Objectives
l
Page1
Contents
1. Preparations before Commissioning
2. Single Station Commissioning
3. Network Commissioning
Page2
Preparations
l
Page3
Preparations (Cont.)
l
Prerequisites
p
Page4
Contents
1. Preparations before Commissioning
2. Single Station Commissioning
3. Network Commissioning
Page5
Sub-item
Checking hardware
Testing power-on of the cabinet
Single station
commissioning
Page6
Sub-item
Testing on/off of all electrical interfaces
Testing the fiber jumper connection
Testing TPS
Single station
Page7
Checking cabinet
p
Page8
Checking sub-rack
p
Page9
Checking cables
p
The power cables and grounding cables outside the cabinet are
arranged separately from the signal cables
Page10
Page11
AUX
EOW
STAT
STAT
C
LK
I1
C
LK
I3
C
LK
O
1
C
LK
O
3
STAT
CLKO1
CLK4
CLKI1
CLK2
CLKO2
EXT
REV
CLKI2
PHONE
F&f
CLK1
CLK2
REV
ETH
F&f
COM
LAMP1
F1
EXT
LAMP2
OAM
ALMO1
S1
F1
PHONE
LAMP1
V1
LAMP2
V2
ALMO1
OAM
ALMO2
V1
V2
S2
ALMO2
S3
ALMI1
S4
ALMI2
COM
ALMI3
S1
ALMI1
S2
ALMI2
S3
ALMI3
S4
ALMI4
ETH
ALMI4
AUX
EOW
Page12
Power module
J9
Page13
Page14
Equipment
Jumpers on
Description
GSCC
OptiX OSN
J16, J17 on
3500
N1GSCC
OptiX OSN
3500/7500
N3GSCC
OptiX OSN
7500
N2GSCC
-48V: capped
(default)
-60V: remove the
caps from jumpers
Page15
3
2
O UT P UT
3 4
ON
3
2
O UT P UT
ON
R T N 1 (+) R T N 2 (+) N EG 1 (-) N EG 2(-)
O FF
IN P U T
3 2A
32A
20A
O FF
32A
2 0A
32A
2 0A
20A
1. Grounding stud
2. PGND
3. RTN1 (+)
4. RTN2 (+)
5. NEG1 (-)
6. NEG2 (-)
Page16
Action
OFF
Subrack
power switches ON
Page17
OSN 1500A
OSN 1500B
OSN 2500
OSN 3500
OSN 7500
Subrack type
Fuse capacity
Common
200
10
Enhanced
313
15
Common
280
10
Enhanced
400
15
Common
400
15
Enhanced
643
25
Common
600
20
Enhanced
1088
32
Common
1000
32
Page18
Testing method
Connect OSN equipment to the power equipment
Ensure that the positive and negative poles are not connected reversely
Measure the voltage of the power supply equipment at the top of the
cabinet
n
Page19
Testing method
p
Check the connection between sub-rack power cables and PIU boards
Turn on the left switches, and every sub-rack can be powered on normally
Turn off the left switches and turn on the right switches, and every
sub-rack can be powered on normally
Page20
The green indicator is on, and you can feel wind blowing normally
Status
Description
On
Off
On
Off
On
Off
On
Off
Page21
Status
Description
On, green
STAT (red or
On, red
green)
Flash, red
Off
On, green
On, red
Off
No power supply.
PROG (red
or green)
Page22
Testing method
p
Page23
ACT1
Status
Description
On
The link between the first GE port and the opposite equipment is established.
Off
Flashing
(orange)
Off
The link between the first GE port and the opposite equipment is not
established.
There are data being exchanged between the first GE port and the opposite
equipment.
There is no data being exchanged between the first GE port and the opposite
equipment.
Page24
Setting NE ID
Page25
Service source
Service sink
VC12
2-PQ1-12
7-SL16-1-1-12
VC12
7-SL16-1-1-12
2-PQ1-12
VC12
VC12
2-PQ1-3132
7-SL16-1-16-12
VC12
7-SL16-1-16-12
2-PQ1-3132
VC12
2-PQ1-3334
12-SL16-1-1-12
VC12
12-SL16-1-1-12
2-PQ1-3334
VC12
VC12
2-PQ1-63
12-SL16-1-16-1
VC12
12-SL16-1-16-1
2-PQ1-63
Page26
Testing method
p
Page27
Testing method
p
Page28
Testing method
p
Check the cable and connection for the alarm output cable.
Page29
Testing method
p
Page30
Testing method
p
Page31
Description
Mandatory
Mandatory
Receiver sensitivity
Optional
Optional
Optional
Optional
Optional
Optional
Optional
Fiber
jumper
Optical
interface
board
Tested
optical
interface
Optical
interface
board
Fiber
jumper
-
ODF
ODF
OUT
Fiber
jumper
Tested
optical
interface
OUT
IN
Optical
power meter
IN
Local station
Adjacent
Page32
station
Action
Configure TPS protection. Suppose that the PQ1 board in slot 1 protects the PQ1 board in slots 2 (with low priority) and 3
(with high priority).
Check the status of TPS protection and the ACT indicators on PQ1 boards.
Connect BER tester to E1 port of the D75S board. The BER tester gives no alarm.
Remove the PQ1 in slot 2. Services are interrupted transiently and resumed immediately.
Page33
Action
Connect the BER tester to protected service interface. The BER tester will be normal.
Insert the working board in slot 3 back to test restoration. Check TPS protection switching status and ACT indicator.
10
11
12
13
After the WTR time, the PQ1 board in slot 3 should work. And the PQ1 board in slot 1 should also work to protect the PQ1
in slot 2.
Insert the working board in slot 2 back to test restoration. Check TPS protection switching status and ACT indicator.
Verify that the switching state of the protected board is WTR. After the WTR time, the PQ1 board in slot 2 should restore
to work.
Page34
Testing method
Configure boards and services
p Self-loop the optical port on DDF, and connect BER tester
p Switch test
p
n
n
n
ACT indicator
1+1 XCS protection status
VC4 services and clock should be good,VC12/VC3 services are
momentarily interrupted.
Page35
Restore test
n
n
n
n
Notes
Page36
Test method
p
Switch test
n
Page37
Restore test
n
n
n
n
n
n
Notes
Page38
Page39
Testing method
p
RX TX
1
2
3
RX TX
.
..
.
60
61
62
63
Page40
Ending NE Commissioning
l
Final Work to Do
p
What else?
n
Page41
Contents
1. Preparations before Commissioning
2. Single Station Commissioning
3. Network Commissioning
Page42
Network Commissioning
Item
Sub-item
Checking actual received optical power and network-wide fiber connection
Configuration network
Testing ECC
Testing service channel availability
Network
commissioning
Page43
Check if the received optical power has been tested in the single
station commissioning.
p
Page44
Page45
Checking Connection of an NM
Computer to the Equipment
l
Direct connection
Page46
Configuration Network
Step
Action
Creating boards
Creating fibers
Configuring clock
10
11
13
14
Page47
Testing ECC
l
NE login test
p
The single-route ECC route is available, if cut off the other fibers.
Pull out SCC board in ADM NE, and other NEs can be logged in.
Page48
Normal testing
n
Interrupted testing
n
Loopback and perform bit error test for 10 minutes, and no bit errors or alarms
Release the loopback, and AIS alarm generates.
NE4
NE1
STM-16
non- protection
chain
NE2
STM-64 two-fiber
bidirectional MSP Ring
loopback
Page49
NE3
EPL/EPLAN
Computer A
EPL/EVPL/EPLAN/EVPLAN
NE1
Computer B
NE4
NE2
STM-64 two-fiber
bidirectional MSP
ring
NE3
STM-16 two-fiber
bidirectional nonprotection chain
VCTRUNK
Page50
Connect the tester, loopback the service port of the other end.
Page51
Test restoration
Page52
SNCP
p
Delay time = 0
Page53
Testing Orderwire
p
Page54
Monitor alarms and performance events of 15m and 24h through NMS
No abnormal alarms
No error
SDH analyzer
n
n
NE
Grounding
NE
SDH analyzer
NE
NE
Loop-back
PDH Port
Page55
NM function verification
Page56
Questions
p
Preparations before
Commissioning
Sub-item
Grasp basic skill
Understand engineering information
Checking Resistance Between Power Cable Posts
Delivering Commissioning Data
Testing optical/electrical interface indices
Single station
commissioning
Network commissioning
Page57
Thank you