Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Al-Hajri Corporation
Kingdom of Saudi Arabia
METHOD STATEMENT
FOR
BUS DUCT INSTALLATION AND TESTING
Document No.: NSH-KBR-SKOP-PRO-E-009
Job No.: 6484-GC-021-SC-008 &
Job No.:6484-AB-012-SC-009
A
B
C
D
Code
Approved
Approved W/Comments
Rejected
Cancelled
Status ()
Legend
KBR
Name
Comments:
Signature
Date
10-Jan-09
For Approval
S. Augustin
Ponraj
Rev.
Date
Reason for
Issue
Prepared By
Name
Signature
Manoj
Sign
Checked
By
Date
D. Harikumar
Sign
Approved
By
Sign
Page 2 of 7
TABLE OF CONTENTS
1. SCOPE
2. PURPOSE
3. REFERENCE
4. DEFINITION
5. RESPONSIBILITIES
6. TOOLS AND EQUIPMENTS
7. MATERIAL STORAGE, HANDLING & INSPECTION
8. INSTALLATION
9. TESTING
10. SAFETY
11. ATTACHMENT
Page 3 of 7
1. SCOPE
This construction procedure covers requirements for the Bus duct installation and
testing in Saudi Kayan Olefins Project. This procedure describes installation
techniques and different requirements to be adhere during execution of bus duct
installation and testing work. It intents to co-relate and control all the tasks needed to
be done in order to get a satisfactory results.
2. PURPOSE
The purpose of this procedure is to ensure all the installation and testing shall be
carried out in a neat, efficient and workmanlike manner, assuring satisfactory /
proper operation. The work shall be in accordance with the requirements of the
project specifications, and shall fulfill their true intent and meaning.
3. REFERENCE
IEC
IEEE
NACE
NEMA
NEC
000-65S-0001
000-65S-0002
000-65S-0057
SES-E25-S01
SES-Q01-G02
4. DEFINITION
SKOP
KBR
NSH
Page 4 of 7
5. RESPONSIBILITIES
5.1
5.2
QA/QC Manager
QA/QC Manager is responsible for the implementation of all required quality
control activities and inspection for this particular job.
5.3
QA/QC Engineer
QA/QC Engineer is responsible for the proper carrying out of the inspection
respective to this procedure.
5.4
Electrical Manager
Electrical Manager will be coordinating with concerned personnel at site, plan
the daily work schedule, allocate the job to concerned supervisors, and
controlling the installation works in all the areas.
5.5
Electrical Supervisor
Electrical supervisor is responsible to monitor all day to day field activities,
assuring that implementation is as per this procedure and relevant referenced
standards and as per HSE policy manual.
5.6
The following necessary construction equipment / instrument, tools & tackles shall
be used to carry out the installation works.
Page 5 of 7
7.1
7.2
Visual inspection shall be carried out to check condition and physical damage
of bus ducts.
7.3
7.4
7.5
7.6
7.7
7.8
7.9
To ensure that the bus ducts and accessories are stored as per the
manufacturers recommendations.
7.10
When outdoor storage is necessary, elevate well above ground and enclose
with durable, waterproof wrapping.
8. INSTALLATION
8.1
Erect horizontal and vertical supports at the required locations as per lay out
drawings and manufacturers instructions.
8.2
The bus duct is to be erected and routed as per the erection drawings.
8.3
8.4
Assembling of all the parts and connections of bus duct shall be made at site.
8.5
8.6
Outdoor enclosures shall have a sloped top that prevents collection of water.
Page 6 of 7
8.7
The insulators in bus ducts shall be inspected for any possible damage.
8.8
8.9
Contact surface of bus bars, bus bar bolts and nuts shall be thoroughly
cleaned and wiped.
8.10
8.11
Confirm the complete bolting for all bus duct and conductors and also confirm
gasketing and check for the water leakage between the ducts.
8.12
Bolted bus bar connections shall be made with the bolts passing through the
bus bars in a way that they can be properly torqued and locked. Ensure that
the connections are torqued as per the manufacturers instructions.
8.13
Termination at correct point at both ends and proper earthing of bus duct to
be checked.
8.14
8.15
8.16
8.17
Ensure for proper clearance, where visible, between bus bars, and between
bus bars and the enclosure.
8.18
8.19
8.20
8.21
The bus duct should be cleaned and ensure that it is free of any foreign
materials inside and then close the bus duct.
8.22
The opening in the wall where the bus duct enters the switchgear room shall
be completely sealed to avoid rainwater entry.
Page 7 of 7
9. TESTING
9.1
The following tests are to be carried out on the bus duct with in the presence
of vendor representative,
IR Test
HV Test
10. SAFETY
10.1
All safety precautions will be taken care as required as per HSE Plan.
10.2
NSH Safety Supervisor shall carry out the safety site inspections to ensure
that safety requirements laid out in the safe work plan are followed during and
after the installation work. NSH Safety Manager / Supervisor shall review
Safety Action Plan and secure Work Permit if necessary prior to start of any
activities shall be strictly followed as per JSA.
10.3
11. ATTACHMENT
JSA
******EEnndd******