Sei sulla pagina 1di 64

Republic of Indonesia

Ministry of Public Works


Directorate General of Highways

Strategic Roads Infrastructure Project


(SRIP)
Technical assistance for Core Team Consultant (CTC)

To Support the Management Unit


Under IBRD Loan No. 4834-IND

PALMERAH RING ROAD JAMBI


ROAD SAFETY AUDIT REPORT
FINAL DESIGN & CONSTRUCTION
FEBRUARY 2012

Table of Contents
1.

Summary in Bahasa................................................................................................. ii

2.

Introduction
2.1.
2.2.
2.3.
2.4.
2.5.
2.6.
2.7.
2.8.
2.9.
2.10.

3.

4.

Audit Process ............................................................................................


SRIP
.......................................................................................................
Objectives of the Road Safety Audit Report ................................................
Project Location .........................................................................................
Project Information
.................................................................................
Plans and Documents
......................................................................
Traffic Volumes
.................................................................................
Members of the Audit Team ......................................................................
Site Visit ......................................................................................................
Completed Sections.....................................................................................

Problems and Recommendations


3.1. Existing Pavement Conditions......................................................................
3.2. Pavement Materials .................................................................................
3.3. Completed Section Safety Issues................................................................
3.4. Bends...........................................................................................................
3.5. Junctions......................................................................................................
3.6. Road-Side Activity........................................................................................
3.7. Narrow Road ...........................................................................................
3.8. Guard rail
.............................................................................................

1
1
2
2
2
5
5
5
5
7

9
14
16
20
24
42
44
44

Road Safety Audit of Construction


4.1. Inadequate Safety Culture
........................................................................ 48

Appendix A. References .............................................................................................

50

Appendix B. Safety Concerns at Roadworks - English ..........................................

51

Appendix C. Safety Concerns at Roadworks Bahasa...........................................

52

Appendix D. Maintenance of Traffic Flow

53

..

Appendix F. High specification of traffic lights and Equipment from DGLT........... 54

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Kesimpulan Permasalahan dan rekomendasi dalam Bahasa


Indonesia
Kondisi Perkerasan yang ada saat ini
Permasalahan
Perkerasan yang ada saat dalam kondisi sangat memprihatinkan di banyak lokasi dan
banyak yang rusak di berbagai tempat. Hal ini menyebabkan kondisi yang sangat kacau
pada saat ini dan menimbulkan banyak masalah, terutama menyulitkan untuk kendaraan
besar seperti truk sehingga menimbulkan kemacetan.
Semua masalah ini memiliki akibat terhadap keselamatan dijalan karena mereka
menyebabkan kelelahan kepada pengemudi kendaraan dan kemungkinan terjadi
kecelakaan antara truk-truk besar dan sepeda motor maupun pengendara ataupun
pengguna jalan lainnya.
Kondisi tersebut juga tidak dapat ditoleransi untuk pejalan kaki di banyak lokasi, tapi
untungnya pada saat survey dilapangan hanya terlihat beberapa pejalan kaki.

Rekomendasi

Kontraktor sekarang memiliki tugas untuk menjaga jalan yang ada dalam kondisi
aman dan perlu menjadi prioritas utama untuk staf dan peralatan.
Prioritas terhadap kondisi jalan yang terburuk dan ditangani dengan cepat.
Hubungan dengan polisi lalulintas setempat sangat diperlukan untuk memastikan
keputusan yang terbaik dalam pengaturan lalulintas karena mereka aktif berada
dilapangan.
Masalah terhadap hasil galian lubang harus diselesaikan secepatnya.

Bahan Perkerasan
Permasalahan.

Selama pertemuan dengan Engineer Pengawasan dan Kontraktor, ada banyak


diskusi tentang kesulitan menentukan bahan perkerasan yang benar untuk
memperbaiki atau membangun kembali jalan.
Bahan untuk rekonstruksi adalah AC-WC, AC-BC, AC-Base, Base Class Agregat A,
Base Kelas B dan timbunan pilihan.
Pengawas Lapangan menunjukkan bahwa material timbunan pilihan harus diubah
dengan menggunakan kerikil yang berpasir.
Drainase yang buruk sangat berkontribusi pada masalah kerusakan perkerasan di
lokasi.

ii

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Rekomendasi

Spesifikasi untuk bahan yang paling efektif dan metode kerja perlu disepakati
secepatnya oleh pihak yang terkait, dan dimungkinkan dalam justifikasi teknis pada
saat ini.

Keamanan dijalan pada Bagian jalan yang Sudah Diperbaiki


Permasalahan.
Ada kekhawatiran tentang masalah keselamatan di jalan pada bagian jalan yang sudah
dikerjakan oleh proyek APBN 2011 yang dilontarkan oleh Bank Dunia, pengamatan
dilapangan dengan desain yang ada perlu dikembangkan lebih lanjut karean sangat
berkesinambungan dengan jalan yang akan diperbaiki melalui proyek SRIP.
Isu-isu keselamatan meliputi:
Pemasangan zona sekolah, (lihat juga 2.10 di atas)
Penyelesaian persimpangan pada STA 16+415
Pedestrian fasilitas
Konstruksi Bahu jalan
Pulau-pulau yang sudah didesain dan penyeberangan banyak yang tidak dikerjakan pada
loksai persimpangan. Site engineer menyatakan bahwa persimpangan ini tidak akan
memperbaiki persimpangan tersebut di bawah proyek SRIP saat ini. Dan juga menunjuk
pada Surat Bank Dunia tanggal 1 Juni 2011 khusus meminta untuk memproteksi pipa
Pertamina di lokasi ini.
Kemungkinan persimpangan tersebut tidak dikerjakan sesuai dengan desain aslinya.

Fasilitas pejalan kaki.


Permasalahan.
Masyarakat setempat sudah mencoba untuk meningkatkan rambu rambu peringatan
pada lokasi yang banyak pejalan kaki agar terjadi perlambatan kendaraan yang berlalu
lintas dengan berbagai macam cara. Ini seharusnya dilakukan dengan benar oleh
desainer

Konstruksi bahu jalan.


Permasalahan.
beberapa tipikal bahu jalan sudah banyak yang rusak yang disebabkan kendaraan berat.
Konstruksi bahu jalan tersebut (APBN proyek), terdiri atas Agregat Kelas B yang ditutup
dengan lapisan laburan Satu lapis (Burtu).
Bahan yang diusulkan untuk bahu di BOQ SRIP adalah Agregat kelas S dan terbuka, jadi
bahu jalan yang ada dalam SRIP lebih buruk daripada konstruksi bahu jalan yang sudah
iii

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

selesai yang didanai dengan anggaran APBN. Meskipun proyek APBN baru selesai pada
Desember 2011, namun banyak bahu jalan yang sudah rusak. Ini bukan pertanda baik
untuk desain bahu yang diusulkan.

Rekomendasi
Diskusi perlu dilakukan antara instansi terkait untuk menyepakati pekerjaan tambahan di
lokasi yang sudah dikerjakan dengan anggaran APBN, pekerjaan tersebut adalah
sebagai berikut:
Zona Sekolah perlu diaplikasikan pada STA.17 +000 dan STA.3+300.
Rambu lalulintas perlu di tambah serta rumble strip perlu dipasang pada tempat
penyeberangan dan menuju lokasi yang padat penduduk untuk menggantikan
rambu buatan sementara.
Simpang pada STA 16+415 perlu dikerjakan sesuai desain jalan pada gambar
kontrak SRIP.
Kegagalan konstruksi bahu jalan pada proyek APBN dapat dijadikan bahan
pertimbangan pada proyek SRIP sebagai berikut:
Tikungan pada proyek SRIP perlu didesain kembali , ini merupakan penerapan
terbaik yang sudah dilakukan oleh proyek APBN dengan menggunakan marka dan
patok pengarah.
Desain Bahu jalan perlu ditinjau untuk menghindari kegagalan yang telah terjadi
pada proyek APBN.

Tikungan
Permasalahan.
Ada banyak tikungan di ruas jalan ini dengan berbagai macam Rambu-rambu yang
bermacam-macam namun indikasi tersebut tidak didetailkan dalam pemasangan guard
rail.
Beberapa tikungan tajam tidak ada rambu peringatan yang sesuai hanya rambu
tikungan saja yang diletakan sebelum tikungan (Tidak ada rambu penunjang
lainnya)
Jarak Antar patok pengarah tidak didetailkan dalam gambar untuk diterapkan pada
lokasi yang membutuhkan.
Ada beberapa rambu arah namun tidak dilengkapi dengan patok pengarah.
250 unit patok pengarah di BOQ tanpa informasi di mana patok tersebut akan
diletakan.
Ada banyak tikungan yang membutuhkan delineasi baik seperti rambu-rambu
peringatan namun tidak memberikan informasi yang cukup bila berdiri sendiri.
Ada juga beberapa daerah timbunan dan lokasi gorong-gorong yang perlu
dilengkapi patok pengarah.

iv

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Rekomendasi

Jarak patok pengarah perlu disusun dan digambar untuk menentukan banyaknya
patok pengarah yang dibutuhkan pada tikungan, timbunan ataupun gorong-gorong
sehingga jumlah total kebutuhan tersebut dapat dipastikani dalam BOQ.

Persimpangan Secara Umum


Permasalahan.
Desain persimpangan dan konstruksi di Indonesia biasanya memiliki kelemahan yang
menyebabkan masalah keselamatan, terutama untuk pejalan kaki. Hal ini dapat diamati
dengan melihat persimpangan yang ada di Jambi dan desain yang diusulkan untuk
persimpangan.
Lansekap adalah manfaat besar bagi lingkungan dan memiliki efek "menenangkan" pada
pengendara yang baik untuk keselamatan tetapi juga menyebabkan banyak
permasalahan. Seperti halnya menghambat pergerakan pejalan kaki serta membuat
rambu-rambu jalan tidak terlihat.

Rekomendasi

Perawatan tanaman harus dilakukan di setiap persimpangan untuk memastikan


tidak menhambat gerakan pejalan kaki yang aman terutama pada pulau-pulau
yang indah dipersimpangan.
Pertamanan dan penanaman jangan sampai menghalangi rambu-rambu jalan
atau pejalan kaki pada saat penanaman atau di masa depan.
Penanaman harus direncanakan dengan kesadaran akan pemeliharaan dimasa
mendatang untuk meminimalkan masalah keamanan kepada pengguna jalan
dan pekerja pemeliharaan tanaman.
Pertamanan selalu membutuhkan pekerjaan pemeliharaan yang rutin. Perlu
pelatihan khusus terhadap para pekerja pemeliharaan tanaman ditengah tengah
kesibukan lalulintas yang sangat tinggi agar dapat bekerja secara aman dan
untuk mengenakan pakaian yang mudah dilihat.

Persimpangan STA 0+000


Permasalahan.

Leher sempit yang diusulkan di awal jalan lingkar akan menyebabkan konflik serius.
Pulau-pulau indah yang diusulkan akan menimbulkan masalah serius bagi
pergerakan pejalan kaki.
Fase Sinyalisasi menunjukkan konflik antara pejalan kaki dan kendaraan.
Tidak ada detil gambar lampu lalulintas cukup untuk memastikan lokasi yang tepat
serta standard lampu yang berspesifikasi tinggi. Lihat lampiran F
Tidak ada jalur atau halte bus..
Ada median kaki Jambi tidak jauh dari persimpangan yang tampaknya tidak
digambarkan dalam desain.

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Rekomendasi

Pulau-pulau indah yang diusulkan dan penyeberangan harus didesain ulang untuk
memastikan pergerakan pejalan kaki mudah dan aman dan pendekatan yang lebih
luas untuk bypass.
Fase Sinyalisasi harus direvisi kembali masih adanya konflik antara pejalan kaki
dan kendaraan
Lokasi lampu lalulintas serta spesifikasinya berikut ukuran lampu harus ditentukan
dengan standar yang tinggi serta penambahan lampu lalulintas kedua (secondary
Traffic light) , Digital penghitung waktu dan lampu harus mempunyai pencahayaan
yang sangat baik (LED Lamps). Lihat lampiran F
Tambahkan halte bis.
Desain dari pulau pulau harus ditinjau kembali dan digambarkan sesuai kondisi
kondisi existing.
Digital penghitung waktu sangat diperlukan karena baik untuk visibilitas Terutama
di malam hari.

Persimpangan Sta. 8+450


Permasalahan

Pulau-pulau indah yang diusulkan akan menimbulkan masalah serius bagi


pergerakan pejalan kaki.
Fase Sinyalisasi menunjukkan konflik antara pejalan kaki dan kendaraan.
Tidak ada detil gambar lampu lalulintas cukup untuk memastikan lokasi yang tepat
serta standard lampu yang berspesifikasi tinggi. Lihat lampiran F
Tidak ada jalur atau halte bus..

Rekomendasi

Pulau-pulau indah yang diusulkan dan penyeberangan harus didesain ulang untuk
memastikan pergerakan pejalan kaki mudah dan aman.
Fase sinyalisasi harus direvisi untuk menunjukan semua pergerakan dan fase.
Lokasi lampu lalulintas serta spesifikasinya berikut ukuran lampu harus ditentukan
dengan standar yang tinggi serta penambahan lampu lalulintas kedua (secondary
Traffic light) , Digital penghitung waktu dan lampu harus mempunyai pencahayaan
yang sangat baik (LED Lamps). Lihat lampiran F

Persimpangan Sta. 16+415


Permasalahan.

Persimpangan dengan pulau-pulau belum dibangun pada proyek APBN dan Bank
Dunia meminta untuk memproteksi pipa pertamina.

vi

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Rekomendasi

Diskusi harus diadakan antara pihak yang berkepentingan untuk memastikan


persimpangan selesai dalam satu proyek atau lain.
Pulau-pulau indah yang diusulkan dan penyeberangan harus didesain ulang untuk
memastikan pergerakan pejalan kaki mudah dan aman.
Memastikan perlindungan pipa Pertamina segera dilaksanakan

Persimpangan Sta. 18+ 440


Permasalahan.

Desain untuk penyeberangan bagi Pejalan kaki, pulau dan pertamanan sangat
buruk.
Penyeberangan yang diusulkan dan pulau-pulau indah yang sangat buruk dalam
gambar dan tidak memungkinkan untuk gerakan pejalan kaki yang sebenarnya
diharapkan.
Fase sinyalisasi tidak cukup untuk menunjukkan semua gerakan pejalan kaki.
Detail Lampu lalulintas tidak mengggambarkan penempatan lampu yang optimal
dan spesifikasi tinggi.

Rekomendasi

Pulau-pulau indah yang diusulkan dan penyeberangan harus didesain ulang untuk
memastikan pergerakan pejalan kaki mudah dan aman
Fase sinyalisasi harus direvisi untuk menunjukan semua pergerakan dan fase.
Lokasi lampu lalulintas serta spesifikasinya berikut ukuran lampu harus ditentukan
dengan standar yang tinggi serta penambahan lampu lalulintas kedua (secondary
Traffic light) , Digital penghitung waktu dan lampu harus mempunyai pencahayaan
yang sangat baik (LED Lamps). Lihat lampiran F

Persimpangan Sta. 22 +550


Permasalahan

Penyeberangan diusulkan dan pulau yang indah tidak memungkinkan untuk


gerakan pejalan kaki yang sebenarnya diharapkan

Rekomendasi

Pulau-pulau indah yang diusulkan dan penyeberangan harus didesain ulang untuk
memastikan pergerakan pejalan kaki mudah dan aman.

Kegiatan Disekitar Ruas Jalan


Permasalahan.
Truk membentuk persentase yang sangat tinggi dari pergerakan lalu lintas tetapi mereka
juga sering berhenti di bahu atau di luar bahu di berbagai lokasi depot peralatan berat
dan lapangan. Banyak truk yang kelebihan muatan yang diijinkan. Hal ini menyebabkan

vii

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

kerusakan ekstrim pada jalan lama dan telah menyebabkan kerusakan pad bahu jalan
yang baru.
Desain yang diusulkan dan metode konstruksi tidak memperhitungkan kebutuhan sopir
truk untuk berhenti dan mereka tampaknya mengabaikan potensi kerusakan yang sangat
serius.

Rekomendasi

Struktur jalan harus harus dirancang untuk dengan berdasarkan kendaraan berat
yang melalui jalan tersebut dan ini harus mencakup desain sebagai berikut;
Bahu jalan yang diperkeras agar dapat dilewati oleh truk biasa, termasuk akses ke
depot.
Desain dan konstruksi area istirahat dan jalur bis.
Jembatan timbang harus dimasukan ke proyek atau direncanakan pada proyek
berikutnya.

Badan Jalan yang Menyempit


Permasalahan.

Tidak ada Detail desain pada lokasi jalan yang menyempit. Kondisi ini sangat
berbahaya bagi pengguna jalan dimana kecepatan kendaraan harus diperlambat
(Dari arah utara ke selatan), meletakan awal atau akhir median jalan harus
diperhitungkan karena akan sangat berbahaya bila awal median hampir dekat
dengan tikungan (dari selatan ke utara).

Rekomendasi

Marka arsir pada jalan yang menyempit harus ditambahkan.


Median harus diperpanjang atau dikurangi sampai tikungan awal (dari selatan ke
utara).

Guard Rail
Permasalahan

Banyak sisi jalan yang terjal dengan bahu sempit serta tersembunyi di banyak
tempat dan juga tidak bisa dilihat pada gambar kontrak.

Rekomendasi

Tim lapangan harus mensurvey kembali untuk mengetahui lokasi dimana tempat
tempat yang terjal ada ruas jalan tersebut. Apabila beda tingginya melebihi dari 2
meter maka harus di desain dengan detail yang baik dengan menggunakan guard
rail.
Guard rail harus dipasang untuk melindungi pengguna jalan.
Ada peningkatan pada proyek APBN di link jalan yang sama, tapi masih tidak
memadai karena hanya menggunakan patok pengarah.
viii

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Budaya Keselamatan jalan yang Tidak Memadai


Permasalahan

Hanya sedikit atau tidak ada peringatan pad zona konstruksi baik di awal proyek
atau di mana pekerjaan konstruksi dilakukan.
Hanya Site Engineer & Survei staf dari konsultan yang memakai pakaian dengan
visibilitas keselamatan yang tinggi.

Rekomendasi

Manajemen lalu lintas harus ditingkatkan khususnya pada awal dan akhir proyek,
seperti ; Memasang papan proyek, Rambu Peringatan, pemasangan barier
(kerucut) serta memoperbanyak jumlah kerucut yang digunakan.
Harus ada upaya langsung untuk meningkatkan jumlah pekerja yang mengenakan
pakaian keselamatan jaket safety.
Staf pengawas Kontraktor harus menerapkan contoh yang baik dengan selalu
mengenakan pakaian keselamatan di lapangan.
Ikuti instruksi dalam spesifikasi kontrak dan saran yang diberikan dalam Lampiran
B&C

ix

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

1.

Palmerah Ring Road Jambi

Introduction

2.1. Audit Process


Road Safety Audit (RSA) can be defined as a formal examination of a highway or
traffic project in which an independent qualified auditor or team of auditors reports on
the road safety problems associated with the designs or construction of the project and
makes recommendations on improvements.
It started in the UK some twenty years ago and is now common practice around the
world. There are several Road Safety Audit Guidelines that are used as standard
practice for Audits around the World; an adaption of the Australian Guidelines are
currently used in Indonesia
Audits can be carried out at various stages and arguably the earlier the better:
Feasibility
Preliminary Design
Final Design
Construction
Pre-Opening
Existing Road

2.2. SRIP
The Strategic Roads Infrastructure Project (SRIP) was developed to meet the
increasing traffic demand and institutional requirements following easing of the 1997
financial crisis in 2001. SRIP, which is supported by the World Bank under IBRD Loan
4834-IND, is being implemented by the Directorate General of Highways within the
Ministry of Public Works over the five-year Loan period following its effectiveness date
of 01 November 2007. Project implementation was initially scheduled to be complete by
the end of 2011 but has now been extended to the end of June 2013.
SRIP originally included twenty two (22) Civil Works packages of road betterment,
capacity expansion and new roads & bridges, encompassing urban and inter - urban
National Roads in 7 provinces (4 provinces on Java and 3 provinces on Sumatra) and
included a trial Performance Based Contract (PBC). The scope of civil works however
has now been reduced to nineteen (19) packages after dropping two civil works
packages and PBC. Details for these packages are given in Appendix A. The
Implementation Support Component includes two (2) road safety components: the
Integrated Road Safety Management System (IRSMS-1) for the Directorate General of
Land Transport (DGLT) and IRSMS-2 for the Indonesian National Traffic Police Corp.
SRIP project implementation was initially supported by four key consulting assignments:
(i) Core Team Consultants (CTC); (ii) Construction Supervision Consultants for nonMetropolitan roads (CSC-1); (iii) Construction Supervision Consultants for Metropolitan
roads (CSC-2); and (iv) Procurement Advisor, which has now been demobilised. The
1

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

original Core Team Consultants responsibilities included a pilot road safety audit on
Semarang Demak and following the successful completion of this audit, the scope of
works was modified to include road safety audits on all SRIP packages.

2.3. Objectives of the Road Safety Audit Report


The objectives of this Road Safety Audit report are to summarise the systematic
review/checking of the safety aspects of the completed road plans (DED plans), traffic
schemes and list the Problems and make feasible Recommendations for
improvements to the designs and construction process.

2.4. Project Location Plan


The proposed bypass project is shown below

Project Map Showing Partial Completion & SRIP Sections

2.5. Project Information


Approximately half the original SRIP project has already been completed with local
funding, see Project Location Map above and transition between uncompleted and
completed in photo below.
2

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Start of
completed
section STA
6+400

Typical completed section shown above and typical cross-sections of proposed SRIP
project are shown below:

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

2.6. Plans and Documents


The documents used in this audit were the contract drawings dated April 2011, but only
December 2007 documents were in site office. The project has changed dramatically
since original designs and aproximately half is already completed with local funding.

Contract Drawings Used for Audit (2011) & On Site (2007)

2.7. Traffic Volumes


The existing road section has a high volume of traffic, mainly heavy trucks carrying coal
and palm oil, or empty, and a small but important number of vulnerable road users;
motorcyclists and pedestrians.
The high volume of traffic in the area reinforces the need to provide a safe road.

2.8. Members of the Audit Team


The road safety audit team members are from the Core Team Consultants of SRIP:
Mike Goodge
Agus Herudianto

Senior Road Safety Audit Engineer


Road Safety Audit Engineer

2.9. Site Visit


The site was visited on 18th January, during daylight hours and darkness and travelled
in both directions. The weather was fine.
The contractors only mobilised a few weeks back and only a few graders and trucks
were in evidence, forming drainage channels at a few locations

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Meetings were held with on the project and in the site office with the following:
Mr Idwan Rozanova, Supervision Engineer
Mr Suyadi, Quality Engineer
Mr Edi Sunaryo, Chief Inspector
Mr Edi Susanto, Contractor
Mr Ariansyah, Contractor

Start of Site Visit near End Junction STA 22+550

Office Meeting:

Reviewing Junctions

& Pavement Material Tests


6

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Reviewing Junction 8+450

Palmerah Ring Road Jambi

& Pavement Material Test Site

Night-time
Visit

2.10

Completed Sections

In a letter dated June 1, 2011, to Mr Harris Batubara, (Director of Planning, Directorate


General of Highways), Mr Mitsuyoshi Asada, (World Bank Task Team Leader SRIP)
suggested several measures still need to be carried out on the completed section
including: that the project provide school safety zones for two schools, (sekolah Dasar
Negeri 211/IV in Kota Baru and Sekolah Dasar Negeri 207/IV in Kecematan Jambi
Selatan) that have direct access to the road to provide safe access for school children.
The locations of these two schools are shown in the photos below.

School at STA.3+300
7

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

School at STA.17+000
The World Bank letter also requested protection of the Pertamina pipe at Kenali
intersection STA 16+415, see below.

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

2.

Palmerah Ring Road Jambi

Problems and Recommendations

3.1 Existing Pavement Conditions


Problem
The existing pavement is in very poor condition at many locations and extremely
damaged in others. This is causing very chaotic conditions at times and many problems,
mainly to trucks, involving congestion, getting stuck, breaking down and over-turning.

Congestion & Extremely Bad Road Condition near End of Project

Queue Approaching End of Project


The congestion was caused by very poor road condition and trucks trying to avoid deep
holes but most could not. This problem lead to grid-lock at times.
One truck did get stuck during the night visit and had to be hauled out by another

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Road Condition near End of Project


Other very poor sections of road are shown below:

10

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

The bad road condition had consequences related to safety. Several vehicles were
observed being repaired, on or at the side of the road, see below:

Three vehicles were seen to be completely stuck, one at night. The truck below had to
be pushed out of the deep hole by a contactors grader. The grader then repaired the
hole.
11

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Truck completely
stuck a few metres
from signal junction at
STA 8+450

Grader Repairing Hole After Removing Stuck Truck

Truck Fell in Ditch in Middle of Daytime 18th January


12

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

All these problems have safety implications as they lead to frustrated drivers, damaged
vehicles and severe conflicts between heavy trucks and motorcycles.
Conditions are also intolerable for pedestrians at many locations, but luckily there are
very few pedestrians even at the junctions, (see photos throughout this report).

Typical Shoulder Conditions at Many Sections of Project


Section 1.8 of Contract Specifications, Maintenance of Traffic Flow, see APPENDIX D,
states the following:
It is the intent of the Article in this Section to ensure that during the performance
of the Works al existing roads are kept open for traffic and are maintained in a
safe and usable condition ----
The word traffic in this section often connoted as any kind of vehicles shall
mean all vehicles and pedestrians
There is little evidence on site of this duty being carried out. While one grader did help
at truck near STA 8+450, and repair the deep hole, there was no staff and no equipment
apparent near the worst problem near STA 22+000

Recommendations
The contractor now has a duty to maintain the existing road in a safe
condition and it needs to be a top priority for his staff and equipment.

A priority list of worst locations should be agreed and tackled as a matter


of urgency

Liaison is needed with local police to decide best traffic management. They
are active on the road, see below:

13

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Problems over materials used needs to be resolved immediately, see


below:

3.2 Pavement Materials


Problem
During meetings with the Supervision Engineer and Contractors, there was much
discussion on the difficulties of specifying the correct pavement material to repair or
rebuild the road
The material for reconstruction is AC-WC, AC-BC, AC-Base, Aggregate Base Class A,
Aggregate Base Class B and Selected Embankment
Efforts to use these materials for repairs had recently been carried out, but very
unsuccessfully, see photos below.

14

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

The materials used had not been effective as the surface deteriorated almost straight
away, see below:

15

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

The Supervision Engineer suggests that the Selected Embankment should be changed
to Sandy gravel.
Poor drainage and other works issues probably contributed to continuing problems at
the above location and other sections along the road

Recommendations

3.3

The specifications for the most effective materials and methods need to be
agreed as soon as possible by the relevant authorities, possibly in the
current Design Review

Completed Section Safety Issues

Problems
There are safety concerns on the completed sections of road that were raised by the
World Bank, observed on site or in the contract documents that need addressing. They
are relevant to the continuity of the ring road and thus the SRIP sections.
The safety issues include the following:

Installation of school zones, (see also 2.10 above)


Completion of junction at STA 16+415
Pedestrian facilities
Shoulder construction

Photos illustrating all these items are shown below:

16

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Junction STA 16+415

Approach to Junction. Tee Junction Sign but Operates as Fast Bend

Centre of Junction

Exposed Pertamina pipe

17

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

The proposed islands and crossings are missing from this junction and there is a
temporary wooden pole holding up wires.
The Supervision Engineer stated that this junction will not be carried out under the
current SRIP project.
The World Bank letter of June 1, 2011 specifically requested protection of the Pertamina
pipe at this location and it is understood that this is currently being addressed within the
locally funded project but with no intention of completing the junction to the original
design, shown below

Design for Junction at STA 16+415

Pedestrian Facilities

Homemade Safety Feature at Pedestrian Crossing


18

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

The local communities shown above have tried to increase the warning of pedestrians
and slow traffic by the home-made features shown above. This should have be done
correctly by the designer
Shoulder Construction

Typical Shoulder Failure Caused by Heavy Trucks


The completed shoulders, (APBN project), comprise Aggregate Base Class B
covered with SST (Burtu).
The proposed material for the shoulders in the SRIP BOQ is Aggregate based class S
and open graded and thus weaker than the completed sections
Even though the APBN project was only finished in December 2011, there are many
damaged sections already. This does not bode well for the proposed shoulder design.

Recommendations

Discussions need to take place between relevant agencies to agree how


additional works can be carried out on the completed sections, including the
following;

19

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

School zones need to be installed at STA.17+000 and STA.3+300 on


completed sections of road

Additional signing and rumble strips should be installed at the busiest


crossings to replace home-made features on the completed sections of road

Junction at STA 16+415 needs completion, see 3.5 below

Lessons learned from the completed sections need to be applied to the SRIP
construction as follows:

Bends on the new project need to be designed to best practice on the


completed section, see 3.4 below

Shoulder design in new sections needs to be reviewed to avoid early failure,


see 3.6

3.4

Bends

Problem
There are many bends on the new project with a variety of different signs but no clear
indication of the proposed delineation using guard rails. See contract drawings below:

20

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Sharp Bend Above Has No Adjacent Warning Signs


Only Series of Bends Signs Some Way in Distance
Three of the 4 standard types of bend warning signs are used but most need guide
posts too to be effective, particularly the Series of Bends signs 1g or 1f, see below

Guidepost Spacing but No Schedule of Locations


21

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

The photos below illustrate the benefit of having well located guide posts to give much
more information to motorists than the warning signs

Series of Bends Sign on Completed Road but No Guide Posts

Bend That is Very Well Defined by Guide Posts

Guide Posts Work Well at Night Too

22

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Bend on Unimproved Road Without Guide Posts Note Skid Mark

Guide Posts Also Used at Embankments & Culverts

Problem
There are 250 guide posts in the BOQ but without any information as to where they are
to located
There are many bends that need good delineation as the warning signs are not
adequate when used alone. There are also some embankments and culverts requiring
guideposts

Recommendation
A schedule of guideposts needs to be drawn up to determine numbers
at each bend, embankment and culverts to ensure there is an adequate
number within the BOQ
23

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

3.5

Palmerah Ring Road Jambi

Junctions

Problems
Junctions design and construction in Indonesia typically has weaknesses that cause
safety problems, particularly for pedestrians. This can be observed by looking at
existing junctions in Jambi and the proposed designs for the junctions, see below:

Crossing in Jambi Leading to Drain & Raised Island Unsuitable for Pedestrians

Close-up of Drain Above

Footpath at Existing Junction STA 0+000

Landscaping is a great benefit to the environment and has a calming effect on


motorists that is good for safety but it also leads to many problems too. It often blocks
pedestrian movements as shown above and often hides signs, see below:
24

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

U Turn Sign Hidden by Palm Tree

Palmerah Ring Road Jambi

U Turn Sign in Front of Palm Tree

Best Practice is to Only Allow Low Level Planting Near Junctions or Gaps

Landscaping maintenance is
usually very good in cities
but often very poor or
missing in rural locations

Recommendations

Care needs to be taken at all junctions to ensure safe movement of


pedestrians particularly at the landscaped islands
25

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Landscaping and planting should not obscure any signs or short


pedestrians at planting or any time in the future
Planting should be planned with an awareness of the level of
maintenance that will occur to minimise safety problems to road users
and maintenance workers
Landscaping always requires maintenance workers to be exposed to
traffic thus they need to be trained in working safely and to wear high
visibility clothing

Junction STA 0+000


The proposed signalised junction designs are shown below together with photos of
existing conditions

Proposed Junction Layout & Signal Phasing. Note Proposed Pedestrian Phases
Conflicting with Green Signals

26

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Proposed Landscaping of Islands Note Location of Crossings

Proposed design of islands


Not pedestrian friendly

27

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Existing Ring Road


approach to
junction at STA
0+000

Conflicts in Centre of Junction

Approach from Jambi

Broken Pedestrian Signals

28

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Many Mini-busses Near Junction

Median on Leg to Jambi as Seen from Junction

Median on Leg to Jambi

29

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Proposed Junction Median Ends Prior to existing Median (Not Shown)

Unacceptable Narrowing at Start of Bypass

Problems
The proposed narrow neck at the start of the ring road will lead to serious conflicts
The proposed landscaped islands will cause serious problems for pedestrian
movements
30

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

The signal phasing shows conflicts between pedestrians and vehicles


Signal head details are insufficient to ensure optimum locations and high specifications
There are no provisions for busses
There is a median on Jambi leg a short distance from junction that appears to be
ignored in the design

Recommendations

The proposed landscaped islands and crossings should be redesigned to


ensure easy and safe pedestrian movements and a much wider approach
to the bypass
The signal phasing should be revised to remove conflicts between
pedestrians and vehicles
Signal head locations and specifications should be determined to include
far side signals, countdown timers and high luminosity, See appendix F
Add bus lay-bys to match existing or expected usage
The design of the central island on Jambi leg needs reviewing to be
compatible with median a short distance away

Countdown Timers Add Greatly to Visibility Especially at Night

31

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Junction STA 8+450


The proposed signalised junction designs are shown below together with photos of
existing conditions

Proposed Layout & Signal Phasing

Proposed Signal Locations are Inadequate Note no Far Side Signals & Some
Heads Behind Stop Line, Circled
32

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Pedestrian Phases are Unclear as Four Crossings on Each Approach

Proposed Landscaping Will Block Pedestrian Movements

Approach Travelling Westward

33

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Defective Countdown

& Signal Heads

Current conditions are poor and many signals are very difficult to see due to poor
location and broken equipment.

34

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

The bright sun makes the problems worse when travelling easterly, see below:

Problems
The proposed landscaped islands will cause serious problems for pedestrian
movements
The signal phasing is insufficient to show all pedestrian movements
Signal head details are insufficient to ensure optimum locations and high specifications

Recommendations

The proposed landscaped islands and crossings should be redesigned to


ensure easy and safe pedestrian movements
The signal phasing should be revised to show all pedestrian movements
and phases
Signal head locations and specifications should be determined to include
far side signals, countdown timers and high luminosity, See appendix F

35

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Junction STA 16+415


The proposed junction design is shown below together with photos of existing
conditions. It is within one of the road sections already completed but as mentioned
above in 3.3, the junction with islands has not been built and the World Bank requested
protection of a Pertamina pipeline

Proposed Junction Layout

Existing Conditions, Note No Islands

Recommendations

Discussions should be held between interested parties to ensure junction


is completed within one project or another
36

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

The proposed landscaped islands and crossings should be redesigned to


ensure easy and safe pedestrian movements
Ensure protection of Pertamina pipeline

Junction STA 18+440


The proposed signalised junction designs are shown below together with photos of
existing conditions

Proposed Layout & Signal Phasing, Note Conflict Between Pedestrian & Vehicle Phases

37

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Very Poor Design for Pedestrians of Crossings, Islands & Landscaping

Approach Travelling Westerly

38

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Travelling Easterly

Problems
The proposed crossings and landscaped islands are very poorly drawn and do not allow
for the actual expected pedestrian movements
The signal phasing is insufficient to show all pedestrian movements
Signal head details are insufficient to ensure optimum locations and high specifications

Recommendations

The proposed landscaped islands and crossings should be redesigned to


ensure easy and safe pedestrian movements
The signal phasing should be revised to show all pedestrian movements
and phases
Signal head locations and specifications should be determined to include
far side signals, countdown timers and high luminosity, See appendix F

39

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Junction STA 22+550


The proposed junction design at the end of the project is shown below together with
photos of existing conditions

Proposed Junction Layout

Poor design for


pedestrians of
crossings,
islands &
landscaping

40

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Existing Landscaped Island

Existing Landscaping Appears Well Maintained but Not Designed for Pedestrians

Problems
The proposed crossings and landscaped island do not allow for the actual expected
pedestrian movements

Recommendations

The proposed landscaped islands and crossings should be redesigned to


ensure easy and safe pedestrian movements

41

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

3.6

Palmerah Ring Road Jambi

Road side Activity

Problems
Trucks form a very high percentage of the moving traffic but they are also frequently
stopped on the shoulders or in an out of various heavy goods depots and yards. Many
are stated as being overloaded. This causes extreme damage to the old road and is
already causing new shoulders to fail.
The proposed designs and construction methods do not take into account the needs of
the truckers to stop and they appear to ignore potential for serious damage

Typical of 100s of trucks stopped at Side of Road

Typical Road Side Commercial Activity. Note Shoulder Damage


42

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Roadside Depot with Heavy Vehicles but Well Designed & Constructed Shoulders
& Access

Recommendations

The road cross-sections should be designed for the expected heavy truck
use and this should particularly include the following

Stronger sealed shoulders where there is regular truck use, including


accesses to depots

Design and construction of resting areas and lay-bys

A weighbridge should be added to the project or planned

43

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

3.7

Palmerah Ring Road Jambi

Narrow Road

Problems
No Detailed design at approaching the narrow road also, this condition is hazard for
road user where the speed need to be reduced. (From north to south)
The nose of road median is a dangerous moreover the nose is very nearly with the bend
(from south to north). In many country the median always get hit by the vehicles were
not designed carefully

Recommendation

3.8

Hatch markings on the road where the road becomes narrow.


The median should be extended or decreased until the starting
bend(from the south to north)

Guardrail

Problems
Many of steeps road side with narrow shoulders are hidden in many places
and also could not be seen at contract drawing, as shown in photograph
bellows;

44

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Steep side at the junction

Steep side at the junction

Steep side with narrow shoulder

45

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Steep side with narrow shoulder

Recommendations
The Site Team should be resurveying the condition on site
where the steeps road side is more than 2 meter and the detailed
design for guard rail location should be proposed.
Guard rail must be installed to protect the road users.
There is a improvement at the APBN project at the same road
link, but still inadequate, As shown bellows;

The same link road , additional shoulder and noticed with guide post at steep side.
(work by APBN 2011)
46

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Guard rail at narrow shoulders at Ngawi Bypass Project (SRIP Project)

Guide post are installed where the steep is between 1 up to 2 meters height (at Ngawi
RR Project)

47

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Road Safety Audit of Construction

4.1

Inadequate Safety Culture

Problems
There was little or no warning of construction zones either at start of project or where
machinery was working
Only the Supervision Engineers & Surveying staff was observed to wear any high
visibility safety clothing

Good Safety Culture

Inadequate Safety Culture

48

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

Recommendations

Carry out an immediate upgrade of traffic management of construction


areas particularly at start and end of project sections, installed project
boards, warning sgns, erection of barriers and increasing the numbers of
cones used

There should be an immediate effort to increase numbers of workers


wearing safety clothing

Contractors supervisory staff should set good example by always wearing


safety clothing on site

Follow instruction in contract specifications and advice given in


Appendices B & C

49

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Palmerah Ring Road Jambi

APPENDIX A References

Pedoman Audit Keselamatan Jalan (PD T-17-2005-B), PU Prasarana Transportasi (Road


Safety Guidelines (PDT -17 2005 B). Public Works, Transportation)
Pedoman Audit Keselamatan di jalan raya (Austroads Standard) edisi ke 2, 2002
(Road safety Audit Guidelines (Austroads Standards) Second edition 2002)
Pedoman Teknis Penanaman Pohon Pada Sistem Jaringan jalan 2010
(Technical Guidelines for Planting trees at Road Network System 2010)
Pedoman teknis Fasilitas Pejalan Kaki di Perkotaan SK.43/AJ 007/DRJD/1997 Direktorat
Jenderal Perhubungan Darat)
(Technical Guidelines for Pedestrian facilities at Cities region, SK.43/AJ
007/DRJD/1997, Directorate General land & transportation)
Mewujudkan Jalan Berkeselamatan di Indonesia, Australia Indonesia bekerjasama dalam
teknis keselamatan di Jalan. Direktorat Jenderal Bina Marga, INDIE 2010
(Making Indonesias Roads Safer, Australia- Indonesia Partnership in Road Safety
Engineering, Directorate General of Bina Marga, INDI 2010)
See extracts on construction zone safety below.
Petunjuk Praktis , Keselamatan Jalan Pada Zona Kerja di Jalan, mendukung Proyek
EINRIP, Direktorat Jenderal Bina Marga
(Practical Guidelines, Road Safety of Construction Zone) to Support EINRIP Projects,
Directorate General of Bina Marga

50

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Appendix B

Palmerah Ring Road Jambi

Safety Concerns at Roadworks - English

51

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

Appendix C

Palmerah Ring Road Jambi

Safety Concerns at Roadworks Bahasa

52

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID

APPENDIX D

Palmerah Ring Road Jambi

MAINTENANCE OF TRAFFIC FLOW

53

Strategic Roads Infrastructure Project (SRIP)

Road Safety Audit

IBRD Loan No. 4834-IND/7786-ID


ID

Palmerah Ring Road Jambi

Appendix F

In specifications chapter XII. Specifications for Traffic Light; explain that the head of traffic lamp
should use the LED lamp with diameter head is 30 cm the requirements from DLLAJR under the
Departement of Transportation could be read as shown below;

Bab XII. Spesifikas


Spesifikasi Teknis
No. 1

Goods/Items
LED Traffic Light

Specifications
Colour of LED
Connecting Structure
Number of LED
LED Type
Wave Length
Power Lamp
Lens Diffuse

: Red Yellow - Green


: Circle
: 200 400 units per Head lamps with Dia. 300 mm
: Super Bright Water Clear 5 mm/10 mm
: M:615-650mm/K:585-597mm/H:500
597mm/H:500-509 mm
: 18 - 25 watt
: UV Resistant Polycarbonate Dia.30 cm with spots
for reflection of light
: 400 cd
: 40.000 50.000 hours
: 90-125 volt and/or 170-240
240 volt with 50Hz
: 50 Hz
>. 0.9
: Red 9.4W/ Yellow 7.8W/ Green 8.6W
: 5 70C

Lumination intensity
Life time
Voltage
Frequency
Power Factor
Power Consumption
Operating Temperature
Humidity
Spesification/features/Other
Facilities

54

Aspects of the light device must be in new


condition, no defects and should be made of
materials / components as required in technical
spesification

Potrebbero piacerti anche