Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
American Connector
Company (A)
Case Submission - 3
Submitted to
Prof.D. Krishna Sundar
Group 1
Varun Prabhat Soreng 1401052
Karunagaran S 1401080
Kunal Nagpal - 1401084
I.
The twin goals that Eli Lilly has set for itself are Reducing time-to-market by 50% and
reduce cost of manufacturing by 25%. Both the objectives are aimed at strengthening the
competitive position in the changing industry landscape. The decision on the kind of facility
to set up, not just for the existing products but for future products also, will have a huge
impact on both time-to-market and manufacturing cost.
II.
How does each facilities option affect Lilly's cost structure, capacity
management and product development capabilities? For what type of
products does the proposed flexible facility provide an efficient (i.e. low
cost) manufacturing capability?
Eli Lilly is expected to come up with 37 new active ingredients by the year 2004. These
products will be much more complex and potent thereby requiring much lower production
volumes. However the manufacturing process will be more complex and hence it can be
assumed that a specialised facility will be able to produce maximum 2 types of products in a
single facility. Thus for 37 products, nearly 18-20 specialised facilities will be required in the
future. Compared to this, assuming that a flexible plant will be able to produce 6-7 such
types of complex products in a single facility, nearly 5-6 flexible plants will be required. A
simple calculation of construction cost and annual operating cost for such a scenario is
shown below:
Assumptions:
III.
How does the utilisation of two types of plants compare for a life of 10
years of a product?
From Exhibit 4, it is observed that a specialised plant always has some excess capacity
whereas a flexible plant has excess capacity only in the first 4 years. This is shown
graphically in the chart below:
1.20
1.00
0.80
Specialised
Flexible
0.40
0.20
0.00
The utilisation of a specialised plant is less than that of flexible plant throughout a products
life of 10 years. This is because the expected sales volume of three products is not enough
to utilise the available capacity of a specialised plant. In the future when molecules will
become more potent and hence their volumes will be less, the utilisation of specialised plant
will drop further. On the other hand, a flexible plant producing more number of products will
always have a higher utilisation rate. It will also be more suitable for the more potent, lowvolume products which will be manufactured in the future.
IV.
V.
Not require require retrofitting the plant, in case there was a change in the production
process.
Given Lilly's strategic goals in the 1990's, which option should Steve
Mueller recommend? Are there other options that Lilly should be
contemplating? If so, what are they?
Steve Mueller is picking between the Specialised and Flexible, with the pros and cons as
mentioned in the earlier question. Another option that is possible here is the hybrid one
both specialised and flexible, where the high volume product Alfatine is produced on a
specialised line, while the lower volume products such as Betazine and Clorazine are
produced on a flexible facility. However, this option is feasible only if certain parameters such
as the production process are locked down, and the necessary approvals have been
obtained for the drugs in the specialised plant.
Considering the two major options available and the costs given in Exhibits 3 & 4, let us try
to calculate the
Construction Cost
No. of Rigs
Per Rig cost
Operating Cost / yr
Capacity of Rig (kg)
Utilization (%)
Actual Output of Rig
Cost for First year (mil/kg)
Cost for Second year (mil/kg)
Specialized
Flexible
37.5 million
1.5
25 million
6.8 million
20000
80%
16000
0.001846
0.001065
150 million
3
50 million
9.48 million
7500
65%
4875
0.010905
0.005776
Continuing this process, we can obtain the following graph, considering a life of 15 years for
the plant.
Specialised
Flexible
0
0
0
Years of Operation
We observe that costs for both the processes stabilise after the 10 year mark. Hence, we
can safely assume that this cost structure will continue, provided there are no upsets such
as drugs being rejected at clinical trials. Since competitive pressure in increasing and there
is emphasis on improving manufacturing costs and shortening the time to market, the
flexible option would be preferred.
The flexible plant can impact the second goal which is to reduce the manufacturing cost by
25%. This is because a flexible plant will be much more suitable to produce low volume but
complex products. Since a flexible plant will be able to produce more number of products,
the costs will be spread over across products thereby reducing unit cost of production.
However, the downside of producing more products in a plant is that the utilisation will
reduce due to increase in number of changeovers.
Eli Lilly has set the target of reducing time-to-market by 50% which means reducing 8 to 12
years which it currently takes to 4 to 6 years, which is a huge task considering that the threephase clinical trials take 7 years. The facility construction becomes critical only when Phase
III clinical trials begin. Considering this, facility decision does not have much impact unless
the time for clinical trials is reduced which is not possible since the Phase III trial is for
checking the long-term side-effects of the product and hence it will take 4 years. The only
positive impact that a flexible plant will have on time-to-market is that the time lost due to
delays in constructing specialised facility will be saved.
References
P.Pisano, G., 1997. The Development Factory: Unlocking the potential of process innovation.
Boston, Massachussets: Harvard Business School Press.
******************