Sei sulla pagina 1di 4

GENERAL NOTES

GENERAL
1. Unless otherwise noted on this drawing, all materials and workmanship
shall be of quality compatible with the requirements of the specification.
2. General notes and tpcal detail shall apply to all drawing unless otherwise
shown or noted.
3. All dimension are in metric system, the basic unti of length is the
milimeter.
4. Unless otherwise noted, details shown on any drawings are to be
considered typical for all similiar condition. Details not shown on the
drawings shall be clarified to meet the specific condition by the shop
drawings and shall be reviewed by the engineer.
5. All dimension and condition shall be verified by the contractor and any
discrepancies shall be brought to the attention of the arcitect or the
engineer before proceeding with the portions of work involved.
6. The contractor shall verified and coordinate all opening in floord, beams,
wall and roof, and shall check any concrete embeddings, such as conduit
pipe, sleeve pipe and outlet, etc., with arcitectural, mecehanical, and
electrical drawings.
7. The condition shall provide all measures and precautions necessary to
prevent settlement or any damage of adjacent existing or new
construction.
8. The constraction load on the floor should not exceed the specific design
live load during any stage of construction.
9. The contractor shall provide periodic elevation readings at specified
locations. Readings shall be taken and recorded at the completion of each
floor level by licensed surveyor wich approved by engineer. Recording
shall be submitted to the engineer of the completion of each floor level
FOUNDATION
1. Foundation is design based on soil test report prepared by PT. SOLEFOUND
SAKTI
2. The following fondation shall be used :
- Type of foundation
: bored pile
- Pile size
: 800
- Effective length
: 28 M
3. Excavation system
: Open cut and braced cut ( soldier pile )
4. Allowable capacity of pile :
- Compression
: 800mm : 350 ton
- Tension
: 800mm : 150 ton
5. Loading test for pile :
- Compression Test
: 800mm : 2 NOS 2.5 x 350
= 875 ton
2 NOS 2 x 350
-

Lateral Test

= 700 ton

: 800mm : 2 NOS 2 x 10= 20 ton

6. Actual pile legnth could vary from the design length based on the actual
soil condition at the site subject to the engineer approval.

7. Actual location of each pile shall be measured and reported to the


engineer immediately.
REINFORCEMENT
1. All reinforcement shall be deformed bars or plains bars and qualified
products manufactured confirming to JIS G3112 or approved equal. The
following grade of reinforcement shall be used.
GRADE

MIN. FY

BJTD U-40

400 Mpa

BAR
ROATATION
D10 THRU D32

BJTP U-24

240 MPa

6 THRU 16

POROTION

REMARKS

MAIN BARS,
HOOPS,
STIRRUPS,
SLAB BARS
SPIRAL OF
BORED PILE,
HOOK & JOINT
OF PC PANEL

DEFORMED
BARS

PLAIN BARS

2. Welded steel, wire fabricating shall conform to JIS G3551.


3. Unless otherwise shown on the drawings, lapping spilce shall be used
other mechanical and gas pressure splices may be applicable subject to
the approval of the engineer.
4. Mill certificate of reinforcemenr shall submited and reiviewed by the
engineer.
5. Tensile tests and bending tests of reinforcement shall be executed and
submitted in accordance with the approved method by the engineer or in
accordance with specification requirment.
6. All reinforcement works shall be inspected by the approved inspectors
before concreting.
CONCRETE
1. All concrete shall be proportion to produce a dense and workable mix
having following concrete compressive strength at 28 days. The concrete
strengths shall be verified by cubic mold tests based on applicable JIS,
ASTM or BS standards.
2. All concrete shall be normal weight concrete wiith aproximately 2.3 T/M 3
of the unit weight and shall be ready-mixed concrete.
3. Cement shall be ordinary portland cement conforming to JIS, ASTM or BS
standard or approved equal.
4. Recomendation slump shall be as follows :
A. For sub Strcuture (in contact with soil/water) 10 CM ~ 2 CM
B. For supper structure
12 CM ~ 2 CM

5.

6.
7.

8.

C. For precast concrete


08 CM ~ 2 CM
D. For miscellaneous concrete
12 CM ~ 2 CM
Adequate admixture, such as water reducing, air entrained or
superplastisizer, can be used in accordance with the manufacturers
recomendation and shall be approved by the engineer.
Trial mix shall be performed and submited to the engineer before
commencement of the work.
Sampling method apr frequency for concrete test shall be based on the
specification or the manner approved by the engineer.
All concrete test results shall be submmitted to the engineer.
Immidietly from approved laboraturium.
Shop drawings for concrete work including all M & E openings shall be
submitted and shall be reviewed by the engineer, prior to the
commencement of the works involved.

STRUCTURAL STEEL WORK


1. All structural steel shall conform to the requirements of JIS or other equal
JIS G-3101/SS 41 rolled steel for general structure.
2. Bolts, nuts, and washers shall conform to the requirement of JIS or other
equal JIS 1180 F10T set of high strenth hexagon bolts, hexagon nuts, and
plain washers for friction grip joints.
3. Welding material shall conform to the requirement of JIS or other equal
JIS Z 3211 D4316 covered electrodes for mild shiled
JIS Z 3211 D4301
JIS Z 3312 steel wires for CO2 gas shield and welding
DESIGN NOTES
1. The building is design based on the following codes and regulation,
A. PPI 1983, SNI 03-2002 in Indonesia codes or ACI 318-08-code.
B. AIJ (Architectural Institute of Japan) code for structural steel, AISC 36005.
2. The design live load is as follow :
Parking and driveway
400 KG/M2
M/E (general)
400 KG/M2
M/E (heavy area)
1000 KG/M2
Loading/unloading
1000 KG/M2
Pool deck
400 KG/M2
Lobby, coridor, stairs
300 KG/M2
Apartment
200 KG/M2
Above live load does not include M/E or plant equipment loading.
3. Seismic load is based on the regulations for earthquake ressistant design
of building in indonesia (SNI-1726-2002) with the following condition :
Importance factor
: I = 1.0
Seismic zone
: Zone 3
Soil condition
: Soft soil
4. Wind load is based on 20 M/SEC of basic wind velocity at 10 M height
above natural ground level

HEIGHT FROM GROUND


BASIC WIND LOAD
0 M to 25 M
50 KG/M2
25 M to 50 M
75 KG/M2
50 M to 75 M
95 KG/M2
75 M to 100 M
110 KG/M2
100 M to 125 M
125 KG/M2
125 M to 150 M
140 KG/M2
150 M to 175 M
150 KG/M2
175 M to 200 M
165 KG/M2
Above basic wind load shall be multiplied by the adequate wind pressure
coefficient.