In accordance with the policy adopted by the Regional Conservation Authority Board of Directors
on February 5, 2007, new transportation facilities (or facilities being widened) that are capacity
enhancements are required to provide a 5% contribution towards the MSHCP as part of obtaining
coverage under the plan.
The following methodology shall be used to determine the WRC MSHCP contribution using the attached WRC
Section A:
Projects that are 100% paid for by TUMF or Measure A or a combination of these
two sources (contribution towards MSHCP is paid by RCTC and WRCOG directly).
Instructions for
WRC MSHCP Contribution Worksheet -- Roads
(Continued)
Use of Federal funds for MSHCP
contribution on local roads is contingent upon
approval by FHWA. Projects with Federal funds shall be evaluated on a case-bycase basis.
Jurisdiction
Project Name:
Project # (if applicable)
Project Description:
No
Mobilization
Grading and Earthwork
Paving and Base
Curb and Gutter
Relocation of Utilities
Catch Basins and Laterals
Culvert Extensions
Bridge Widening Portions
Other
4) Determine the portion of the project that is funded by TUMF or Measure A, and the MSHCP eligible
construction portion.
A) Total eligible construction cost (total of 3A thru 3I)
$
$
Note: Attach bid sheet/engineer's estimate to verify line item costs. If the fee calculation is based on the
engineers estimate provided at the time of advertisement, then the calculation may need to be adjusted
based on the actual bid award. Adjustment to fees will be accomplished by prorating the fee by the same
percentage that the actual bid increased or decreased in comparison to the engineers estimate.
Report and remit payment of 5% to RCA within 90 days of construction contract award. Be sure to report
all exempt projects.
(Date)
Approved by:
(Date)