Sei sulla pagina 1di 31

Proj.

Engineer
Construction Foreman
Mason
Carpenter
H.E. Operator
L.E. Operator
Driver
Steelman
Labor
Painter
Roof Installer

Welder
Glass Installer
Plumber
Electrician

Rate/day
Rate/hour
600.00
75.00
450.00
56.25
375.00
46.88
375.00
46.88
400.00
50.00
325.00
40.63
300.00
37.50
300.00
37.50
250.00
31.25
350.00
43.75
350.00
43.75
375.00
46.88
300.00
37.50
325.00
40.63
325.00
40.63

Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT


Pilar St., Zamboanga City
GANTT CHART
PROJECT
Location
Project Cost
Project Duration
Manpower Requirements

:
:
:
:
:

IMPROVEMENT OF WATER SYSTEM AT CANELAR ELEMENTARY SCHOOL


Tripplet Road, Canelar Moret, Zamboanga City

Php

26,653.27

Twelve (12) Calendar Days


5 Manpower (1-Construction Foreman/Eng'g Assist., 2-Laborer and 2-Skilled Laborer)

Work Item
SPL
SPL
SPL
SPL
SPL

1
2
3
4
5

Amounts

Mobilization/Demobilization
Standpost Concrete Pad (500mm. x 1000mm.)
Plumbing Works
Concrete Cutting
Concrete Restoration

TOTAL PROJECT COST


CASH OUTLAY REQUIREMENT
TARGETED COMPLETION THIS PERIOD

PhP
PhP
PhP
PhP
PhP
Php

253.84
3,858.82
19,275.95
771.50
2,493.16
26,653.27

% Perfected

CALENDAR
1

DAYS
8

0.95%
14.48%
72.32%
2.89%
9.35%
100%
Php26,653.27
100.00%

COMMULATIVE COMPLETION TO DATE

100.00%
Recommending

Prepared by:

Checked & Submitted by:

Approved by:

Project Implementation

FELIXBERTO R. CAARE, JR. RMP


Researcher/Analyst A (J.O.)
Planning Division

EDITO M. BAUTISTA
Officer-In-Charge
Design Division

MARLI ACOSTA-DE FIESTA


Officer-In-Charge
Engineering and Construction Department

ARNULFO A. ALFONS
Assistant General Mana
Technical Services Grou

public of the Philippines

NGA CITY WATER DISTRICT

ar St., Zamboanga City

AR ELEMENTARY SCHOOL

CALENDAR

DAYS
9 10 11 12

Php26,653.27
100.00%
100.00%
Recommending
Project Implementation:

Approved for Project Implementation:

ARNULFO A. ALFONSO
Assistant General Manager
Technical Services Group

LEONARDO REY D. VASQUEZ


General Manager

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
Standard Form Number: SF-INFR-01
Revised on: July 28, 2004

APPROVED BUDGET FOR THE ADMIN.


IMPROVEMENT OF WATER SYSTEM AT CANELAR ELEMENTARY SCHOOL
Tripplet Road, Canelar Moret, Zamboanga City
Stations :
Length :
ITEM
NO.

DESCRIPTION

(1)

(2)

SPL - 1
SPL - 2
SPL - 3
SPL - 4
SPL - 5

Mobilization/Demobilization
Standpost Concrete Pad (500mm. x 1000mm.)
Plumbing Works
Concrete Cutting
Concrete Restoration

QUANTITY

UNIT

ESTIMATED
DIRECT COST

MARK-UPS
IN PERCENT

TOTAL MARK-U

OCM

PROFIT

(3)

(4)

(5)

(6)

(7)

(8)

1
0.20
1.00
10.80
0.324

lot
cu.m.
lot
ln.m.
cu.m.

253.84
3,710.40
18,534.57
741.83
2,397.27

0%
4%
4%
4%
4%

0%
0%
0%
0%
0%

0%
4%
4%
4%
4%

TOTAL

25,637.91

Prepared by:

Checked & Reviewed by:

Approved by:

FELIXBERTO R. CAARE, JR., RMP


Researcher/ Analyst A (J.O.)
Planning Division

EDITO M. BAUTISTA, JR.


Officer-In-Charge
Design Division

MARLI ACOSTA - DE FIESTA


Officer-In-Charge
Engineering & Construction Department

Approved for Project Implementation:

LEONARDO REY D. VASQUEZ


General Manager

epublic of the Philippines


ANGA CITY WATER DISTRICT
ar Street, Zamboanga City
Contract Reference Number
Name of the Contract
Location of the Contract

VED BUDGET FOR THE ADMIN.

R SYSTEM AT CANELAR ELEMENTARY SCHOOL


Canelar Moret, Zamboanga City
Contract Duration: Twelve (12) Calendar Days
TOTAL MARK-UP
VAT

TOTAL
INDIRECT COST

TOTAL COST

UNIT
COST

(10)
5%((5)+(9))
0.00
0.00
0.00
0.00
0.00

(11)
(9)+(10)
0.00
148.42
741.38
29.67
95.89

(12)
(5)+(11)
253.84
3,858.82
19,275.95
771.50
2,493.16

(13)
(13)/(3)
253.84
19,294.08
19,275.95
71.44
7,694.94

1,015.36

26,653.27

VALUE
(9)
(5)X(8)
0.00
148.42
741.38
29.67
95.89

Recommending Project Implementation:

Engineering & Construction Department

ARNULFO A. ALFONSO
Assistant General Manager
Technical Services Group

PROJECT/LOCATION OF PROJECT:

IMPROVEMENT OF WATER SYSTEM AT CANELAR ELEMEN


Tripplet Road, Canelar Moret, Zamboanga City
BREAKDOWN OF EXPENDITURES
I - ESTIMATED COST
A. DIRECT COST:
1. Mobilization/Demobilization . . . . . . . . . . . . . . . . . . . . .
2. Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.1 Supply Delivery . . . . . . . . . . . . . . . . . . . . . . . . .
2.2 Testing Materials . . . . . . . . . . . . . . . . . . . . . . . .
3. Labor (including fringe benefits) . . . . . . . . . . . . . . . . . .
4. Equipment Expenses . . . . . . . . . . . . . . . . . . . . . . . . .
B.1. INDIRECT COST:
1. Overhead contingency Miscellaneous . . . . . . . . . . . . . .
2. Profit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
B.2. VAT & INCIDENTAL EXPENSES:
1. Comprehensive All Risk Insurance . . . . . . . . . . . . . . . .
2. Value Added Tax (5% of EDC, OCM and Profit) . . . . . .
3. Materials Testing 7% of 1% of OCM . . . . . . . . . . . . . .
SUB-TOTAL

(CONTRACT COST)

II - ESTIMATED GOVERNMENT EXPENDITURES


1. Engineering & Administrative Overhead
2. POW/Site Acquisition/Pre-Engineering
3. Materials to be furnished by the government
4. Materials Quality Control & Hydrology (MQCH)
5. Retention for RO & C.O.
SUB-TOTAL
III - CONTINGENCIES/RESERVED:
1. Physical (up to 5% of the Estimated Contract Cost) . . . . . . .
2. Price Escalation (up to 12% of the Estimated
Contract Cost) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3. Preliminary Engineering . . . . . . . . . . . . . . . . . . . . . . . . . .
TOTAL ESTIMATED PROJECT COST
PREPARED BY:

FELIXBERTO R. CAARE, JR., RMP


Researcher/Analyst A (J.O.)
Planning Division

CHECKED & SUBM

EDITO
Offi
D

APPROVED BY:

RECOMMENDING

MARLI ACOSTA - DE FIESTA


Officer - In - Charge
Eng'g and Construction Department

ARNU
Assista
Techn

APPROVED FOR PROJECT IMPLEMENTATION:

LEONARDO REY D. VASQUEZ


General Manager

SYSTEM AT CANELAR ELEMENTARY SCHOOL


Canelar Moret, Zamboanga City
% OF TOTAL

AMOUNT

0.89
53.34

253.84
15,271.37

31.10
4.23

8,902.45
1,210.25

3.55

1,015.36

26,653.27

2.25

643.57

643.57

4.65

100.00
CHECKED & SUBMITTED BY:

EDITO M. BAUTISTA, JR.


Officer - In - Charge
Design Division

1,332.66

28,629.50

RECOMMENDING PROJECT IMPLEMENTATION:

ARNULFO A. ALFONSO
Assistant General Manager
Technical Services Group

OR PROJECT IMPLEMENTATION:

ARDO REY D. VASQUEZ


General Manager

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
INDIVIDUAL PROGRAM OF WORK

PROJECT/LOCATION OF PROJECT:
IMPROVEMENT OF WATER SYSTEM AT CANELAR ELEMENTARY SCHOOL

APPROPRIATE:
SOURCE OF FUNDS
ISSUED OBLIGATED
AUTHORITY RELEAS
CALENDAR DAYS
TO COMPLETE:
DESIRABLE STARTIN

Tripplet Road, Canelar Moret, Zamboanga City


PROJECT CATEGORY:
School Facility

CONTRACT / /
PROJECT DESCRIPTION:
Construction of 10 Units Faucet Hand Washing Counter

Description

MININUM EQUIPMENT REQUIRED


No.
Description

No.
1
1
1
2

ITEM NO.
SPL
SPL
SPL
SPL
SPL

1
2
3
4
5

Descriptio
Construction Forem
Mason
Plumber
Laborers

ESTIMATED COST OF PROPOSED PROJECTS


% OF
DESCRIPTION
UNIT
TOTAL
lot
Mobilization/Demobilization
0.99%
14.47%
cu.m.
Standpost Concrete Pad (500mm. x 1000mm.)
72.29%
Plumbing Works
lot
2.89%
ln.m.
Concrete Cutting
Concrete Restoration
9.35%
cu.m.

TOTAL
PREPARED BY:

FELIXBERTO R. CAARE, JR., RMP


Researcher/Analyst A (J.O.)
Planning Division
APPROVED BY:

MARLI ACOSTA - DE FIESTA


Officer - In - Charge
Eng'g and Construction Department

100%

CHECKED & SUBMI

EDITO M
Offic
De

RECOMMENDING P

ARNUL
Assistan
Technic

APPROVED FOR PROJECT IMPLEMENTATION:

LEONARDO REY D. VASQUEZ


General Manager

public of the Philippines


NGA CITY WATER DISTRICT
Street, Zamboanga City

DUAL PROGRAM OF WORK


2-Jul-15

APPROPRIATE:
SOURCE OF FUNDS:
ISSUED OBLIGATED:
AUTHORITY RELEASED:
CALENDAR DAYS
TO COMPLETE:
DESIRABLE STARTING DATE:
CONTRACT / /

Php28,629.50

Twelve (12) Calendar Days


upon Approval

ADMINISTRATION / X /

TECHNICAL PERSONNEL REQUIRED


Description
No.
Description
Construction Foreman/Eng'g Assist.
Mason
Plumber
Laborers

COST OF PROPOSED PROJECTS


QTY.
1.00
0.20
1.00
10.80
0.324

DIRECT COST
TOTAL
UNIT COST
253.84
253.84
3,710.40
18,552.00
18,534.57
18,534.57
741.83
68.69
2,397.27
7,398.98

25,637.91
CHECKED & SUBMITTED BY:

EDITO M. BAUTISTA, JR.


Officer - In - Charge
Design Division
RECOMMENDING PROJECT IMPLEMENTATION:

ARNULFO A. ALFONSO
Assistant General Manager
Technical Services Group

ADJUSTED
UNIT COST
253.84
19,294.08
19,275.95
71.44
7,694.94

FOR PROJECT IMPLEMENTATION:

ARDO REY D. VASQUEZ


General Manager

DETAILED UNIT PRICE ANALYSIS


PROJECT NAME:

IMPROVEMENT OF WATER SYSTEM AT CANELAR ELEM

Location:

Tripplet Road, Canelar Moret, Zamboanga City

Item No./Description:
Unit of Measurement:
Output per day:
Quantity:

SPL - 2
cu.m.
0.20
0.20

Standpost Concrete Pad (500mm. x 1000m


cu.m.

/day

cu.m.

Designation
A.

No. Person

Labor
a.

Construction Foreman/Eng'g Assist.

b.

Skilled Laborer

b.

Laborer

Sub-Total for A
Name and Capacity
B.

No. of Units

Equipment
Minor Tools (10% of labor cost)

C.
D.

Output per day

Sub-Total for B
Total (A+B)
=

0.20 cu.m.

Name and Specifications


E.

Quantity

Materials
a.

b.

Portland Cement
Washed Sand

0.10

c.

Gravel (G-1)

0.20

d.

10mm. x 6.00m. Def. Reinforcing Steel Bar

e.

#16 G.I. Tie-wire

f.

12mm. Thk. x 1.20m. x 2.40m. Ordinary Plywood

g.

2" C.W. Nail

h.

Hacksaw Blade

Sub-Total for E
F.
G.
H.
I.
J.

/day

Direct Cost (C+E)


Overhead, Contingencies & Miscellaneous
Contractor's Profit (CP)
Value Added Tax (VAT)
Total Cost

k.

Total Unit Cost

D UNIT PRICE ANALYSIS

ATER SYSTEM AT CANELAR ELEMENTARY SCHOOL

ar Moret, Zamboanga City

ost Concrete Pad (500mm. x 1000mm.)

No. of Days

Daily Rate

Amount

524.00

524.00

366.00

366.00

317.00

634.00

P
No. of Days

Daily Rate

1,524.00
Amount

152.40

152.40
1,676.40

Unit

Unit Cost

Amount

bags

285.00

570.00

cu.m.

1,000.00

100.00

cu.m.

1,000.00

200.00

pcs.

140.00

280.00

kg.

63.00

pc.

730.00

kg.

43.00

43.00

pc.

48.00

48.00

63.00
730.00

P
4% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015

2,034.00
3,710.40
148.42
3,858.82

19,294.08

DETAILED UNIT PRICE ANALYSIS


PROJECT NAME:

IMPROVEMENT OF WATER SYSTEM AT CANELAR ELEM

Location:

Tripplet Road, Canelar Moret, Zamboanga City

Item No./Description:
Unit of Measurement:
Output per day:
Quantity:

SPL - 3
lot
1.00

Plumbing Works

lot

Designation
A.

No. Person

Labor
a.

Construction Foreman/Eng'g Assist.

b.

Skilled Laborer

b.

Laborer

Sub-Total for A
Name and Capacity
B.

No. of Units

Equipment
Minor Tools (10% of labor cost)

C.
D.

Output per day

Sub-Total for B
Total (A+B)
=

Name and Specifications


E.

Quantity

Materials
At Standpost
12mm. G.I. Coupling, ANSI B16.3 Class 150-Standard

12mm. Brass Faucet Plain Bibb


12mm. x 50mm. G.I. Nipple, ANSI B16.3 Class 150Standard (Standard BSP Thread, Both Ends)
12mm. x 90o G.I. Elbow, ANSI B16.3 Class 150-Standard

12mm. x 700mm. G.I. Nipple, ANSI B16.3 Class 150Standard (Standard BSP Thread, Both Ends)
12mm. x 850mm. G.I. Nipple, ANSI B16.3 Class 150Standard (Standard BSP Thread, Both Ends)
12mm. x 12mm. G.I. Tee, ANSI B16.3 Class 150-Standrad

Page 20 of 31

2
6

2
1

12mm. Plasson Male Adaptor BSP Thread


12mm. x 960mm. G.I. Nipple, ANSI B16.3 Class 150Standard (Standard BSP Thread, Both Ends)

19mm. Teflon Tape

At Boy's CR
12mm. Brass Faucet Plain Bibb

11
6

19mm. Teflon Tape

Page 21 of 31

At Girl's CR
12mm. Brass Faucet Plain Bibb

19mm. Teflon Tape

12mm. x 12mm. G.I. Tee, ANSI B16.3 Class 150-Standrad

12mm. Plasson Male Adaptor BSP Thread

19mm. Teflon Tape

At Inlet

For Leakage Repair


19mm. x 30.00m. P.E. Tubing, SDR-11
12mm. x 6.00m. G.I. Pipe ASTM A53-90A Heavy Gauge
Standard
12mm. x 90o G.I. Elbow, ANSI B16.3 Class 150-Standard

30
1
1

12mm. G.I. Coupling, ANSI B16.3 Class 150-Standard

12mm. Plasson Tee

12mm. Plasson Female Adaptor


12mm. x 90o Plasson Elbow

12mm. Plasson Coupling

19mm. Teflon Tape

For Interconnection
12mm. Plasson Male Adaptor BSP Thread

12mm. Brass Gate Valve

19mm. Teflon Tape

Sub-Total for E
F.
G.
H.
I.
J.
k.

Direct Cost (C+E)


Overhead, Contingencies & Miscellaneous
Contractor's Profit (CP)
Value Added Tax (VAT)
Total Cost
Total Unit Cost

Page 22 of 31

ED UNIT PRICE ANALYSIS

WATER SYSTEM AT CANELAR ELEMENTARY SCHOOL

lar Moret, Zamboanga City

No. of Days

Daily Rate

Amount

524.00

2,096.00

455.00

1,820.00

317.00

2,536.00

P
No. of Days

Daily Rate

6,452.00
Amount

645.20

645.20
7,097.20

Unit

Unit Cost

pcs.

17.33

pcs.

376.95

pcs.

12.34

24.68

pcs.

12.34

74.04

pcs.

66.15

132.30

pcs.

80.33

160.66

pc.

16.28

16.28

Page 23 of 31

Amount

34.66
753.90

pc.

38.33

38.33

pcs.

90.72

181.44

pcs.

15.75

78.75

pcs.

376.95

pcs.

15.75

Page 24 of 31

4,146.45
94.50

pcs.

376.95

pcs.

15.75

78.75

pcs.

16.28

32.56

pcs.

38.33

114.99

pcs.

15.75

31.50

ln.m.

13.39

401.70

pc.

711.90

711.90

pc.

12.34

12.34

pcs.

17.33

34.66

pc.

89.25

89.25

pcs.

38.33

153.32

pc.

66.15

66.15

pcs.

59.85

179.55

pcs.

15.75

47.25

pcs.

38.33

76.66

pc.

262.50

pc.

15.75

3,392.55

262.50
15.75

P
4% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015

Page 25 of 31

11,437.37
18,534.57
741.38
19,275.95
19,275.95

DETAILED UNIT PRICE ANALYSIS


PROJECT NAME:

IMPROVEMENT OF WATER SYSTEM AT CANELAR ELEM

Location:

Tripplet Road, Canelar Moret, Zamboanga City

Item No./Description:
Unit of Measurement:
Output per day:
Quantity:

SPL - 4
ln.m.
50.00
10.80

Concrete Cutting
ln.m.

/day

ln.m.

Designation
A.

No. Person

Labor
a.

Construction Foreman/Eng'g Assist.

b.

Skilled Laborer

b.

Laborer

Sub-Total for A
Name and Capacity
B.

No. of Units

Equipment
1

Concrete Cutter
Minor Tools (10% of labor cost)

C.
D.

Output per day

Sub-Total for B
Total (A+B)
=

Name and Specifications


E.

Materials

Sub-Total for E
F.
G.
H.
I.
J.
k.

Direct Cost (C+E)


Overhead, Contingencies & Miscellaneous
Contractor's Profit (CP)
Value Added Tax (VAT)
Total Cost
Total Unit Cost

50.00 ln.m.

/day
Quantity

D UNIT PRICE ANALYSIS

ATER SYSTEM AT CANELAR ELEMENTARY SCHOOL

ar Moret, Zamboanga City

No. of Days

Daily Rate

Amount

0.22

524.00

113.18

0.22

366.00

79.06

0.22

317.00

136.94

P
No. of Days

Daily Rate

0.22

1,758.00

329.18
Amount
379.73
32.92

Unit

Unit Cost

Amount

P
4% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015

412.65
741.83

741.83
29.67
771.50
71.44

DETAILED UNIT PRICE ANALYSIS


PROJECT NAME:

IMPROVEMENT OF WATER SYSTEM AT CANELAR ELEM

Location:

Tripplet Road, Canelar Moret, Zamboanga City

Item No./Description:
Unit of Measurement:
Output per day:
Quantity:

SPL - 5
cu.m.
0.875
0.324

Concrete Restoration
cu.m.

/day

cu.m.

Designation
A.

No. Person

Labor
a.

Construction Foreman/Eng'g Assist.

b.

Skilled Laborer

b.

Laborer

Sub-Total for A
Name and Capacity
B.

C.
D.

Equipment
None

Output per day

Sub-Total for B
Total (A+B)
=

Name and Specifications


E.

0.875 cu.m.

/day
Quantity

Materials
a.

Portland Cement

b.

Washed Sand

c.

Gravel (G-1)

12

Sub-Total for E
F.
G.
H.
I.
J.
k.

No. of Units

Direct Cost (C+E)


Overhead, Contingencies & Miscellaneous
Contractor's Profit (CP)
Value Added Tax (VAT)
Total Cost
Total Unit Cost

D UNIT PRICE ANALYSIS

ATER SYSTEM AT CANELAR ELEMENTARY SCHOOL

ar Moret, Zamboanga City

No. of Days

Daily Rate

Amount

0.4

524.00

194.03

0.4

455.00

168.48

0.4

317.00

234.76

P
No. of Days

Daily Rate

597.27
Amount

597.27

Unit

Unit Cost

Amount

bags

285.00

855.00

bags

52.50

315.00

bags

52.50

630.00

P
4% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015

1,800.00
2,397.27
95.89
2,493.16
7,694.94

DETAILED UNIT PRICE ANALYSIS


PROJECT NAME:

IMPROVEMENT OF WATER SYSTEM AT CANELAR ELEM

Location:

Tripplet Road, Canelar Moret, Zamboanga City

Item No./Description:
Unit of Measurement:
Output per day:
Quantity:

SPL - 1
lot
1.00

Mobilization/Demobilization

lot

Designation
A.

No. Person

Labor
None

Sub-Total for A
Name and Capacity
B.

No. of Units

Equipment
None

C.
D.

Output per day

Sub-Total for B
Total (A+B)
=

Name and Specifications


E.

Materials
Note: Per D.O. 22 Series 2015, Mobilization
should not exceed 1% of Estimated Direct Cost

Sub-Total for E
F.
G.
H.
I.
J.
k.

Direct Cost (C+E)


Overhead, Contingencies & Miscellaneous
Contractor's Profit (CP)
Value Added Tax (VAT)
Total Cost
Total Unit Cost

Quantity

D UNIT PRICE ANALYSIS

ATER SYSTEM AT CANELAR ELEMENTARY SCHOOL

ar Moret, Zamboanga City

No. of Days

Daily Rate

Amount

P
No. of Days

Daily Rate

Amount

Unit

Unit Cost

Amount

Estimated Direct Cost

25,384.07

Mobi/Demo (1% of E.D.C.)

253.84

P
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015

253.84
253.84
253.84
253.84

Potrebbero piacerti anche