Sei sulla pagina 1di 8

SITE SURVEY CHECK LIST FOR TELLABS 6340/6325

i. PROJECT AND CUSTOMER INFORMATION


Customer:
SMART
Project:
Contact Person(s):
Site:
MAKINABANG
Site Number:
Address:
J.P. RIZAL AVE., BRGY. MAKINABANG,
BALIUAG, BULACAN
Tel.:
Inspected by:

TCDI/Tellabs
representative

Customers
representative

Name

Name

J. ROSIANA
Name

A.B. CASTILLO
Name

K. BUNOZ
Name

Name

Date of Inspection:

Site Checklist

Page 1

1. SITE INFORMATION
Access time limitations:

_________________________________

Is there a need for access pass?


Keys available
Is site manned?
Prior Arrangements

Yes
No
Yes
No
Yes
No
________________________________
________________________________

Vehicles access
Is there a parking place?
Is there a loading dock?

Yes
Yes
Yes

No
No
No

Are the stairs or elevator (if any) big enough?

Yes

No

Location of equipment room

BTS CABIN ROOM_____________


________________________________

Access to Equipment room

________________________________

Environment
Air conditioning:

Yes

No

Noticeable dust:

Yes

No

Smell or chemical fumes:

Yes

No

Temperature:

_______________________________

Humidity

_______________________________

Raised floor:
Yes
No
Height and Material of raised floor: ______________________________
Any holes to be cut in flooring tiles: Quantity:
Size:
______________________________
Is EMC required?

Site Checklist

Yes

No

Page 2

2. MECHANICAL DATA
Dimensions : 19 x 8 RU (19width x 15 height)
Type of Node
Number of nodes

6340
1

Any 19 racks available on site?


Number of racks to be installed

6325
1
Yes
No
______________________________

Are racks to be installed on a row?

Yes

No

Cabling access to the racks?

Top

Bottom

Power
Power feed for T6300:

- 48VDC

24 VDC

110 VDC

230 VAC

Is there power feed redundant?

Yes

No

Are there any main circuit breakers


Available? Specify the rate/type

Yes

No

Rate:
16 A

Any additional circuit breakers


Needed? Specify the rate/type

Yes

No

Rate:
Type:
________________

Type of Connection (rectifier)

__________________________________

Type of Connection (cabinet)

__________________________________

AC availability?

Yes, 110VAC

Type
ABB_

Yes, 230VAC

No

- Type of wall sockets

__________________________________

- Distance to 6300

__________________________________

Grounding
Is there a station earth bar available?

Yes, Distance to equipment: 10m each

Type of Grounding bar:

________________________________

Bolt and crimp ring sizes:

________________________________

Site Checklist

No

Page 3

3. DATA CABLING
Number of Fiber Patch Cord to be installed
Gigabit Ethernet
Fast Ethernet
STM-64
STM-16

_____________________________
_____________________________
_____________________________
_____________________________
______________________________

Type of Terminating Fiber Connectors


Gigabit Ethernet
Fast Ethernet
STM-64
STM-16

______________________________
_____________________________
_____________________________
_____________________________
______________________________

Length of Fiber Patch Cords


Gigabit Ethernet
Fast Ethernet
STM-64
STM-16

_____________________________
_____________________________
_____________________________
______________________________

Available DDF(s) on-site:


Type of DDF:

Yes
No
______________________________

Cable trays available:


Type of cable Tray:
Additional cable trays required:

Yes

No

______________________________
______________________________
Yes

No

Details of additional cable trays:

______________________________
______________________________

Available ODF(s) on-site:


Type of ODF:

Yes
No
______________________________
______________________________
Yes
No
______________________________

Additional ODF(s) required:


Details of additional ODF(s):

______________________________
______________________________

Site Checklist

Page 4

4. SITE REFORMS
Reforms to be done at the site

______________________________
______________________________
______________________________
______________________________

Person responsible for the reforms

______________________________

5. CABLES NEEDED
Power Cables (m)
Type:
Grounding Cable (m)

8 meters (each)_______________
______________________________
______________________________

Type:
Fiber Patch Cord
Type: (STM-16)
Type: (STM-4)
UTP Cables:

______________________________
______________________________
______________________________
______________________________

6. CONNECTORS
Connectors for STM-64 ports

______________________________

Connectors for STM-16 ports

______________________________

Connectors for Ethernet port

______________________________

Other connectors (pls. specify)

______________________________

Site Checklist

Page 5

7. FLOORPLAN
Note: Floor plan should reflect the following:
a.
b.
c.
d.
e.
f.
g.
h.

Site Checklist

Equipment and Cabinet Layout


Power Cables Layout
Copper/ Co-axial Cables Layout
Clock Cables Layout
Cable Runways and Portholes
Location of Rectifiers, Grounding Bus Bars. Etc.
Equipment Room Dimensions
Spacing between Racks to other Racks, Racks to Walls, etc.

Page 6

8. MISCELLANEOUS
Obstruction in the cable path:__________________________________________
__________________________________________________________________
Any Underfloor work required:________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
Any overhead work required:__________________________________________
__________________________________________________________________
__________________________________________________________________
Loading/Unloading details (bay etc.):____________________________________
__________________________________________________________________
Obstacles on route to the equipment room: _______________________________
__________________________________________________________________
__________________________________________________________________

9. NOTES
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
Site Checklist

Page 7

10. Site Survey Team Requirements


1. Measuring Tape
2. Graphing Paper
3. Masking Tape
4. Pentel Pen
5. Pencil and eraser
6. Ballpen/ Sign Pen/ Tech Pen
7. Site Survey Checklist
8. ID
9. Ruler
10. Cellphone with sufficient power and load
11. House Rules
1. ALWAYS BE ON TIME.
2. OBSERVE BEHAVIOR ON SITE.
3. NO HORSE PLAYING.

Site Checklist

Page 8