Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
contacts. The rotational movement of male contact causes to come itself into female contacts and
isolators becomes closed. The rotation of male contact in opposite direction make to it out from
female contacts and isolators becomes open. Rotation of the central post insulator is done by a
driving lever mechanism at the base of the post insulator and it connected to operating handle (in
case of hand operation) or motor (in case of motorized operation) of the isolator through a
mechanical tie rod.
Earthing Switches
Earthing switches are mounted on the base of mainly line side isolator. Earthing switches are
normally vertically break switches. Earthing arms (contact arm of earthing switch) are normally
aligned horizontally at off condition. during switching on operation, these earthing arms rotate and
move to vertical position and make contact with earth female contacts fitted at the top of the post
insulator stack of isolator at its outgoing side. The erarthing arms are so interlocked with main
isolator moving contacts that it can be closed only when the main contacts of isolator are in open
position. Similarly the main isolator contacts can be closed only when the earthing arms are in open
position.
Substation Layout
in the figure. By closing any of the breakers and its associated isolators, one can put the feeder to
respective bus. Both of the buses are energized and total feeders are divided into two groups, one
group is fed from one bus and other from other bus similar to previous case. But any feeder at any
time can be transferred from one bus to other. There is no need of bus coupler as because the
operation is done by breakers instead of isolator. For transfer operation, one should first close the
isolators and then the breaker associated with the bus to where the feeder would be transferred
and then he or she opens the breaker and then isolators associated with the bus from where feeder
is transferred.
Switching operation for transferring a feeder to transfer bus from main bus
without interruption of power
(i) First close the isolators at both side of the bus coupler breaker.
(ii) Then close the bypass isolator of the feeder which is to be transferred to transfer bus.
(iii) Now energized the transfer bus by closing the bus coupler circuit breaker from remote.
(iv) After bus coupler breaker is closed, now the power from main bus flows to the feeder line
through its main breaker as well as bus coupler breaker via transfer bus.
(v) Now if main breaker of the feeder is switched off, total power flow will instantaneously shift to
the bus coupler breaker and hence this breaker will serve the purpose of protection for the feeder.
(vi) At last the operating personnel open the isolators at both sides of the main circuit breaker to
make it isolated from rest of the live system.
So it can be concluded that in Main & Transfer Bus System the maintenance of circuit breaker is
possible without any interruption of power. Because of this advantage the scheme is very popular
for 33KV and 13KV system.
Electrical Substation
Electrical Substation
Now days the electrical power demand is increasing very rapidly. For fulfilling these huge power
demands the modern time requires creation of bigger and bigger power generating stations. These
power generating stations may be hydro electric, thermal or atomic. Depending upon the
availability of resources these stations are constructed different places. These places may not be
nearer to load centers where the actual consumption of power takes place. So it is necessary to
transmit these huge power blocks from generating station to their load centers. Long and high
voltage transmission networks are needed for this purpose. Power is generated comparatively in
low voltage level. It is economical to transmit power at high voltage level. Distribution of electrical
power is done at lower voltage levels as specified by consumers. For maintaining these voltage
levels and for providing greater stability a number of transformation and switching stations have to
be created in between generating station and consumer ends. These transformation and switching
stations are generally known as electrical substations. Depending upon the purposes, the
substations may be classified as
Step up Substation
Step up substations are associated with generating stations. Generation of power is limited to low
voltage levels due to limitations of the rotating alternators. These generating voltages must be
stepped up for economical transmission of power over long distance. So there must be a step up
substation associated with generating station.
Distribution Substation
Distribution Substation are situated where the primary distribution voltages are stepped down to
supply voltages for feeding the actual consumers through a distribution network.
Mining Substation
The mining substation are very special type of substation and they need special design construction
because of extra precautions for safety needed in the operation of electric supply.
Mobile Substation
The mobile Substations are also very special purpose sub station temporarily required for
construction purpose. For big construction purpose this Substation fulfils the temporary power
requirement during construction work.
Depending upon the constructional feature categories of sub station may be divided into
following manner
Indoor Substation
The substations are constructed under roof is called indoor type substation. Generally 11KV and
sometime 33KV substation are of this type.
Underground Substation
The substation are situated at underground is called underground substation. In congested places
where place for constructing distribution substation is difficult to find out, one can go for
underground sub station scheme.
a. Merits
1. Low Cost
2. Simple to Operate
3. Simple Protection
b. Demerits
1. Fault of bus or any circuit breaker results in shut down of entire substation.
2. Difficult to do any maintenance.
3. Bus cannot be extended without completely deenergizing substations.
c. Remarks
1. Used for distribution substations up to 33kV.
2. Not used for large substations.
3. Sectionalizing increases flexibility.
a. Merits
1. Low initial & ultimate cost
2. Any breaker can be taken out of service for maintenance.
3. Potential devices may be used on the main bus.
b. Demerits
1. Requires one extra breaker coupler.
2. Switching is somewhat complex when maintaining a breaker.
3. Fault of bus or any circuit breaker results in shutdown of entire substation.
c. Remarks
1. Used for 110kV substations where cost of duplicate bus bar system is not justified.
a. Merits
1. High flexibility
2. Half of the feeders connected to each bus
b. Demerits
1. Extra bus-coupler circuit breaker necessary.
2. Bus protection scheme may cause loss of substation when it operates.
3. High exposure to bus fault.
4. Line breaker failure takes all circuits connected to the bus out of service.
5. Bus couplers failure takes entire substation out of service.
c. Remarks
Most widely used for 66kV, 132kv, 220kV and important 11kv, 6.6kV, 3.3kV
Substations.
a. Merits
1. Each has two associated breakers
2. Has flexibility in permitting feeder circuits to be connected to any bus
3. Any breaker can be taken out of service for maintenance.
4. High reliability
b. Demerits
1. Most expensive
2. Would lose half of the circuits for breaker fault if circuits are not connected to
both the buses.
c. Remarks
1. Not used for usual EHV substations due to high cost.
2. Used only for very important, high power, EHV substations.
a. Merits
1. Most flexible in operation
2. Highly reliable
3. Breaker failure on bus side breaker removes only one ckt. From service
4. All switching done with breakers
5. Simple operation, no isolator switching required
6. Either main bus can be taken out of service at any time for maintenance.
7. Bus fault does not remove any feeder from the service
b. Demerits
1. High cost due to three buses
c. Remarks
1. Preferred by some utilities for 400kV and 220kV important substations.