Sei sulla pagina 1di 8

INTERNATIONAL

PRACTICE

IP 16-13-1

Field Installation and


Testing of Electrical Equipment

Page 1 of 8
Rev. 0

June 1997

Changes shown by

SCOPE
I

1.1

This practice covers installation and field testing of electrical distribution systems. The contents of this
practice are arranged as follows:

TABLE OF CONTENTS
SCOPE.......................................................................................................................... 1
SUMMARY OF ADDITIONAL STANDARDS ................................................................. 1
DEFINITIONS................................................................................................................ 2
CONDUIT SYSTEM INSTALLATION............................................................................. 2
BURIED CABLE INSTALLATION.................................................................................. 2
GROUNDING CABLE INSTALLATION ......................................................................... 3
ABOVE-GROUND WIRING SYSTEM INSTALLATION - CABLE TRAYS ...................... 3
INSULATED WIRE AND CABLE INSTALLATION......................................................... 3
TEST PROCEDURES.................................................................................................... 3
LIQUID DIELECTRIC TESTS ........................................................................................ 4
CABLE HIGH VOLTAGE TESTS................................................................................... 4
WIRING INSULATION TESTS....................................................................................... 5
POWER TRANSFORMER TESTS................................................................................. 6
SWITCHGEAR TESTS .................................................................................................. 6
MEDIUM VOLTAGE MOTOR CONTROL CENTER TESTS........................................... 7
TESTING OF LV CONTROL CENTERS, SWITCHRACKS, AND TURNAROUND
POWER CENTERS ....................................................................................................... 7
MOTOR INSULATION RESISTANCE TESTS AND RUN-IN .......................................... 7
GROUNDING RESISTANCE TESTS ............................................................................. 7
BATTERY CHARGING AND CHARGER TEST ............................................................. 7
TESTING OF PACKAGED UNIT SYSTEMS.................................................................. 8
ALARMS, EMERGENCY CONTROL SYSTEMS AND OTHER EQUIPMENT TESTS .... 8
I
I

1.2

1.3

An asterisk (V) indicates that additional information is required. If a job is contracted, this additional
information is furnished in the Job Specification.
The following references are synonymous: BP and IP.

SUMMARY OF ADDITIONAL STANDARDS


I

2.1

For installation of above-ground wiring and all conduit wiring, the appropriate sections of ANSI/NFPA
70, National Electrical Code (NEC) and other requirements of the authority having jurisdiction shall be
followed for plant locations in the U.S.A.

2.2

For testing, Table 1 lists the standards which are to be used for the applicable equipment. For general
testing methodology and minimum acceptable test values, refer to NETA.
TABLE 1
STANDARDS
ASTM Standard
D117
Testing Electrical Insulating Oils
NETA - International Electrical Testing Association
Acceptance Testing Specifications for Electrical Power Distribution Equipment and Systems

2.3

Applicable standards and testing for equipment used in the USA are given in this practice. For facilities
installed in other countries, field tests shall conform to the nationally recognized standards which are
required within that country.

THIS INFORMATION FOR AUTHORIZED COMPANY USE ONLY


EXXON RESEARCH AND ENGINEERING COMPANY FLORHAM PARK, N.J.

IP 16-13-1

Field Installation and


Testing of Electrical Equipment

Page 2 of 8
Rev. 0

June 1997

INTERNATIONAL
PRACTICE

DEFINITIONS
I

3.1

Acceptable and Preferred Practices. Where this practice lists more than one type of material or method
as acceptable, the Contractor shall make the selection based on installed cost. Where one particular type
of equipment or method is listed as preferred, it shall be selected, provided it is lower or equivalent in
installed cost to other acceptable types or methods. Optimum cost benefits may be achieved by reducing
maintenance and operating expense through initial added investment. Economic basis for calculating
optimum cost benefits will be included in the general job specification. Owners Engineer shall approve
alternative choices.

CONDUIT SYSTEM INSTALLATION


S

4.1

All underground conduit runs and duct banks shall be encased in red concrete and shall be as follows:
a.
Concrete shall be colored red with a permanent coloring additive mixed with the concrete.
b.
The minimum thickness of encasement shall be 3 in. (75 mm) on top, and 2 in. (50 mm) on sides
and bottom. If conduits rise above ground, the encasement shall extend 6 in. (150 mm) above
ground.
c.
The top of the concrete encasement shall be at least 18 in. (450 mm) below grade. At road and
railroad crossings, the top of the encasement shall be at least 30 in. (750 mm) below the road
surface or rail base.

BURIED CABLE INSTALLATION


C

5.1

Cables shall be laid in trenches in single horizontal tiers, unless a 2-tier design is approved by the
Owners Engineer, as follows:
a.
Before cables are placed, the trench bottom shall be leveled and backfilled with a layer of sand 4
in. (100 mm) thick.
b.
The cables shall be placed on the sand, then be covered with another layer of sand 4 in. (100 mm)
deep as measured from the top of the largest cable.
c.
A protective covering 2 in. (50 mm) thick of red concrete, shall then be applied, using either
precast concrete slabs (preferred) or cast-in-place concrete (alternate). Size of pre-cast concrete
slabs shall be at least 10 in. x 12 in. (250 mm x 300 mm). The protective cover shall extend a
minimum of 3 in. (75 mm) beyond the outer cables in the trench, but need not be extended under
elevated substations.
d.
The top surface of the largest cable in the trench shall be a minimum of 30 in. (750 mm) below
finished grade. This may be reduced to 18 in. (450 mm) for trenches outside process unit limits
containing only lighting circuits.
e.
Burial depth may be increased where necessary to meet underground conditions, but it is preferred
that burial depth does not exceed 48 in. (1.2 m).

MARKING
M

5.2
V

Underground cables shall be identified by circuit number stamped on bands attached to each cable as
follows:
a.
Bands shall be corrosion resistant metal, except that plastic bands designed for the purpose, with
machine-raised lettering and mechanical (not adhesive) closure, may be approved by the Owner's
Engineer.
b.
Bands shall be attached to cables at intervals not over 25 ft (7.5 m), at every splice, at entrance
and exit of duct banks and at the equipment supplied. Bands on cables originating at elevated
substations shall be located visibly between the substation floor and grade.

THIS INFORMATION FOR AUTHORIZED COMPANY USE ONLY


EXXON RESEARCH AND ENGINEERING COMPANY FLORHAM PARK, N.J.

INTERNATIONAL
PRACTICE

Field Installation and


Testing of Electrical Equipment

IP 16-13-1
Page 3 of 8
Rev. 0

June 1997

5.3

A system of aboveground concrete markers shall be provided to locate and identify direct buried cables
as follows:
a.
Markers shall be located at every point where the trench changes direction, and at intervals not
greater than 50 ft (15 m) within process unit limits and 150 ft (45 m) outside process unit limits.
b.
Markers shall be located above every underground splice.

5.4

For trenches 3 ft (900 mm) or more in width, markers shall be provided on both edges of the trench; if
less than 3 ft (900 mm) in width, provide markers at one edge of the trench only.

5.5

Markers shall have identification plates of corrosion-resistant metal suitable for marking with a steel die
stamp. Plates shall have the following information:
a.
Direction of cable runs.
b.
Location of splices.
c.
Location of trench with respect to marker.

GROUNDING CABLE INSTALLATION


S,R

6.1

Separate grounding cables when specified shall be installed as follows:


a.
In trenches with buried insulated cables, with the same protection as the other cables.
b.
In separate trenches with a 3 in. (75 mm) sand bedding all around plus a red concrete cover. The
concrete cover shall not be extended under elevated substations, or installed in switch or
transformer yards.
c.
Alongside a duct bank with a 3 in. (75 mm) sand bedding all around but no concrete cover.
d.
Soil free of stones over 1/4 in. (6 mm) may be substituted for sand.

ABOVE-GROUND WIRING SYSTEM INSTALLATION - CABLE TRAYS


M

7.1

Each cable shall be identified as for Buried Cable Installation in Par. 5.2 of this practice, except
marker intervals shall be 50 ft. (15 m). Bands shall be attached to cables where cables enter and leave
trays or ladders, or enter branch trays or ladders.

7.2

Plastic and nylon cable straps shall not be used to tie cables to vertically mounted cable trays.

INSULATED WIRE AND CABLE INSTALLATION


R

8.1

Qualification of Contractor's splicing personnel for both control cables and power cables, shall be
approved by Owner's Engineer.

8.2

Splices and taps. Wire and cable shall be run in single lengths between terminations, where practical.

8.3

Wire and cable connections at motors having pigtail leads shall be made with lug type connectors and
corrosion resistant bolts, nuts, washers, and lockwashers. Motors with pigtail leads shall be lugged in the
field if not so furnished.

8.4

All stranded conductors which connect to terminal strips or boards having screw type terminals shall be
connected to the terminal screws with lugs. All wiring shall be terminated with a lug or ferrule applied with
a mechanical crimp. CT secondary wiring shall be terminated with ring lugs.

TEST PROCEDURES
R,C

9.1

Before the electrical facilities are placed in operation, the Contractor shall make suitable field tests to
establish that all equipment, devices, and wiring have been correctly installed, are in satisfactory working
condition, and will operate as intended. Unless otherwise specified, manufacturer's recommendations
shall be included. All tests specified in this practice must be performed in the field before energizing. Shop
tests shall not be used to satisfy any field test requirement. When pre-fabricated building modules are
tested prior to shipping, Contractor shall propose a field test program for Owners Engineer approval.

THIS INFORMATION FOR AUTHORIZED COMPANY USE ONLY


EXXON RESEARCH AND ENGINEERING COMPANY FLORHAM PARK, N.J.

IP 16-13-1

Field Installation and


Testing of Electrical Equipment

Page 4 of 8
Rev. 0

R,C

June 1997

INTERNATIONAL
PRACTICE

9.2

Before field testing begins, the Contractor shall submit for review by the Owner's Engineer a list of
minimum acceptable test values and procedures, to be followed in the measurement of liquid dielectric
strength, equipment dielectric absorption ratios, and insulation resistance for circuits and equipment.
Values shall conform to those specified in manufacturers' instructions or applicable national standards.
Liquid dielectric strength values shall include the method of test (ASTM D-117 or equivalent national
standard).

9.3

When specified, detailed step-by-step procedures shall be prepared to verify correct operation of main
switchgear. These procedures shall be reviewed in detail with the Owner's Engineer prior to the start of
field testing.

9.4

The results (i.e., test values) of all tests described in this practice which are marked with () shall
be recorded on forms provided by the Contractor, consistent with established site data form requirements.
These forms shall be first approved by the Owner's Engineer.

9.5

Testing evaluation shall be as follows:


a.
b.

Test results shall be submitted to the Owner's Engineer for review before circuits or equipment are
energized for the first time.
Individual measurements which fall below the average of like measurements on similar equipment
by more than 25% shall be submitted to the Owner's Engineer for specific approval.

9.6

Unless otherwise specified, the Owner's Engineer will witness all tests, and shall be notified one week
before tests are to take place.

9.7

Test reporting shall comply with the following:


a.
b.
c.

d.

Two certified copies of the () test data shall be given to the Owner's Engineer.
One copy of test reports shall be submitted immediately after each test is completed to facilitate a
timely review by the Owner's Engineer prior to energizing equipment.
Upon completion of all other tests described in this practice, Contractor shall submit to Owner's
Engineer two copies of certified report attesting that each test has been performed in accordance
with this practice.
The report for each test shall include the date of performance and name of the person in charge of
the test.

LIQUID DIELECTRIC TESTS


R

10.1

10.2 Before energizing any oil-immersed equipment, a sample of the oil taken from the enclosure shall be
tested for dielectric strength. This shall not apply to small equipment shipped sealed from the factory,
such as current and potential transformers and sealed power transformers 100 kVA and smaller. It shall
apply to the following:

Each container of oil to be used for filling power transformers shall be sampled and tested for
dielectric strength. Only oil which by test shows an acceptable dielectric strength shall be used.

a.

Transformers over 100 kVA.

b.
c.
d.

Transformer primary disconnect switches.


Transformer on-load tap changer arcing compartments.
Bulk oil circuit breakers.

e.

Minimum oil content circuit breakers, unless manufacturer's instructions do not recommend.

f.

Motor starters.

CABLE HIGH VOLTAGE TESTS


R

11.1 A D-C high voltage test shall be made, after installation, on metallic shielded or metallic sheathed cables,
and test data shall be recorded to include (for record purposes) measured values of leakage current versus
time, for the following cable services:
a.
All cables, except motor feeder cables, operating at nominal system voltages of 1001 through
7,200 volts.
b.
All cables, including motor feeder cables, operating at nominal system voltages of 7,201 volts and
above.

THIS INFORMATION FOR AUTHORIZED COMPANY USE ONLY


EXXON RESEARCH AND ENGINEERING COMPANY FLORHAM PARK, N.J.

Field Installation and


Testing of Electrical Equipment

INTERNATIONAL
PRACTICE

IP 16-13-1
Page 5 of 8
Rev. 0

June 1997

11.2

The D-C high voltage tests shall be performed in accordance with the following:
a.
Cables shall be installed in final position, with all through splices and end terminations complete.
b.
Terminations shall be kept disconnected so that equipment (e.g., motor, switchgear, transformers)
is not subjected to the test voltage; however, insulation shall be penciled and otherwise prepared
for completion of the terminations to the greatest extent possible for protection of the cable,
including making up and grounding of stress cones for shielded cable.
c.
Where potheads are employed, all internal work in making up the pothead shall be complete
including filling. Pothead insulators shall be clean and dry, and if high voltage test lead is attached
to pothead terminal it shall leave terminal in a direction parallel to the axis of the pothead for a
distance of not less than the dry arcing distance over the insulator. Test voltage shall not exceed
the maximum withstand test voltage guaranteed by the pothead manufacturer.

11.3

Test voltage, duration of test, and test procedure shall be in accordance with nationally recognized
standards to which the cable conforms. Contractor shall submit proposed test values to Owner's Engineer
for agreement prior to start of testing.

11.4

Cumulative Insulation Breakdown Tests. If insulation failures or other interruptions result in a total
(cumulative) time under test at the test voltage, for a given cable, exceeding twice the time specified in
applicable standards for other cable types, then the duration of any subsequent tests shall be reduced to
1/3 of the times specified.

WIRING INSULATION TESTS

12.1

Insulation resistance of each circuit shall be measured before energizing (with neutral ground
disconnected) as follows
a.
Line(s) to neutral.
b.
Line(s) to ground.
c.
Neutral to ground.

R,C

12.2

Circuit testing shall be as follows: Test scheduling shall minimize disconnection and reconnection.
a.
Motor feeders are tested with motors disconnected and controller open. For VFD feeders, the VFD
shall be disconnected prior to testing.
b.
Motor control circuits are tested with control stations and overcurrent devices connected, from
phase to ground only.
c.
Lighting feeders are tested with feeder breaker open and panelboard connected. If a lighting
transformer is associated with the panelboard, it shall be connected and the test made for both
primary and secondary sides.
d.
Lighting branch circuits are tested after all lamp holders, receptacles, fixtures, and similar items
are connected, with switches turned on but before lamping. If circuits feed auto-transformer type
ballasts, the only reading possible will be from line, or neutral, to ground. If fixtures with power
factor correcting capacitors connected line-to-line are involved, it may be necessary to disconnect
them to avoid capacitor overvoltage.

e.

f.
R,C

12.3

Circuits rated above 1000 volts having splices or having potheads or similar terminating devices
are tested before splicing, and before terminating. Repeat test after splices and terminations have
been completed.
Direct buried cable circuits are tested before cable trenches are backfilled. Repeat test after
backfilling.

When "mineral insulated" cable is used for pipe heating, circuit continuity shall be checked, and
insulation resistance shall be measured as follows:
a.
Prior to removing cable from reel.
b.
c.

Prior to installing cable on pipe.


Prior to installing insulation on pipe.

d.

Prior to energizing cable.

THIS INFORMATION FOR AUTHORIZED COMPANY USE ONLY


EXXON RESEARCH AND ENGINEERING COMPANY FLORHAM PARK, N.J.

IP 16-13-1

Field Installation and


Testing of Electrical Equipment

Page 6 of 8
Rev. 0

June 1997

INTERNATIONAL
PRACTICE

POWER TRANSFORMER TESTS


R
O

13.1

Winding insulation resistance shall be measured from primary and secondary to ground, and from
primary to secondary.

13.2

Test operation of fault pressure relays and temperature device in accordance with manufacturers'
instructions.

13.3

Tap changer operational test. De-energize transformer before operating no-load tap changers. Turn-toturn ratio tests shall be made to verify that winding ratios are in accordance with transformer nameplate.
Measure ratio with changer in each position.

SWITCHGEAR TESTS
14.1 Prior to energizing, insulation resistance of each bus shall be measured from phase-to-phase and
from phase-to-ground with breakers withdrawn. Measurements shall be repeated with circuit breakers in
operating position and contacts open.

14.2

Prior to energizing, control circuit insulation resistance shall be measured to ground.

O,I

14.3

Before operating, all circuit breakers shall be subjected to the following tests:
a.
Contact alignment and wipe shall be checked and adjusted if necessary in accordance with
manufacturer's instructions.

b.

c.
O

14.4

S,O

Before switchgear is energized, each circuit breaker shall be checked in its "test" position and again in
its operating position as follows:
a.
Close and trip circuit breaker from its control switch, remote control station, or operating handle.
Switchgear bus may become energized from a limited-fault source (such as construction power
lighting) to permit test operation of circuit breakers with a-c closing.
b.
Trip each electrically operated circuit breaker with its mechanical trip device.
c.
Test operation of circuit breaker latch check switch, if provided.
d.
Test proper operation of lockout device in the closing circuit, where provided, by simulating
conditions which would cause a lockout to occur.
e.
Trip breaker by manually operating, or by applying current or voltage to, each of its associated
protective relays.

14.5 Each adjustable relay shall be set, calibrated, and tested using standard test equipment.
calibration points, and check points shall conform to the protective relay settings record data.

O,R

14.6
V

b.

14.7

Settings,

Instrument transformer secondary circuits shall be tested by the following methods:


a.
Make a visual check of all current transformer terminals to determine if shorting bars are installed.
Record and submit to Owner's Engineer, the location and reason for any shorting bar left on
current transformers after current injection tests.

c.
O

Each circuit breaker shall be drawn out of its cubicle, closed manually, and its insulation resistance
measured from phase-to-phase and from phase-to-ground. Contact resistance (ductor) readings
shall be taken across each set of contacts with the circuit breaker closed.
All adjustable direct acting trip devices shall be set according to the protective relay settings record
data.

Apply current to the secondary winding of current transformers and verify that proper relays and
meters (as applicable) operate. When specified, perform primary injection testing to verify
continuity of the complete current circuits.
Apply voltage to the secondary winding of potential transformers and verify that proper relays and
meters (as applicable) operate.

Automatic transfer circuits of secondary selective substations shall be completely tested for proper
operation as follows:
a.
A detailed step-by-step test procedure shall be followed that will verify the correct operation of all
contacts in each of the two incoming circuit breakers and the tie breaker.
b.
Test transfers shall be initiated by simulated fault and undervoltage conditions.
c.
The transfer time under no-load conditions shall be measured with a cycle counter.

THIS INFORMATION FOR AUTHORIZED COMPANY USE ONLY


EXXON RESEARCH AND ENGINEERING COMPANY FLORHAM PARK, N.J.

Field Installation and


Testing of Electrical Equipment

INTERNATIONAL
PRACTICE

14.8

IP 16-13-1
Page 7 of 8
Rev. 0

June 1997

After energizing switchgear but before closing tie circuit breakers (where provided), phase out across
tie circuit breakers using "hot sticks" or potential transformers and voltmeters.

MEDIUM VOLTAGE MOTOR CONTROL CENTER TESTS


R

15.1

S,O
O

Before energizing the equipment, the insulation resistance of each bus shall be measured from phaseto-phase and from phase-to-ground with disconnect devices open. Repeat measurements with disconnect
devices closed but with switching devices open.

15.2 Contact alignment and wipe for each switching device shall be checked and adjusted where necessary
in accordance with manufacturers' instructions.
15.3

Relay and Direct Acting Trip Device Settings. Set each adjustable relay and direct acting trip device in
accordance with the protective relay settings record data.

15.4

Operation of Contactor. Each contactor shall be closed and tripped from its control switch and remote
control station to test proper operation.

TESTING OF LV CONTROL CENTERS, SWITCHRACKS, AND TURNAROUND POWER CENTERS


16.1 Bus Insulation Resistance. Before energizing, the bus insulation resistance shall be measured from
phase-to-phase and from phase-to-ground with disconnect devices open. Measurements shall be repeated
with disconnect devices closed.

MOTOR INSULATION RESISTANCE TESTS AND RUN-IN


R,C

17.1 Insulation resistance of all motor windings shall be measured before connecting power cables to motors.
Measurements shall be repeated after power cable terminations are completed.

R,C

17.2 Measure the 60:30 second dielectric absorption ratio of motor windings rated above 1000 V. Measure
the 10:1 minute polarization index of windings on motors rated above 1500 HP.

17.3

All motors shall run uncoupled for a minimum continuous period of 2 hours before the driven equipment
is placed in regular service. On larger machines, run-in period may need to be extended to allow bearing
temperatures to stabilize.

GROUNDING RESISTANCE TESTS


S,R

18.1 The resistance to earth shall be measured at the following locations:


a.
At each ground provided for structure lightning protection. Resistance shall not exceed 5 ohms. If
driven rod electrodes for this purpose are interconnected with other grounding, the connections
shall be opened for this test.
b.
At one point of each grounding system used to ground electrical equipment enclosures and wiring
system enclosures, such as metal conduits, cable sheaths or armor. Resistance shall not exceed
5 ohms.
c.

At grounds for lightning arresters. Resistance shall not exceed 1 ohm. These grounds are
generally interconnected with enclosure grounds, and then the combined ground shall not exceed 1
ohm.

18.2 Resistance to earth of system neutral grounds shall be measured. Resistance shall not exceed the
following:
a.
b.

For systems operating at 1000 volts or less between conductors: 5 ohms.


For high resistance grounded systems: 5 ohms.

c.
d.

For low resistance grounded systems operating at above 1000 volts: 1 ohms.
For systems grounded through Petersen coil: 5 ohms.

BATTERY CHARGING AND CHARGER TEST


O

19.1

All battery chargers shall be tested for proper operation and to verify that they can deliver their maximum
rated output. A load discharge test shall be made to confirm that battery design capability can be
delivered.

THIS INFORMATION FOR AUTHORIZED COMPANY USE ONLY


EXXON RESEARCH AND ENGINEERING COMPANY FLORHAM PARK, N.J.

IP 16-13-1

Field Installation and


Testing of Electrical Equipment

Page 8 of 8
Rev. 0

June 1997

INTERNATIONAL
PRACTICE

TESTING OF PACKAGED UNIT SYSTEMS


O

20.1

Packaged unit systems such as generators, variable speed drives, desalters, HVAC, etc. shall be
functionally tested to insure proper operation. A detailed step-by-step test procedure that will verify the
correct operation of all circuitry in each package unit, shall be agreed with the Owners Engineer.

ALARMS, EMERGENCY CONTROL SYSTEMS AND OTHER EQUIPMENT TESTS


O

21.1

Alarms for all electrical equipment shall be tested for proper operation by causing alarms to sound under
simulated abnormal conditions.

21.2

All adjustable protective or control devices shall be checked and adjusted in accordance with drawings
or manufacturer's bulletins. This includes molded case circuit breakers, overload protective devices,
pressure switches, limit switches, temperature switches, and level switches.

S,O

21.3

Emergency startup and shutdown systems shall be given a full operational test using the minimum
practical number of simulated operations.

21.4

Operational testing of motor-operated valves shall be checked by the following procedure:


a.
Manually set valve midway between open and closed positions.
b.
Bump motor by pushing CLOSE button immediately followed by pushing the STOP button. When
rotation is correct, start valve "closing" and immediately operate closing torque switch manually.
Motor should stop. Start valve "opening" and immediately operate opening torque switch
manually. Motor should stop. The above procedure shall be followed before allowing valve to
reach fully open or fully closed positions. Limit switches on all motor operators shall be set in the
field.

S,O

21.5

Emergency power systems, emergency lighting, and uninterruptable power systems shall have full
functional tests to insure proper operation as shown on drawings or manufacturer's data.

9/68
1/73
4/92
6/97

Revision Memo
Original Issue of Basic Practice
Revision 1
Revision 2
Revision 0 - Original Issue of International Practice
Purpose Codes added throughout. Paragraphs Deleted. The following paragraphs contained in BP16-13-1 Revision
2 have been deleted: 1.2, 4.1-3, 4.4a-c, g, h, 4.5-4.8, 4.9c, 4.10-12, 5.1-5.4, 6.1b, e, f, 8.1-8.8, 8.11-8.15, 9.3, 9.5c, 9.6,
10.1, 11.1, 13.2, 14.5-14.7, 16.4, 16.5, 19.1, 22.1, 22.3, and 22.4. Low voltage of 600 V changed to 1000 V throughout.
Par. 1.1 editorial changes. Par. 1.2 updated table of contents. Par 1.3 added statement for BP/IP cross referencing.
Par. 2.1 U.S.A. locations reference was added. Par. 2.2 reference to NETA methodology and test values was added.
Par. 2.3 modified to meet national standards. Par. 3.1 added optimum cost benefits. Par. 4.1 removed concrete
strength requirement. Par. 4.2 seals now per manufacturers instructions. Par. 4.2d. deleted strength of concrete. Par.
5.1 option for 2-tier design was added. sand depth and cover dimensions were revised. Par. 5.2b added bands at
equipment location. Par. 6.1 now an asterisk paragraph, when specified. Par 7.1 marker intervals longer for tray
systems. Par. 8.1 our practice was clarified. Par. 8.2 construction details surrounding splices have been deleted. Par.
8.4 added ring lugs on CT wiring. Par. 9.1 added testing of pre-fabricated modules. Par. 9.2 specific 2-month
requirement has been deleted. Par. 9.4 made consistent with site forms. Par. 9.5b note on minimum values was
deleted. Par. 9.6 made an asterisk paragraph. Par. 9.7 two copies of test reports now required. Pars. 10.1 and 10.2
references to PCB were removed. Par. 11.1 6,600 V changed to 7,200 V. Par. 11.2a end terminations added. Par. 11.4
modified for consistency. Pars. 12.1, 12.2, 12.3 and 14.7 deleted the requirement to submit test data, () items. Par.
12.2b added VFD feeders. Par. 13.2 added temperature device. Par. 14.2 now covers A-C and D-C controls. Pars.
14.3c, 14.5 and 15.3 clarified that relay settings record data to be used. Par. 14.5 deleted list of possible test devices.
Par. 14.6b primary injection testing added. Pars. 15.2 and 16.1 deleted ductor readings. Par. 17.2 condensed wording.
Par. 17.3 minimum run-in period lowered to 2 hours with the proviso that bearing temperatures have stabilized. Pars.
18.1 and 18.2 acceptable ground resistance values were lowered to meet customary present values. Par. 20.1 added
requirement for detailed test procedures for all packaged unit systems.
Paragraphs renumbered:
Old Par. No.
New Par. No.
Old Par. No.
New Par. No.
1.3, 1.4
1.1, 1.2
14.1-4.4
11.1-11.4
4.4
4.1
15.1-15.3
12.1-12.3
4.9
4.2
16.1-16.3
13.1-13.3
6.1-6.3
5.1-5.3
17.1-17.8
14.1-14.8
6.4, 6.5
5.4
18.1-18.4
15.1-15.4
6.6
5.5
19.2
16.1
7.1
6.1
20.1
17.1
8.9, 8.10
7.2, 7.1
20.2 & 20.3
17.2
9.1, 9.2
8.1, 8.2
20.4
17.3
9.4, 9.5
8.3, 8.4
21.1, 21.2
18.1, 18.2
12.1-12.7
9.1-9.7
22.2, 22.3
19.1
13.1
10.1
23.1
20.1
13.3
10.2
24.1-24.5
21.1-21.5
Exxon Research and Engineering Company, 1992, 1997

THIS INFORMATION FOR AUTHORIZED COMPANY USE ONLY


EXXON RESEARCH AND ENGINEERING COMPANY FLORHAM PARK, N.J.

Potrebbero piacerti anche