributed
generation plays a vital role in emerging power system to serve energy to power systems
utilizing the different types of resources and technologies. Initially Distributed generation
units are in standby mode and starts when some load points are interrupted from the
2
supply to serve backup generation which could reduce the cost and improve reliability of
the system.
But the existence of the DG units in distribution units will effect on the
restoration time of the load points, this impact can be assessed using the concept of
conditional probability.
1.4 ORGANIZATION OF THE THESIS
Chapter 1 Presents introduction to the overall thesis and the overview of the project. In
the project overview a brief introduction of problems associated with reliability of
distribution system.
Chapter 2 Presents an introduction to reliability, reliability assessment, types of
reliability assessments.
Chapter 3 Presents introduction to DG and its types, advantages, disadvantages,
applications, impact of DG on Power system
Chapter 4 Presents an introduction to reliability assessment indices - General and
Customer oriented indices. Presents use of reliability indices, potential problems with
indices, factors affecting reliability performance
Chapter 5 Presents a details ofreal distribution test system and the required test data
Chapter 6 Presents the results, discussion of results, conclusion and future scope of the
project.
1.5 LITERATURE SURVEY
Prior to the 1960s, the reliability of proposed power systems was often estimated
by extrapolating the experience obtained from existing systems and using rule-of-thumb
methods to forecast the reliability of new systems.
During the 1960s considerable work was performed in the field of power system
reliability and some excellent papers were published. The most significant publications
were two company papers by a group of Westinghouse Electric Corporation and Public
Service and Gas Company authors. These papers introduced the concept of a fluctuation
environment to describe the failure rate of transmission system components. The
techniques presented in these papers were approximations which provided results within
3
a few percent of those obtained using more theoretical techniques, such as Markov
processes. The application of Markov Chains in the power system reliability field was
illustrated in Reference. The Markov approach is limited in application because of
computer storage requirements and the rounding errors which occur in thesolution of
large systems. Most previous publications have focused on transmission system
reliability. This research focuses on distribution system reliability. This work extends
previous research, which demonstrated sets used in describing power system reliability
calculations. Further References presented the first application to apply linked lists and
pointer concepts to reliability analysis. It took into account constraints associated with
switching operations, but it was relatively slow due to running numerous power flow
calculations. One aspect investigated h ere is the effect of Distributed Generators (DG) on
power system reliability. Standards for connecting DGs into distribution systems are just
being developed. It deals with issues related to existing DG interconnection practices. An
investigation of eleven utilities and industry interconnection standards was performed to
identify the key requirements for a DG connection. The results of this investigation led to
the development of a unified approach for determininginterconnection requirements.
Some considers many aspects of DGs in distribution systems, including protection,
harmonics, transients, voltage and frequency control. A Power flow calculation based on
the positive sequence model of the distribution circuits was presented.
CHAPTER 2
DISTRIBUTION RELIABILITY ASSESSMENT
2.1 INTRODUCTION
Distribution reliability primarily relates to equipment outages and
customer interruptions. In normal operating conditions, all equipment (except
stand by is energized and all customers are energized. Schedule and unscheduled
events disrupt normal operating conditions and can lead to outages and
interruptions. The unscheduled events are caused either due to human error or due
to equipment failures. The schedule events are meant for periodic maintenance of
the equipment and shall be notified in advance to the customers. Several
indicators are used to evaluate reliability in the transmission and distribution
system. The Regulation can aim to compensate customers for very long
interruptions, keep restoration times under control and create incentives to reduce
the total number and duration of interruptions (disincentives to increase them).
Power quality is an ambiguous term that means many things to many
people. From a consumer perspective, a power quality problem might be defined
as any electric supply condition that causes appliances to malfunction or prevents
their use. From a utility perspective, a power quality problem might be viewed as
noncompliance with various standards such as RMS voltage or harmonics.
Perfect power quality is a perfect sinusoidal with constant frequency and
amplitude. The power Quality is affected when a voltage waveform is distorted
by transients or harmonics, changes its amplitudes or deviates in frequency.
Customer interruptions are power quality concern since it reduces voltage to zero.
Reliability is primarily concerned with customer interruptions and is therefore a
subset of power quality.
Availability is defined as the percentage of time a voltage source is
uninterrupted. The hierarchy of power quality, reliability and availability is shown
in figure 2.1.1. The figure 2.1.1 indicates availability is a subset of reliability and
reliability is a subset of power quality. Power quality deals with any deviation
from a perfect sinusoidal voltage source. Reliability deals with interruptions.
Availability deals with the probability of being in a interrupted state.
5
SYSTEM
SYSTEM ADEQUACY
SYSTEM SECURITY
FIGURE 2.2.1 Sub
division System
Reliability
Figure 2.2.1 represents two basic aspects of a power system: system adequacy and
security.Adequacy relates to the existence of sufficient facilities within the system to
satisfy the consumer load demand. These include the facilities necessary to generate
sufficient energy and the associated transmission and distribution facilities required to
transport the energy to the actual consumer load points. Security relates to the ability of
the system to respond to disturbances arising within that system. Security is therefore
associated with the response of the system to perturbations. Most of the probabilistic
techniques presently available for power-system reliability evaluation are in the domain
of adequacy assessment.
2.2.2 Reliability Assessment
Reliability analysis has a wide range of applications in the engineering
field.Distribution reliability is the ability of the distribution system to perform its
function under stated conditions for a stated period of time without failure. Distribution
reliability is becoming significantly important in the current competitive climate because
the distribution system feeds the customer directly. The distribution system is the face of
the utility to the customer. Its assessment is to determine the system reliability and
customer satisfaction.
Rigorous analytical treatment of distribution reliability requires well defined units
of measurement, referred to as metrics. Many utilities across the world today use
reliability indices to track the performance of the utility or a region or a circuit.
Regulators require most investor owned utilities to report their reliability indices. The
regulatory trend is moving to performance based rates where performance is penalized or
rewarded based as quantified by reliability indices. Most of the utilities also pay bonuses
to managers or others based in part on reliability achievements. Even some of the
commercial and industrial customer asks utilities for their reliability indices when
planning to find a location for their establishments.
all systems are different and stressed by different factors, it can be very hard to make a
legitimate comparison between two systems. This means reliability indices are situational
in nature and will present different baselines depending on the many intrinsic factors
affecting the system.
Reliability statistics can help drive utility improvement programs. Nonetheless,
when pursuing reliability improvement, taking a splintered approach can be damaging.
As such, utility managers should be sure to include all departments in a uniform plan to
understand and act on reliability data. In some cases, a system reliability meeting will
help bring other departments into the process of reinforcing system reliability. Whether a
utility decides to use meetings or have technical specialists focus on the issues, it should
be sure to identify gaps and create a uniform approach to reliability.
2.4 RELIABILITY ASSESSMENT TECHNIQUES
The ultimate goal of reliability analysis is to help answer questions like is the
system reliable enough? which scheme will fail less? and where can the next dollar
be best spent to improve the system?. Reliability in power system can be divided in two
basic aspects System adequacy and System security. Adequacy relates to the capacity of
the system in relation to energy demand and security relates to the dynamic response of
the system to disturbances (such as faults). Since distribution systems are seldom loaded
near their limits, system adequacy is of relatively small concern and reliability emphasis
in on system security.
The two main approaches applied to reliability evaluation of distribution systems are ;
Simulation methods based on drawings from statistical distributions (Monte Carlo).
Analytical methods based on solution of mathematical models
The Monte Carlo techniques are normally very time consuming due to large
number ofdrawings necessary in order to obtain accurate results. The fault contribution
from each component is given by a statistical distribution of failure rates and outage
times. The analytical approach is based on assumptions concerning the statistical
distributions of failure rate and repair times. The most common evaluation techniques
9
using a set of approximate equations are failure mode analysis or minimum cut set
analysis. This method is less time consuming than the simulation methods, but suffers
from problems of representing repair times adequately. The analytical approach to
reliability evaluation of radial distribution system shall be used. The approach is called
RELRAD (Reliability in Radial systems) and is complimentary to the minimum cut set
approach.
2.5 IMPACTS OF MITIGATION TECHNIQUES AND PROTECTION SYSTEM
ON RELIABILITY
A properly co-ordinate protection system is vital to ensure that an electricity
distribution network can operate within preset requirements for safety for individual
items of equipment, staff and public, and the network overall. Suitable and reliable
equipment should be installed on all circuits and electrical equipment and to do this,
protective relays are used to initiate the isolation of faulted sections of a network in order
to maintain supplies elsewhere on the system. This then leads to an improved electricity
service with better continuity and quality of supply. This can reduce the permanent
outages and its durations. Nowadays, with the increase of sensitive load with the end
users, to improve the power quality and to mitigate the momentary interruptions is also
equally important. The first step is to find out the root cause of the problem and apply
mitigation solutions to a circuit that affects the largest number of customers.
A better over-current protection scheme can reduce number of customers affected
by temporary and permanent faults. The reliability of the system depends on the
mitigation techniques being used by the utility namely, electric and non-electric
mitigation techniques. So, historical data can be used to quantify improvements and
predict the best locations for sectionalizing devices for reliability improvements. Adding
numbers of recloser at optimal locations can reduce SAIFI, SAIDI but it should be
economically viable. The location and installation of number of Auto-recloser, Switches,
Load Break Swtiches and Sectionalizers either manual or automated helps to reduce fault
rate, repair time and sectioning time which directly reduces the impacts on the system
when fault occurs. The Mitigation Techniques applied shall depend on the need of utility
whether it wants to reduce fault rate, repair time or both or outage duration.
10
11
CHAPTER 3
DISTRIBUTED GENERATION
3.1 INTRODUCTION
DG is not a new concept. A number of utility consumers have been using DG for
decades. Over the last 10 years, the DG market has been somewhat turbulent. In the late
1990s, new regulations/subsidies, such as net metering and renewable portfolio
requirements, and the development of new DG technologies, have sparked broader
interests in distributed generation. DG is power generation built near consumers. DG
sources include small-scale, environmentally-friendly technologies (e.g., photovoltaic and
wind) installed on and designed primarily to serve a single end users site. But when
reliability and power quality issues are critical, DG most often includes more traditional
fossil fuel fired reciprocating engines or gas turbines.
The limited generation in the power sector has continually been exacerbated by
load growth, power demand, limitations in the ability to site new transmission lines,
limitations in the ability to construct large scale generation due to increased
environmental regulation, and lack of technology development to meet the new
requirements. Manpower is required to achieve the development of a sustainable,
secured, and economically-viable society and infrastructure. The growth in developed
and developing countries has created an energy divide in terms of wealth. The major
disparities of energy consumption per capita are reflected in developing countries. The
universal electrification challenge to meet the worlds population growth in order to attain
its current per capita electricity consumption will require massive increases in electricity
generation capacities.
Electric energy is produced and delivered practically on real time and there is no
convenient method to readily store it. This makes necessary to maintain a continuous and
almost instantaneous balance between production and consumption of electricity in
power systems. A way to ensure energy balance is by keeping some margin of generation
above the expected demand load, so the system can deal with unexpected mismatches
between supply and demand leading to power shortages. Generation margins are attained
12
by providing stand-by plant capacity and they represent reservesof generation capacity
that can be rapidly utilized in case of a supply shortage.
Utilities have traditionally determined reserve requirements using working rules
and more recently probabilistic techniques. They estimate a reasonable amount of
capacity to be reserved and kept available, so that credible contingencies will not cause a
failure of supply. Nevertheless, even when analytical methods are used, a final decision
regarding reserve levels depends on the operators judgment of what is the acceptable risk
of system failure. In fact, although it is not always made explicit, this decision is a tradeoff between the additional reliability offered to customers and the cost of keeping the
reserves available.
In some cases, properly planned and operated DG can provide consumers, as well
as society, with a wide variety of benefits. These include economic savings because of
government subsidies and improved environmental performance. Many utilities have
installed DG on their systems and support federal funding of research to develop new
technologies.
The interconnection of DG with the electric grid continues to pose genuine safety
and reliability risks for the utility. DG could reduce the demand for traditional utility
services. DG also poses an economic risk to incumbent utilities and their consumers
unless appropriate rate structures or cost recovery mechanisms are put into place.
Though a small scale power plant, DG is environmentally friendly due to its
friendly technologies. These friendly technologies include: photovoltaics (PV), fuel
cells, small wind turbines, or more conventional technologies such as: micro turbines and
reciprocating engines that are fueled by renewable fuels, for instance, landfill gas. DG
encompasses generation built near to a consumers load despite size or energy source.
The latter definition could include diesel-fired generators with significant emissions.
Other definitions of DG include some or all of the following:
Any qualifying facilities under the Public Utility Regulatory Policies Act of 1978
(PURPA);
Commercial emergency and standby diesel generators installed, (i.e., hospitals and
hotels);
13
Demand side management (DSM), energy efficiency, and other tools for reducing energy
usage on the consumers side of the meter. The alternative to this definition would be to
abandon the term distributed generation completely and use instead distributed
resources (DR) or distributed energy resources (DER).
14
15
18
The objective of this thesis, is to investigate the technical impact that the
integration of DG have on the protection coordination of distributed power systems. A
method to asses this impact, is based on investigate the behaviour of an electric system,
with and without the presence of DG. The difference between the results obtained in
these two operating conditions, gives important information for both, companies in the
electric sector and customers. In that sense, a general view of the main problems
encountered in the integration of DG to the distributed network is presented.
3.3.1 Impact of DG on Voltage Regulation
Radial distribution systems regulate the voltage by the aid of load tap changing
transformers (LTC) at substations, additionally by line regulators on distribution feeders
and shunt capacitors on feeders or along the line. Voltage regulation is based on one way
power flow where regulators are equipped with line drop compensation.
The connection of DG may result in changes in voltage profile along a feeder by
changing the direction and magnitude of real and reactive power flows. Nevertheless,
DG impact on voltage regulation can be positive or negative depending on distribution
system and distributed generator characteristics as well as DG location.
20
21
Fig. 3.3.3 Comparison between pure sinusoidal wave and distorted wave
Harmonics are always present in power systems to some extent. They can be
caused by for instance: non-linearity in transformer exciting impedance or loads such as
fluorescent lights, AC to DC conversion equipment, variable-speed drives, switch mode
power equipment, arc furnaces, and other equipment.
DG can be a source of harmonics to the network. Harmonics produced can be
either from the generation unit itself (synchronous generator) or from the power
electronics equipment such as inverters. In the case of inverters, their contribution to the
harmonics currents is in part due to the SCR (Silicon Controlled-Rectifier) type power
inverters that produce high levels of harmonic currents. Nowadays, inverters are designed
with IGBT (Insulated Gate Bipolar Transistor) technology that use pulse width
modulation to generate the injected pure sinusoidal wave. This new technology
produces a cleaner output with fewer harmonic that should satisfy the IEEE 1547-2003
standards.
Rotating generators are another source of harmonics, that depends on the design
of the generators winding (pitch of the coils), core non-linearity's, grounding and other
factors that may result in significant harmonics propagation.
When comparing different synchronous generator pitches the best configuration
encountered is with a winding pitch of 2/3 as they are the least third harmonic producers.
Third harmonic is additive in the neutral and is often the most prevalent. On the other
hand, 2/3 winding pitch generators have lower impedance and may cause more harmonic
22
currents to flow from other sources connected in parallel with it. Thus, grounding
arrangement of the generator and step-up transformer will have main impact on limiting
the feeder penetration of harmonics. Grounding schemes can be chosen to remove or
decrease third harmonic injection to the utility system. This would tend to confine it to
the DG site only.
Normally, comparing harmonic contribution from DG with the other impacts
that DG may have on the power system, it is concluded that they are not as much of a
problem. However, in some instants problems may arise and levels can exceed the IEEE519 standard (these levels are shown in table 2.1). These problems are usually caused by
resonance with capacitor banks, or problems with equipment that are sensitive to
harmonics. In the worst case, equipment at the DG may need to be disconnected as a
consequence of the extra heating caused by the harmonics.
Table 3.3.3Harmonic current injection requirements for distributed generators per IEEE
519-1992.
Harmonic order
< 11th
< 11th to < 17th
< 17th to 23rd
1.5%
0.6%
35th or greater
0.3%
5%
24
G1
SUBSTATION
G2
FEEDER
BREAKER
G3
FUSE
LATERAL
FAULT
Fig. 3.3.4Fault contributions due to DG units 1, 2 and 3 are embedded in the system.
Fuse-breaker coordination may be no longer achieved
If the DG is located between the utility substation and the fault, a decrease in
fault current from the utility substation may be observed. This decrease needs to be
investigated for minimum tripping or coordination problems. On the other hand, if the
DG source (or combined DG sources) is strong compared to the utility substation source,
it may have a significant impact on the fault current coming from the utility substation.
This may cause fail to trip, sequential tripping, or coordination problems.
The nature of the DG also affects the short circuit levels. The highest
contributing DG to faults is the synchronous generator. During the first few cycles its
contribution is equal to the induction generator and self excited synchronous generator,
while after the first few cycles the synchronous generator is the most fault current
contributing DG type. The DG type that contributes the least amount of fault current is
the inverter interfaced DG type, in some inverter types the fault contribution lasts for
less than one cycle. Even though a few cycles are a short time, it may be long enough to
impact fuse breaker coordination and breaker duties in some cases.
25
The connection of DG to the power system could improve the voltage profile,
power quality and support voltage stability. Therefore, the system can withstand
higher loading situations.
The installation of DG takes less time and payback period. Many countries are
subsidizing the development of renewable energy projects through a portfolio
obligation and green power certificates. This incentives investment in small
generation plants.
Some DG technologies have low pollution and good overall efficiencies like
combined heat and power (CHP) and micro-turbines. Besides, renewable energy
based DG like photovoltaic and wind turbines contribute to the reduction of
greenhouse gases.
2) Drawbacks
Many DG are connected to the grid via power converters, which injects
harmonics into the system.
Depending on the network configuration, the penetration level and the nature of
the DG technology, the power injection of DG may increase the power losses in
the distribution system.
CHAPTER 4
28
MEASURING RELIABILITY
Along with the variety of definitions of reliability come a variety of ways to
measure it. A metric for reliability is required for assessment of past performance,
consideration of reliability in design, and setting of reliability goals. Many indices have
been defined as measures of reliability. They measure different aspects of reliability or
combinations of different aspects. Only a small number of these are common across
several utilities, and the ones that are commonly used are not always defined in the exact
same manner.
Reliability measures dealing with interruptions address three factors: frequency,
duration, and extent or severity. The extent is the number of customers or load affected,
which is determined by the layout of the distribution system Combining the two key
factors of frequency and duration into a single appropriate measure may not be possible,
so any one index may not be very valuable alone. When assessing reliability, all three
factors should be considered. Each reliability index may be important for a different
purpose. Different utilities use different sets of indices.
29
The Utilities commonly use the following two reliability indices for frequency
and duration to quantify the performance of their systems.
System Average Interruption Frequency Index (SAIFI):
System Average Interruption Frequency Index (SAIFI) is designed to give
information about the average frequency of sustained interruptions per customer over a
predefined area.
SAIFI =
Where is the failure rate and Ni is the number of customers at load points i.
System Average Interruption Duration Index (SAIDI):
System Average Interruption Duration Index, (SAIDI) is commonly referred to as
customer minutes of interruption or customer hours, and is designed to provide
information about the average time that the customers are interrupted
SAIDI =
Where Ui is the annual outage time and Niis the number of customers at load
Point i.
Customer average interruption duration index (CAIDI):
Customer Average Interruption Duration Index (CAIDI) is the average time
needed to restore service to the average customer per sustained interruption
CAIDI=
i Ni
Where is the failure rate, Ui is the annual outage time, and Ni is the number of
customers at load point i.
30
CAIDI=
Li N i
Total energy not supplied
=
Total no of customers served
Ni
31
32
are mature in their reliability improvement process. Once first round of investment is
made, traditional reliability measure may present complications.
The following describes the potential problem with the standard indices.
SAIDI and SAIFI When making reliability investments, reductions in SAIDI and
SAIFI are proportional to the number of affected customers. This means projects that
affect many customers are preferred to those that affect few customers. However, feeders
with many customers typically have better than average reliability, and feeders with few
customers have worse than average reliability. Therefore, reliability investment based on
SAIFI and SAIDI can drive investments towards densely populated areas where
reliability is already satisfactory.
CAIDI Although popular with many utilities and regulators, CAIDI is
problematic as measure of reliability. This is because, any view CAIDI as a measure of
operation efficiency; when utility responds more quickly after a fault, CAIDI will go
down. In fact, CAIDI is mathematically equal to SAIDI divided by SAIFI. That is
reliability could be improving in both frequency and duration, but CAIDI could be
increasing. Because of the above problem, the use of CAIDI is decreasing in todays
world.
4.4 FACTORS AFFECTING RELIABILITY PERFORMANCE
Reliability performance varies dramatically from one system to another and this is
not necessarily an indication that one system has poor performance. Many factors
influence the expected reliability at a particular location or for an entire system.
Reliability indices that reflect reliability performance differ with data definitions
and data classifications. Most Utilities define separate indices for planned and unplanned
events. The interruption caused due to major event like storm, forest fire or a forced
majeure may or may not be considered in reliability performance. Transmission and
Distribution events are considered separately for reliability performance evaluation due to
data classes or nature of events.
The service territory of the utility determines the nature of the events that could be
expected which effect reliability performance. Geography of the service territory such as
thick forest, mountainous terrain, etc is likely to cause reliability issues. Weather is an
important factor that can seriously affect reliability levels. The effects of vegetation such
33
as tree falls, branch intrusion and animal activity from birds, squirrels and pests causing
ground faults affect reliability levels. Maintenance practices such as tree trimming
programs and installation of animal guards could help achieve higher levels of reliability.
Hence, it is obvious to expect a different reliability levels at various locations.
34
CHAPTER 5
DETAILS OF TEST SYSTEM
Introduction
Reliability evaluation techniques have been widely used in many industries such
as power, nuclear, airspace etc. Many techniques have been developed for different
applications. The basic function of an electric power system is to supply customers with
reasonably economical and reliable electricity.
To build an absolutely reliable power system is neither practically realizable nor
economically justiable. The reliability of a power system can only be improved through
the increased investment in system equipment during either the planning phase or
operating phase. However, over-investment can lead to excessive operating costs, which
must be reected in the tariff structure.
35
Table 5.1 shows the data associated with sections and load points. Average failure rate of
sections is assumed to be 1.49(failure/yr.km).
Section
Number
Length(Km)
0.42
Loadpoint
number at end
node
1
Average Load at
end node(KVA)
90
No. of
Customer at
end node
137
0.25
0.294
100.1
126
0.411
18.7
20
0.190
0.190
90
284
0.340
269.5
210
0.110
0.124
50.6
57
10
0.030
87.6
135
11
0.124
90
172
12
0.200
85
170
13
0.140
10
200
190
14
0.104
11
51.04
56
15
0.167
12
26.4
38
16
17
0.189
0.033
16
45.1
49
18
0.138
13
16.5
10
19
0.481
20
0.200
14
374
280
21
0.290
15
90
204
In this network there are five locations for possible installation of DG units that is shown
in Figure 5.1.1 (these points are defined by the utility considering various factors)
38
The purpose is to determine the best location and optimum number of DG units in order
to maintain the predefined reliability level. The capacity of each DG unit is assumed to be
650 KVA.
CHAPTER 6
EXPERIMENTAL RESULTS
39
INTRODUCTION:
This chapter presents final results tested on RBTS test system. Average values of
load point and system indices are calculated and presented. Even the probability
distributions of various reliability indices are presented.
6.1 RESULTS
A computer program has been developed to perform necessary computations. This
program first computes failure rate( ),restoration time(r), and annual outage time(u) for
each load point then calculate system indices such as SAIFI, SAIDI, CAIDI and AENS as
described before. Three different case studies are considered. For each case it is assumed
that 0, 1, 2, 3, or 4 DG units can be established in each location and then system indices
are calculated.
With Location 1 and availability 0.95
No. of DGs
SAIFI
SAIDI
CAIDI
AENS
6.5932
23.0272
3.6599
19.79
6.5932
19.875
3.457
17.943
6.5932
19.763
3.013
15.993
6.5932
17.89
2.763
13.987
6.5932
17.54
2.694
13.854
SAIFI
SAIDI
CAIDI
AENS
6.5932
23.95
3.412
18.12
6.5932
20.02
3.027
15.95
6.5932
18.54
2.843
13.98
6.5932
17.32
13.98
13.82
No. of DGs
SAIFI
SAIDI
CAIDI
AENS
6.5932
23.0272
3.6599
19.79
6.5932
23.002
3.423
18.12
6.5932
19.724
2.997
15.987
6.5932
2.997
2.639
13.83
6.5932
15.987
2.598
13.72
CONCLUSION
41
FUTURE SCOPE
42
Reliability assessment has become important for utility planners in recent years.
Improved service reliability might be motivated by government regulation or by market
competition, but providing superior service at an attractive price is in the interest of both
utilities and customers.
At present the electric power utilities are not much reliable leading to the increase
in the cost of interruptions and power outages effecting economically on the utility and its
customers.
In the near future,these deregulated power utilities must be restructured and
operated as distinct generation, transmission and distribution. This can be achieved by
combining conventional based generation units with the distributed generation units. The
responsibility of maintaining the reliability of the overall power system must and should
be shared by all the involving companies instead of by a single electric utility which leads
to the decrease in the power outages and interruption cost and increases the reliability of
the system.
REFERENCES
43
2. A. Chowdhury and D. O. Koval, Generation reliability impacts of Industryowned distributed generation sources, in IndustryApplications Conference, vol.
2, Oct. 2003, pp. 13211327.
3. Ackermann,T.; Andersson,G.; Soder, L.; "Distributed Generation: A Definition,
Electric Power Systems Research, Vol 57, 2001, pp195 204.
4. P. A. Daly and J. Morrison, Understanding the potential benefits of distributed
Generation on power delivery systems, in Proc.Rural Electric Power Conf.,
2001, pp. A2/1A2/13.
5. R. Billinton, R, N. Allan, "Reliability Evaluation of Power Systems",2nd edition,
Plenum Press, New York, 1996.
6. R. Billinton and R. Allan, Reliability Evaluation of Engineering Systems:
Concepts and Techniques: Plenum Press, 1994.
7. IEEE Standard 1366-1998, IEEE trial-use guide for electric powerdistribution
reliability Index, 1998.
APPENDIX
#include<stdio.h>
#include<conio.h>
void main()
{
44
Float
AFR,AFLT,ART,AL[100],UL[100],RL,NC[100],ALD[100],LS[100],A,w,x,y,z,T
NCS,TNCI,SCID,ENS,AENS,SAIDI,SAIFI,CAIDI,ASAI,ASUI;
intn,i;
printf("\n ENTER THE NO. OF LOAD POINTS");
scanf("%d",&n);
printf("\nENTER THE AVERAGE FAILURE RATE OF THE SECTIONS");
scanf("%f",&AFR);
printf("\nENTER THE AVERAGE FAULT LOCATION TIME");
scanf("%f",&AFLT);
printf("\nENTER THE AVERAGE REPAIR TIME");
scanf("%f",&ART);
printf("\nENTER THE AVAILABILITY OF DG UNITS");
scanf("%f",&A);
for(i=0;i<n;i++)
{
printf("\n enter the no of customers,avg load demand,Length(km) of the section of
load point %d",i);
scanf("%f%f%f", &NC[i],&ALD[i],&LS[i]);
}
RL=AFLT+ART;
x=0;
for(i=0;i<n;i++)
{
AL[i] = AFR*LS[i];
UL[i] = x+AL[i]*RL;
x = AL[i]*RL
}
printf("\n load point reliability incides for the given system");
printf("\nload pt.\tAvg. Failure rate\tAvg. Outage time\tAnnualAvg.outage time");
for(i=0;i<n;i++)
{
printf("\n %d\t %0.2f\t %0.2f\t %0.2f",i,AL[i],RL[i],UL[i]);
}
w=0;x=0;y=0;z=0;
for(i=0;i<n;i++)
{
TNCS=x+NC[i];
x=TNCS;
TNCI=y+AL[i]*NC[i];
y=TNCI;
SCID=z+UL[i]*NC[i];
z=SCID;
ENS=w+ALD[i]*UL[i];
45
w=ENS;
}
SAIFI=(TNCI/((1-A)*TNCS));
SAIDI=(SCID/((1-A)*TNCS));
CAIDI=SAIDI/SAIFI;
ASAI=(8760-SAIDI)/8760;
ASUI=1-ASAI;
AENS=(ENS/((1-A)*TNCS));
printf("\n System indices are");
printf("\n SAIFI=%0.6f\n SAIDI=%0.6f\n CAIDI=%0.6f\n ASAI=%0.6f\n
ASUI=%0.6f\n ENS=%0.6f\n AENS=
%0.6f",SAIFI,SAIDI,CAIDI,ASAI,ASUI,ENS,AENS);
}
46