Abstract

Piasau Slipways Sdn. Bhd. (PSSB) focuses on building tugboats, barges and small
vessels and also provides ship repair services. Throughout these 13 training weeks, the
industrial training activities mainly focused on the piping system of two 55ton bollard
pull tug ships. The purpose of these 55ton bollard pull tug ships is to import iron ores in
bulk from Brazil, then further export the processed iron ores through blending and
pelletizing in smaller vessels to other clients within the Asian regions. Once the harbor
tug ship is approved for sailing, the ship will be tendered over to the owner, Nautilus Tug
& Towage Sdn. Bhd. PSSB offers two units of the 55ton Bollard Pull Tug ships, with the
code/name of YD408/BPT Larut and YD409/BPT Lumut respectively. This projects
tender started in early 2012 and the ships construction started on 1st September 2013 and
currently one of the ships (YD408/BPT Larut) had been successfully delivered to the
owner on 22/2/2015. Meanwhile, YD409/BPT Lumut was still under construction and
was expected to be completed by early March 2015.

There were 11 types of piping systems been exposed throughout these 13 training
weeks, under a 2 years experienced piping engineer, Miss Elizacorina ak. Siguru
supervision. Many types of piping systems activities had been conducted and the
activities conducted were literatures studies on piping systems, site visit on piping
systems, assisted supervisor, contractors and yards foremen in hands on the pipes and
fittings, conducted material listing for each of the piping systems, assisted engineers and
Germanisher Lloyd (GL) representative in doing inspection and last but not least interact
with other engineers on solving tasks given by supervisor or any problems encountered
throughout these 13 training weeks.

Table of Contents
Chapter 1: Backgrounds of Company............................................................................1
Chapter 2: Summary of Duties.......................................................................................3
2.1 Week 1 (1/12/2014 6/12/2014)............................................................3
2.2 Week 2 (8/12/2014 13/12/2014)..........................................................7
2.3 Week 3 (15/12/2014 20/12/2014)......................................................13
2.4 Week 4 (22/12/2014 27/12/2014)......................................................15
2.5 Week 5 (29/12/2014 3/1/2015)..........................................................17
2.6 Week 6 (5/1/2015 10/1/2015)............................................................19
2.7 Week 7 (12/1/2015 17/1/2015)..........................................................21
2.8 Week 8 (19/1/2015 24/1/2015)..........................................................23
2.9 Week 9 (26/1/2015 31/1/2015)..........................................................25
2.10 Week 10 (2/2/2015 7/2/2015)..........................................................27
2.11 Week 11 (9/2/2015 14/2/2015)........................................................29
2.12 Week 12 (16/2/2015 21/2/2015)......................................................31
2.13 Week 13 (23/2/2015 25/2/2015)......................................................35

Chapter 3: Working Experience...................................................................................36


3.1 Project Carried Out............................................................................... 36
3.2 Supervisory work................................................................................. 59
3.3 Problem encountered and solving experiences....................................77

Chapter 4: Conclusion...................................................................................................80
Reference Lists................................................................................................................81
Appendix.........................................................................................................................82
Appendix A: Schematic diagrams of piping systems in a BPT ship............82

List of Tables
Table 1: 55ton Bollard Pull Tug ship details.................................................................2
Table 2: Week 1 summary of duties........................................................................... 3
Table 3: Pipes and bends in ships.............................................................................. 5
Table 4: Valves used in ships................................................................................... 6
Table 5: Week 2 summary of duties........................................................................... 7
Table 6: Common fittings used in BPT ships................................................................8
Table 7: Common valves used in BPT ships.................................................................9
Table 8: Week 3 summary of duties.........................................................................13
Table 9: Week 4 summary of duties.........................................................................15
Table 10: Week 5 summary of duties........................................................................17
Table 11: Week 6 summary of duties........................................................................19
Table 12: Week 7 summary of duties........................................................................21
Table 13: Week 8 summary of duties........................................................................23
Table 14: Week 9 summary of duties........................................................................25
Table 15: Week 10 summary of duties......................................................................27
Table 16: Week 11 summary of duties......................................................................29
Table 17: Week 12 summary of duties......................................................................31
Table 18: Several types of common piping corrosion....................................................33
Table 19: Corrosion and its preventions....................................................................34
Table 20: Week 13 summary of duties......................................................................35
Table 21: Material listing for bilge, ballast, firemain & wash deck system..........................39
Table 22: Material listing for fuel oil transfer system....................................................42
Table 23: Material listing for engine cooling system.....................................................45
Table 24: Material listing for domestic fresh water & sea water supply..............................48
Table 25: Material listing for grey water & black water system.......................................50
Table 26: Material listing for oily bilge & dirty oil system.............................................53
Table 27: Material listing for oil dispersant system......................................................54
Table 28: Material listing for lube oil system..............................................................55
Table 29: Material listing for external fire fighting system.............................................57
Table 30: Material listing for CO2 fire fighting system..................................................58
Table 31: Supervisory work for the BPT ships' piping construction progress.......................59
Table 32: Summary of the construction progress for both ships.......................................69

List of Figures
Figure 1: Flow chart of shipyard piping engineers roles..................................................4
Figure 2: Bilge, ballast, firemain & wash deck system block diagram...............................38
Figure 3: Fuel oil transfer system block diagram.........................................................41
Figure 4: Engine cooling system block diagram..........................................................44
Figure 5: Domestic fresh water & sea water supply system block diagram.........................47
Figure 6: Oily bilge & dirty oil system block diagram..................................................52
Figure 7: Lube oil piping system block diagram..........................................................56
Figure 8: Exhaust pipeline for port side....................................................................67
Figure 9: Exhaust pipeline for starboard side..............................................................68
Figure 10: Exhaust problem encountered..................................................................77
Figure 11: Initial design for the new exhaust arrangement..............................................78
Figure 12: Final design for the new exhaust arrangement...............................................79

Chapter 1: Backgrounds of Company

Piasau Slipways Sdn. Bhd. (PSSB) was formed on 17 October 1977, located at Lot
516, Piasau Industrial Estate. During that time, PSSB focused on building tugboats,
barges and small vessels. PSSB also provided ship repair services. As time passed by and
high fluctuation of economy, more vessels were required for timber products
transportation, PSSB decided to improvise their services by constructed a new shipyard
located at Lot 523, Kuala Baram Industrial Estate, 98000, Miri, Sarawak (Shin Yang
2013). Ever since 1996, PSSB had constructed and fabricated more than 199 vessels
which include motor launch, dump barges, hopper barges, coastal and deep sea tugboats,
landing crafts, container vessels and oil tankers for domestic and overseas market (Shin
Yang 2013).

According to Shin Yang (2013), the vision of PSSB is to be the Premier Shipbuilder
& Integrated Marine Structural Fabricator and One-stop Quality Marine Engineering &
logistics service provider in South East Asia and beyond. Meanwhile the missions are:

To operate a Modern Integrated shipbuilding base benchmarked for


Excellence in providing comprehensive, innovative and efficient Quality
services.
1

Adaptability to changes to retain sustained success and steadfast in


commitments to Heath, Safety, Environment and Quality values.

Committed to achieve Quality Assurance Management through quality


Planning, quality Improvement and quality control.

An integrated and proactive Heath, Safety & Environment Management


System, with full concern for preserving the Environment, health and safety
of its Employees, Neighboring Community and Customers

Currently, PSSB focuses on the construction of harbor tug ships, which offers
technical specification details within the scope of supply and services for the ships
design, engineering, construction and performance of sea trials for the ships.

The current project ongoing in PSSB is the ship construction of 55ton Bollard Pull
Tug (BPT) ship for VALE Malaysia Manufacturing (VMM) Project, located at Teluk
Rubiah, Perak state, Malaysia. As a brief introduction of this project, the purpose of this
project is to import iron ores in bulk from Brazil, then further export the processed iron
ores through blending and pelletizing in smaller vessels to other clients within the Asian
regions. Once the harbor tug ship is approved for sailing, the ship will be tendered over
to Nautilus Tug & Towage Sdn. Bhd. PSSB offers two units of the 55ton Bollard Pull
Tug ships, with the code/name of YD408/BPT Larut and YD409/BPT Lumut
respectively. This projects tender started in early 2012 and the ships construction
2

started on 1st September 2013 and currently is still under construction and is expected to
be completed by early February next year, 2015. Based on the final conceptual design,
both of these BPT ships have identical details as shown in Table 1 below:

Table 1: 55ton Bollard Pull Tug ship details


Ships details
Length
Breadth
Depth
Submerged depth
Diesel oil tank capacity
Fresh water tank capacity
Number of engines
Engines type

Dimension
28.00m
11.80m
5.00m
4.00m
150.50m3
51.20m3
2
Four
stroke
diesel
engines
turbochargers
Engine rating capacity
1920kW @ 750RPM
Bollard pull forward performance
About 60.00 ton
Bollard pull aft performance
About 56.10 ton
Free
running
speed
forward 12 knots (maximum)
performance

with

The supervisor in charge throughout these 13 training weeks is a 2 years


experienced piping engineer, named Miss Elizacorina Ak. Siguru.

Chapter 2: Summary of Duties


2.1 Week 1 (1/12/2014 6/12/2014)

For the first week, few things regarding piping system for ships were learnt which
were summarized as shown in Table 2 below.

Table 2: Week 1 summary of duties


Date

Time
11.00 am

Duration
15 minutes

Types of duties
Briefing on piping engineers roles in shipping.
Exposure on ship building, piping construction

2.00 pm

3 hours

standard and ship design titled: 55T Bollard Pull

3 hours
1 hour &

Tug ship, 2012 via AutoCAD software.


Introduction to pipes and bends on ships.
Site visit on YD408 ship for an overview look of

1/12/201
4
2/12/201
4
3/12/201
4
4/12/201
4
5/12/201
4

9.00 am
3.30 pm

15 minutes

8.00 am

4 hours

2.00 pm

2 hours

8.00 am

4 hours

2.00 pm

2 hours
1 hour and

8.00 am

30 minutes

10.00 am

2 hours

2.30 pm

2 hours

the ship.
Case studies on YD408 ships piping system
based on the AutoCAD drawings.
Site visit on YD409 ship for an overview look of
the ship.
Case studies on YD408 ships piping system,
involving piping equipments.
Hands on piping equipments (fittings & valves).
Site visit on YD418 ship for exposure on the
valves and fittings installed in the ship.
Conduct research on the fittings functions
installed in a ship.
Conduct research on the valves functions
4

6/12/201
4

8.00 am

3 hours

installed in a ship.
Site visit on YD408 and YD409 ships on the
piping alignments based on schematic diagrams.

Shipyard piping engineers play major role in reviewing and amending the piping
systems schematic diagram provided by the designers implemented throughout the entire
ships and purchase logical amount of valves, fittings and pipes for the ships. Once the
piping system design is completed and approved for construction, piping engineers will
assist the constructors during the construction process to ensure safe and smooth
construction process. A summarized shipyard piping engineers roles are shown in a flow
chart as shown in Figure 1.

Review and amend schematic diagrams


drawn by designers

Prepare material list for each piping


systems involved

If no leakage is presence, the piping


systems instllation are complete

Once the installation is compelete, assist


commisioning engineers to conduct air test
to identify and solve any leakage

Send the material list to both project


engineer and yard manager for approval

Assist contractors and check the


construction progess to ensure smooth
construction process

Contact suppliers for material purchasing

Contact piping contracors for


fabrication and installtion for the
piping and fittings

Figure 1: Flow chart of shipyard piping engineers roles

For every ship, the mandatory components required are hull, steamers, hold and
hatch, mast, deck fittings, anchor, cable, shackles, rooms and lastly cabins. The pipelines
implemented for these mandatory components come together with piping systems
equipments such as joint, vent, valves, sounding, pipes, penetration and many more,
which must follow the piping construction standard for safe operations.

There are many types of bend and pipes used in ships, which can be summarized as
shown in Table 3 below. However, there are two differences between pipes and tubes.
Pipes are highly resistance towards bending, meanwhile tubes are flexible. Besides,
pipes are classified based on the schedule and nominal diameter, A (Sch. 80, 250A),
whilst pipes are classified based on the outer diameter and thickness. Apart from bend
and pipes, several types of valves are used in the piping systems in ships which are
summarized in Table 4.

Table 3: Pipes and bends in ships


Component
Function
Pipe &
Basic piping equipment for transportation of fluid

Example
Pipe & tubes.

tubes

(Sanguri 2012, 4).


Allow integration of flexibility of design by change in

Bend

flow direction of the medium carried inside it (90 0 Miter bends.


pipe bends) (Sanguri 2012, 10).
Allow integration of flexibility of design by change in

Elbows

Nipple
Adapters

flow direction of the medium carried inside it (450 and Street bend.
900 pipe bends) (Sanguri 2012, 10).
A pipe with male threads on each side to facilitate Hexagonal
joining (Sanguri 2012, 19).
reducer nipple.
Extend and terminate similar pipes and connect Hose adapter.

Tee

dissimilar pipes (Sanguri 2012, 23).


Gauge adapter.
Extend and terminate similar pipes and connect Street tee.
dissimilar pipes (Sanguri 2012, 26).

Cross tee.

Table 4: Valves used in ships


Valves
Gate
Globe
Butterfly
Check
Stop cock
Diaphrag
m
Angle
Relief
Ball

Function
To stop the fluid flow across the valve completely and minimize pressure
drop across the valve in fully opened position (Vuthaluru 2014).
Regulate the fluid flow for on-off and throttling services (Vuthaluru 2014).
Similar as globe, but used for low pressure drop cases (Vuthaluru 2014).
To allow the fluid to flow in one direction only (Vuthaluru 2014).
To regulate small fluid flow rate within the pipeline (Vuthaluru 2014).
To regulate corrosive and viscous fluid across the valve (Vuthaluru 2014).
Similar as globe, but used with the presence of fittings (Vuthaluru 2014).
Regulate fluid flow rate when pressure consideration is required
(Vuthaluru 2014).
For flow control and on-off service for isolated fluid (Vuthaluru 2014).

These scheduled site visits mainly focused on the piping systems in both of the BPT
ships, in order to have better and indepth understanding on real life pipeline
applications. These scheduled site visits contributed knowledge on the type of valves and
fittings in 10 core piping systems presence which are bilge, ballast, firemain & wash
deck system, fuel oil transfer system, engine cooling system, domestic fresh water & sea
water supply system, grey water & black water system, oily bilge & dirty oil system, oil
dispersant system, lube oil piping system, external fire fighting system and CO 2 fire
fighting piping system.

Exposure on the floating dock and rexpeller were conducted too. The purpose of
this floating dock it to conduct ship repair and docking for ships in the middle of the sea.
Rexpeller is a newly developed technology for ships movement as it combines both
propeller and rudder which promotes azimuth movement for the ships.

2.2 Week 2 (8/12/2014 13/12/2014)

For the second week, few things regarding piping system for ships were learnt
which were summarized as shown in Table 5 below.

Table 5: Week 2 summary of duties


Date

Time

Duration

9.00 am

3 hours

2.00 pm

3 hours

9.00 am
2.00 pm

3 hours
2 hours

8/12/2014

9/12/2014

3 hours
10/12/201

8.00 am

minutes

11/12/201
4
12/12/201
4
13/12/201
4

and 30

2.00 pm

2 hours

8.00 am

3 hours

2.00 pm

2 hours

8.00 am

3 hours

2.00 pm

2 hours

8.00 am

4 hours

Types of duties
Application of common fittings and valves in
both YD408 & YD409 BPT ships.
Bilge, ballast, firemain & wash deck piping
system analysis.
Fuel oil transfer piping system analysis
Engine cooling piping system analysis
Site visit on both YD408 & YD409 BPT ships
on bilge, ballast, firemain & wash deck, fuel oil
transfer, engine cooling and domestic fresh
water & sea water supply piping systems.
Domestic fresh water & sea water supply piping
system analysis.
Grey water & black water piping system
analysis.
Site visit on YD408 BPT ships external fire
fighting piping system.
Oily bilge & dirty oil piping system analysis.
Site visit on YD408 BPT ships oily bilge &
dirty oil piping system.
Oil dispersant piping system and lube oil piping
system analysis.
10

11

Apart from doing research on the theoretical piping equipments used in ships,
analysis was done on the common piping equipments (valves and fittings) used in the
BPT ship, which are summarized in Table 6 and Table 7 respectively. These analyses
were required before making any valves and fittings installation along the pipelines.

Table 6: Common fittings used in BPT ships


Fittings

system, whilst cast iron short radius 450 is widely used for lube oil and

Elbow

Reducer

Applications
Installed between pipes/tubings, which requires bending of 450 or 900.
Galvanized steel short radius 450 elbows are used for water circulation

fuel oil system.


Galvanized steel 900 street elbows are used for connection for hoses to

valves, water pressure pumps and deck drums.


To connect two pipes with different outer diameter/size to meet the

hydraulic flow requirements of the system.


Widely used reducers are bronze threaded reducer and copper sweat

reducer.
To connect two pipes with same outer diameter/size to meet the
hydraulic flow requirements of the system through welding process,

Union

without welding.
Provide quick and convenient connection of pipe and disconnection of

pipes for maintenance.


To extend and terminate similar pipes and connect dissimilar pipes.
Female tee is used to join male threads pipe in a perpendicular

direction.
Male tee is used to join female threads pipe in two perpendicular

directions.
Similar as union, however, gasket is needed in between two flanges for

the ease of pipe removal and maintenance.


Welding process is required.

Tee

Flange

12

Table 7: Common valves used in BPT ships


Valves
Gate

SDNR

Butterfl
y

Applications
To minimize pressure drop across the valve in a fully opened position.
To ensure the fluid flows continuously to the desired location,

otherwise is stopped completely in case of emergency situations.


Uses in all of the piping systems.
Also known as Screw Down Non Return valve.
To ensure that the fluid flow in one direction across it, this is to prevent

the fluid from flowing back to the starting point.


To regulate fluid flow rate at low pressure drop applications.
Usually connect with any flanged pipe.
Common used butterfly valves are geared type butterfly valves, for ease

on control.
Applicable for emergency situations only, whereby the valves will be

Quick

used to stop all the fluid flow almost immediately via controlling

closing

configurations in the control room.


Usually installed along the fuel oil systems pipeline.
To regulate fluid flow rate at different altitude.
This valve transports horizontal fluid to upper area/move vertically

upwards and then move horizontally to the desired location.


These valves are used in engine cooling system.
To regulate the isolated fluid flow rate.
Used in fuel oil transfer system, to prevent the oil from been isolated in

the pipeline, which may cause blockage or difficulties in cleaning.


Similar as angle SDNR valve, but the transportation direction is

different.
Angle storm transports horizontal fluid to lower area/move vertically

downwards and then move horizontally to the desired location.


These valves are used in grey water & black water system.
To regulate fluid flow rate at any pressure drop requirements.
Usually connect with any flanged pipe.
To regulate fluid with tendency of being isolated throughout the

pipeline.
Usually applied in the fuel oil system, as the fuel oil tends to isolated as

Angle
SDNR

Check

Angle
storm

Angle

Ball

time passes by.

13

Fire
hydrant

Transport CO2 from CO2 storage area located in main deck to put out

fire in the engine room.


Applied for firemain system only.

In a BPT ship, there are 10 main piping systems presence which are bilge, ballast,
firemain & wash deck system, fuel oil transfer system, engine cooling system, domestic
fresh water & sea water supply system, grey water & black water system, oily bilge &
dirty oil system, oil dispersant system, lube oil piping system, external fire fighting
system and CO2 fire fighting piping system. Detailed drawings, explanations and valves
applications are addressed in Section 3.1. All of the pipes used in these systems must be
flanged with the gap of 1.50m between two pipes for the ease of construction,
maintenance and removal (Lloyd 2012, 11-33).

Bilge, ballast, firemain & wash deck system

In this system, three different types of piping systems are installed, which are bilge
piping system, ballast piping system and firemain piping system. The purpose of bilge
piping system is to remove small quantities of fluid that have leaked out or condensed
into a dry space with the aid of two centrifugal pumps. The purpose of ballast piping
system is to stabilize the ships weight and coordination by adjusting the input, output
and storage of the fresh water in the ballast tank with the aid of a centrifugal pump. The
purpose of firemain piping system is to transport sea water for firefighting system in the
ship for both main deck and below main deck with the aid of a centrifugal pump.
14

Fuel oil transfer system


The purpose of this piping system is to transport diesel oil to both main and
auxiliary engines with the aid of built-in centrifugal pump installed in each of the
engine; operated at 25m3/h @ 2bar powered by a 220V AC motor and a duplex strainer.
This system also transports diesel oil to generator for electricity generation in the ship.

Engine cooling system

The purpose of this piping system is to transport sea water to cool down two main
engines of the ship via heat exchanger equipment installed in the engines circulated by
generator built-in pump. This system also transports sea water for air cooling system.

Domestic fresh water and sea water supply system

15

The purpose of this system is to transport fresh water supply for ballast tank, engine
cooling, main deck area (toilet, galley/kitchen and washing machine) and for window
wiper water supply in wheelhouse deck area. Generator with built-in heat exchanger is
installed with the closed fresh water circuit for heating and cooling function.

Grey water & black water system

The purpose of this system is to transport both grey water and black water away
from the ship either through overboard or into sewage tank. The black water means
human excretory waste from the washroom, whilst the grey water means waste water
produced other than human waste, such as from kitchen/galley. Black water will be
transported into a sewage treatment plant for treatment and disinfection purposes and
then stored in a sewage tank or discharged to the sea through the below main decks
overboard. Grey water will be discharged directly to the sea via main decks overboard.
If the treated/waste water from the sewage treatment plant and sewage tank is needed to
be discharged to the sea, the water can only be discharged at least 3 nautical miles from
the nearest land (Lloyd 2012, 11-49).

Oily bilge & dirty oil system

The purpose of this system is to transport oily waste fluid/bilge from various
sections in the ships and dirty oil from the engines into a sludge tank and oily water
storage for disposal upon docking. Strum box is required to filter out large sized and
non-biodegradable wastes before entering the sludge tank. Two separate tanks are
required to store oily bilge and dirty oil respectively (Lloyd 2012, 11-42). Sludge tank is

16

used to store dirty oil/lubricant oil from the main engines, meanwhile oily water storage
is used to store oily bilge from various sections in the ship.

Oil dispersant system

The purpose of this system is to transport oil from the dispersant tank to two
dispersant booms at both left/port and right/star board side for cleaning service. Since
most of the oily bilge, waste fluid and grey water are disposed into the sea directly
through overboard, thus the dispersant boom system is required to clean the ships
exterior from these wastes.

Lube oil system

The purpose of this system is to transport lubricant oil from the sump tank to the
main engines in order to ensure the main engines operate smoothly, reliable lubrication
in order to have adequate heat transfer and also to reduce the corrosion rate occurring in
the main engines. According to Lloyd (2012, 11-30), emergency lubrication oil supply
can be installed for the main engines in case of interruption of lubricating oil supply
from the main storage, and besides the lubricant oil treatment is a mandatory for
adequate treatment of the oil via several processes such as filtering, purifiers and
centrifuging.

17

These scheduled site visits contributed knowledge on the piping systems along with
valves and fittings applications implemented in the BPT ships.

2.3 Week 3 (15/12/2014 20/12/2014)

For the third week, few things regarding piping system for ships were learnt which
were summarized as shown in Table 8 below.

Table 8: Week 3 summary of duties


Date
15/12/201
4

Time

Duration

9.00 am

3 hours

2.00 pm

2 hours

8.30 am

3 hours

16/12/201
4
17/12/201
4

2.00 pm

piping system analysis.


Comparison between external fire fighting,
firemain and CO2 fire fighting systems.
Site visit on YD408 BPT ships CO 2 fire

2 hours

fighting piping system.


Teaching & learning session with supervisor on

and 30

the material purchasing technique and procedure

minutes

for valves to be installed for the BPT ships.


Sketch bilge, ballast, firemain & wash deck

8.00 am

2 hours

10.30

1 hour

am

Types of duties
External fire fighting and CO2 fire fighting

piping system based on the schematic diagram.


Site visit on both YD408 and YD409 BPT ships
main engines piping alignment.
18

18/12/201
4
19/12/201
4
20/12/201
4

2.00 pm

2 hours

9.00 am

2 hours

2.00 pm

2 hours

8.30 am

2 hours

2.00 pm

2 hours

9.00 am

2 hours

Material listing for bilge, ballast, firemain &


wash deck system.
Sketch fuel oil transfer piping system based on
the schematic diagram.
Material listing for fuel oil transfer system.
Sketch engine cooling piping system based on
the schematic diagram.
Material listing for engine cooling system.
Site visit on YD408 BPT ships grey water &
black water piping system.

19

External fire fighting system

The purpose of this system is to transport foam from the storage located at below
main deck area to main deck and wheelhouse deck for external fire control purposes.
This system also transport foam to the fire monitor to put out fire on the other ships and
burning/fire zones. Air operated sirens are installed as a part of the external fire fighting
system, to provide warning/emergency sound during emergencies. There are two types
of foam to be used, which are the low expansion foam and high expansion foam. For the
low expansion foam, the ratio volume of foam produced to the mixture of water and
foam concentration supplied must not exceed 12:1, whereas for the high expansion form,
the ratio must not exceed 1000:1 (Lloyd, 12-28).

CO2 fire fighting system

The purpose of this system is to transport CO 2 from the CO2 room located at the
main deck to 12 different positions at the below main deck area for fire fighting purpose.
The difference between this system and the firemain system is that; CO 2 fire fighting
system uses CO2, whereas firemain system uses sea water to put out fire in the below
main deck area. However, firemain is only used as the last resort where CO 2 fire fighting
system fails to put out the fire completely.

20

The aim of this teaching & learning session with supervisor on the material listing
for purchasing technique and procedure of piping materials was to make quantitative and
qualitative analysis on choosing valves and materials for the piping systems based on the
schematic diagram. Drawing review on materials basis was required to ensure the
material list provided by the designers is accurate. To conduct material listing, few
criteria are required, such as items, size, material, allowable pressure drop and materials
purchased reference number (JIS). The reference numbers are usually referred to the
supplier such as Sun Korea Co., LTD. (2005) and Najin Corp. (n.d.) Material listing for
all of the 10 systems based on the schematic diagram were and tabulated in Section 3.1.

2.4 Week 4 (22/12/2014 27/12/2014)

For the fourth week, the daily duties given and conducted were summarized as
shown in Table 9 below.

Table 9: Week 4 summary of duties


Date

Time

Duration

8.00 am

4 hours

2.00 pm

3 hours

22/12/201
4

8.00 am

3 hours

2.00 pm

3 hours

23/12/201
4

Types of duties
Check the construction progress of YD409 BPT
ships pipeline piping system.
Sketch and conduct material listing for domestic
fresh water & sea water system based on the
schematic diagram.
Check the construction progress of both YD408
&YD409 BPT ships pipeline piping system.
Sketch and conduct material listing for oily
bilge & dirty oil piping system based on the
schematic diagram.
21

Conduct material listing for grey water & black


9.00 am

2 hours

24/12/201

water and oil dispersant system based on the


schematic diagram.
Check the construction progress of both YD408

4
2.00 pm
25/12/201
4
26/12/201
4
27/12/201
4

2 hours

9.00 am

2 hours

2.00 pm

2 hours

8.00 am

3 hours

& YD409 BPT ships firemain and fuel oil


piping system.
None, due to public holiday (Christmas)
Literature studies on the BPT ships Daihatsu
main engines.
Hands on BPT ship main engines fittings
arrangement based on the manual.
Sketch and conduct material listing for lube oil
piping system based on the schematic diagram.

As for week 4, material listing and block diagram sketching activities were
continued for the remaining piping systems. Apart from that, checking and updating the
piping construction progress for both YD408 and YD409 BPT ships were conducted to
ensure

the

construction

progress

ran

smoothly.

All

of

the

construction

progress/supervisory work were summarized in Section 3.2.

Since the ships main engines piping system is the most crucial system, a literature
studies on the main engines was conducted. The main engines used are Daihatsu main
engine, built in Osaka, Japan, with the function to provide both mechanical and electrical
energy for the ship at maximum continuous output of 1920kW @ 750RPM. In order to
understand the piping mechanisms of the main engines, the arrangement of the main
engines fitting and the relevant piping system are required. The piping systems involved
in these Daihatsu main engines are ballast system, domestic fresh water & sea water

22

supply system, engine cooling system, fuel oil transfer system, oily bilge & dirty oil
system and lastly lube oil system. The fitting arrangements are like lube oil inlet &
outlet, fresh water inlet & outlet, fuel oil inlet & outlet and other fittings. Once the main
engines fittings arrangements are recognized, the alignment for the involved piping
systems can be conducted.

A hand on BPT ship main engines fittings arrangement based on the manual was
conducted. The purpose of this activity is to provide industrial application on the piping
connection in the Daihatsu main engines. In practical, the piping connection throughout
the main engines are mostly welded and flanged with a maximum distance gap of 1.50m.
Daihatsu main engines required lubricant oil, fuel oil, sea water and fresh water in order
to operate smoothly. Lubricant oil is used to provide sufficient oil for smooth mechanical
process; meanwhile fuel oil is used for operating services. Both sea water and fresh
water are used for engine cooling system and also for cleaning service. Although this
activity is more to mechanical engineering applications, one requires this knowledge in
the piping field, so that the piping misalignments can be reduced.

2.5 Week 5 (29/12/2014 3/1/2015)

For the fifth week, the daily duties given and conducted were summarized as shown
in Table 10 below.

23

Table 10: Week 5 summary of duties


Date
29/12/201
4

30/12/201
4

Time

Duration

9.00 am

2 hours

2.00 pm

2 hours

9.00 am

3 hours

2.00 pm

2 hours

8.00 am

2 hours

10.30
31/12/201
4

am
2.00 pm

3.00 pm
1/1/2015

2/1/2015

8.00 am
9.30 am
2.00 pm

3/1/2015

1 hour and
30
minutes
40

Types of duties
Conduct material listing for CO2 fire fighting
and external fire fighting systems.
Check the piping construction progress of both
YD408 & YD409 BPT ships.
Revised on the piping systems block diagrams,
processes and descriptions.
Revise on the piping systems block diagrams,
processes and descriptions.
Check the piping construction progress of both
YD408 & YD409 BPT ships.
Revised on the piping systems block diagrams,
processes and descriptions.
Task briefing for the upcoming Germanisher

minutes
Lloyd (GL) overboard checking.
1 hour and
Site visit on YD408 BPT ships overboard for
30
the upcoming GL supervision.
minutes
None, due to public holiday (New Year).
1 hour
Literature studies on a BPT ships overboard.
Assist GLs representative on YD408 BPT ships
2 hours
overboard checking.
Revise on the piping systems block diagrams,
2 hours
processes and descriptions.
None, due to public holiday (S.A.W. birthday)

As for week 5, supervisory work for the piping construction progress for both
YD408 and YD409 BPT ships was continued, which were summarized in Section 3.2.

24

All of the piping systems block diagram sketches and the process flow explanation
were revised to meet the ships classification society, Germanisher Lloyd (GL) and also
the constructor standard, Shin Yang Shipyard Sdn. Bhd.

Meanwhile on 2/1/2015, a Germanisher Lloyd (GL) representative Mr. Gan Chee


Kian came to check the overboard position, construction progress for YD408 BPT ship.
To assist the GLs representative, overboards schematic diagram and information such
as size, valve used, location and the height from the Draft Water Level (DWL) are
required. Detailed explanation and working experience were addressed in Section 3.2.

25

2.6 Week 6 (5/1/2015 10/1/2015)

For the sixth week, the daily duties given and conducted were summarized as
shown in Table 11 below.

Table 11: Week 6 summary of duties


Date

Time

Duratio

Types of duties

n
9.00 am

2 hours

2.00 pm

2 hours

8.30 am

3 hours

2.00 pm

2 hours

8.30 am
10.00

1 hour

5/1/2015

6/1/2015

7/1/2015

am
1.30 pm

8/1/2015

9/1/2015

2 hours

Check the piping construction progress of both


YD408 & YD409 BPT ships.
Sort out piping equipments of external fire
fighting system for both YD408 & YD409 ships.
Site visit on YD408 ships main engines and its
external fire fighting systems piping alignments.
Check the air test status of YD409 BPT ships
bilge, ballast & firemain system.
Literature studies on exhaust system.
Check the piping construction progress of both
YD408 & YD409 BPT ships.
Check the air test status and piping construction

3 hours

progress of YD409 BPT ships fresh water & sea

8.00 am

1 hour

9.30 am

2 hours

water system.
Exhaust system arrangement analysis.
Site visit on YD408 BPT ships main engines and

2.00 pm

2 hours

8.30 am

3 hours

generators exhaust system.


Check the piping construction progress of both
YD408 & YD409 BPT ships.
Check the exhaust system installation progress of
26

10/1/2015

2.00 pm
8.30 am

2 hours
3 hours

both YD408 & YD409 BPT ships.


Problem solving on the main engines exhaust.
Problem solving on the main engines exhaust.

As for week 6, supervisory work for the piping construction progress for both
YD408 and YD409 BPT ships was continued, which were summarized in Section 3.2.
However, a problem encountered within one of the main engines exhaust system
connection and alignment. The problem encountered from the main engines left
side/starboard is that when the expansion joint, bend and the silencer are connected as
shown in Figure 10 in Section 3.3, the drainage system for condensed exhaust vapour
was unable to be installed due to its unsuitability. In order to solve this problem,
knowledge, fittings and the mechanism of the exhaust system are required. Thus,
literature studies, site visit and analysis on the main engines exhaust system were
conducted in order to have better understanding on the exhaust system. Problem solving
for the starboard side main engines exhaust system was addressed in Section 3.3.

As for the exhaust system literature studies, the fittings and the mechanism of the
exhaust system from exhaust piping arrangement schematic diagram (Appendix A) is
summarized as follow. Exhaust system is applied for both main engines and its
generators (genset), whereby the main engines and the genset have their own respective
pipeline, fittings and arrangements. However, they have the same purpose. The purpose
of the exhaust system is to remove exhaust gas from both main engines and genset,
similar to any vehicles. Both main engines and genset are connected with expansion
joint, silencer and lastly exhaust funnel. The function of expansion joint is similar to
flange which connect between pipes for the easy of construction and removal.
Meanwhile, silencer reduces the exhaust sound to the minimal level and lastly the
exhaust funnel channels out the exhaust gas from the ship.

27

This system does not require any valves but require Schedule 40 seamless black
mild steel pipes, except for the exhaust funnels which require Schedule 40 stainless steel
pipes. Besides, both of the main engines and genset exhaust pipe are insulated with
aluminum sheet of 75mm and 50mm thick respectively, with mineral wool in between
the aluminum sheet and the exhaust pipeline for heat insulation purpose.

28

2.7 Week 7 (12/1/2015 17/1/2015)

For the seventh week, daily duties given and conducted were summarized as shown
in Table 12 below.

Table 12: Week 7 summary of duties


Date

Time

Duratio

Types of duties

n
3 hours

2.00 pm

2 hours

8.00 am

3 hours

progress

2.00 pm

2 hours

8.30 am

2 hours

progress.
Revised on main engines exhaust drawings.
Site visit on hydraulic power pack machinerys

12/1/2015

13/1/2015

14/1/2015

15/1/2015

16/1/2015

Check both of the ships main engines piping

8.30 am

11.00
am

1 hour

1.30 pm

3 hours

8.30 am

3 hours

1.30 pm

1 hour

3.00 pm
8.30 am

2 hours
3 hours

construction and air test progress.


Assist supervisor in rearrange the pipe connection
due to misalignment in YD408 BPT ship.
Check both of the ships piping construction
and

observe

scupper

installation

fittings and alignment.


Revised on main engines exhaust drawings.
Check the piping construction progress of both
YD408 & YD409 BPT ships.
Check and update on the main engines exhaust
new design installation.
Check on the scuppers installation progress on
both YD408 and YD409 BPT ships.
Revised on the material listing for each system.
Check both of the ships piping construction
29

17/1/2015

2.30 pm

2 hours

9.00 am

2 hours

progress and scuppers installation progress.


Revised on the material listing for each system.
Assist supervisor in checking the outstanding
piping construction progress for both BPT ships.

30

As for week 7, supervisory work for the piping construction progress for both
YD408 and YD409 BPT ships was continued, which were summarized in Section 3.2.

On 12/1/2015, scuppers were planned to be installed for both ships main deck, one
on port side and another on the starboard side respectively, as water always accumulated
on the main deck when it rains. Therefore, this task was assigned to the yards welders
and fitters in order to speed up the construction progress and this task was expected to be
completed within 4 working days. Thus, an additional supervisory work was assigned by
supervisor, by checking and updating the scuppers installation progress. This task was
completed on 16/1/2015.

Site visit on hydraulic power pack machinerys fittings and alignment was
conducted on 14/1/2015 in order to have better understanding on the purpose and the
piping connection; as the hydraulic power pack was initially placed on YD408 BPT ship
on 17/1/2015, whereas the hull and piping fitting and alignment will be conducted on
training week 8. The purpose of this hydraulic power pack is to provide hydraulic power
supply to the ships capstan and anchor windlass via two respective control stations. The
function of a ships capstan is to hold the ship in position during docking session by
applying forces on ropes and cables; whereas the function of a ships anchor windlass is
to restrain and control the ships anchor chain for mobility purpose.

31

2.8 Week 8 (19/1/2015 24/1/2015)

For the eighth week, the daily duties given and conducted were summarized as
shown in Table 13 below.

Table 13: Week 8 summary of duties


Date

Time

Duratio

Types of duties

n
8.30 am

3 hours

1.30 pm

3 hours

9.00 am

3 hours

2.00 pm

2 hours

8.30 am

3 hours

2.00 pm

2 hours

8.00 am

2 hours

1.30 pm

1 hour

2.30 pm

2 hours

8.30 am

3 hours

19/1/2015

20/1/2015

21/1/2015

22/1/2015

23/1/2015

Assist supervisor in ships outstanding tasks


distribution to contractors and yards foremen.
Assist main engines engineers (Daihatsu) in main
engines exhaust cleanliness checking.
Site visit on genset testing by Daihatsus
engineers.
Assist main engines engineers (Daihatsu) on the
main engines exhaust second checking.
Check the main engines fuel oil piping progress
for both YD408 & YD409 BPT ships.
Assist supervisor in rearrange YD408 BPT ships
lube oil piping connection due to misalignment.
Site visit on main engines and genset testing by
Daihatsus engineers.
Assist yard foremen in the installation of the main
engines turbo charger in YD409 BPT ship.
Check the main engines piping connection and
alignment progress in YD409 BPT ship.
Check the outstanding compressed air piping

32

connection progress for both BPT ships.


Check air test status of YD408 BPT ships fresh
2.00 pm

2 hours

water & sea water and oily bilge & dirty oil
systems.

24/1/2015

8.00 am

3 hours

Update outstanding piping progress for both ships.

As for week 8, supervisory work for the piping construction progress for both
YD408 and YD409 BPT ships was continued, which were summarized in Section 3.2.

On 19/1/2015, YD408 both port and starboard main engines cleanliness was
scheduled to be inspected by the Daihatsu engineers. In order to assist the engineers, the
expansion joint attached between the two pipelines (turbo charger pipeline and silencer
pipeline) needed to be detached as per referred to the exhaust piping arrangement
schematic diagram in Appendix A. Detailed explanation and working experience were
addressed in Section 3.2. The exhaust cleaning for both of the main engines exhausts
was conducted on the following next day (20/1/2015) as per requested. The Daihatsu
engineers were satisfied with the results and the expansion joint was flanged back to
each of the main engines respectively.

YD408 BPT ship was planned to be delivered to the owner within the first week of
February 2015, thus, several machinery tests were required to be conducted. Gensets
testing was scheduled to be tested and operated on 20/1/2015, whilst main engines
testing was schedule to be tested and operated on 22/1/2015.Thus, the supplier, Daihatsu
33

sent two of their engineers to conduct testing and operated the main engines and gensets
to test the machines efficiency and endurance for a maximum of 4 hours per day.
Therefore, site visits were conducted to observe and to learn on how these machines
were being tested and operated by the engineers.

YD408 BPT ship was scheduled to be delivered to the owner (Nautilus Tug &
Towage Sdn. Bhd.) within the first week of February 2015, all of the outstanding piping
tasks were expected to be completed by the end of January 2015 but all of the
outstanding tasks were completed one week earlier. Since all of the piping construction
for YD408 had completed, therefore all of the supervisory works will be focused on
YD409, which still have 58 outstanding tasks to be completed in three weeks time.

34

2.9 Week 9 (26/1/2015 31/1/2015)

For the ninth week, the daily duties given and conducted were summarized as
shown in Table 14 below.

Table 14: Week 9 summary of duties


Date

Time

Duratio

Types of duties

n
26/1/2015

Assist supervisor and yards foreman in finding

9.30 am

2 hours

2.00 pm

2 hours

copper tubing and copper sockets with supplier.


Participate in YD408 BPT ships yard trial.
Assist supervisor and yards foremen in doing

8.30 am

3 hours

minor piping adjustment for engine cooling in

2 hours

YD408 ship.
Assist supervisor and yards foremen in installing

and 30

copper tubing of air supply from air reservoir to

minutes

control panel and main engines in YD409 ship.


Assist supervisor and contractor in doing minor

3 hours

piping adjustment for chain wash at YD408 ship

27/1/2015
2.00 pm

9.00 am
28/1/2015
1.30 pm

3 hours

9.30 am

2 hours

29/1/2015
2.00 pm

2 hours

firemain system.
Check the piping construction progress of YD409
BPT ship.
Check and update the YD408 BPT ships main
deck penetration of air vents, soundings and filling
tanks.
Assist supervisor in reconfirm the air vents size
and position on YD408 BPT ships main deck.
35

Assist yards foremen in doing piping adjustment


8.30 am

3 hours

30/1/2015

31/1/2015

2.00 pm

2 hours

8.00 am

3 hours

for the rexpeller cooling system for both BPT


ships.
Check the piping construction progress of YD409
BPT ship.
Check the piping construction progress of YD409
BPT ship.

As for week 9, supervisory work for the piping construction progress for both
YD408 and YD409 BPT ships was continued, which were summarized in Section 3.2.

Since YD408 BPT ship had completely constructed and passed all of the machinery
tests, the ship was scheduled to undergo yard trial for 2 hours on 26/1/2015. The purpose
of this yard trial is to check and test the overall ships performance on river with the
minimum depth of 15m. After passing the yard trial, the ship will undergo sea trial which
takes places at the wide open sea area, which is to check and test the overall ships
performance under sea condition. However, on the way back to the site, the YD408
experienced some vibration at the port side rexpellers shaft due to less tighten of bolt
and nut. This vibration will cause fatal problem if not taken seriously. Thus, the ship
required to undergo some modifications. Since there was a problem detected on the
ships, therefore the ship need to undergo second sea trial which was scheduled to be on
3/2/2015.

36

Although the YD408 BPT ship had fully constructed, however minor piping,
fittings and electrical modifications were conducted to resolve for any problems
encountered during and after the yard trial. As for piping, the minor adjustments were
made on the engine cooling pipelines, rexpeller cooling pipelines and the hawse pipe
wash down pipelines. On 27/1/2015, minor piping adjustment for engine cooling in the
YD408 ship was conducted due to main engines unbalance pressure. Meanwhile, on
28/1/2015, the chain wash pipe of firemain system in YD408 ship was reallocated to
allow the bollard installation on the main deck. Whilst, on 30/1/2015, rexpeller cooling
system pipelines in both BPT ships were readjusted as per requested by the Daihatsus
engineers.

37

2.10 Week 10 (2/2/2015 7/2/2015)

For the tenth week, the daily duties given and conducted were summarized as
shown in Table 15 below.

Table 15: Week 10 summary of duties


Date

Time

Duratio

Types of duties

n
9.00 am

3 hours

Check the piping construction progress of both


YD408 & YD409 BPT ships.
Check the main engines piping connection and
alignment progress and also the copper tubing

2/2/2015
2.00 pm

2 hours

installation of air supply from air reservoir to both


control panel and main engines in YD409 BPT

3/2/2015

9.00 am

7 hours

9.00 am

3 hours

2.00 pm

2 hours

8.00 am

3 hours

2.00 pm

2 hours

8.30 am

2 hours

2.00 pm

2 hours

4/2/2015

5/2/2015
6/2/2015

ship.
Participate in YD408 BPT ships second yard trial.
Update the exhausts expansion joint reinstallation
in YD409 and butterfly valve tightening in YD408.
Check the main engines piping connection and
alignment progress in YD409 BPT ship.
Assist yards foremen in doing minor modification
of soundings for both BPT ships.
Check the soundings modification progress of
both BPT ships.
Check the soundings modification progress of
both BPT ships.
Assist supervisor in checking and updating any

38

7/2/2015

8.00 am

and 30

outstanding piping construction tasks for YD409

minutes

BPT ship with contractors and yards foremen.


Assist supervisor in checking and updating any

3 hours

outstanding piping construction tasks for YD409


BPT ship with contractors and yards foremen.

As for week 10, supervisory work for the piping construction progress for both
YD408 and YD409 BPT ships was continued, which were summarized in Section 3.2.

On 3/2/2015, a yard trial for YD408 BPT ship was conducted at 9.00 am. The first
phase of the trial was conducted to travel back and forth from PSSB to Shin Yang
Dockyard Sdn. Bhd. which is about 3km far, which minimum water depth of 15m for 4
times. Then, the ship docked at Shin Yang Dockyard Sdn. Bhd. or also known as
Shipyard 1, for fresh water filling, which took about 3 hours to fully fill the fresh water
tanks. At 3.30pm, the ship departed from Shipyard 1 and docked safety at PSSB at 4.00
pm. This yard trial considered as a successful yard trial as no machinery problems were
encountered throughout the entire trial, only a minor leakage occurred for standby main
engines cooling pump was detected. The leakage problem was solved on 4/2/2015, by
tightening the butterfly valve along the pipeline.

On 3/2/2015, main engines exhaust cleanliness checking was conducted by the


Daihatsus engineers for YD409 BPT ship. This inspection was conducted during the
night time. Similarly with YD408 BPT ship, dirt was detected surrounding the exhaust
39

pipeline, which required cleaning. On the next day 9.00 am, second inspection was
conducted and the Daihatsus engineers were satisfied with the exhaust cleanliness. The
expansion joint was installed back to the main engines exhaust, completed at 11.00 am.

On 5/2/2015, minor modification was made to 5 soundings located on the main


deck by fabricated an adapter in between current sounding cap and the sounding pipeline
for each of the soundings for both of the BPT ships. The purpose of adding this adapter
for each of the soundings is to ensure the soundings are having the same height level
with the main deck flooring board, in order to prevent water being accumulated around
the soundings due to height difference. This task was completed on 6/2/2015 for YD408
BPT ship and 7/2/2015 for YD409 BPT ship.

2.11 Week 11 (9/2/2015 14/2/2015)

For the eleventh week, the daily duties given and conducted were summarized as
shown in Table 16 below.

Table 16: Week 11 summary of duties


Date
9/2/2015

Time

Duratio

Types of duties

8.30 am

n
3 hours

Check the lube oil piping systems welding and

40

2.00 pm

2 hours

9.00 am

2 hours

10/2/2015

minor piping modification for both of the BPT


ships external fire fighting systems pump.
Check the YD409 BPT ships main engines fuel

2 hours

8.30 am

2 hours

1.30 pm

3 hours

minor piping modification for YD408 BPT ships

9.00 am

2 hours

2.00 pm

2 hours

fresh water pipeline.


Follow up yards foremen tasks progress.
Check the YD409 BPT ships main engines fuel

8.30 am

2 hours

2.00 pm

2 hours

8.30 am

3 hours

13/2/2015

14/2/2015

(Marpol and decks penetration) for YD408 ship.


Assist supervisor and yards foremen in doing

2.00 pm

11/2/2015

12/2/2015

connection progress for YD409 BPT ship.


Check the main deck piping construction progress

oil piping construction progress.


Check and update the ships external fire fightings
pump piping modification with yards foremen.
Assist supervisor and yards foremen in doing

oil piping alignment and connection progress.


Assist yards foremen in relocating the chain wash
pipeline of YD409 ships firemain system.
Assist supervisor in updating any outstanding tasks
for YD409 BPT ship with contractors.
Assist supervisor in updating any outstanding tasks
for YD409 BPT ship with contractors.

As for week 11, supervisory work for the piping construction progress both YD 408
and YD409 BPT ships was continued, which were summarized in Section 3.2.

Few piping modifications were made throughout this week due to minor technical
problems or as per suppliers request. On 10/2/2015, minor piping modification was
made for both BPT ships external fire fighting systems pump as per required by the
supplier, FITECH Engineering Pte. Ltd. This modification was conducted by removing

41

all of the pipes connected to the fire fighting pump as well as the pump itself. This is for
the ease of the installation of additional device on the pump and along the pipelines. This
task was partially completed on 12/2/2015, whereby the firefighting pump and the pipes
were removed from its position, whereas the additional device was not installed yet as it
had not arrived yet and was expected to arrive on 13/2/2015. Thus, this task was
completed on 14/2/2015 and underwent fire hydrants testing at 3.00 pm.

Apart from external fire fighting system, minor piping modification was conducted
on 11/2/2015 for one of the YD408 BPT ships domestic fresh water system pipelines
(main decks washrooms pipeline). With the current fresh water pipeline, there was
tendency for the fresh water to flow back into the water tank. To solve for this problem,
a bronze swing check valve was installed along the pipeline, after the gate valve. The
purpose of installed an additional swing check valve is to ensure the fresh water flow in
one direction only, which is to the washrooms. The installation of the swing check valve
can be checked by referring to the domestic fresh water & sea water supply systems
schematic diagram in Appendix A. This task was completed on 12/2/2015. This
modification was applied to YD409 BPT ship and was scheduled to be conducted on
16/2/2015.

The chain wash pipeline for YD409 was reallocated on 13/2/2015 to allow the
bollard installation on the main deck and was completed at 4.00pm.

42

2.12 Week 12 (16/2/2015 21/2/2015)

For the twelfth week, the daily duties given and conducted were summarized as
shown in Table 17 below.

Table 17: Week 12 summary of duties


Date

Time

8.30 am
16/2/2015
2.00 pm

Duratio

Types of duties

n
2 hours

Assist supervisor and yards foremen in doing

and 30

minor piping modification for YD409 BPT ships

minutes

fresh water pipeline.


Follow up yards foremen tasks progress and

2 hours

check the YD409 BPT ships main engines fuel oil

8.30 am

2 hours

2.00 pm

2 hours

9.00 am

2 hours

2.00 pm

3 hours

19/2/2015
20/2/2015

21/2/2015

8.00 am

3 hours

17/2/2015

18/2/2015

piping alignment and connection progress.


Check the YD409 BPT ships main engines fuel
oil piping alignment and connection progress.
Literature studies on corrosion control and paint
system.
Check the YD409 BPT ships hydraulic piping
connection progress.
Literature studies on corrosion control and paint
system.
None, due to public holiday (Chinese New Year).
None, due to public holiday (Chinese New Year).
Assist supervisor in updating any outstanding tasks
for YD409 BPT ship with contractors.

43

44

As for week 12, supervisory work for the piping construction progress YD409 BPT
ship was continued, which were summarized in Section 3.2.

Since the all of the minor piping modifications for both piping and fittings had
completed, YD408 BPT was set off for sea trial on 16/2/2015, 1.00 pm. The sea trial was
conducted at the sea area with the sea depth of more than 60m and safe location away
from subsea cables for 5 days continuously. The sea trial program for YD408 BPT ship
was listed as shown below:
1. Anchor dropping and hoisting test @ 100% Maximum Continuous Rating
2.
3.
4.
5.
6.
7.

(M.C.R) of main engines.


Steering gear test @ 100% M.C.R of main engines.
Turning circle test @ 100% M.C.R of main engines.
Crash stop test @ 100% M.C.R of main engines.
Inertia test
Straightness checking with vessel astern at 7knot and rudder at 00
Speed trial & endurance trial
Operates at 25% M.C.R.
Operates at 50% M.C.R.
Operates at 75% M.C.R.
Operates at 100% M.C.R.
Auto pilot test to verify and accept conformance by ship officer.
Navigation and communication equipments to verify and accept

conformance by ship officer.


8. Escort trial to perform test for
Verify the speed for assisted vessel speed during full scale trial.
Verify the maneuvering time needed to shift indirect towing from an oblique

angular at stern of assisted vessel to mirror position at other side.


Verify maximum steering force.

Verify towing wince damping system.

45

Similarly with YD408 BPT ship, minor piping modification was conducted on one
of the YD409 BPT ships domestic fresh water system pipelines (main decks
washrooms pipeline) with the same problem encountered whereby the fresh water had
the tendency to flow back into the fresh water tank. Thus, a bronze swing check valve
was installed along the pipeline, after the gate valve to ensure that the fresh water flows
directly to the washrooms only. The installation of the swing check valve can be checked
by referring to the domestic fresh water & sea water supply systems schematic diagram
in Appendix A.

There are many types of corrosion tend to occur on any part of the ships, especially
hull and pipelines. Table 18 below summarized the common corrosion and its
description that occurred on the pipes of any ships, whereas Table 19 shows the
common prevention for the corrosion listed in Table 18.

Table 18: Several types of common piping corrosion


Type of corrosion

Description
A common type of corrosion which depends on the relative

Atmospheric

humidity, oxygen and salt content that occurs widely on pipes on

corrosion

deck, in bilge and ballast tanks and pipes that are exposure to rain
(Eyres 2001, 299).
A localized breakdown of the inert protective surface layer that

Pitting corrosion

protect the mild steel and stainless steel from corrosion (Murdoch
2012, 22). A prolong condition may caused the formation of
cavities on the pipes surface.
Cavitation damage caused by frictional force occurred between

Erosion

turbulent fluid flow and the pipes inner surface (Eyres 2001, 304).

Graphitic damage

Severe condition may occur when sea water flows within the pipes.
A common type of corrosion which often found at cast iron bends

46

and elbows, whereby fluid often accumulates at that area due to


different in velocities (Murdoch 2012, 25).

Table 19: Corrosion and its preventions


Type of corrosion
Atmospheric
corrosion
Pitting corrosion

Prevention
Protection by using paints
Cathodic and anodic protection

Cathodic and anodic protection


Use higher alloys for increased resistance to pitting corrosion
Reduce the occurrence of turbulent flow by using larger

Erosion

Graphitic corrosion

diameter pipes and reduce the pumping rate; to reduce the

fluid flow rate (Eyres 2001, 304).


Inspect every cast iron pipe or fittings that have a connection
to the sea during docking session (Murdoch 2012, 25).

In PSSB, the corrosion preventive method widely practiced for pipes are applying
blast cleaning, followed by pickling and lastly paint application on the pipes surfaces.
Initially all of the welded pipes will undergo blast cleaning, whereby sand is thrown into
the pipes surfaces at high velocity by using an impeller wheel plant. The purpose of
blast cleaning is to brush of any rust on the pipes surfaces. After blast cleaning, the
pipes will undergo pickling process. Pickling process is defined as an immersion process
of metallic pipes in an acid solution, such as hydrochloric acid or sulphuric acid. The
purpose of pickling process is to remove rust and millscale which are unable to be
removed by the blasting process and also to remove the excess sand from the blasting
process. Both blasting process and pickling process serve as a surface preparation for the
pipes to ensure successful painting on the pipes. The common types of paints applied on
the pipes are alkyd resin paints and oleo-resinous paints. Alkyd resin paints are paints
made from alcohols and acids which provide enhanced drying time and film forming
47

properties of drying oil. This paint is only applicable for indoor use. Oleo-resinous paints
are paints made from natural or artificial resins into drying oil protective layer, which is
applicable for any pipes exposed to weather such as main decks and wheelhouse decks
pipes and also for underwater service.

48

2.13 Week 13 (23/2/2015 25/2/2015)

For the twelfth week, the daily duties given and conducted were summarized as
shown in Table 20 below.

Table 20: Week 13 summary of duties


Date

Time

Duratio

Types of duties

n
Check the completion status for all of the drainage
9.00 am

2 hours

23/2/2015

24/2/2015
25/2/2015

2.00 pm

2 hours

8.30 am

2 hours

2.30 pm

2 hours

8.30 am

3 hours

pipelines for the grey & black water system of


YD409 BPT ship.
Check the main engines exhaust joint and
connection progress of YD409 BPT ship.
Check the misc fittings of YD409 BPT ship.
Assist supervisor in updating any outstanding tasks
for YD409 BPT ship with contractors.
Revise corrosion control and paint system
applications with assistant paint coating engineer.

As for week 13, supervisory work for the piping construction progress YD409 BPT
ship was continued, which were summarized in Section 3.2. YD408 BPT ship had been
successfully delivered to the owner on 22/2/2015. Meanwhile, YD409 BPT ship was still
under construction and was expected to be completed by early March 2015.
49

50

Chapter 3: Working Experience

In this section, the working experiences gained throughout these 12 weeks are case
studies on the piping systems in harbor tug ship, site visit on harbor tug ships
(YD408/BPT Larut and YD409/BPT Lumut), material listing for each of the piping
systems, literature studies on machines, supervisory works and problem solving.

3.1 Project Carried Out

One of the projects carried out during the 13 weeks of industrial training is
conducting case studies and analysis on the piping systems in PBBSs Bollard Pull Tug
(BPT) ships. Most of the pipeline implemented in both YD408/BPT Larut and
YD409/BPT Lumut practiced these exercises (Lloyd 2012, 11-2):
1. Welds on pipe shall be with full penetration.
2. The usage of galvanized bolts and nuts.

51

3.
4.
5.
6.

The usage of long radius elbows for curves in the pipeline.


All pumps are installed with pressure gauge, vacuum gauge and relief valve.
Corrosion inhibitor is added to the cooling system of the diesel engines.
All service tanks and non structural tanks are installed with level indicators;

meanwhile all storage tanks are installed with sensor.


7. All equipment designed to work with any type of oil shall be fitted with trays
with drains.
8. Prohibited to use any piping materials with low heat resistance (melting point
below 9250C), as it will cause outflow of flammable liquids.
9. All valves require open/shut off indicator.

52

Since there are 10 main piping systems in the BPT ships that had been explored,
simplified block diagrams were drawn based on the schematic diagrams (Appendix A)
in order to have preliminary understandings and concepts on the piping systems.

Bilge, ballast, firemain & wash deck system

Figure 2 shows the summarized schematic diagram for bilge, ballast, firemain and
wash deck piping system for below main deck area via block diagram. The bilge system
transport non/low level toxin waste fluid (bilge) within the ship into manifolds and later
discharged those bilge into the sea via overboard compartment. Manifold act as a mixer
whereby it accumulates all the bilge from different sections. Sea water strainer is used to
remove most of the sodium chloride, NaCl contain to reduce corrosion rate in the pump.
Overboard is a section where the waste water and bilge are discharged from the ship to
the sea. SDNR valves are widely used to ensure the bilge flow in one direction only.

As for the ballast system, the fresh water is used to balance the ships weight and
coordination by filling up the ballast tank. The excess water transported from the fresh
water tanks can be further used for domestic usage in the main deck area and cooling
reagent for heat exchanger for the ships engines in the below main deck area. Butterfly
valves are used to regulate low pressure fresh water flow rate. Sea water strainer is used

53

for emergency purpose, just in case sea water is used for the ballast piping system. Gate
valves are used to minimize pressure drop across the valve in fully opened condition.

The firemain system uses sea water for firefighting purpose in below main deck
area, in case for fire activities. Excess water is discharged back to the sea via overboard.
SDNR valves are used to ensure the excess sea water is flown back to the sea directly
and the fire hydrant valves are used for emergency situations where sea water is released
in the engine room to put out fire. For this bilge, ballast, firemain & wash deck system,
the pipes used are Schedule 80 hot dipped galvanized mild steel.

54

55

Figure 2: Bilge, ballast, firemain & wash deck system block diagram

56

Table 21 shows the material listing for bilge, ballast, firemain & wash deck system
based on the schematic diagram in Appendix A.
Table 21: Material listing for bilge, ballast, firemain & wash deck system
Item

Size

Gate valve (V1)


Gate valve (V2)
Gate valve (V3)
Gate valve (V4)
Gate valve (V5)
Gate valve (V6)
SNDR valve (V7)
SNDR valve (V8)
SNDR valve (V9)
Butterfly valve (V10)
Butterfly valve (V11)
Swing check valve (V12)
Swing check valve (V13)
SNDR valve (V14)
Angle screw down check
valve (V15)

Pressure

Material

Quantity

JIS

300A
50A
65A
50A
50A
25A
80A
65A
50A
300A
50A
65A
40A
50A

(bar)
10
5
5
5
5
5
5
5
5
5
5
5
5
5

Cast steel
Cast steel
Cast iron
Cast steel
Bronze
Bronze
Cast iron
Cast iron
Cast iron
Cast steel
Cast iron
Bronze
Bronze
Cast steel

1
2
3
1
4
2
1
8
6
2
9
4
2
2

F7366
F7363
F7363
F7363
F7367
F7367
F7353
F7353
F7353
F7371
F7371
F7353

300A

Cast steel

F7354

F7121

F7121

F7203

Galvanize
Sea water strainer (SW1)

300A

d mild
steel
Galvanize
d mild
steel
Galvanize
d mild
steel
Galvanize
d mild
steel
Galvanize

Sea water strainer (SW2)

65A

Mud box (M1)

65A

Strum box (SB1)

65A

Bell mouth (B1)

50A

d mild

5
5

steel
Bronze
Cast iron

6
2

Fire hydrant valve (FH)


Hand pump (P3)
Fuel oil transfer system

50A
40A

57

Figure 3 shows the summarized schematic diagram for fuel oil transfer system for
both main engines and generators via block diagram. This system transports fuel oil to
the two ships main engines and to two ships generators from two identical fuel oil
services tanks. By referring to the generator fuel oil supply line block diagram, it is
observed that the fuel oil is transported from the fuel oil services tank directly to the
generator by passing through two racor filters. The excess fuel oil is then recycled back
to the storage tank. This system applies to the second generator too. Racor filters are
installed to remove impurities contained in the fuel oil.

By referring to the main engine fuel oil supply line block diagram, fuel oil is
transported from the fuel oil services tank to manifold, then passes through mercury
filter for mercury removal then lastly to the main engine. Excess fuel oil is then recycled
back to the storage tank by passing through air separator, with the purpose of releasing
the confined vacuum pressure in the recycled fuel oil via air vent. Dirty used fuel oil is
transported to the sludge tank for disposal. Emergency fuel oil services pipeline is
installed to provide fuel oil for the main engines in case of emergency situations via
stand-by fuel pump operating at 25m3/hr @ 30m head. This cycle applies to the second
main engine too.

Several valves are used for this system, such as gate valve (to minimize pressure
drop across the valve in fully opened condition), swing check valve (to ensure the oil
flow in one direction only, back to the storage tank) and flange end ball valve (to
regulate the oil flow rate to the main engine, in-case the oil is isolated to prevent the oil
been isolated in the pipeline). Several quick closing valves are installed along the fuel oil
storage tanks pipeline to shut off the fluid transportation immediately in case of
emergency situation, especially when there is a fire breaks out. For this system, the pipes
used are Schedule 40 black and seamless mild steel pipes.

58

Figure 3: Fuel oil transfer system block diagram

59

Table 22 shows the material listing for fuel oil transfer system based on the
schematic diagram in Appendix A.
Table 22: Material listing for fuel oil transfer system
Item

Size

Gate valve (V1)

100A

Gate valve (V2)

Pressure

Material

Quantity

Cast steel

50A

Cast steel

Gate valve (V3)

50A

Bronze

Gate valve (V4)

40A

Bronze

Gate valve (V5)

25A

Bronze

SNDR valve (V6)

80A

Cast iron

SNDR valve (V7)

50A

Cast iron

Quick closing valve (V8)

50A

Cast steel

13

Spring loaded valve (V9)


Swing check valve

25A

Bronze

50A

Cast iron

25A

Bronze

20A

Bronze

50A

Cast iron

12

1
-

25A

Bronze

50A
1330

Mild steel

13

5
5
5

Bronze
Cast iron
Galvanize

2
1
1

F720

(V10)
Swing check valve (V11)
Swing check valve
(V12)
Butterfly valve (V13)
Flange end ball valve
(V14)
Bell mouth (B1)
Flat sight glass (SG1)
Kamlock (K1)
Hand pump (P2)
Duplex strainer (Y1)

mm
80A
50A
100A

(bar)

JIS
F736
3
F736
3
F736
7
F736
7
F736
7
F735
3
F735
3
F739
9
F737
2
F737
1
F737

60

d mild

steel
Galvanize
Duplex strainer (Y1)

25A

d mild

steel
Galvanize
Racor filter (Y3)

50A

d mild

F720
8

steel

61

Engine cooling system


Figure 4 shows the summarized schematic diagram for engine cooling piping
system for below main deck area via block diagram. This system cools the ships main
engines by regulating the sea water flow rate via built-in generator pump and valves into
the heat exchanger and then discharge the output hot water to the sea through the
overboard. This system also provides seawater to the air condition condensing units for
air cooling system throughout the ship via air-cond cooling pump operating at 30m 3/h @
30m head.

Sea water strainers are used to remove most of the NaCl contains and impurities in
the sea water, in order to reduce the corrosion rate in air-cond cooling pump, generators
built-in pumps and the heat exchangers. Emergency cooling system pipeline from ballast
system is installed to provide cooling system for the main engines in case of emergency
situations via gate valves.

Several valves are used such as gate valves (to minimize pressure drop across the
valve in fully opened condition), check valves (to ensure the cooled water from the airconditional cooling pump flow in one direction only, to the air condition condensing
units), butterfly valves (regulate the low pressure fresh water for air ventilation purpose)
and lastly angle SDNR valve (to ensure the hot water exit from the heat exchangers;
located in below main deck area to flow upwards to the main decks overboard in one
direction only for water discharge purpose). Shut off valves are required at the outlet and
inlet for both of the heat exchangers (Lloyd 2012, 11-35). For this system, the pipes used
are Schedule 80 galvanized mild steel pipes.

62

Figure 4: Engine cooling system block diagram

63

Table 23 shows the material listing for engine cooling system based on the
schematic diagram in Appendix A.
Table 23: Material listing for engine cooling system
Item

Size

Gate valve (V1)

200A

Gate valve (V1)

Pressure

Material

Quantity

Cast iron

100A

Cast iron

13

Gate valve (V3)

80A

Bronze

Gate valve (V4)

65A

Cast iron

Gate valve (V5)

50A

Cast iron

Gate valve (V6)

15A

Bronze

Angle SNDR valve (V7)

100A

Cast steel

Angle SNDR valve (V8)

80A

Cast steel

Angle SNDR valve (V9)

65A

Cast steel

50A

Cast steel

SDNR valve (V11)

200A

Cast iron

SDNR valve (V12)

100A

Cast iron

SDNR valve (V13)

50A

Cast iron

Butterfly valve (V14)


Butterfly valve (V14)
Butterfly valve (V16)
Sea water strainer (SW2)

200A
100A
80A
80A

5
5
5
5

Cast iron
Cast iron
Cast iron
Galvanize

2
6
1
1

Angle SNDR valve


(V10)

(bar)

d mild

JIS
F736
3
F736
3
F736
7
F736
3
F736
3
F736
7
F735
4
F735
4
F735
4
F735
4
F735
3
F735
3
F735
3
F712
1

64

steel
Galvanize
Sea water strainer (SW3)

50A

d mild
steel

F712
1

65

Domestic fresh water & sea water supply system


Figure 5 shows the summarized schematic diagram for domestic fresh water & sea
water transfer system for below main deck area via block diagram. This system
transports fresh water from the fresh water tanks and from ballast system into filing
manifolds and suction manifolds, then further transport the fresh water throughout the
whole ship for domestic activities via Pump 1 and Pump 3. Filling manifolds act as the
distribution centre, whereby fresh water supply is distributed throughout the whole ship
when in need. External fresh water supply can be transported into the ship via external
pumps, just in case of insufficient fresh water supply. Apart from fresh water, sea water
is also transported from the sea into the ship for washroom purpose via Pump 2.

Three pumps are operating for this system, a pair of identical pumps; fresh water
pump (P1) and sea water pump (P2) operating at 3.8m3/h @ 35m head and another fresh
water pump (P3) operating at 25m3/h @ 30m head. A basket strainer is used to filter out
any impurities from the fresh water supply for safe and clean consumption.

Gate valves are widely used in this system; to ensure that the fresh water does not
change its fluid flow direction and also to stop the flow completely in case the fresh
water supply is contaminated or due to emergency situations. Two SDNR valves are
used to ensure that the fresh water flowing out from the pump does not flow back to the
pump. UV light device is recommended to be installed after P1 to kill bacteria contained
in the fresh water. Since the fresh water can be transported via two directions, pumps are
required to justify the flow direction. For this system, the pipes used are Schedule 80
galvanized mild steel pipes.

66

Figure 5: Domestic fresh water & sea water supply system block diagram

67

Table 24 shows the material listing for domestic fresh water & sea water system
based on the schematic diagram in Appendix A.
Table 24: Material listing for domestic fresh water & sea water supply
Item

Size

Gate valve (V1)

65A

Gate valve (V2)

Pressure

Material

Quantity

Cast iron

50A

Cast iron

Gate valve (V3)

32A

Bronze

15

Gate valve (V4)

25A

Bronze

SDNR valve (V5)

50A

Bronze

SDNR valve (V6)

25A

Bronze

SDNR valve (V7)

15A

Cast iron

Swing check valve (V8)

32A

Bronze

(bar)

JIS
F736
3
F736
3
F737
6
F737
6
F730
9
F730
9
F735
3
F737
1

Galvanize
Bellmouth (B1)

32A

d mild

steel
Galvanize
Y strainer (Y1)

d mild

steel
Galvanize
Two way cock (FC)

d mild

F722
0

15

steel
Galvanize
Spectacle flange (S1)
Spectacle flange (S2)

32A
25A

d mild

steel
Galvanize

d mild
68

Kamlock (K1)

65A

steel
Bronze
Galvanize

Basket strainer (BS)

65A

d mild
steel

2
1

F712
1

69

Grey water & black water system


By referring to the ships grey water & black water system schematic diagram as
shown in Appendix A, the piping system is installed at both main deck and below main
deck. For the main deck area, the grey water is discharged directly to the sea through
overboard by using angle storm valve for each overboard. Angle storm valve transport
the gray water from the source area down to the main decks overboard sections. The
black water is transported to the sewage treatment plant located in the below main deck
area.

As for the below main deck area, both of the gray water and black water from the
washrooms are transported to the sewage tank via check valves for each pipeline. These
check valves are used to ensure that both of the grey water and black water do not flow
back to the washroom.

In the sewage treatment tank, the accumulated waste water in the sewage tank can
only be discharged to the sea through the below main decks overboard at least 3 nautical
miles from the nearest land, otherwise during docking cleaning session. Two check
valves are used after the sewage treatment plant, to ensure that the treated water either
flows directly to sewage tank or below main decks overboard respectively, without
flowing back to the sewage treatment plant. Several gate valves are used to ensure the
treated/waste water flows continuously to the desired location, otherwise is stopped
completely in case of emergency situations. For this system, the pipes used are Schedule
40 galvanized carbon steel pipes.

70

Table 25 shows the material listing for grey water & black water system based on
the schematic diagram in Appendix A.
Table 25: Material listing for grey water & black water system
Item

Size

Angle storm valve (V1)

100A

Angle storm valve (V2)

Pressure

Material

Quantity

Cast steel

50A

Cast steel

Gate valve (V3)

100A

Cast iron

Gate valve (V4)

50A

Cast iron

Check valve (V5)

100A

Cast iron

Check valve (V6)

0A

Cast iron

(bar)

JIS
F306
0
F306
0
F736
3
F736
3
F737
2
F737
2

Galvanize
Bellmouth (B1)

50A

d mild

steel
Galvanize
Scupper (S1)

50A

d mild
steel

71

Oily bilge & dirty oil system


Figure 6 shows the summarized schematic diagram for oily bilge & dirty oil system
for below main deck area via block diagram. The purpose of this system is to transport
oily bilge from four different locations (three from strum boxes and one from holding
tank) and dirty oil from the main engine lubricant sump tank into a sludge tank for
disposal purpose. The oily bilge will be accumulated in a manifold which later been
filtered via a simplex strainer then pump into an oily water storage and finally to the
sludge tank when the disposal process is ready. As for the dirty oil, the waste lubricant
oil from the main engines will be pumped to the sludge tank directly via semi rotary
pump. Strum box acts both filter and storage for the oily bilge.

Swing check valves are used for the oily bilge transportation to ensure that the oily
bilge flow to the manifold and oily water storage directly. Swing check valves are used
for the dirty oily transportation before the semi-rotary pump to ensure the dirty oil flow
in one direction only, which is to the semi-rotary pump and also to shut off the valve
when necessary to prevent the semi-rotary pump from overloaded with the dirty oil.

During the oil disposal process, the accumulated waste oil will be pumped out from
the sludge tank and gate valve is used to ensure that the waste oil flows continuously to
the desired location, otherwise is stopped completely in case of emergency situations.
For this system, the pipes used are Schedule 40 mild steel pipes.

72

Figure 6: Oily bilge & dirty oil system block diagram

73

Table 26 shows the material listing for oily bilge & dirty oil system based on the
schematic diagram in Appendix A.
Table 26: Material listing for oily bilge & dirty oil system
Item

Size

Gate valve (V1)

40A

Gate valve (V2)

Pressure

Material

Quantity

Bronze

25A

Bronze

Swing check valve (V3)

40A

Bronze

SDNR valve (V4)

25A

Bronze

12

(bar)

Galvanize
Simplex strainer (S1)

40A

d mild

steel
Galvanize
Simplex strainer (S2)

25A

d mild

steel
Galvanize
Strum box (SB1)

25A

d mild

JIS
F736
7
F736
7
F737
1
F735
1
F720
9
F720
9

steel
Galvanize
Bellmouth (B1)

25A

d mild
steel
Galvanize

Bellmouth (B2)

40A

d mild

Hand pump (P3 & P4)

40A

steel
Cast iron

74

Oil dispersant system


By referring to the ships oil dispersant system schematic diagram as shown in
Appendix A, this system transport fuel oil from the dispersant tank (located at below
main deck area) to the dispersant boom (located at main deck area) via detergent pump
operating at 50m3/hr @ 30m head for cleaning the ships body from discharged waste
fluid and bilge. The transported fuel passes through SDNR valve and swing check valve.
These valves are installed to ensure that the oil flow directly to the desired locations. Sea
water is also transported into the detergent pump for cleaning purpose. For this system,
the pipes used are Schedule 40 galvanized seamless carbon steel pipes.

Table 27 shows the material listing for oil dispersant system based on the schematic
diagram in Appendix A.
Table 27: Material listing for oil dispersant system
Item

Size

Gate valve (V1)

65A

SNDR valve (V2)

Pressure

Material

Quantity

Cast iron

65A

Cast iron

Swing check valve (V3)

65A

Cast iron

Butterfly valve (V4)


Angle valve (V5)

300A
300A

5
5

Cast iron
Cast iron
Galvanize

2
2

Sea water strainer (SW1)

65A

d mild

(bar)

steel
Galvanize
Simplex strainer (S1)

300A

d mild
steel

JIS
F736
3
F735
3
F737
2
F712
1
F712
1

75

Lube oil system


Figure 7 shows the summarized schematic diagram for lube oil system for below
main deck area via block diagram. This system transport lubricant oil from sump tank to
the main engines, while undergoing filtering process; to ensure the lubricant oil is clean
and free from unwanted particles. The excess lubricant oil from the main engines will be
recycled back to the sump tank. Check valves are used in this system to ensure that the
lubricant oil flow directly to the desired location without flowing back to the origin. A
relief valve is installed for each main engine; to regulate lubricant oil flow rate at a
required pressure so that the lubricant oil filters and main engines are not destroyed due
to excess pressure. The pipes used are Schedule 40 black seamless carbon steel pipes.

Table 28 shows the material listing for lube oil system based on the schematic
diagram in Appendix A.
Table 28: Material listing for lube oil system
Item

Size

SNDR valve (V1)

100A

SNDR valve (V2)


SNDR valve (V3)

Pressure

Material

Quantity

Cast iron

125A

Cast iron

80A

Cast iron

(bar)

Stainless

Ball valve (V4)

15A

Gate valve (V5)

80A

Cast iron

Gate valve (V6)

100A

Cast iron

Gate valve (V7)

15A

Bronze

Relief valve

80A

Cast iron

steel

JIS
F735
3
F735
3
F735
3
F736
3
F736
3
F736
7
-

76

Figur
e 7: Lube oil piping system block diagram

77

External fire fighting system


By referring to the ships external fire fighting system schematic diagram as shown
in Appendix A, this system transports foam from storage tank to water spray system in
both main deck and wheelhouse deck via fire fighting pump operated at 1500m 3/hr @
115m head. Additional two pipelines are installed to transport foam to two fire monitors
located at the wheelhouse deck to put out fire on other ships as well as the burning/fire
areas. The difference between this system and firemain system is that external fire
fighting system puts out fire externally, whilst firemain system puts out fire internally.
Butterfly valves regulate the low pressure foam to the fire monitors at wheelhouse deck.
A SDNR valve is used to discharge the excess foam to the sea directly. Several gate
valves are used to provide on-off service for the entire external firefighting system. For
this system, the pipes used are Schedule 40 galvanized mild steel pipes. Table 29 below
shows the material listing for external fire fighting system based on the schematic
diagram in Appendix A.
Table 29: Material listing for external fire fighting system
Item

Size

Gate valve (V1)

100A

Gate valve (V2)

Pressure

Material

Quantity

10

Cast steel

65A

10

Cast iron

Gate valve (V3)

50A

16

Cast iron

Gate valve (V4)

40A

16

Cast iron

SDNR valve (V5)

50A

16

Cast iron

Butterfly valve (V6)


Butterfly valve (V7)
P/V valve (V8)

350A
250A
65A

10
16
16

1
2
1

Reducer (R1)

150/250A

Reducer (R1)

100/150A

Cast iron
Cast iron
Cast iron
Galvanize
d mild
steel
Galvanize
d mild

7
-

(bar)

JIS
F736
6
F736
4
F736
9
F736
9
F737

78

Reducer (R1)

50/150A

Reducer (R1)

65/100A

steel
Galvanize
d mild
steel
Galvanize
d mild
steel

CO2 fire fighting system


By referring to the CO 2 fire fighting system schematic diagram as shown in
Appendix A, this system transports CO2 from the CO2 storage room located at the main
deck to the main engines area, located at below main deck. The transported CO 2 is later
further distributed to 12 different locations. To control this system, a manual operated
ball valve is required, whereby the ball valve is installed along the CO 2 rooms pipeline
which transports CO2 to the 12 locations at below main deck area when fire breaks out.
The pipes from the ball valve to CO2 nozzles (12 distribution locations) are to be welded.
For this system, the pipes used are Schedule 40 galvanized mild steel pipes.

Table 30 shows the material listing for CO 2 fire fighting system based on the
schematic diagram in Appendix A.
Table 30: Material listing for CO2 fire fighting system
Pressure

Item

Size

Ball valve

10A

(bar)
5

Reducer (R1)

110/185A

Material

Quantity

JIS

Cast iron
Galvanize

d mild

steel
Galvanize
Reducer (R2)

110/135A

d mild
steel
Galvanize

Reducer (R3)
Reducer (R4)

110/130A
130/140A

d mild

steel
Galvanize

79

d mild
steel
Galvanize
Reducer (R5)

130/155A

d mild

steel
Galvanize
Reducer (R6)

155/185A

d mild
steel
Galvanize

Reducer (R7)

155/170A

d mild
steel

80

3.2 Supervisory work

Table 31 below shows the supervisory work for the BPT ships' piping
construction progress as per assigned by supervisor throughout these 13 training weeks.
Table 31: Supervisory work for the BPT ships' piping construction progress
Training

Date

YD408 progress

YD409 progress

week

22/12/2014

Installed copper tubing

Installed water sprays

for washrooms for

at both main deck and

both main deck and

wheelhouse deck.
Installed mast water

below main deck.


Installed tubing

sprays

solenoid valve for


fresh water supply to

23/12/2014

24/12/2014

29/12/2014

5/1/2015

Started piping

piping alignment.

alignment for fuel oil

Installed fire monitors

system.
Installed sight glass

Installed water spray

for fuel oil service

tanks.
Completed the

nozzles for external

installation for fuel oil

fire fighting system.


Main engines piping

service tanks tray.


Major piping welding

alignment in progress.

31/12/2014

on wheelhouse deck.

wiper
Started main engines

and alignment for


main engines

Installation for the


main engines

generators
Started the installation
for the main engines

81

generators (genset)

exhaust in progress.
No air tests been

exhaust
Conducted air test for

planned or conducted.

6/1/2015

both bilge and


firemain systems,

7/1/2015

generators (genset)

Installed silencer drain

and exhaust drain for

drain and exhaust

gensets exhaust.
Started the main

pipelines for gensets

engines exhaust

pipeline connection.

8/1/2015

9/1/2015

Major changes

13/1/2015

exhaust.
Completed air test for
fresh water & sea

water system.
Completed fuel oil

implemented for the

supply pipeline and

starboard side main

return pipeline from

engines exhaust

fuel oil tank to main

system due to leakage.

engines generators

Modification for

(and vice versa).


Installed gensets air

starboard side main

breather pipeline to

engines exhaust in

the exhaust funnel.

progress.
Completed the main

engines fresh water


12/1/2015

except ballast system.


Installed both silencer

supply connection.
Conducted air test for

Installed pressure
gauges for main

engines.
Conducted air test for

main engines cooling

main engines cooling

and fuel oil systems.


Main engines piping

and fuel oil systems.


Installed gensets

alignment in progress.
Preparation for

exhaust drain and

scuppers installation.

expansion joint.

support for gensets

82


14/1/2015

CO2 fire fighting

engines engine

systems piping

cooling piping

installation in

alignment.
Scuppers and main

progress.
Scuppers installation

engines exhaust

15/1/2015

16/1/2015

Completed main

in progress.

installation in

progress.
Completed scuppers

installation.
Completed all of the

Completed scuppers
installation.

main engines piping

17/1/2015

21/1/2015

connection
Completed fuel oil

Completed fresh

supply to main

water supply to galley

engines.
Completed fuel oil

sink, oily water

return pipeline from

tank and engine room.

main engines to tanks.


Completed fuel oil

piping alignment.
Completed main

engines exhaust joint.


Completed the

separator, expansion

Completed the fuel oil

pipeline for leaked oil

piping connection

from both main

from the tank to both

engines and generators

cargo and filling.


Installed fuel oil

to the sludge tank.


Completed main

service tank overflow

engines compressed

pipeline back to the

air and lube oil

tank.

pipeline
22/1/2015

None, due to Long

Installed main
83

23/1/2015

Range Identification

engines turbo charger

and Tacking (LRIT)

and expansion joint,

test been conducted

whereas the

for 18 hours

connection is still

continuously.
Conducted air tests for

pending.
Major piping welding,

fresh water & sea

grinding and

water and oily bilge &

alignment for the

dirty oil systems.


Major piping

compressed air
system.

alignment for the


compressed air

24/1/2015

system.
Completed oil

Completed oil

dispersant, hydraulic

dispersant piping

and compressed air

system.
58 outstanding tasks

piping systems.
Completed all of the

outstanding tasks.
Conducted minor

27/1/2015

remaining.

Started copper tubing

piping adjustment for

installation for air

engine cooling system.

supply to both control


panel and main

28/1/2015

Conducted minor

engines.
Completed all of the

piping adjustment for

compressed air supply

chain wash pipeline of

piping connection,

firemain system at

except main engines

main deck.

and control panel (to


be completed by

30/1/2015

Conducted minor
piping adjustment for

yards foremen).
Completed CO2 fire
fighting piping
84

the rexpeller cooling

system.
None

system.

Ongoing compressed
air pipeline

31/1/2015

installation to both
main engines and

10

2/2/2015

Completed all of the

control panel.
Completed

minor outstanding

compressed air piping

tasks as per conducted

installation.
Ongoing main

on training week 9.

engines lube oil

4/2/2015

Tighten the butterfly

piping connection.
Reinstalled back the

valve along the

main engines exhaust

pipeline of the main

expansion joint after

engines standby

cleanliness inspection

cooling pump.

by the Daihatsus

engineers.
Completed engine
cooling piping system

5/2/2015

6/2/2015

Assisted in doing the

installation.
Assisted in doing

minor modification for

minor modification

the ships soundings.

for the ships

Completed the

soundings.
Ongoing modification

modification of the

of the ships

ships soundings

soundings.
Completed all of the
firemain systems
outstanding piping
tasks.

85

Completed main
engines air vent
connection and sea
water supply

None

connection to pump.
Completed the ships
soundings

modification.
Completed the suction
and discharge pipeline

7/2/2015

of external fire
fighting system and
bilges hand pump

11

None

installation
Completed all of the
lube oil system
pipeline connection

9/2/2015

and welding.
Completed all of the
decks penetrations
and Marpol

Started the external

firefightings pump
piping modification.
10/2/2015

connection tasks.
Started the external
firefightings pump

piping modification.
Ongoing main
engines fuel oil
piping connection and

11/2/2015
12/2/2015

Ongoing external

alignment.
Ongoing external

firefightings pump

firefightings pump

piping modification.
Partially completed the

piping modification.
Partially completed

86

firefightings pump

the firefightings

piping modification.
Completed the minor

pump piping

piping modification

modification.
Ongoing main

for fresh water

engines fuel oil

pipeline.

piping connection and

None

alignment.
Conducted and

completed chain wash


13/2/2015

pipeline relocation of
firemain system at

14/2/2015

Completed the

main deck.
Completed the

firefightings pump

firefightings pump

piping modification.

piping modification.
Conducted air test for

oily bilge & dirty oil

None

system
Conducted and
completed the minor

16/2/2015

piping modification
for fresh water

None

12

pipeline.
Completed the main
engines fuel oil

17/2/2015

piping alignment and


connection.

13

None

Completed all of the

18/2/2015

hydraulic system

23/2/2015

piping connection.
Completed two out of

None

three of the grey &

87

black water systems


drainage, except for
washing machine and

dryer hose.
Completed main
engines exhaust joint

None

and connection.
Completed all of the
misc fittings (vacuum
relief valve, valve
cover, orifice and

water spray nozzles).


Completed the
pipeline installation
from the main engine
lubricant oil sump
tank to hand pump

24/2/2015

and sludge tank and


suction from every
compartment in the

engine room.
Installed pipeline
from sewage
treatment plant to
sewage tank and
terminate sewage
treatment plant air

vent through funnel.


On 2/1/2015, 9.30 am, a Germanisher Lloyd (GL) representative Mr. Gan Chee
Kian came to check the overboard position and construction progress for YD408 BPT
ship. To assist the GLs representative, overboards schematic diagram and information
such as size, valve used, location and the height from the draft water level (DWL) were
required. An outfitting engineer, Mr. Aung Zin Myat assisted throughout the session as
88

Ms. Elizacorina was attending the company meeting regarding the BPT ships
construction progress. During the supervisory progress, Mr. Gan asked three questions
regarding the overboard such as the function of the valves used associated with the
overboard location, the overboard construction progress and the purpose of the
overboard associated with the piping systems. The checking progress went smoothly and
Mr. Gan was satisfied with the overboard construction progress.

On 19/1/2015, 1.30 pm, two Daihatsu engineers came to check on the cleanliness of
YD408 both main engines exhaust. In order to assist the surveyors, four foremen were
assigned to detach the expansion joint; where two foremen are assigned for each main
engine respectively. After detached the expansion joint for both main engines, one of the
engineers went to do the checking. As the result, he was not satisfied with the port side
main engines exhaust cleanliness as it was very dirty, whereby dirt and grease were
found within the exhaust pipeline as shown in Figure 8.

Figure 8: Exhaust pipeline for port side


Meanwhile, he was quite satisfied with the starboard side main engines exhaust
cleanliness, as it was cleaner compared to the port side, although there was few welding
and grinding waste found as shown in Figure 9.

89

Figure 9: Exhaust pipeline for starboard side

In conclusion, both of the main engines exhaust had to be cleaned before the
second inspection, which was on the next following day (20/1/2015). On 20/1/2015, the
second exhaust cleanliness inspection was carried out for both of the main engines and
the engineers were satisfied with the result. Thus, the expansion joints were flanged back
to the origin at 2.30pm leading completion work at 4.00 pm.

90

Table 32 below shows the summary of the construction progress for both YD408
and YD409 BPT ships throughout these 13 training weeks. A tick symbol and date
indicated the completion status for the respective outstanding tasks throughout the 13
training weeks. Whilst, the tick symbol without date indicated that the outstanding tasks
had completed before the industrial training. Empty entry indicates the outstanding tasks
were not completed throughout the 13 training weeks.
Table 32: Summary of the construction progress for both ships
System

Outstanding tasks
Install fire hydrant valve in

engine room
Install hydraulic power pack
cooling to overboard

Firemain

Install fire hydrant at main deck

Add gate valve for sewage tank


for sea water supply

Engine

Conduct air test

Minor piping adjustment for

chain wash pipeline

Bilge

YD408 / Date

(28/1/2015)

Install hand pump at main deck

Repair pipe above manhole


Conduct air test & hydrostatic

test
Main engines generators

cooling pipe
Main engines air vent

cooling

connection

Main engines fresh water

supply connection
Cooling system for rexpeller

YD409 / Date

(6/2/2015)

(6/2/2015)

(6/2/2015)

(6/2/2015)

(6/1/2015)

(13/2/2015)

(7/2/2015)

(6/1/2015)

(16/1/2015)

(6/2/2015)

(12/1/2015)

(4/2/2015)

(4/2/2015)
91

Sea water supply to pump

Install fresh water tanks drains

and sight glass


Install water strainer
Main engines cooling system

(6/2/2015)

connection
Cooling and overboard for

(16/1/2015)

(4/2/2015)

(16/1/2015)

external fire fighting pump


Install pressure gauges for main

(14/2/2015)

engines

Fuel oil

Conduct air test

Minor piping adjustment for

main engine cooling system.


Minor piping adjustment for the

(2/2/2015)

(2/2/2015)

rexpeller cooling system.


Piping connection from the tank
to both cargo and filling

Install tray for fuel oil service


tank

Install fuel oil service tank


overflow pipe back to the tank

(12/1/2015)

Install sight glass for fuel oil


service tank

(12/1/2015)

(12/1/2015)

(21/1/2015)

(29/12/2014
)

(21/1/2015)

(24/12/2014

Fuel oil supply for both main

engines and pump


Fuel oil return from both main

(17/1/2015)

(17/2/2015)

(17/1/2015)

(17/2/2015)

engines and generators


Leaked oil from both main

(21/1/2015)

(17/2/2015)

engines and generators to the

sludge tank
Fuel oil supply pipeline from

92

fuel oil tank to racor filters and

oil tank
Conduct air test, acid cleaning

(12/1/2015)

& flushing
Fresh water, sea water and hot

(12/1/2015)

water supply for washroom at

(22/12/2014

main deck and below main deck


Fresh water supply to main

engines expansion tank


Fresh water supply to engine

room for general services


Fresh water supply to oily water

separator unit
Fresh water supply to sink at

galley
Fresh water supply to washing
machine

Fresh water supply to wiper


along with solenoid valve

Install vacuum relief valve for


water supply to water heater

Grey water

Conduct air test & hydro test

Minor piping modification on

one of the pipelines.


Install grey water pipeline for

washrooms
Install hose/drain for washing

machine and dryer to overboard


Install pipeline from sewage

& black
water

main engines generators to fuel

Fresh water
& sea water

(7/1/2015)

main engines generators


Fuel oil return pipeline from

treatment plant to sewage tank

(7/1/2015)

(17/1/2015)

(17/1/2015)

(17/1/2015)

(17/1/2015)

(22/12/2014
)

(24/2/2015)

(23/1/2015)

(7/1/2015)

(12/2/2015)

(16/2/2015)

(24/2/2015)
93

Close the grey water inlet


flanged connection in the
sewage treatment plant because

the connection is not in used


Terminate sewage treatment

plant air vent through funnel


Install drainage pipeline from

galley/kitchen to overboard
Install and connect the Marpol

connection
Install drainage pipeline from

air handling unit to overboard


Conduct air & flow test
Install pipeline from the oily
water separator to bilge holding

Oily bilge

tank
Install and connect the Marpol

connection
Install pipeline from the main
engine lubricant oil sump tank

& dirty oil

to hand pump and sludge tank


Suction from every
compartment in the engine

room

Oil

Conduct air test

Main deck connection to spray

booms
Repair pipeline in the engine

dispersant

Lube oil

room

(24/2/2015)

(23/2/2015)

(9/2/2015)

(23/2/2015)

(24/2/2015)

(9/2/2015)

(24/2/2015)

(24/2/2015)

(23/1/2015)

(14/2/2015)

(24/1/2015)

(24/1/2015)

(24/1/2015)

Conduct air test

Terminate mist gas through

(24/1/2015)

exhaust funnel
Weld the pipeline from lube oil

(21/1/2015)

(9/2/2015)

94

(9/2/2015)

after filter and recycled pipeline


Final connection to main

(21/1/2015)

(9/2/2015)

engines
Conduct air test & flushing
Suction and discharge pipeline

(21/1/2015)

(9/2/2015)

in engine room.
Install valve cover for fire

fighting 4 way deck head


Install water sprays for both

storage tank to hand pump


Repair lube oil pipe pipeline

main deck and wheelhouse

Install mast water sprays

(24/2/2015)

(22/12/2014
)

deck

(7/2/2015)

(22/12/2014
)

External
fire fighting

Install fire monitors

(24/12/2014
)

Install orifice meter for all of


the water sprays

Install nozzle for each of every


water sprays

Conduct air test


Minor piping modification for
external fire fighting systems

CO2 fire
fighting

pump.
Install pipe distribution from

CO2 manifold
Install relief valve within the

Compressed
air

pipeline inside the CO2 room


Conduct air test
Air supply from air reservoir to
main engines

(29/12/2014
)

(14/2/2015)

(24/2/2015)

(24/2/2015)

(14/2/2015)

(14/2/2015)

(30/1/2015)

(30/1/2015)

(21/1/2015)

(2/2/2015)

95

Air supply from air reservoir to

control panel
Air supply from air reservoir to

(21/1/2015)

(2/2/2015)

bilge, ballast & firemain system


Air supply from air reservoir to

(21/1/2015)

(28/1/2015)

(24/1/2015)

towing hook
Air supply from air reservoir to

(28/1/2015)

horn
Air supply from air reservoir to

(28/1/2015)

oily water separator


Air supply from air reservoir to

(24/1/2015)

(28/1/2015)

fresh water & sea water tanks

(21/1/2015)

(28/1/2015)

Air supply from air reservoir to

sea chest air blow


Air supply from air reservoir to
general service & fire fighting

pneumatic valve
Conduct air test
Complete main engines
exhaust pipeline connection

Exhaust

Install gensets exhaust pipeline

Connect gensets air breather to

exhaust funnel
Install silencer drain for both
main engines & genset

Hydraulic

Install gensets expansion joint

Install gensets exhaust drain

Pipeline connection from power


pack manifold block &

windlass
Pipeline connection from power

(28/1/2015)

(21/1/2015)

(28/1/2015)

(17/1/2015)

(23/2/2015)

(7/1/2015)

(7/1/2015)

(9/1/2015)

(7/1/2015)

(13/1/2015)

(7/1/2015)

(13/1/2015)

(24/1/2015)

(18/2/2015)

96

pack to capstan & local panel


Pipeline connection from power

pack to rexpeller
Conduct air test & flushing

Install camlock for filling

Install air vent for sea chest


strainer

Tank, vent,
sounding
(Decks
penetration)

Install filling & air vent from


storage tanks to main deck

Relocate ballast tanks air vent

Install trays for all oil air vent

& filling
Minor modification for the
soundings

Scuppers

Install scuppers on main deck

(18/2/2015)

(18/2/2015)

(9/2/2015)

(9/2/2015)

(9/2/2015)

(9/2/2015)

(9/2/2015)

(6/2/2015)

(7/2/2015)

(16/1/2015)

(16/1/2015)

97

3.3 Problem encountered and solving experiences

On 2.00pm, 9/1/2015, a problem encountered on the main engines left


side/starboard, whereby the drainage system for the condensed exhaust vapour was
unable to be installed along the 900 mild steel elbow as shown in Figure 10 below.
Without the drainage system, the condensed exhaust vapour will flow back into the main
engine, causing severe damages on the main engine.

98

Figure 10: Exhaust problem encountered


To solve this problem, a discussion was made between project engineer, yard
manager, supervisor and contractors at 3.00pm on 9/1/2015. Several ideas were given
out and explained in details; however the chosen idea was to install a mild steel box
between the 900elbow. This mild steel box allowed the installation of the drainage
system for the main engines exhaust. Therefore, the first conceptual design was drawn
as shown in Figure 11.

Figure 11: Initial design for the new exhaust arrangement

99

However, another problem was encountered on 12/1/2015 after conducted some


tests on the prototype. From Figure 11, it was observed that a large amount exhaust
vapour/gas emitted from the main engine tended to accumulate at the edge of the mild
steel box, which will cause damages on the main engine when the exhaust condensed
exhaust vapour/gas condensed flow into the main engines turbo charger. In order to
solve this problem, the exhausts design was revised by reducing the length and edges of
the box mild steel box as shown in Figure 12. With the revised drawing, it was
observed, lesser exhaust vapour/gas was accumulated at the edge of the mild steel box
when conducting testing on a prototype. The revised drawing was handed over to the
contractors on 14/1/2015 and the exhaust installation was completed on 17/1/2015.
These changes were implemented on YD409 ships starboard side exhaust system too.

Figure 12: Final design for the new exhaust arrangement

100

Chapter 4: Conclusion

In conclusion, these 13 training weeks mainly focused on the piping systems of


two bollard pull tug ships. Many types of piping systems activities had been conducted
and the activities conducted were literatures studies on piping systems, site visit on
piping systems, assisted supervisor, contractors and yards foremen in hands on the pipes
and fittings, conducted material listing for each of the piping systems, assisted engineers
and Germanisher Lloyd (GL) representative in doing inspection and last but not least
interact with other engineers on solving tasks given by supervisor or any problems
encountered throughout these 13 training weeks. Among of the activities, the major work
performed was checking and updating the piping construction, alignment and connection
progresses for the bollard pull tug ships.

Since there six objectives set for this industrial training, all of the 6 objectives were
achieved. A part of the engineering knowledge learnt in classroom was applied in
throughout this industrial training, which is the application of fluid mechanics
knowledge. Besides, professional engineering practices in the industries were been
exposed too, such as wearing Personal Protection Equipment (PPE) when working on
site. Furthermore, the role and responsibilities as well as code of ethics those engineers
should uphold are practiced too, in such way that piping engineers should be alert and
involve in solving any piping problem encountered efficiently. Apart from that, general
workplace and interpersonal skills were developed such as wearing PPE interact with
others when working on site. Despite that, all piping construction progresses were
recorded and tabulated neatly as a part of the industrial training objective. Lastly, rapport
and network with future employers were built by interacting with them in solving
problems encountered together as well as gaining additional knowledge (other than
piping) with other engineers. As for recommendation, relevant software should be
provided to enhance the understanding of the piping systems and its applications.

101

Reference Lists
Eyres, D. J. 2001. Ship Construction. 5th ed. Great Britain: Butterworth Heinemann.
Lloyd, Germanischer. 2012. Rules for Classification and Construction: Ship
Technology. Hamburg: Germanishcer Lloyd SE.
Murdich, Eric. 2012. A Masters Guide to Ships Piping. 2nd ed. London: The
Standard P&I Club.
Najin Corp. n.d. Marin Valves. 1st ed. Korea: Najin Corp.
Sanguri, Mohit. 2012. The Basics of Pipes and Bends on Ships. Mumbai: Marine
Insight.
Shin Yang. 2013. Piasau Slipways Sdn. Bhd.
http://www.syshippingcorp.com.my/index.php/corporate/ship-building/aboutshipyard
Shin Yang. 2013. Vision & Mission.
http://www.syshippingcorp.com.my/index.php/corporate/vision-mission
Sun Korea. 2005. Valves and Fittings Handbook. Busan: Sun Korea Co., LTD.
Vuthaluru, Rupa (2014). Lecture 6: Valves. PowerPoint Lecture notes.

102

Appendix

Appendix A: Schematic diagrams of


piping systems in a BPT ship

103

Potrebbero piacerti anche