HV BREAKER:
CONTACT RESISTANCE TEST:
HV Breaker comprises three units such as Incomer,
Transformer and outgoing feeders. Each of these units must be
subject to contact resistance prior to High Volt test.
The following procedures must follow for all three phases
1. Incomer to Ground
The above sequence carried out by making earth
switch ON in Incomer breaker and then conduct the Contact
resistance test by applying 100Amps to R phase to ground, Y
phase to ground and B phase to ground.
2. Outgoing to Ground
The above sequence carried out by making
earth switch ON in Outgoing breaker and then conduct the
Contact resistance test by applying 100Amps to R phase to
ground, Y phase to ground and B phase to ground.
3. Transformer unit or Fuse unit to ground.
The above sequence carried out by making
earth switch ON in Fuse unit breaker and then conduct the
Contact resistance test by applying 100Amps to R phase to
ground, Y phase to ground and B phase to ground.
4. Transformer unit (Fuse unit) to Incomer unit.
For the above sequence test, we need to ON
the breaker of Transformer unit and Incomer unit. Regarding fuse
unit we need dummy fuse to conduct the test. The dummy fuse
RatedVolta ge 2
HV Test at
The above High Volt must inject for 1 minute and it should
withstand. Record the leakage current at the time of injection.
FUNCTIONAL CHECKS:
The following Mechanical interlocks must be tested
A- OPENING/ CLOSING SWITCH DISCONNECTORS
B- OPENING/ CLOSING TRANSFORMER TEE ON
C- OPENING/ CLOSING EARTH SWITCH OF
TRANSFORMER TEE
D- OPENING/ CLOSING FOR SWITCH
DISCONNECTORS
E- CIRCUIT BREAKER EARTH SWITCH INTERLOCK