SUBJECT:
SOP No.
SOP OF DESIGN AND DEVELOPMENT DEPARTMENT (D&D)
2.0
PURPOSE:
Issued Date:
3.0 SCOPE:
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10.
3.11
Reference No:
Page 2 of 5
Task
4.1
Electronic / Manual
(E / M)
Responsible
Personnel
E/M
HOD
Incharge Prod.
Development
PRODUCT DEVELOPMENT
Receipt of Drawing(s) / Sample(s) / Data Sheet(s) through
Commercial Department for new development queries
4.2
4.3
E/M
Incharge Prod.
Development
4.4
E/M
HOD
4.5
E/M
Incharge Design
Section
4.6
HOD
4.7
HOD
4.8
Incharge Prod.
Development
4.9
E/M
Incharge Prod.
Development
Incharge Design
Section
E/M
Incharge Design
Section
HOD
E/M
Incharge Design
Section
of
4.10.
4.11
4.12
4.13
4.14
Submission of FPA to QA
HOD
4.15
HOD
4.16
Incharge Design
Section
Remarks
Page 3 of 5
SERVICES
5.1
5.2
E/M
HOD
Incharge Design
Section
5.3
Incharge Design
Section / HOD
5.4
HOD / Incharge
Design Section
5.5
Incharge Tool
Room
6.1
Incharge Design
Section
6.2
Incharge Design
Section
6.3
HOD
6.4
Incharge Design
Section
6.5
HOD
6.6
HOD / Incharge
Design Section
7
7.1
Annexure 1
VENDOR DEVELOPMENT
VENDOR EVALUATION - NEW ORDER
Annex -2
7.1.1
7.1.2
7.1.3
HOD
7.1.4
Incharge Vendor
Development
7.1.5
HOD
7.1.6
Incharge Vendor
Development
7.1.7
HOD
Annex -3
Annex - 4
Page 4 of 5
7.2
7.2.1
7.2.2
7.2.3
7.2.4
C&S case will be prepared on C&S proforma (Annex -6) after receipt
of all relevant information(s)
Incharge Vendor
Development
7.2.5
HOD
7.2.6
C&S Committee will review C&S cases and if found OK will be sent
to Incharge Vendor Development for arrangement of C&S Meeting
C&S Committee
7.2.7
C&S Committee
7.2.8
HOD
7.2.9
Incharge Vendor
Development
ERP / M
Commercial
Department
Incharge Vendor
Development
7.2.10.
7.2.11
7.3
7.3.1
Incharge Vendor
Development
7.3.2
Incharge Vendor
Development
7.3.3
Incharge Vendor
Development
Annex - 6
(Annex -7)
Page 5 of 5
7.4
7.4.1
(Annex -8)
7.4.2
7.4.3
Incharge Vendor
Development
7.4.4
In case of acceptance of samples, vendor will be informed alongwith FPA report for the submission of Pilot Lot
Incharge Vendor
Development
7.4.5
Incharge Vendor
Development
7.4.6
Vendor will submit Pilot Lot along with Inspection report within
approved Time frame
7.4.7
Incharge Vendor
Development
7.4.8
In case of acceptance of Pilot Lot, vendor will be informed alongwith Inspection report. In addition to above MMD will also be
informed for issuance of monthly schedule for regularization of
supplies.
Incharge Vendor
Development
7.4.9
Incharge Vendor
Development
Annex - 8
(Annex 9)
Annex -9
(Annex 10)
Annex -10
Date: 31-01-2010
Reviewed By:
Approved By: