Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
(NSF ISSUES)
4/27/2015
Outline
Pile Design using EC7
Problems with BS 8004, CP4, and EC7 on dragload
Design example of dragload using EC7
Unified pile design concept
4/27/2015
4/27/2015
4/27/2015
4/27/2015
The results of static load tests, which have been demonstrated, by means
of calculations or otherwise, to be consistent with other relevant experience;
Empirical or analytical calculation methods whose validity has been
demonstrated by static load tests in comparable situations;
The results of dynamic load tests (PDA and CAPWAP) whose validity has
been demonstrated by static load tests in comparable situations;
The observed performance of a comparable pile foundation, provided that
this approach is supported by the results of site investigation and ground
testing
Other methods
Dynamic impact tests (7.6.2.4); Pile driving formulae (7.6.2.5); wave equation
analysis (7.6.2.6); Re-driving (7.6.2.7)
4/27/2015
4/27/2015
4/27/2015
10
Min
;
3
4
Rc;cal
10
1.55
1.47
1.42
1.38
1.36
1.33
1.30
1.55
1.39
1.33
1.29
1.26
1.20
1.15
4/27/2015
11
4/27/2015
12
13
4/27/2015
14
Outline
Pile Design using EC7
Problems with BS 8004, EC7, and CP4 on dragload
Design example of dragload using EC7
Unified pile design concept
4/27/2015
15
4/27/2015
16
17
4/27/2015
18
General
Basic of geotechnical design
Geotechnical data
Supervision of construction, monitoring and maintenance
Fill, dewatering, ground improvement and reinforcement
Spread Foundations
Pile Foundations
Anchorages
Retaining Structures
Hydraulic failure
Overall stability
Embankments
19
20
4/27/2015
21
EC7 on Dragload
7.6.2.2 Ultimate compressive resistance from static load tests
(5)P In the case of a pile foundation subjected to downdrag, the pile resistance
at failure, or at a displacement that equals the criterion for the verification of the
ultimate limit state determined from the load test results, shall be corrected.
The correction shall be achieved by subtracting the measured, or the most
unfavourable, positive shaft resistance in the compressible stratum and in the
strata above, where negative skin friction develops, from the loads measured at
the pile head.
(6) During the load test of a pile subject to downdrag, positive shaft friction will
develop along the total length of the pile and should be considered in
accordance with 7.3.2.2(6). (The maximum test load applied to the working pile
should be in excess of the sum of the design external load plus twice the
downdrag force.)
4/27/2015
22
CP4 on Dragload
7.3.6 Negative skin friction
Q al
where
4/27/2015
Qb Qsp
Fs
Pc Qsn
23
24
Outline
Pile Design using EC7
Problems with BS 8004, EC7, and CP4 on dragload
Design example using EC7
Unified pile design concept
4/27/2015
25
4/27/2015
Pile type
Bored pile
Pile diameter
300 mm
20 kPa
50 kPa
300 kN
26
27
DA2: A1 + M1 + R2
Total design load, Fcd = 1.35 x 300 + 1.35 x 94.2 = 532.2 kN
Design resistance, Rc;d = 47.1LR/1.1 = 42.8LR kN
Condition Fc;d Rc;d leads to LR 532.2/42.8 = 12.43 m
DA3: (A1 or A2) + M2 + R3
Total design load, Fcd = 1.35 x 300 + 1.25 x 94.2 = 522.8 kN
Design resistance, Rc;d = 47.1LR/1.25 = 37.7LR kN
Condition Fc;d Rc;d leads to LR 417.8/37.7 = 13.87 m
Conclusion
DA-3 requires the longest pile length of the three Design Approaches: LR = 13.87 m, compard with LR
= 11.54m for DA-1 and LR = 12.43m for DA-2. This is due to the fact that for DA-3 the values of the
three partial factors are equal to 1.25 or 1.35. It can also be argued that the application of the
correlation factor to the estimated values of shaft friction qs in DA-1 and DA-2 (see clauses
7.6.2.2(8)P and 7.6.2.3(5)P) would have led to lower values for qs;k than in DA-3 (for which they are
not used).
4/27/2015
28
DA1 Combination 1: A1 + M1 + R1
Total design load, Fcd = 1.35 x 300 = 405 kN
Design resistance, Rc;d = (94.2 + 47.1LR)/1.0 = 94.2 + 47.1LR kN
Condition Fc;d Rc;d leads to LR 310.8/47.1 = 6.70 m (cf. 11.30m)
DA1 Combination 2: A1 + (M1 or M2) + R4
Total design load, Fcd = 1.0 x 300 = 300 kN
Design resistance, Rc;d = (94.2 + 47.1LR)/1.3 = 72.5 + 36.2LR kN
Condition Fc;d Rc;d leads to LR 227.5/36.2 = 6.28 m (cf. 11.54m)
DA2: A1 + M1 + R2
Total design load, Fcd = 1.35 x 300 = 405 kN
Design resistance, Rc;d = (94.2 + 47.1LR)/1.1 = 85.6 + 42.8LR kN
Condition Fc;d Rc;d leads to LR 319.4/42.8 = 7.46 m (cf. 12.43m)
DA3: (A1 or A2) + M2 + R3
Total design load, Fcd = 1.35 x 300 = 405 kN
Design resistance, Rc;d = (94.2 + 47.1LR)/1.25 = 75.4 + 37.7LR kN
Condition Fc;d Rc;d leads to LR 329.6/37.7 = 8.74 m (cf. 13.87m)
4/27/2015
29
Imagine that the project requires 1000 piles, the cost saving will be
1000 x 5.13 m = 5,130 m pile length!
Assuming that the thickness of the soft clay layer is now 15m instead of
5m (in Singapore, typical Marine clay thickness is 10-30 m). The
dragload force becomes 282.7 kN.
Using 13.87m embedded pile length in stiff clay (from DA-3), the pile
design will have a negative capacity (Fc;d = 1.35 x 300 + 1.25 x 282.7 =
758.4 kN cf. Rc;d = 37.7LR = 522.9 kN).
Therefore, in order to satisfy the total design load based on EC7, the
embedment length in stiff clay need to be LR = 758.4/37.7 = 20m.
In order words, to sustain 300 kN permanent load, the total pile length
required is 25 + 20 = 45m.
4/27/2015
30
Outline
Pile Design using EC7
Problems with BS 8004, EC7, and CP4 on dragload
Design example using EC7
Unified pile design concept
4/27/2015
31
4/27/2015
32
500
1,000
1,500
2,000
CAPACITY
2,500
DEPTH (m)
DEPTH (m)
LOAD (KN)
10
1,000
1,500
2,000
CAPACITY
2,500
10
15
15
DRAG LOAD
20
500
LOAD (KN)
DRAG LOAD
20
INCREASE !
If the pile capacity had first been
reduced with the amount of the drag
load, there would have been no room
left for the working load!
4/27/2015
33
Do not include the drag load when determining the factored resistance!
1,000
1,500
2,000
FACTORED RESISTANCE
minus FACTORED DRAGLOAD
Factors = 0.6 and 1.5, respectively
2,500
10
DRAG LOAD
15
DEPTH (m)
DEPTH (m)
500
FACTORED RESISTANCE
LOAD (KN)
1,000
1,500
2,000
CAPACITY
2,500
10
15
DRAG LOAD
20
4/27/2015
20
34
SETTLEMENT
Load placed on a pile causes downward movements of the pile head due to:
1. 'Elastic' compression of the pile.
2. Load transfer movement -- the movement response of the soil at the pile toe..
3. Settlement below the pile toe due to the increase of stress in the soil. This is
only of importance for large pile groups, and where the soil layers below the piles
are compressible.
A drag load will only directly cause movement due to Point 1, the
'elastic' compression. While it could be argued that Point 2 also is at
play, because the stiffness of the soil at the pile toe is an important
factor here, it is mostly the downdrag that governs (a) the pile toe
movement, (b) the pile toe load, and (c) the location of the neutral
plane in an interactive "unified" process.
The drag load cannot cause settlement due to Point 3, because there
has been no stress change in the soil below the pile toe.
4/27/2015
35
Therefore, negative-skin-friction/dragload
does not diminish geotechnical capacity.
4/27/2015
36
The dead plus live load must be smaller than the pile capacity
divided by an appropriate factor of safety. The drag load is not
included when designing against the bearing capacity.
2.
The dead load plus the drag load must be smaller than the
structural strength divided with a appropriate factor of safety. The live
load is not included because live load and drag load cannot coexist.
3.
37
"
38
39
40
SETTLEMENT
1,500
200
Utimate
Resistance
DEPTH
NEUTRAL PLANE 1
NEUTRAL PLANE 2
1 2
Toe Penetrations = Movement into the soil
41
SETTLEMENT
1,000
200
Utimate
Resistance
DEPTH
NEUTRAL PLANE 1
NEUTRAL PLANE 2
TOE PENETRATION
0
Toe Resistances
Toe Penetrations
TOE RESISTANCE
12
2
3
Outline
Pile Design using EC7
Problems with BS 8004, EC7, and CP4 on dragload
Design example using EC7
Unified pile design concept
4/27/2015
43
Hypothetical site with three soil layers: fill, soft clay and dense sand
Simulation of short-term pile load test (undrained situation)
Ground settlement due to surcharge loading at various magnitude
(10, 20 and 40 kPa)
Pile load transfer due to dragload at different working load (2000,
4000 and 6000 kN)
Consolidation analysis to simulate the development of dragload as
the soils settle with time
Effect of bitumen coating
Results comparison
4/27/2015
44
Hypothetical site
Head load (P)
2, 4 and 6 MN
Surcharge loading
(10, 20 and 40 kPa)
Axi-symmetric model
Pile diameter, D = 1.128 m
Pile length, L = 20 m
(pile cross-sectional area = 1 m2)
25 m
4/27/2015
25 m
45
2000
4000
Load (kN)
6000
8000
10000
12000
0
Head load - Head Mvmnt
40
Movement (mm)
Elastic comprs
80
120
160
200
4/27/2015
Head Load
[kN]
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Toe Load
[kN]
0
344
595
931
1269
1714
2228
2779
3445
4053
4752
Shaft Load
[kN]
0
656
1405
2069
2731
3286
3772
4221
4555
4947
5248
Head mvmnt
[mm]
0
3.785
9.914
20.273
32.066
48.3
68.757
93.178
121.227
150
182.28
Toe mvmnt
[mm]
0
3.135
8.708
18.519
29.752
45.411
65.266
89.074
116.491
144.647
176.289
Elastic compr
[mm]
0
0.65
1.206
1.754
2.314
2.889
3.491
4.104
4.736
5.353
46
5.991
2000
4000
Settlement (mm)
6000
200
400
600
-100
100
200
300
Subjected to
dragload
Working load
condition
10
(2) DRAG LOAD
Neutral plane
15
20
(1) + (2)
Long-term
load transfer
25
Net toe
penetration
0
Toe movement (mm)
Depth (m)
soil
settlement
Pile
6000
0
50
100
150
200
2000
Settlement (mm)
4000
6000
200
400
600
800
-100
100
200
300
Working load
condition
Depth (m)
Initial load
distribution
10
Large
transition
zone
Small
transition
zone
15
20
soil settlement at
10, 20 and 40 kPa
Unit resistance at
10,20 and 40kPa
pile settlement at
10, 20 and 40 kPa
Long-term load
transfer for 10,20
and 40 kPa
Settlement (mm)
100
200
300
25
Depth (m)
10
12
14
16
48
2000
4000
Settlement (mm)
6000
8000
200
400
600
-100
100
200
300
0
2MN
4MN
6MN
soil
settlement
10
NP:
3436KN
Unit resistance at
WL=2, 4 and 6MN
NP:
NP:
7224KN
5324KN
15
pile settlement at
WL=2, 4 and 6 MN
20
WL=2000kN
Net toe
penetration
WL=4000kN
25
WL=6000kN
0
Toe movement (mm)
Depth (m)
6000
0
50
100
150
200
49
2000
Settlement (mm)
4000
6000
200
400
600
-100
100
200
300
0
1 yr
5 yr
15 yr
Working load
condition
Depth (m)
final soil
settlement
10
Neutral Plane
Unit resistance at
1, 5, 15 yr
consolidation and
fully drained
15
20
25
4/27/2015
Initial
1 year
5 year
15 year
Fully Drained
50
Effect of bitumen coating (R=0.1 for fill and soft clay layers)
Load (kN)
0
2000
4000
Settlement (mm)
6000
200
400
600
-100
100
200
300
0
Short-term load
transfer without
bitumen
10
Depth (m)
with
bitumen
Working load
condition
without
bitumen
without
bitumen
soil
settlement
with bitumen
NP=4285 kN
with
bitumen
Neutral
Plane
without
bitumen
15
without
bitumen
N=5324 kN
20
25
30
51
1000
5000
6000
40
80
120
160
4/27/2015
200
52
2,000
SETTLEMENT (mm)
LOAD (KN)
4,000
6,000
Silt
Sand
200
Clay
DEPTH (m)
DEPTH (m)
150
10
10
15
100
0
5
50
Soil Settlement
15
20
20
O-cell
25
25
Till
30
30
0
1,000
q-z relation
2,000
3,000
4,000
0
50
100
The final solution is based on three "knowns": The shaft resistance distribution, the toe load-movement response, and the
overall
settlement distribution. Which all comes from basic site and project knowledge.
4/27/2015
53
10
30
50
2000
4/27/2015
4000
6000
LOAD [kN]
SUMMARY RESULTS
NSF do not affect Ultimate Pile Resistance (about 6500 kN in above cases)
Soil settlements (So) produce drag-loads (NSF) on piles
Larger So showed softer pile response; and larger pile settlements
54
10
30
Uncoated Pile
Bitumen coated piles
50
2000
4000
6000
LOAD [kN]
Bitumen Coating reduces total resistance (geotechnical capacity) of pile from 6500 kN to
5300 kN
But the external ground settlements influence on pile movement is almost insignificant
compared to uncoated pile
4/27/2015
55
3x3m
(9 piles)
6x6m
(36 piles)
4/27/2015
2x2m
(4 piles)
2x1m
(2 piles)
1x1m
(1 pile)
corner
side
interior
centre
4/27/2015
57
Surcharge 40 kPa
1x1m
(1 pile)
30 m
2x2m
(4 piles)
3x3m
(9 piles)
corner
Dense sand (15m thick)
s = 20 kN/m3; E50;ref = 30MPa; c = 0; = 40o
4/27/2015
30 m
single
centre
58
200
Load (kN)
400
600
Settlement (mm)
200
400
600
800
0
soil
settlement
5
single
Pile
settlement
centre
Interior
15
20
25
Single pile
corner
Side
Interior
Centre
10
15
Neutral
Plane
0
Settlement (mm)
5
10
15
20
12
20
single
25
Depth (m)
10
Depth (m)
Depth (m)
corner
side
piles in
group
14
16
soil
59
18
200
Load (kN)
400
600
600
single
10
15
20
25
400
Depth (m)
Depth (m)
200
Load (kN)
10
single
centre
side
corner
15
20
Single pile
2 piles group
4 piles group
25
Single pile
9 piles group (corner)
9 piles group (centre)
9 piles group (side)
60
61
Centrifuge Experiments
62
Outline
Pile Design using EC7
Problems with BS 8004, EC7, and CP4 on dragload
Design example using EC7
Unified pile design concept
4/27/2015
63
Summary
Pile design according to EC7 design approaches has been
presented
EC7, BS8004 and CP4 do not address the dragload (or NSF)
correctly.
It has been shown here using FE analysis of single pile and groups
of piles that dragload does not reduce pile geotechnical capacity.
The key point in pile design is settlement not capacity.
FE analysis can easily predict the location of NP with no iterations
required.
64
4/27/2015
65
EC7 ALLOWS FOR INNOVATIVE DESIGN FOR NSF BY USING GOOD FEM PILE-SOIL
INTERACTION ANALYSIS TO ACCOUNT FOR CORRECT CONSOLIDATION
SETTLEMENTS (TREATED AS ACTION)
4/27/2015
66