Rev 7
SAIC NUMBER
PROJECT TITLE
WBS / BI / JO NUMBER
31-Mar-13
DATE APPROVED
SAIC-A-2015
EQUIPMENT ID NUMBER(S)
EQUIPMENT DESCRIPTION
REV. NO.
QR NUMBER
30-Apr-13
PIPE-
CONTRACTOR / SUBCONTRACTOR
EQPT CODE
SYSTEM ID.
PLANT NO.
MH's SPENT
TRAVEL TIME
ITEM
No.
ACCEPTANCE CRITERIA
REFERENCE
A1
SAES-A-004,
Para. 9.1.2
A2
All joints including welded shall be left exposed for visual leak detection
during the strength test. External coating & priming of such joints is not
allowed unless approved by the Manager of Inspection Department and the
proponent Organization representative. The pipe itself can be externally
primed and coated to a final coat.
See
Attachment 3 (Walkdown Inspection Technique).
SAES-L-150,
Para. 7.3
A3
The test pressure shall be maintained for a sufficient time, but shall not be
less than 30* minutes, to determine that there are no leaks.
*Large systems (Plant Piping) can take longer to complete.
PASS
FAIL
N/A
RE-INSP DATE
SAES-L-150,
Para. 7.2
A4
SAES-L-150,
Exceptions to Item A3 above, Plant Piping Pressure Testing & Visual
Section 7
Inspection Requirements. See Attachment 4.
Visual
Inspection & Testing meets SAES-L-150 reqmts.
Plant Piping
A5
SAES-L-150,
Exceptions to Item A3 above, Pipeline Pressure Testing & Visual Inspection
Section 8
Requirements. See Attachment 4.
Visual Inspection
& Testing meets SAES-L-150 reqmts.
Pipelines
A6
SAES- L-108,
Para. 4.7.5
A7
Test Records for each test are entered on a Pressure Test Report Form
2642-ENG. Test duration & Acceptance is shown in Comment section of
report. (Tape has test pressure & test start/finish time)
Remove tape from gage & press into Test
Report. Attachment 2.
SAES-A-004,
Para. 9.3
REMARKS:
ATTACHMENTS: Attachment 1 - Pressure Testing Details --------- Attachment 2 - Efficient Practice For Acceptance of Pressure Tests
Attachment 3 - Walkdown Inspection Techniques ----------- Attachment 4 - SAES-L-150 Pressure Testing Application & Insp
REFERENCE DOCUMENTS: 1. SAES-A-004, General Requirements for Pressure Testing, (30-Jan-2011)
2. SAES-L-150, Pressure Testing of Plant Piping and Pipelines, (25-April-2010)
3. SAES-L-108, Selection of Valves, (11-Oct-2010)
Contractor / Third-Party
Construction Representative*
Saudi Aramco
PMT Representative
QC Inspector
QC Record Reviewed
Work Verified
T&I Witnessed
QC Record Reviewed
Work Verified
PID Representative
Performed Inspection
T&I Witnessed
Name, Initials and Date:
Page 1 of 8
QC Supervisor
Name, Organization,
Initials and Date:
T&I Witnessed
QC Record Reviewed
Y = YES
Page 2 of 8
Work Verified
N = NO F = FAILED
Rev 7
SAIC NUMBER
SAIC-A-2015
31-Mar-13
DATE APPROVED
QR NUMBER
30-Apr-13
PIPE-
Page 3 of 8
Rev 7
SAIC NUMBER
SAIC-A-2015
31-Mar-13
DATE APPROVED
30-Apr-13
QR NUMBER
PIPE-
Page 4 of 8
Rev 7
SAIC NUMBER
SAIC-A-2015
31-Mar-13
DATE APPROVED
QR NUMBER
30-Apr-13
PIPE-
Rev 7
SAIC NUMBER
SAIC-A-2015
Page 6 of 8
31-Mar-13
DATE APPROVED
30-Apr-13
QR NUMBER
PIPE-
Rev 7
SAIC NUMBER
31-Mar-13
DATE APPROVED
SAIC-A-2015
QR NUMBER
30-Apr-13
PIPE-
7.5.5 Service test is acceptable for the following per L-150, Para. 7.5.5 (Threaded Joints)
a) Plant utility piping in air & inert gas services with designed pressure & equal to less than 035 kPa (ga) (150 psig).
b) Low pressure steam piping designed for 60 psig or less.
INSPECTION SHALL REFER TO SAIC-L-2015 CHECKLIST FOR THREADED JOINTS AS APPLICABLE.
7.6 For revalidation purposes of existing plant piping, test pressure shall be minimum req'd by ASME B31.3.
Actual piping wall thickness and flange rating shall be taken into consideration when calculating the test pressure.
Rev 7
SAIC NUMBER
SAIC-A-2015
Page 8 of 8
31-Mar-13
DATE APPROVED
30-Apr-13
QR NUMBER
PIPE-