Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
4-1 INTRODUCTION
This Section of the Manual provides routine operating information for the system installed. Nature of
the installation is such that other than the initial operation of dead circuits, there are only a few tasks to
perform on a regular basis.
The services to the premises will have been energised and set to work with tests carried out to ensure
its correct operation and function particularly with regard to safety systems and interlocks.
These Operating routines should only be carried out by trained and competent personnel who have an
understanding of the systems being energised and its implication on other related systems.
When operating and setting equipment and systems a systematic approach must be taken. Therefore
it is essential that the operative understand the system controls and settings at each stage of operation,
so that they can properly react to any unexpected or unforeseen condition and take the appropriate
action.
The manufacturers manuals and literature must be consulted and referenced to ensure that routines
are followed particularly if there is an unexpected loss or supply or service.
For Specialist systems detailed in this Section as a minimum the authorised user should ensure the
following operations and system information is available, noted and followed:
Ensuring system is tested and maintained in compliance with the relevant legislation,
Codes of Practice, Fire Authority or Insurance Company requirements.
4-6 LV SWITCHBOARDS
A substation has been provided on site by Scottish and Southern Energy (S&SE). The substation is
located in a reinforced section of the Energy Centre at Ground Floor Level. LV supply cabling has
been installed from the transformer LV cabinet in the substation to the LV switch panel located in the
adjacent room of the Energy Centre allocated as the main LV switchroom.
Ensure power is available to both sides of the LV Switchboard via the HV/LV
Transformers.
2.
Visually inspect the HV switches on the transformers. The upper mechanism has two
operating springs; one for closing and one for opening. Both springs are charged in one
operation. Open and Close the circuit breakers by operating the mechanical push
buttons.
3.
The lower mechanism operates the earth switch. There is a mechanical interlock
between these two mechanisms which prevents operating of the disconnector and
earthing switch when the circuit breaker is in closed position. When the earthing switch
is in closed position it will be impossible to operate the disconnector, but the circuit
breaker can be closed for testing purpose.
4.
Once the transformers have been connected to the H.V. mains voltage will be applied in
a non-load state and observed for one hour. No anomalies should occur during this
period of time.
5.
6.
The voltage will be measured at the L.V. terminals to check the corresponding output
voltage depending on the transformation ratio.
7.
Apply the load progressively until the rated power is reached and check the increase in
temperature.
8.
9.
10.
11.
12.
13.
Voltage should be applied to the Transformer for 1-4 hours with no load to ensure no
anomalies occur.
14.
15.
Visually inspect LV switchboard and ensure all outgoing devices are open. Check
settings/ratings of outgoing devices.
16.
The main ACB is motorised and will automatically recharge after each closing. Check
the unit shows a charge and OK display.
17.
18.
19.
20.
21.
Check earth fault relay unit LED show a healthy condition (GREEN).
22.
Confirm the meter readings and breaker status indication is correct on the BMS PC.