Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
TESP10701R0/KSB
TES-P-107.01, Rev. 0
TABLE OF CONTENTS
1.
SCOPE
2.
INTRODUCTION
3.
SYSTEM DESIGN
3.1
3.2
3.3
4.
FUNCTIONAL REQUIREMENTS
4.1
4.2
4.3
5.
Message Performance
System Performance
7.
PERFORMANCE REQUIREMENTS
5.1
5.2
Reliability Aspects
General Design Requirements
8.
9.
GENERAL REQUIREMENTS
9.1
9.2
10.
PROJECT EXECUTION
10.1
10.2
10.3
10.4
10.5
11.
Engineering
Factory Acceptance Test (FAT)
SAT (Site Acceptance Test)/Pre-commissioning and Commissioning
Design and Operating Requirements
Services, After Sales and Maintenance
DOCUMENTATION
TESP10701R0/KSB
PAGE 2 OF 119
12.
13.
KEMA CERTIFICATION
14.
15.
DRAWINGS
TESP10701R0/KSB
TES-P-107.01, Rev. 0
PAGE 3 OF 119
1.0
TES-P-107.01, Rev. 0
SCOPE
This Transmission Engineering Standard (TES) specifies Substation Automation System
(SAS) required for 110kV through 380kV system voltage for the transmission system of
National Grid, Saudi Arabia.
2.0
INTRODUCTION
2.1
The Substation Automation System (SAS) shall be installed to monitor, control and
protect all the substation equipment connected to SAS. Monitoring and control shall
be from the remote control center (Power Control Center/SCADA Master Stations)
as well through local means within the substation (e.g. Bay Oriented Local Control
with Mimic, Local HMI contained in the Control IED and Station HMI).
The Substation Automation System (SAS) comprises full station and bay protection
as well as control, monitoring and communication functions and provides all
functions required for the safe and reliable operation of the substation. It shall enable
local station control via a PC by means of a human machine interface (HMI) and
control software package, which shall contain an extensive range of Supervisory
Control and Data Acquisition (SCADA) functions. It shall include Communications
Gateway, station bus, inter-bay bus, time synchronization system and intelligent
electronic devices (IEDs) for bay control & protection.
The attached diagram entitled, Substation Automation System Diagram
(Conceptual), Fig 07-01, is conceptual drawings for substation SAS configuration.
The Communications Gateway shall enable and secure the information flow with
remote Power Control Center and other remote Master Stations. Besides performing
protocol conversion, the Communications Gateway will perform Network/Port
Address Translation from internal SAS IP/Port addresses to external IP/Port
addresses in integrated units/computers.
The station bus shall provide the interconnections between the station level
subsystems (Front End/Station computer, Operators Workstation, Engineers
Workstation, printer etc.). The inter-bay bus shall provide independent station-to-bay
and bay-to-bay data exchange. The bay level intelligent electronic devices (IEDs) for
protection and control shall provide the direct connection to the switchgear without
the need of interposing components and perform control, protection, and monitoring
functions.
The SAS control and monitoring system (SCMS) shall implement a network
redundancy based on IEC62439-3 PRP 1 (Parallel Redundancy Protocol) as shown
in the attached Substation Automation System Diagram (Conceptual), Drawing Fig
07-01, and as further explained in this Standard. Implementation of IEC62439-3 PRP
1 (Parallel Redundancy Protocol) applies to both the station LAN and bay LAN at all
voltage levels.
TESP10701R0/KSB
PAGE 4 OF 119
TES-P-107.01, Rev. 0
2.2
All the SAS components shall comply with latest revision of SEC standards
wherever applicable.
2.3
TESP10701R0/KSB
2.3.1
As a summary, the SAS shall contain (but may not be limited) to the
following main functional parts:
2.3.2
Bay Control Intelligent Electronic Devices (Control IEDs) for control and
monitoring.
2.3.3
2.3.4
2.3.5
2.3.6
2.3.7
Peripheral equipment like printers, display units, key boards, Mouse, KVM
switches, etc.
2.3.8
2.3.9
2.3.9
PAGE 5 OF 119
TES-P-107.01, Rev. 0
2.3.10 Redundant standalone Firewalls to provide one of the means for cyber
security for the SAS.
2.3.11 Quantities of VF Modems to support the IEC-101 interconnections between
the SCADA Master Stations and the redundant Communications Gateways.
2.3.12 Collection of the relevant data concerning the substation and distribution of
the data where needed.
2.3.13 Data exchange between the different system components via the inter-bay
bus (for data exchange between bay level IEDs) and other communications
buses (such as station bus for interconnecting the station level subsystems:
Operators Workstations, Engineering Workstation, Front End Computers,
and Printers etc).
2.3.14 Bay-oriented local control panels with mimic diagram. One of the functions
of the Bay-Oriented local control panels with mimic diagram is to provide
emergency local operation of related Bay switchgear in the event of failure
and/or disabling of the Bay Control IED(s).
2.3.15 Local Control Cubicles (LCCs) for all High Voltage (above the medium
voltage (34.5 kV and below) level) switchgear which will be installed in the
related High Voltage GIS Switchgear Rooms which will house/contain the
Control IEDs, Bay-oriented local control panels with Mimic Diagram and
required Annunciator Panels.
2.3.16 For the Medium Voltage level (34.5 kV voltage and below), unless otherwise
specified differently in other sections/appendices of the main PTS,
combined Control/Protection IEDs which are to be mounted/installed in the
Low Voltage Compartments of the Metal Clad Medium Voltage Switchgear
as specified in latest revision of 32-TMSS-01 (for Metal Clad Switchgear)
and as specified in latest revision of 32-TMSS-03,( Metal Clad GIS
Switchgear), and with these IEDs fully integrated into this Metal Clad
Switchgear by the SAS Solution provider /Sub Solution provider .
2.3.17 SAS Cubicles/Panels which will contain SAS equipment which includes,
computers, Ethernet switches, firewalls/routers, VF modems, maintenance
displays, common alarm panels and related annunciators, terminal blocks,
MCBs, internal cabling/wiring, etc.
2.3.18 Protection Cubicles/Panels which will contain Protection IEDs. terminal
blocks, physical switches, MCBs, auxiliary relays, internal cabling/wiring,
etc.
2.3.19 All cabling/wiring/terminations required to provide for a fully functional
SAS installation to be provided/installed by the SAS Solution provider and
interconnected between SAS equipment as well as any SAS equipment and
external Communications/WAN/LAN equipment. The only exception to this
TESP10701R0/KSB
PAGE 6 OF 119
TES-P-107.01, Rev. 0
TESP10701R0/KSB
Definition of Terms
2.4.1
HMI
Human Machine Interface: Display screen, either part of an IED or as a
stand-alone device, presenting relevant data in a logical format, with which
the user interacts. An HMI will typically present windows, icons, menus,
pointers, and may include a keypad to enable user access and interaction.
2.4.2
IED
Intelligent Electronic Device: Any device incorporating one or more
processors, with the capability to receive or send, data/control from, or to an
external source, for example electronic multifunction meters, digital relays,
controllers. Device capable of executing the behavior of one, or more,
specified logical nodes in a particular context and delimited by its interfaces.
Also see definitions relating to Protection IED, and Control IED.
2.4.3
Bay
A substation consists of closely connected sub parts with some common
functionality. Examples are the switchgear between an incoming or outgoing
line, and the bus bar, the bus coupler with its circuit breaker and related
isolators and earthing switches, the transformer with its related switchgear
between the two bus bars representing the two voltage levels. The bay
concept may be applied to 1 1/2 breaker and double bus substation
arrangements by grouping the primary circuit breakers and associated
equipment into a virtual bay. These bays comprise a power system subset to
be protected, for example a transformer of a line end, and the control of its
switchgear that has some common restrictions such as mutual interlocking or
well-defined operation sequences. The identification of such subparts is
important for maintenance purposes (what parts may be switched off at the
same time with minimum impact on the rest of the substation) or for
extension plans (what has to be added if a new line is to be linked in). These
subparts are called 'bay' and may be managed by devices with the generic
name 'bay controller' and have protection systems called 'bay protection'. The
bay level represents an additional control level below the overall station
level.
PAGE 7 OF 119
2.4.4
TES-P-107.01, Rev. 0
TESP10701R0/KSB
2.4.5
2.4.6
Process:
The scheme which contains the actual conventional switchgear which
includes Breakers, Disconnect Switches, Tap Changers, Instrument
transformers and all instrumentation like Gas Density Monitors, etc.
2.4.7
2.4.8
2.4.9
Station HMI
The set of computers/workstations and other equipment inside each
substation where control, data acquisition, monitoring, configuration of SAS
equipment and other SAS functions on a station level takes place.
PAGE 8 OF 119
TES-P-107.01, Rev. 0
PAGE 9 OF 119
TES-P-107.01, Rev. 0
Protection IEDs being installed for all voltage levels above the Medium
Voltage level, and where related Appendix of the main PTS to this standard
specifies dedicated Protection IEDs at the Medium Voltage Level.
2.4.16 Combined Control/Protection IED
An intelligent electronic device that provides for combined control and
protection functions on a bay level. Depending on the equipment
manufacturer's design, data acquisition functions may also be provided as
part of the Combined Control/Protection IED. Also, depending on the
equipment manufacturer's design, the combined Control/Protection IED may
provide for a single protective relay function, or multiple protective relay
functions in the same combined Control/Protection IED unit. Also,
depending on the equipment manufacturer's design, additional
features/functions of the combined Control/Protection IED may include
status recording functions (such as fault recording and other status recording
functions), and other features. Also, combined Control/Protection IED's shall
be considered as Protective Relays which are integrated in the SAS and with
IEC 61850 connectivity/functionality Also, depending on the equipment
manufacturer's design, a Local HMI may be integrated as part of the
combined Control/Protection IED, or the combined Control/Protection IED
may be separate from the Local HMI. For the purposes of this Standard,
combined Control/Protection IEDs shall be provided for all Medium Voltage
(34.5 kV and below) applications, unless separate dedicated Control IEDs,
and separate dedicated Protection IEDs are specified for some or all of the
Medium Voltage applications in the main PTS.
2.4.17 Station Bus
The medium through which communications takes place among the station
level subsystems such as Operators Workstation, Engineering Workstation,
Front End Computers, Printers etc. Station bus shall be fully compliant with
IEC 62439-3 (PRP1).
2.4.18 Inter-Bay Bus:
The medium through which communications takes place between the baylevel IEDs and the station HMI interface and which protection, control and
data acquisition/monitoring signals for the SAS pass through. The Inter-Bay
Bus shall be fully compliant with IEC 61850 for all voltage levels of the
substation, and also will be fully compliant with IEC-62439-3 PRP1 for all
voltage levels of the substation.
2.4.19 Bay-oriented Local Control Panel with Mimic Diagram
A panel, which is installed on a bay level which provides for local indication
of switchgear status, limited alarm indication, other sets of limited readings,
and local switchgear control (on an emergency basis upon failure of a Control
IED and/or local HMI.
2.4.20 Time Synchronization System: A redundant set of GPS receivers which
provide for time synchronization data to all equipment contained as part of
the SAS within each substation.
TESP10701R0/KSB
PAGE 10 OF 119
TES-P-107.01, Rev. 0
SYSTEM DESIGN
3.1
TESP10701R0/KSB
3.1.1
The systems shall be: State-of-the art based on IEC61850 for operation under
electrical conditions present in high-voltage substations, follow the latest
engineering practice & ensure long term compatibility requirements,
continuity of equipment supply and the safety of the operating staff.
3.1.2
The offered SAS shall support remote control and monitoring from remote
SCADA Master Stations via Communications Gateways.
3.1.3
The offered SAS shall provide for SOE (Sequence of Events) points support
and overall SOE functions, with SOE monitoring information forwarded to
both the Station HMI and the external SOE Master Station (which is located
outside of the substation) through the Communications Gateways.
Date of Approval: February 26, 2013
PAGE 11 OF 119
TES-P-107.01, Rev. 0
3.1.4
The offered SAS shall provide for Protective Relay functions, (through baylevel Protection IEDs) for each substation.
3.1.5
The offered SAS shall provide for the substations interlocking functions,
both through hard-wired interlocks in the substation as well as a system of
software/GOOSE interlocks.
3.1.6
The offered SAS shall provide for other miscellaneous functions related to
substation control, data acquisition, protection and other functions as
described elsewhere in this Standard and the related Main PTS and other
Appendices to the Main PTS.
3.1.7
The system shall be designed such that personnel with little background
knowledge in microprocessor-based technology are able to operate the
system
easily after
having
received
some
basic
training.
Installation/Maintenance/Operating Manuals/ documentation describing the
features and functions of the system shall be provided. Necessary 'HELP'
files shall be built into the HMI and database software. Also, the Operator
Interface (through the Engineering Workstation and Operator's Workstation)
shall be intuitive such that operating personnel shall be able to operate the
system easily after having received basic training on the SAS.
3.1.8
3.1.9
Maintenance, modification or extension of components may not cause a shutdown of the whole SAS. Self-monitoring of single components, modules and
communication shall be incorporated to increase the availability and the
reliability of the equipment and minimize maintenance. In the cases of
modification or extension of components, if a shutdown of the SAS is
required, features, functions and configurations shall be provided to keep the
shutdown time of all or part of the SAS to an absolute minimum.
PAGE 12 OF 119
TES-P-107.01, Rev. 0
inter-bay bus, Ethernet switches, GPS receivers and other components of the
SAS). For further details refer to Section 14.26 as well as latest revision of
TES-P-119.27 for SCADA points list and 38-TMSS-05 for Alarms list. It
should be noted that these are minimum requirements and the complete lists
to be provided by the SOLUTION PROVIDER which will be subject to
review and acceptance.
3.1.13 Generally, part or all of the SAS will be installed inside the substation
building, which will be air conditioned. However in some cases, where
outdoor switchyards are used (refer main PTS) all bay-level unit hardware
(such as Bay Control IEDs and Bay Oriented Local Control Panels with
Mimic Operation) which need to be co-located with the outdoor switchgear
shall be designed and constructed to meet and fully operate without failure in
the outdoor environmental conditions in Saudi Arabia at the substation's
location. Refer to latest revision of standard 01-TMSS-01 (Outdoor
Environmental Conditions) for further details. However in the case of SAS
equipment located inside the substation building, the SAS equipment shall be
operational during both normal indoor conditions, and emergency indoor
conditions for a minimum 12 hour period where there is no heating/air
conditioning inside the substation building (for this matter, refer section 14.
of this standard for further detail on these requirements).
3.2 System Architecture
TESP10701R0/KSB
3.2.1
For safety and availability reasons the Substation Automation System shall
be based on a decentralized architecture and on a concept of bay-oriented
distributed intelligence.
3.2.2
3.2.3
3.2.4
The proposed SAS layout shall be structured in three levels, i.e. a Station, a
Bay and a Process level.
3.2.5
The Station level shall provide all the station level functions related to
monitoring, control and protection. It shall consist of the station level
subsystems such as operators workstations, engineering workstation, front
end computers, printers, etc. interconnected via the Station Bus. At bay level
the IEDs shall provide all bay level functions regarding control, monitoring
and protection, inputs for status indication and outputs for commands. The
inter-bay bus shall provide the interconnection between the bay level IEDs
and other bay level IEDs, the bay level IEDs and SAS front end
computers/Communications Gateways, and between SAS front end
computers and SAS Communications Gateways. The IEDs should be directly
connected to the switchgear without any need for additional interposition or
transducers.
It
shall
be
the
responsibility
of
the
SAS
Manufacturer/SOLUTION PROVIDER to determine the proper layout for
Date of Approval: February 26, 2013
PAGE 13 OF 119
TES-P-107.01, Rev. 0
the SAS and the independent from each other and its functioning shall not be
affected by any fault occurring in any of the other bay control units of the
station. The only exception to this section will be for GOOSE interlocks,
where GOOSE interlocking information from one bay control unit to other
bay control units and in the event of the failure of the bay control unit
(Control IED) GOOSE interlocks may not be functional.
3.2.6
3.2.7
3.2.8
the
cable
TESP10701R0/KSB
The Station bus shall be fully redundant. At station level, the entire station
shall be controlled and supervised from the station HMI. It shall be possible
to control and monitor the bay from the bay level equipment in the event that
the communication link fails. The station wide interlocking shall also be
available when the station computer, IED(s), communications link, or other
component of the SAS fails. To support station wide interlocking upon failure
of the station computer, IED(s), communications link, or other component,
there shall be hard wired interconnection both within a bay and between the
Date of Approval: February 26, 2013
PAGE 14 OF 119
TES-P-107.01, Rev. 0
required bays for keeping the interlocking intact. For the substation's
interlocking requirements, manufacturer/SOLUTION PROVIDER shall meet
the latest revision requirements of 32-TMSS-01 for metal clad switchgear
(11kV, 13.8kV, 33kV or 34.5kV), 32-TMSS-02 for SF6 GIS (69kV through
380kV) and 32-TMSS-03 for metal clad gas insulated medium voltage
switchgear (11kV, 13.8kV, 33kV OR 34.5kV).
3.2.10 To provide highest reliability the station HMI and the Communications
Gateways shall work completely independent, i.e. the process data can be
retrieved directly from the bay level devices. Additionally the
Communications Gateway, Station HMI, communication buses (inter-bay bus
and station bus), GPS Receiver (which are part of the Time Synchronization
System) and Front End / Station Computer Unit, Firewalls and other related
hardware shall be built and configured fully redundant to ensure full
functionality and avoid single point of failure.
3.2.11 Clear control priorities shall prevent the initiation of operation of a single
switch at the same time from more than one of the available control levels, i.e.
SCADA Master Station(s), station level, bay level or apparatus level. To
ensure that clear control priorities exist, a hierarchy scheme between the
various control levels shall exist.
3.2.12 The priority shall always be on the lowest enabled control level. The station
level contains the station-oriented functions, which cannot be realized at bay
level, e.g. alarm list or event list related to the entire substation's SAS and
Communications Gateway required for the communication with remote
control centers.
3.2.13 Dedicated master clock (GPS Receivers which are part of the Time
Synchronization System) for the synchronization of the entire system shall be
provided. This master clock should be independent of all station computer
equipment and of the Communication Gateway and should synchronize all
devices via the communication buses
3.3
Ethernet Topology
The following described criterias have to be fulfilled concerning the Ethernet
switches and the topology.
3.3.1
TESP10701R0/KSB
Ethernet Switches
a.
b.
PAGE 15 OF 119
TES-P-107.01, Rev. 0
The proposed LAN switches shall be equipped with dual DC (125 VDC)
power supplies.
d.
The switches shall support priority tagging and open standards for ring
management.
e.
External switches are required as they have the advantage that there is no
interruption or reconfiguration of the Ethernet ring if one or several bay
devices are taken out of service.
f.
g.
Security Features:
h.
TESP10701R0/KSB
Support authentication/Centralized
(RADIUS)
password
management
Management Features:
PAGE 16 OF 119
3.3.2
TES-P-107.01, Rev. 0
System Architecture
The system architecture shall be based on completely distributed approach
also concerning the connection of any device to the system. Meaning any
device protection as well as control and station level devices shall be directly
connected to the Ethernet backbone.
3.3.3
4.0
Redundant Networks
a.
b.
For the inter-bay bus level of the SAS which contains the Ethernet
Switch connections for the Control IEDs, the Protection IEDs, the
SAS Front End Computers, and Communications Gateways, as a
minimum, redundant LAN configuration shall be provided by the
SOLUTION PROVIDER at all voltage levels, with separate redundant
networks provided for the IEDs at each voltage level.
c.
d.
e.
The Bid proposal shall fully describe the proposed networks scheme.
This shall be supported by detailed network block/schematic
diagrams.
FUNCTIONAL REQUIREMENTS
4.1
TESP10701R0/KSB
PAGE 17 OF 119
b.
4.1.2
TES-P-107.01, Rev. 0
4.1.3
Self Supervision
The entire SAS shall be designed with continuous self-supervision features
of the entire SAS installation, with self-diagnostic features for the SAS to
specifically pinpoint trouble/mal-operation areas of the SAS. Generally, the
self-diagnostic features will be built into the Station HMI, with displays
available for these diagnostics on the Operator's Workstation and/or
Engineering Workstation.
4.1.4
4.1.5
User Configuration
a.
b.
TESP10701R0/KSB
The functional requirements shall be divided into two areas which are
shown in the two paragraphs below.
PAGE 18 OF 119
4.1.6
TES-P-107.01, Rev. 0
b.
The Bay level functions shall comprise of operations within one bay
only, with the bay comprising of one circuit breaker, associated
disconnectors (isolation switches), earthing (grounding switches) and
associated instrument transformers (PTs and CTs).
c.
System Level functions which look at the SAS and the substation as a
whole.
4.2.2
4.2.3
a.
b.
c.
Overview
Basic functions
TESP10701R0/KSB
PAGE 19 OF 119
TES-P-107.01, Rev. 0
o
Double command
Autoreclosing (may be considered as either a control function
or protection function, depending on National Grid Saudi
Arabia requirements)
Synchrocheck, voltage selection (may be considered as either
a control function or protection function, depending on
National Grid Saudi Arabia requirements)
Interruption of drive latching in case runtime is exceeded
Monitoring pole discrepancy and trip function, if applicable
Transformer tap changer control raise/lower (for power
transformer bays)
Operation counters for circuit breakers and pumps, if
applicable
Hydraulic pump control and runtime supervision, if
applicable
Pump start cascading, if applicable
Anti pumping of circuit breaker (open/close)
Operating pressure supervision through digital contacts only
Display of interlocking and blocking
Breaker position indication on a three phase basis with
indication showing pole discrepancy conditions/alarms where
pole discrepancy between the phases is detected/indicated
Alarm annunciation
Measurement display
Local HMI (local guided, emergency mode)
Interface to the station level
Data storage for at least 200 events
Run Time Command cancellation
Extension possibilities with additional I/O's inside the unit,
installation of additional units and/or via fiber optic
communication and process bus
Additional functions, if any, specified in Main PTS/SCADA
& Protection Appendices.
Advanced functions
b.
TESP10701R0/KSB
PAGE 20 OF 119
TES-P-107.01, Rev. 0
OFF Mode
It is not possible to operate any object, neither locally
nor remotely.
ii
iii.
TESP10701R0/KSB
EMERGENCY Mode
A.
B.
B.
PAGE 21 OF 119
C.
iv.
TES-P-107.01, Rev. 0
v.
c.
Command supervision
TESP10701R0/KSB
ii.
PAGE 22 OF 119
TESP10701R0/KSB
TES-P-107.01, Rev. 0
iii.
iv.
ii.
iii.
PAGE 23 OF 119
TES-P-107.01, Rev. 0
TESP10701R0/KSB
ii.
iii.
iv.
PAGE 24 OF 119
v.
TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 25 OF 119
ii.
TES-P-107.01, Rev. 0
Voltage selection
A. The voltages relevant for the synchro-check
functions are dependent on the station topology, i.e.
on the positions of the circuit breakers and/or the
isolators.
B. The correct voltage for synchronizing and
energizing is derived from the auxiliary switches of
the circuit breakers, the isolator, and earthing
switch and related PTs and shall be selected
automatically by the Bay Control IEDs and/or
Protection IEDs. The correct voltage selection shall
also be dependent on the bay/station one-line
scheme (e.g. double bus bar-single breaker, breaker
and one-half, double bus, etc.) for each substation
to be equipped with SAS.
C. Voltage selection (which is required for
synchronism and energizing check as described
Section i under Synchronism and energizing check)
shall be an integral function of the IED or
Synchrocheck Relay, and NOT through external
means.
D. Depending on National Grid Saudi Arabia
requirements as stated in related Appendix of the
main PTS, voltage selection may be required to be
performed
by
dedicated
Synchrocheck
Relays/IEDs and NOT Control IEDS or combined
Control/Protection IEDs
TESP10701R0/KSB
ii.
PAGE 26 OF 119
TES-P-107.01, Rev. 0
iv.
v.
TESP10701R0/KSB
PAGE 27 OF 119
TES-P-107.01, Rev. 0
TESP10701R0/KSB
ii
iii.
iv.
PAGE 28 OF 119
d.
TES-P-107.01, Rev. 0
e.
4.2.4
TESP10701R0/KSB
General
For all voltage levels except for the Medium Voltage level, the
protection functions shall be independent of the control
functions (i.e. the Protection IED will NOT be performing
Control IED functions). For the Medium Voltage level, unless
specified in the main PTS, both control functions and
protection functions for a bay can be provided in one IED
(which will be known as a combined Control/Protection IED).
Refer to the related Appendix of the main PTS involving Relay
and Protection for further details on the functionalities
involved, as well as other details.
PAGE 29 OF 119
b.
TES-P-107.01, Rev. 0
All IEDs shall be serial integrated for data sharing and meet
the real-time communication requirements for automatic
functions. The data presentation and the configuration of the
various IEDs shall be compatible with the overall system
communication and data exchange requirements.
Self-supervision
Continuous self-supervision function with self-diagnostic possibilities
shall be included.
c.
TESP10701R0/KSB
PAGE 30 OF 119
d.
4.2.5
TES-P-107.01, Rev. 0
Local HMI
The local human machine interface (HMI) shall be frontmounted and based on a user-friendly, menu-structured
program, and performed with the use of a permanently
installed human machine interface unit, type-tested together
with the protection terminal.
Line protection
a.
b.
General
Distance function
Distance function requirements shall be compatible to the relay
requirements indicated in Protective Relaying Appendix to the main
PTS/Protective Relay Standard.
c.
Differential function
Differential function requirements shall be compatible to the relay
requirements indicated in Protective Relaying Appendix to the main
PTS/Protective Relay Standard.
d.
TESP10701R0/KSB
PAGE 31 OF 119
TES-P-107.01, Rev. 0
Fault location
Fault location function requirements shall be compatible to the relay
requirements indicated in Protective Relaying Appendix to the main
PTS.
f.
Transformer protection
General
i.
ii.
Other functions
Refer to the Protective Relaying Appendix to the main PTS or
Protective Relay Standard for further details.
TESP10701R0/KSB
ii.
iii.
PAGE 32 OF 119
TES-P-107.01, Rev. 0
Control
a.
4.3.2
TESP10701R0/KSB
b.
c.
Status supervision
a.
b.
c.
The SAS shall also monitor the status of substation auxiliaries (which
will include, but not be limited to auxiliary relays such as trip current
supervision, DC supervision, etc.).. The status and control of
auxiliaries shall be done through separate one or more Control IEDs
and all alarm and analogue values shall be monitored and recorded
through the respective Control IEDs. It is noted also by the National
Grid Saudi Arabia that monitoring of the status of auxiliaries shall
NOT be performed from dedicated Protection IEDs or combined
Control/Protection IEDs.
Date of Approval: February 26, 2013
PAGE 33 OF 119
4.3.3
4.3.4
TESP10701R0/KSB
TES-P-107.01, Rev. 0
Measurements
a.
b.
c.
b.
c.
d.
During the Base Design Stage, the Solution provider shall submit the
Events and Alarms List (Signals List) for National Grid Saudi Arabia
approval, and once approved the Solution provider will use this
approved list as a basis for development of his SCD files for SAS.
e.
As a minimum, the Signals and Events List shall contain all applicable
points as identified in TES-P-119.27 the SOE Points List and the
approved Annunciator Alarms List for the Substation. Also, in
development of the Events and Alarms List, separate dedicated lists
shall be generated for SOE, SCADA, and the Station HMI contained
as part of the Substation Automation System for review and approval.
f.
PAGE 34 OF 119
TES-P-107.01, Rev. 0
4.3.5
TESP10701R0/KSB
In/Out facility for the protection is isolating trip out put only during
maintenance of relays. However during this condition all alarms to
remote Master stations shall be isolated in order to avoid receiving any
nuisance alarms during maintenance. Facility for isolating alarms shall
be provided as part of relays or at the Gateways.
A dedicated clock synchronization unit shall set the time within the
SAS. Time synchronization of all SAS equipment shall be
independent of the station level equipment e.g. station computer or
Communications Gateway. Time Synchronization shall be from
redundant GPS receivers located on the property of each substation.
The time shall then be distributed to the control IEDs, combined
Control/Protection IEDs and protection IEDs and other SAS
equipment via the communication buses. An accuracy of 1ms (from
the actual time) within the substation (and for ALL SAS components
within the substation which require time signals) is required.
b.
c.
d.
PAGE 35 OF 119
e.
4.3.6
TES-P-107.01, Rev. 0
In the event of failures of both GPS clock receivers which are beyond
the control of the GPS clock receivers (e.g. shutdown of the GPS
satellite network, atmospheric conditions blocking reception of GPS
signals at the GPS receivers, etc.) there shall be a means of time
synchronization by the use of either internal SAS clocking sources
(e.g. internal clocks inside the IED(s), etc). or tertiary clocking
sources from the respective SCADA Master Station(s). In this respect,
during the Base Design Stage, the SOLUTION PROVIDER shall state
the holdover clocking accuracy of the internal SAS clocking sources,
the clocking drift of these internal SAS clocking sources and the
maximum allowable time which the SOLUTION PROVIDER feels
that the infernal SAS clocking sources will provide accurate (+ 1 ms
accuracy from real time) timing. If in the event that based on the
SOLUTION PROVIDER provided information, that the internal SAS
clocks will NOT provide accurate time information in the event of
both GPS receivers failing, the National Grid Saudi Arabia during the
Base Design will instruct the SOLUTION PROVIDER to utilize the
existing SCADA Master Station(s) Clocks as a tertiary
clocking/synchronization source and incorporate this SCADA Master
Station(s) clock as a tertiary clocking/synchronization source.
Telecontrol
Remote access to each substation data shall be enabled via the control centers
(SCADA Master Stations) upon request. The respective owners in the utility
organization may use some or all information related to the conditions of high
voltage apparatus.
4.3.7
TESP10701R0/KSB
General
The Station HMI shall be fully redundant and shall provide the
functions for supervision and control of the substation. Access
to the redundant Front End Computers shall be through the
Operator's Workstations and the Engineer's Workstation.
However to meet the redundancy requirements a backup
workstation (included as part of a Maintenance Laptop
Computer) shall be provided with software and firmware fully
loaded which can be used to act as either the Operator's
Workstation or Engineering Workstation in the event of failure
of either the Operator's Workstations or Engineering
Workstation contained as part of the SAS.
PAGE 36 OF 119
TESP10701R0/KSB
TES-P-107.01, Rev. 0
The Station HMI shall give the operator access to alarms and
events displayed on the screen. Aside from these lists on the
screen, there shall be a printout of alarms or events in an event
log.
ii.
iii.
iv.
Measurement dialogues
v.
vi.
vii.
System status
viii.
ix.
Interlocking details
PAGE 37 OF 119
x.
b.
c.
TESP10701R0/KSB
TES-P-107.01, Rev. 0
ii.
iii.
iv.
v.
vi.
warning or blocked
vii.
viii.
ix.
normal state
PAGE 38 OF 119
TES-P-107.01, Rev. 0
d.
TESP10701R0/KSB
This display shall cover the status of the entire SAS including
IEDs, communication links (inter-bay bus and station bus),
Ethernet switches, HMI equipment, Time Synchronization,
Communications Gateway equipment, GPS receivers,
Firewalls, Inverters/UPS, printers and other SAS equipment.
PAGE 39 OF 119
e.
Event list
The event list shall contain events that are important for the
control and monitoring of each substation.
v.
TESP10701R0/KSB
TES-P-107.01, Rev. 0
PAGE 40 OF 119
iii.
iv.
v.
f.
Device
Function
e.g.
trips,
protection
operations,
autoreclosures, level where function was performed
(e.g bay level through an IED, Station HMI, etc.) etc.
Alarm class
Alarm list
iii.
iv.
ii.
iii.
iv.
TESP10701R0/KSB
TES-P-107.01, Rev. 0
PAGE 41 OF 119
TES-P-107.01, Rev. 0
g.
Object picture
When selecting an object such as a circuit breaker or isolator in the
single-line diagram, the associated bay picture shall be presented first.
In the selected object picture, all attributes like:
type of blocking
authority
local / remote control
PCC(SCADA Master Station(s))/SAS control
errors
etc.,
Shall be displayed.
h.
TESP10701R0/KSB
Control dialogues
PAGE 42 OF 119
i.
ii.
i.
No engineering allowed
Engineering/configuration allowed
Entire system management allowed
Station HMI-Reports
a.
TESP10701R0/KSB
Display only
Normal operation (e.g. open/close apparatus)
Restricted operation
System administrator
4.3.8
User-authority levels
j.
TES-P-107.01, Rev. 0
Trend reports:
Date of Approval: February 26, 2013
PAGE 43 OF 119
i.
ii.
iii.
iv.
Historical reports:
i.
ii.
iii.
iv.
b.
c.
It shall be possible to select the time period for which the specific data
are kept in the memory.
d.
TESP10701R0/KSB
TES-P-107.01, Rev. 0
PAGE 44 OF 119
4.3.9
4.3.10
TES-P-107.01, Rev. 0
It shall be possible to illustrate all types of process data as trends input and output data, binary and analogue data.
b.
c.
d.
4.3.11
TESP10701R0/KSB
PAGE 45 OF 119
TES-P-107.01, Rev. 0
short fault summaries and automatic printouts of the fault history and
fault location.
4.3.12
b.
c.
d.
The protection engineer may also have his own PC-based system
which will be located outside each substation (and not provided under
this contract) which will also be used to evaluate all the required
information for proper fault analysis, independent of the Power
Control Center. However, connectivity facilities shall be provided by
the SAS in the substation to allow connection between the external
Protection Engineering workstation (not provided under this contract)
and the disturbance archive facilities provided as part of the SAS
Station HMI/Engineering Workstation.
d.
Automatic sequences
a.
TESP10701R0/KSB
PAGE 46 OF 119
TES-P-107.01, Rev. 0
4.3.14
4.3.15
TESP10701R0/KSB
Load shedding
a.
If load shedding is required, the criteria for the shedding and the
criteria for the choice of the feeders to be shed should be described.
b.
c.
b.
PAGE 47 OF 119
TES-P-107.01, Rev. 0
of circuit breakers, transformers, tap changers etc. by means of a costeffective data sharing approach.
4.3.16
TESP10701R0/KSB
c.
d.
As part of the SAS design for the substation, there shall be the full
ability to provide normal SCADA functions for the substation, which
include data acquisition, control, and monitoring for the station. This
will be accomplished through an interconnection between the SCADA
Master Station(s) through the Communications Gateways and other
SAS equipment which in turn will send the control and/or data
acquisition signals through the SAS to the IEDs inside the substation
for further action and vice versa.
b.
For the station SCADA functions, the SAS shall emulate the
functional features of RTU Standard based on latest revision of 38TMSS-03
c.
Given that the SAS will now replace the SCADA RTU with IEDs and
the local/station HMI, the overall SAS will serve the SCADA function
for the station(s) where SAS will be implemented. In this respect, the
SCADA points list requirement as indicated in latest revision of TES119.27 shall be implemented as part of the SAS SCADA functions for
each substation.
d.
PAGE 48 OF 119
TES-P-107.01, Rev. 0
b.
For the substation SAS involved under this project, the SOLUTION
PROVIDER shall do the following:
Perform FAT (Factory Acceptance Tests) and SAT (Precommissioning and commissioning) of the SOE functions for
each substation.
c.
For the station SOE functions, the SAS shall emulate the functional
features of SOE standard based on latest revision of 38-TMSS-04
d.
TESP10701R0/KSB
General
PAGE 49 OF 119
TES-P-107.01, Rev. 0
b.
Self-supervision
Continuous self-supervision function with self-diagnostic possibilities
shall be included.
c.
User configuration
It shall be possible to monitor, control and configure all logical input
and output signals and binary inputs and relay outputs for all built-in
functions and signals.
d.
e.
TESP10701R0/KSB
Local HMI
The local human machine interface (HMI) shall be frontmounted and based on a user-friendly, menu-structured
program, and performed with the use of a permanently
installed human machine interface unit. This is valid for the
central unit. For the bay units it is only valid in case of a
decentralized arrangement.
PAGE 50 OF 119
f.
TESP10701R0/KSB
TES-P-107.01, Rev. 0
Busbar protection
PAGE 51 OF 119
g.
TESP10701R0/KSB
TES-P-107.01, Rev. 0
PAGE 52 OF 119
TES-P-107.01, Rev. 0
5.0
PERFORMANCE REQUIREMENTS
5.1
Message Performance
5.1.1
The given (message) performance times are referring to the total transfer time
t that includes the IED's internal processing time as defined in IEC 61850 as
well as the transmission time used over the communications network (interbay bus, switches, etc.). Different requirements concerning performance for
messages apply depending on the application. Referring to the IEC 61850
standard part 5, one can distinguish the different performance classes for the
various applications (e.g. control and protection, metering and power quality,
etc.) which must be adhered to by the SOLUTION PROVIDER in the
message performance requirements for the overall design of the SAS.
5.1.2
5.2
TESP10701R0/KSB
System Performance
5.2.1
It is expected that a SAS during its lifetime will have to face different
situations concerning the number of events appearing in each substation and
the resulting load on the SAS communication network.
5.2.2
During the normal load situation only occasional alarms and events are
occurring at the substation with analog reporting as load demand changes.
5.2.3
The updating times on the operator station under normal and calm conditions
in the substation shall be as follows:
Date of Approval: February 26, 2013
PAGE 53 OF 119
Function
Typical values
<1s
5.2.4
In terms of the overall SAS design, the most important issue when planning
each substation's communication are a proper assignment of freely allocable
logical nodes to physical devices and the arrangement of the communication
network itself to minimize point-to-point communication requirements.
5.2.5
5.2.6
When defining the actual network and stacks, the SOLUTION PROVIDER
is encouraged to combine data objects in such a way that the traffic is
minimized.
5.2.7
6.0
TES-P-107.01, Rev. 0
5.2.8
For the LAN simulation study, for all cases, the SOLUTION PROVIDER
shall state the assumptions used and the conditions stated in his study, any
weak points which may be apparent in the LAN communications system (e.g.
inter-bay bus, switches, station bus, etc.) as well as methods which the
SOLUTION PROVIDER will use to minimize LAN traffic on the system (to
avoid LAN bottlenecks).
5.2.9
Also, for the LAN simulation study, this shall be performed during the base
design stage of the project
TESP10701R0/KSB
Reliability Aspects
Date of Approval: February 26, 2013
PAGE 54 OF 119
6.1.1
The SAS shall be designed to satisfy the very high demands for reliability and
availability concerning:
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
m.
n.
o.
p.
q.
r.
s.
TESP10701R0/KSB
TES-P-107.01, Rev. 0
PAGE 55 OF 119
TES-P-107.01, Rev. 0
6.2
TESP10701R0/KSB
In order to meet the requirements of this specification, the design of the SAS
is within the manufacturers/SOLUTION PROVIDER's responsibility but
subject to approval by the National Grid Saudi Arabia.
6.2.2
b.
The IEDs at bay level like the Protection IEDs, Control IEDs and
combined Control/Protection IEDs are directly connected to the interbay bus.
c.
d.
e.
PAGE 56 OF 119
TES-P-107.01, Rev. 0
6.2.3
f.
g.
Bay-oriented arrangements
For each type of bay (line, transformer, coupler, and other bays) the
SOLUTION PROVIDER shall present the principal arrangement of the
cubicles: type of hardware units and associated functions.
6.2.4
Station-oriented arrangements
The SOLUTION PROVIDER shall present a detailed schematic diagram and
the drawings of the station level and the optical connections.
6.2.5
7.0
TESP10701R0/KSB
The definition of the IEC61850 communication profile shall assure that the
offered solution complies with the minimum requirements requested in the
standard and also shall ensure that the offered architecture can be realized
with the proposed products and their implemented services.
7.1.2
For interoperability, not only data have to be standardized but also the access
to these data called services. The SOLUTION PROVIDER shall include in
Date of Approval: February 26, 2013
PAGE 57 OF 119
TES-P-107.01, Rev. 0
his Proposal a filled out interoperability list of each typical device provided in
the offered system to determine compliance with IEC 61850 requirements.
Some of the relevant areas to be covered by the profile with regard to IEC
61850 are:
a.
Communication Services
Abstract Communications Services (ACSI) (7-2)
b.
Data Modeling
The data modeling is not specifically listed but the supplier shall
comply fully with the logical nodes described in the standard for the
devices where they are required. As a minimum all the mandatory data
of the used logical nodes must be supported.
7.2
7.3
TESP10701R0/KSB
7.3.1
Confirmation that all IEDs supplied shall provide a IEC 62439-3 PRP 1
DAN (Double Attached Node) connection to redundant ring inter-bay busses.
7.3.2
PAGE 58 OF 119
8.0
7.3.3
Transit times of IEC 61850 signals through IEC 62439-3 PRP 1 equipment
(e.g. SANS, DANS, Redboxes, etc.).
7.3.4
7.3.5
8.2
Portable Maintenance Laptop Computers (which plug into the IED serial, Ethernet RJ
45, and/or Optical Port) as a service unit shall be provided for on-site review of
settings, and emergency on-site modifications of the Control IED and Protection IED
devices. This service unit shall be used for documentation, IED Parameter
readings/settings (IED Parameter settings on an emergency basis only), testing and
commissioning, etc.
8.3
The service & support system shall be used for the following purposes:
8.3.1
8.3.2
8.3.3
8.3.4
8.3.5
8.3.6
8.3.7
8.3.8
8.4
9.0
TES-P-107.01, Rev. 0
System configuration
System testing
Help functions
Program documentation
Down and uploading of programs
System commissioning
Data base management
Changing peripheral parameters
The service & support system shall be able to monitor data in the operating
substation's control system and to present changing variables on the display screen in
graphic representation.
GENERAL REQUIREMENTS
9.1
TESP10701R0/KSB
For design and type testing of the protection and control equipment as well as
other equipment associated with the SAS as well as overall implementation of
the SAS, the following standards, protocols, and industry practices shall be
applicable:
PAGE 59 OF 119
a.
General
b.
Cyber Security
TESP10701R0/KSB
CE-marking
d.
c.
TES-P-107.01, Rev. 0
IEC 62443-2-1, Ed 1.0 Industrial communication networksNetwork and system security- Part 2-1 Establishing an
industrial automation and control system security
NERC CIP North American Electric Reliability CouncilCritical Infrastructure Protection
IETF RFC-2196, Site Security Handbook
IETF RFC-3093 Firewall Enhancement Protocol
IEEE 1686-2007 IEEE Standard for Substation Intelligent
Electronic Devices (IEDs) Cyber Security Capabilities
Date of Approval: February 26, 2013
PAGE 60 OF 119
e.
IEEE 802.3
IEEE 802.3u
IEEE 802.3ab
IEEE 802.3z
IEEE 802.3x
IEEE 802.3ad
IEEE 802.1d
IEEE 802.1w
IEEE 802.1p
IEEE 802.1q
IEEE 802.1x
IEEE 1613
IEC 61850-3
IEC 61850-5
TESP10701R0/KSB
TES-P-107.01, Rev. 0
10BASE-T specification
100BASE-TX, 100BASE-FX specification
1000BASE-TX specification
1000BASE-LX specification
Flow Control
Link Aggregation Control Protocol (LACP)
for creation of Ether channels with other LACP
compliant devices
Spanning Tree Protocol support for redundant
Backbone connections and loop-free network
with improved fault tolerance
Rapid Spanning Tree Protocol (RSTP)
Specification for traffic prioritization.
Specification for VLAN tagging.
Specification to allow for dynamic, port-based
security providing user authentication
Standard for Networking Devices in Electrical
Power Substations which specifies electrical
immunity, temperature ratings and other
environmental requirements
Communication Network and Systems in
Substations Part 3-General Requirements
Communication Network and Systems in
Substations
-Part5
Communication
requirements for functions and Device models
PAGE 61 OF 119
f.
TES-P-107.01, Rev. 0
TCS-P-105
PAGE 62 OF 119
9.2
TES-P-107.01, Rev. 0
9.2.2
9.2.3
TESP10701R0/KSB
PAGE 63 OF 119
10.
TES-P-107.01, Rev. 0
PROJECT EXECUTION
During the project execution phase the following activities have to be considered:
Engineering
FAT
Site installation
SAT/Commissioning
10.1
Engineering
10.1.1 During the engineering phase the following milestones are very important and
have to be agreed upon between the SOLUTION PROVIDER and the
National Grid Saudi Arabia:
TESP10701R0/KSB
a.
b.
Acceptance of: event list, alarm list, the main pictures displayed at
station level & used in the single-line diagram etc.
c.
Acceptance of: the lists of events and alarms (including their names)
with the indication of the particular signal to be sent (station event list,
remote signal list, etc).
Date of Approval: February 26, 2013
PAGE 64 OF 119
TES-P-107.01, Rev. 0
d.
Cubicle layout.
e.
TESP10701R0/KSB
PAGE 65 OF 119
TES-P-107.01, Rev. 0
10.2.4 For the portion of the FAT which deals with the SCADA and SOE functions
of the SAS, the SOLUTION PROVIDER shall verify as part of the FAT that
all the required functions and requirements of the National Grid Saudi Arabia
for the SCADA, and SOE functions are met.
10.2.5 It is extremely important that the SOLUTION PROVIDER have a full
traceability of all test data generated during the Type Tests, Factory Tests
(FT) and the FAT to assure that repeating of tests is minimized during all
stages of the testing process. Full traceability shall include full recording of
values on test sheets, appropriate test instructions and other data to allow the
National Grid Saudi Arabia to confirm that ALL functionalities as indicated
in the SAS Equipment Manufacturer's Specifications/Technical Brochures,
applicable accepted International Standards, and National Grid Saudi Arabia
specifications/requirements are complied with. Failure of the SOLUTION
PROVIDER to provide a full traceability record of these tests may require
the National Grid Saudi Arabia to demand that the SOLUTION PROVIDER
repeat such tests (for National Grid Saudi Arabia /Independent Inspection
Agency Witness) which have no traceable record to satisfy to the National
Grid Saudi Arabia that such equipment contained in the SAS meets ALL SAS
Equipment Manufacturer's Specifications/Technical Brochures, applicable
accepted International Standards and National Grid Saudi Arabia
specifications/requirements.
10.3
TESP10701R0/KSB
PAGE 66 OF 119
TES-P-107.01, Rev. 0
interfacing of the SAS with the simulated equipment. Prior approval for the
Simulator (including its hardware and software parts) shall be obtained from
National Grid Saudi Arabia to ensure its adequacy/suitability.
10.3.2 Also, IEDs used for protection, control, etc., the redundant inter-bay bus (and
associated communications hardware/software), the redundant station bus (and
associated communications hardware/software),the Time Synchronization
System (redundant GPS receivers) and the local/station HMI (including all
computer equipment), Operator/Engineering Workstations and related
peripheral equipment (e.g. all displays/keyboards, printers, etc.) and all
interconnecting communications devices (e.g. VF modems, Firewalls, etc.) and
inverters/UPS equipment providing power for SAS are to be considered
component
parts
of
the
SAS,
and
shall
undergo
precommissioning/commissioning requirements as part of the SAT.
10.3.3 The SOLUTION PROVIDER shall, as part of the base design engineering
package which he will develop will include a listing of the tests, test
procedures and test forms/reports which the SOLUTION PROVIDER will
perform for the SAS components as part of the SAT (precommissioning/commissioning tests), which is to be submitted for National
Grid Saudi Arabia review and approval.
10.3.4 All primary equipments site pre-commissioning/commissioning tests shall be
prepared by SOLUTION PROVIDER in accordance with TCS-P-105 IEC
61850 requirements regarding commissioning of SAS, and commissioning
tests for the SAS as required under this standard and the main PTS document,
and equipment manufacturer's commissioning test recommendations. This
documentation (pertaining to site pre-commissioning/commissioning tests
prepared by the SOLUTION PROVIDER) shall be submitted to National Grid
Saudi Arabia for National Grid Saudi Arabia review and approval not less than
six (6) months before the scheduled date of tests.
10.3.5 In cases where the SOLUTION PROVIDER cannot provide to the National
Grid Saudi Arabia adequate type test documentation for all SAS components
from the respective manufacturers of SAS equipment, and/or in cases where
the FAT Testing was performed with missing tests which are required by the
National Grid Saudi Arabia and/or in cases where factory production test runs
were not submitted, the SOLUTION PROVIDER shall be required to
demonstrate to the satisfaction of the National Grid Saudi Arabia through
performance of the pre-commissioning/commissioning tests that the required
tests which were not documented by the SOLUTION PROVIDER either
during the Type Testing stage and/or the FAT Testing stage and/or factory
production test run stage.
10.3.6 Depending on the overall complexity of the SAS, and to avoid repeating of
tests, the National Grid Saudi Arabia may allow some of the tests which were
to be provided as part of the SAS SAT to be performed during the final
substation commissioning stage of the project (e.g.. this may include the
TESP10701R0/KSB
PAGE 67 OF 119
TES-P-107.01, Rev. 0
testing of binary inputs which were not performed during the SAS SAT, full
functionality tests with the interconnected SCADA Master Stations, etc.). In
this respect, as part of the development of the SAS SAT Test Book/Document,
the SOLUTION PROVIDER shall identify which tests that he will perform
during the SAS SAT, and which tests will be remaining to be tested by the
SOLUTION PROVIDER which are related to the SAS during the final
commissioning stage of the project which will then be submitted for National
Grid Saudi Arabia approval.
10.3.7 For the SCADA function of the SAS, in addition to the precommissioning/commissioning SAS SAT requirements specified in Sections
10.3.1 through 10.3.5 of this Standard, the following shall be included as a
minimum:
a.
b.
TESP10701R0/KSB
PAGE 68 OF 119
TES-P-107.01, Rev. 0
b.
10.3.9 For the Protection IEDs contained as part of the SAS and for the Protection
functionalities for the combined Control/Protection IEDs, in addition to the
pre-commissioning/commissioning requirements specified in Sections 10.3.1
through 10.3.5 of this Standard National Grid Saudi Arabia requirements for
pre-commissioning/commissioning of Protective Relays (as defined elsewhere
in the main PTS and related Protective Relaying Appendix of the main
PTS/Protection Standards shall be followed by the SOLUTION PROVIDER .
10.3.10For the pre-commissioning and commissioning requirements relating to
EMI/RFI immunity, the SOLUTION PROVIDER shall provide as part of his
overall pre-commissioning and commissioning testing scheme (which will be
submitted to the National Grid Saudi Arabia during the Base Design Phase of
the Project), a proposal for testing all SAS equipment from immunity to
external EMI/RFI sources which may occur within each substation. National
Grid Saudi Arabia notes that if the SOLUTION PROVIDER submits adequate
TESP10701R0/KSB
PAGE 69 OF 119
TES-P-107.01, Rev. 0
type test data for part or all of the SAS equipment items showing that some, or
all the SOLUTION PROVIDER 's SAS equipment items meet the applicable
IEC requirements for EMI/RFI immunity (including IEC 61850 requirements),
National Grid Saudi Arabia will waive the field EMI/RFI immunity test
requirements for the SAS equipment items whose adequate type test reports for
EMI/RFI immunity are provided.
10.4
view only
operation
modifications
responsible for the allowance of permission
TESP10701R0/KSB
a.
b.
c.
PAGE 70 OF 119
TES-P-107.01, Rev. 0
b.
b.
10.5.2 Training
The SOLUTION PROVIDER shall also provide training as described in
related Attachments of the main PTS and the scope of each service shall be
given.
10.5.3 Operating Spare parts
a.
TESP10701R0/KSB
PAGE 71 OF 119
TES-P-107.01, Rev. 0
b.
TESP10701R0/KSB
a.
b.
c.
PAGE 72 OF 119
TES-P-107.01, Rev. 0
e.
10.5.6 Maintenance
a.
b.
11.
special maintenance
predictive maintenance
periodical maintenance
condition maintenance
on-fault maintenance
DOCUMENTATION
11.1
During the Base Design Stage of the project, the SOLUTION PROVIDER shall
submit the following documentation related to the Base Design for the SAS as a
minimum. The documentation shall be both in hard copy and CD format. The
documentation shall be consistent, CAD supported:
TESP10701R0/KSB
List of Drawings
Assembly Drawing
System main objective and basic features
Design principles
Schematic Drawings
Construction Time Schedule (design, manufacturing, commissioning periods)
Listing of type tests and copy of type test reports
Listing of routine tests
Listing, and description of tests, and test specifications for tests which will be
performed as part of the Factory Acceptance Testing (FAT) phase
Site commissioning requirements (including listing, description of tests,
procedures/ test specifications and test forms/reports which will be included
Date of Approval: February 26, 2013
PAGE 73 OF 119
TESP10701R0/KSB
TES-P-107.01, Rev. 0
as part of the Pre-Commissioning Test Plan and Procedures, and the Final
Test/Commissioning Test Plan and Procedures)
Operations Requirement
Technical data and catalogues
Product Manuals which do not appear in the Technical data and catalogues
List of all international standard references
List of all technical requirements that are to be provided by other
manufacturers for items not manufactured by the same SOLUTION
PROVIDER 's manufacturer
System Block and Logic Diagrams
Training Plan and Resume's of SOLUTION PROVIDER 's trainers during all
phases of the training.
Control Room Layout and other room layouts in the substation showing
locations of SAS equipment relative to other equipment
Typical Standard Alarms/Events Pictures for SOE functions which will
appear on the Station HMI
Typical Standard Pictures from Station HMI as specified in Section 4 of this
Standard.
List of all items included as part of the SAS
Overall single-line diagram for the entire substation (with
demarcations/boundaries drawn on the diagram to show each bay)
Bay single-line diagrams
Bay oriented Local Control Panel with Mimic Diagram detail drawings
Relay and Metering single-line diagrams for each entire substation (prepared
in accordance with National Grid Saudi Arabia Engineering requirements for
Relay and Metering single-line diagrams)
General system architecture
Location of the substation's buildings
Control and operating principles
Protection principles
Functional Design Specification (FDS)
List of Signals
Calculation for uninterrupted power supply (UPS) dimensioning (if a UPS is
used as part of the Project to supply AC power to SAS equipment requiring
AC Power)
Calculation and design details for the Inverter scheme (if redundant inverters
are used as part of the Project to supply AC power to SAS equipment
requiring AC Power)
Concept for maintenance, including any SOLUTION PROVIDER proposals
for operations and maintenance of the SAS for a two year period after
National Grid Saudi Arabia accepts the SAS installation.
Time plan for the project realization
Circuit Diagrams
List and Scheme for Colors, Symbols, Labels, Dialogues and Fonts to be used
in all components of the SAS
LAN Simulation Study results
Cable Routing Details within each substation for SAS equipment
interconnections
Date of Approval: February 26, 2013
PAGE 74 OF 119
TESP10701R0/KSB
TES-P-107.01, Rev. 0
PAGE 75 OF 119
TES-P-107.01, Rev. 0
11.2
During the Detailed Design Stage of the Project, the SOLUTION PROVIDER shall
update and revise the initial SOLUTION PROVIDER 's Base Design for the SAS
based on previous National Grid Saudi Arabia comments during the Base Design
Stage of the Project. Additionally, the SOLUTION PROVIDER may provide
additional design drawings/documentation of his SAS for National Grid Saudi Arabia
review and comment during the Detailed Design Stage of the Project. After the
SOLUTION PROVIDER completes his detailed design of the SAS, the SOLUTION
PROVIDER shall submit all detailed design drawings and related documents (both in
hard copy and in soft copy in a format acceptable to the National Grid Saudi Arabia)
for final National Grid Saudi Arabia review and approval of the SAS as a whole.
11.3
At least four (4) weeks prior to the start of pre-commissioning by the SOLUTION
PROVIDER, he shall submit the following documentation related to precommissioning for the SAS as a minimum. The documentation shall be both in hard
copy and CD format. The documentation shall be consistent, CAD supported:
Copies of Routine Test Reports
Copies of Valid Calibration Certificates for all test equipment used to precommission the SAS
Copies of the initial SCL (Substation Configuration Language) files for all IED's
installed by the SOLUTION PROVIDER (in accordance with IEC 61850 format)
which will be used by the SOLUTION PROVIDER
during the PreCommissioning and Final Test/Commissioning phases of the SAS for the Project
Copies of initial SCD (Substation Configuration Description) and CID
(Configured IED Description) files
Copies of other initial configuration data (such as relays/IED settings, etc).
Copies of the results of the Factory Acceptance Tests for all SAS equipment.
TESP10701R0/KSB
PAGE 76 OF 119
TES-P-107.01, Rev. 0
Copies of the National Grid Saudi Arabia approved Pre-Commissioning Test Plan
and Procedures
NOTE:
Some of the documentation indicated in Section 11.3 of this Standard may be
required by the National Grid Saudi Arabia at a time earlier than the minimum of four
(4) weeks prior to the start of pre-commissioning of the SAS. If this is the case,
National Grid Saudi Arabia will notify the SOLUTION PROVIDER accordingly as
part of the Base Design stage of the Project.
11.4
At least two (2) weeks prior to the start of final test/commissioning by the
SOLUTION PROVIDER , the SOLUTION PROVIDER shall submit the following
documentation related to final test/commissioning for the SAS as a minimum. The
documentation shall be both in hard copy and CD format. The documentation shall
be consistent, CAD supported:
11.5
Prior to final acceptance by the National Grid Saudi Arabia, the SOLUTION
PROVIDER shall submit the following documentation for the SAS as a minimum.
The documentation shall be both in hard copy and CD format. The documentation
shall be consistent, CAD supported:
TESP10701R0/KSB
Copies of Valid Calibration Certificates for all test equipment used for final
testing/commissioning of the SAS
Copies of the National Grid Saudi Arabia approved Final Test/Commissioning
Test Plan and Procedures
Copies of all Pre-commissioning Test Data (for tests which were performed as
part of the Pre-Commissioning Test Phase of the project)
Copies of final SCD (Substation Configuration Description) and CID
(Configured IED Description) files
Copies of the final SCL (Substation Configuration Language) files for all IEDs
installed by the SOLUTION PROVIDER (in accordance with IEC 61850
format) which will be used by the SOLUTION PROVIDER during Final
Test/Commissioning phases of the SAS for the Project
Copies of other final configuration data (such as relays/IED settings, etc).
PAGE 77 OF 119
11.6
12.
TES-P-107.01, Rev. 0
For the hard copy requirements, the SOLUTION PROVIDER shall submit a
minimum quantity of the sets of drawings/documents which are specified in the main
PTS document for National Grid Saudi Arabia review. For the soft copy
requirements, documents and drawings which are prepared by SOLUTION
PROVIDER shall be readable by the Adobe Acrobat Reader version which is in use
by the National Grid Saudi Arabia at the time of the documents/drawings submittal,
and a minimum of two (2) CD copies shall be distributed by the SOLUTION
PROVIDER to the National Grid Saudi Arabia. For drawings and documents which
will ultimately be submitted by the SOLUTION PROVIDER in final form to the
National Grid Saudi Arabia's CAD system, the final format which will be used for
submission to the National Grid Saudi Arabia's CAD System shall be in accordance
with the National Grid Saudi Arabia./ CAD requirements (SEEDS I & SEEDS-II).
CYBER-SECURITY REQUIREMENTS
Cyber-Security-hardened network with the use of defense-in-depth Industrial Control
Systems (ICS) cyber-security standards, protocols, and industry practices shall be provided.
12.1
The communications network shall be security-hardened with the use of IEC, IEEE
and IETF security standards and practices.
12.2
In addition to traditional IEC, IEEE and IETF network security practices, the
communications network shall also be security hardened with the use of Industrial
Control Systems (ICS) standards and practices according to the NERC-CIP, NIST,
ISA standards and practices. For more explicit security requirements, National Grid
Saudi Arabia may also opt to require Solution provider to harden the SAS network
based from internationally agreed cyber-security practices like the Cyber Security
Procurement Language for Control Systems, and other defense-in-depth strategies
based from aforementioned standards, which are designed to harden control system
facilities.
12.3
IEC utility-centric protocols, IEC 62443-2-1 (latest edition), and IEC 62351 (as soon
as applicable), shall be complied with to harden the IEC 61850 network against
attacks by internal and external utility users.
12.4
12.5
12.6
TESP10701R0/KSB
PAGE 78 OF 119
TES-P-107.01, Rev. 0
12.7
Threats and vulnerabilities in the network and administration shall be identified and
fortified against cyber-attacks. Ready countermeasures and defenses shall always be
pre-planned and available.
12.8
12.9
USB and CD/DVD ports shall be deactivated. Unused ports shall be closed. Periodic
port scanning shall be automatically configured with option for manual
configuration.
12.10 Ports into which maintenance laptops will be plugged into the embedded operating
systems in the IEDS and PLCs shall be installed with intrusion detection devices or
software. Updated anti-virus software shall be installed in these IEDs and PLCs to
counteract the latest discovered Industrial Control System Trojans and rootkits. Such
hardening measures shall also apply to the computer equipment and switches from
the station level to the bay level.
12.11 Access to OPC and database servers, if used, shall be secured and measures against
SQL or database injection shall be provided.
12.12 Maintenance laptops shall be configured such that only currently authorized users in
the substation can log in.
12.13 Security measures shall be applied in the 7 OSI (Open System Interconnection)
layers.
12.14 Measures shall be provided to secure the IEC-101 communications to the control
centers and related devices like modems and telephone equipment shall be
performed.
12.15. The IEC-1O4 communication lines shall be firewalled. All ends of electronic
perimeters shall be firewalled and secured.
12.16 Likewise, the premises cabling system shall be secured to prevent data from being
sniffed or corrupted from the cables, junction boxes, patch panels and other
vulnerable portions of the premises cabling system.
12.17. In case of attack, emergency measures shall be pre-planned for implementation
during the attack and disaster recovery shall be pre-planned to recover lost data and
put substation operation back to normal in the shortest possible time.
12.18 Cyber-security testing and cyber-security quality assurance shall be part of the
Factory Acceptance Procedures (FAT) and Site Acceptance Procedure (SAT).
12.19 Training shall include topics on Industrial Control Systems (ICS) cyber-security in
general, and the cyber-security measures employed in this project.
TESP10701R0/KSB
PAGE 79 OF 119
TES-P-107.01, Rev. 0
12.20 As part of the SOLUTION PROVIDER 's SAS design and implementation, the
SOLUTION PROVIDER shall provide the it's Cyber-Security proposal and scheme
in the form of a manual which the SOLUTION PROVIDER shall implement (after
National Grid Saudi Arabia. approval of its Cyber-Security proposal and scheme)
pertaining to providing a Cyber-Security hardened network for the SAS which is
consistent with all Cyber-Security requirements as specified in this Appendix, as
well as other National Grid Saudi Arabia. related Cyber-Security requirements which
are related to the SAS communications interconnection with equipment outside each
substation.
12.21 The aforementioned cyber-security Manual shall show specific deployment
instructions to be followed in implementing cybersecurity in the operating systems,
applications, database. For example, where in the configuration of the OS default
open and existing ports in the MS operating systems are closed or deactivated shall
be addressed. How are the remote access, MS operating sytem's Outlook Express,
Messenger, MSN Explorer, Windows Media Player, Games de-activated. How are
IPsec, VPN, SNMP configured, how is the firewall of the OS made compatible to the
firewall configuration of Solution provider SAS applications, what are the BIOS
settings that are enabled or disabled to implement security are some of the required
content of Solution provider security manual. Additionally, to illustrate the required
content, there are Windows services that should be disabled to harden the OS: e.g.
IIS admin, Mnmsrvc, MSFtpsvc, Fax, Tapisrv, etc. there are more or less 25 of these
services. Security policies of OS and Solution provider applications may need to be
firmed on whether to use OS or Solution provider application defaults. e.g.
password age, password minimum/maximum characters, lockouts, etc. How is OPC
and database servers are secured shall be addressed. Dialog boxes of the OS shall be
shown to illustrate the deployment instructions. Above mentioned samples are meant
to show required content from the Solution provider security manual. Such examples
are not meant to be complete.
12.22 The manual shall detail the SOLUTION PROVIDERs solutions to cyber-security
issues indicated in the standards and industry practices indicated in Item 12.2 and
other clauses under this section on cyber-security requirements.
12.23 As part of the SOLUTION PROVIDER's Cyber-Security proposal and scheme, the
SOLUTION PROVIDER shall provide, install, test and commission all required
hardware, software, and other equipment which is required to provide for a fully
operational and National Grid Saudi Arabia. approved SAS Cyber-Security scheme
for the substation.
12.24. Manual shall also contain operator-and-maintenance-centric instructions and
suggestions that could maintain cyber security in the course of National Grid Saudi
Arabia. operations and maintenance of substation.
12.25. SOLUTION PROVIDER shall include in his proposed manual content pertaining to
cyber security training program proposals. Content shall include importance and
details of content of security in the design, manufacture, factory/site testing,
operation and maintenance of proposed SAS system.
TESP10701R0/KSB
PAGE 80 OF 119
TES-P-107.01, Rev. 0
12.26. In the National Grid Saudi Arabia. review of the SOLUTION PROVIDER proposed
cyber security manual, National Grid Saudi Arabia. will use applicable portions of
standards and defense-in-depth practices on Industrial Control Systems cyber
security from IEC 62443-2-1, IEC 62351, NERC-CIP, IETF, IEEE, NIST, US-DHS
documents.
12.27
In the case where the SAS Equipment Manufacturer offers anti-virus software for his
SAS installation, the SAS Cyber-Security proposal shall include the requirements for
supply and installation of the anti-virus software. As part of the supply and
installation of the anti-virus software, only versions of the SAS Equipment
Manufacturers anti-virus software which has been tested (and if required debugged) at the SAS Equipment Manufacturers test laboratory facilities, and which
has been certified by the SAS Equipment Manufacturer to fully function properly on
the SAS which is being supplied under the project shall be used in the SAS.
Furthermore, with regard to updates to the SAS Equipment Manufacturers antivirus software (including, but may not be limited to updates/new virus/worm/Trojan
definitions), the same SAS Equipment Manufacturers testing and certification
requirements as described in this section will still be required.
12.28
AUTOMATION
SYSTEM
(SAS)
GENERAL
This section describes additional Substation Automation System (SAS) general requirements.
14.1
Environmental Requirements
14.1.1
14.1.2
TESP10701R0/KSB
PAGE 81 OF 119
TES-P-107.01, Rev. 0
Temperature
Humidity
Barometric pressure
Mechanical and seismic
Pollution and corrosion EMI immunity
o
o
o
o
o
o
14.1.4
14.2
Grouping/Location of Equipment
14.2.1
TESP10701R0/KSB
PAGE 82 OF 119
TES-P-107.01, Rev. 0
c.
TESP10701R0/KSB
PAGE 83 OF 119
TES-P-107.01, Rev. 0
TESP10701R0/KSB
d.
e.
PAGE 84 OF 119
TES-P-107.01, Rev. 0
14.3
f.
g.
14.4
14.5
TESP10701R0/KSB
PAGE 85 OF 119
TES-P-107.01, Rev. 0
14.7
TESP10701R0/KSB
PAGE 86 OF 119
TES-P-107.01, Rev. 0
connections for SCADA to three Control Centers) and one (1) IEC-104 for
SOE available to it as part of the Communications Gateway design. National
Grid Saudi Arabia.will make the assignment (of either IEC-101, or IEC-104
or both to connect to SCADA/SOE Master Station equipment) prior to the
completion of commissioning for the project.
14.7.3 Firewalls physically independent from the gateways shall be installed to
secure the gateway, which is the one of the end-points of the SAS electronic
perimeter. Two (2) firewalls be required for IEC 104 and other remote access
requirements.
14.7.4 Means to secure the IEC 101 communications shall be provided by the
Solution provider .
14.7.5 The Substation Automation System (SAS) shall be sized to accommodate and
shall connect to all external Master Station(s) and other external equipment
as specified in the PTS.
14.7.6 To support the interfacing of the IEC-101 connections referenced in Section
14.7.2 of this Standard, SOLUTION PROVIDER shall supply, install test
and commission one (1) National Grid Saudi Arabia. approved VF Modem
per IEC-101 connection referenced in Section 14.7.2.. This will require the
supply, installation, testing, and commissioning of a total of six (6) National
Grid Saudi Arabia approved VF Modems.
14.7.7 In terms of the routing of the data and the type of data which will be
terminated at the external Master Station(s) and other external equipment (as
required by the National Grid Saudi Arabia.), National Grid Saudi Arabia.
will provide the details of the routing and type of data during the Base Design
Stage of the project, so that the SOLUTION PROVIDER can implement
these National Grid Saudi Arabia requirements during the Detailed Design
and implementation stages of the project.
14.7.8 As part of the requirement for the SAS to connect to multiple SCADA
Master Stations, Command Arbitration facilities shall be supplied and
installed as part of the SAS. In this respect, Command Arbitration is
defined/means that if the same object/device (switchgear) is selected for a
control operation at the same time (or in very close time proximity) by two or
more SCADA Master Stations, the SCADA Master Station that gets access to
the device first will have control permission granted, while the other SCADA
Master Station(s) will be denied control of that object/device (switchgear).
As part of Command Arbitration, the SCADA Master Station(s) which had
the object/device (switchgear) permission denied will receive a message from
the SAS back to the SCADA Master Station(s) that control of the specific
object/device (switchgear) was denied.
TESP10701R0/KSB
PAGE 87 OF 119
14.8
TES-P-107.01, Rev. 0
14.9
For all SAS equipment, except the Protection IEDs, the Ethernet switches
and ac powered SAS equipment if any, the power input distribution
requirements shall be provided from the substation DC battery voltage
(usually 125 VDC, but NOT the -48 VDC Communications DC battery
voltage) in each substation. Wherever possible the dual substation DC battery
supplies shall be utilized.
14.9.2
For the Protection IEDs, the power input distribution requirements shall
follow current National Grid Saudi Arabia practices for input power
distribution for stand-alone Protective Relays.
14.9.3
For the Ethernet Switches, the power input distribution requirements shall be
from dual 125 VDC sources, which will power redundant power supplies in
the Ethernet Switch equipment.
14.9.4
For the SAS equipment requiring an AC Power input, refer to Section 14.25
of this Standard for the AC Power input scheme.
14.9.5
14.10 Various National Grid Saudi Arabia Standard Display Requirements for SAS
14.10.1
TESP10701R0/KSB
For the various National Grid Saudi Arabia Standard Display requirements
which may include (but may not be limited to) labels, colors, line
thicknesses, dialogues, fonts, alarm lists and symbols which will be provided
by SOLUTION PROVIDER as part of his SAS, the SOLUTION
PROVIDER shall design and provide all portions of the SAS with the
National Grid Saudi Arabia Standard Display requirements which are in
effect at the design stage of the Project.
PAGE 88 OF 119
TES-P-107.01, Rev. 0
14.10.2
14.10.3
For the Local HMI displays contained as part of each IED, the following
shall be applicable:
a.
b.
For the Protection IEDs, the Local HMI display shall be sufficient in
size for the National Grid Saudi Arabia maintenance personnel to
obtain and interpret related readings for the Protection IEDs.
c.
For all types of IEDs Local HMI requirements, either a backlit Local
HMI display or a active matrix LCD display shall be provided to
allow for National Grid Saudi Arabia maintenance personnel to read
details and parameters in low ambient light conditions
14.12.2
TESP10701R0/KSB
PAGE 89 OF 119
14.13
TES-P-107.01, Rev. 0
14.12.3
14.12.4
14.12.5
For this project three (3) Maintenance Laptop Computers along with all
required software and firmware to configure the SAS installation from each
Maintenance Laptop Computer will be required to be supplied by the
Solution provider .
14.12.6
14.14
14.15
TESP10701R0/KSB
PAGE 90 OF 119
TES-P-107.01, Rev. 0
14.17
14.16.3
14.16.4
Dual Active Communications Port Requirements for all IED's, interfacing on the
computer ends to support IEC 62439-3 PRP 1 compliance, and redundancy
implementation requirements
14.17.1
Each Bay-level IED (which will include ALL Control IEDs. Protection
IEDs and combined Control/Protection IEDs) shall be provided with dual
ACTIVE IEC 61850 and Ethernet compatible communications ports (with
two ACTIVE transmit and two receive communications ports per IED) for
interconnection/interface with redundant networks connection (redundant
networks connection as referred to in Section 3 of this Standard) which will
use fiber optics cable for each interconnection/interface. Bay-level IEDs with
either single IEC 61850 & Ethernet compatible communications port (single
transmit and single receive communications port per IED) or dual IEC 61850
and Ethernet ports containing one active port and one inactive port will NOT
be accepted by the National Grid Saudi Arabia.
14.17.2
TESP10701R0/KSB
PAGE 91 OF 119
TES-P-107.01, Rev. 0
Protocol scheme which is now in force and which will be (anticipated to be)
integrated into the future IEC 61850 Version (Edition2).
14.18
14.17.3
As part of the Bid Proposal the SOLUTION PROVIDER shall provide the
schematic diagram and description showing the dual ACTIVE
communications port connections of each IED with the redundant networks
as well the redundant networks diagram and description which will be
supplied by the SOLUTION PROVIDER for the SAS.
14.17.4
14.17.5
TESP10701R0/KSB
PAGE 92 OF 119
TES-P-107.01, Rev. 0
14.18.3
The Displays used for maintenance of the computer equipment (front end
computer equipment and Communications Gateways, etc.) shall be 19 inch or
larger and shall be branded High Definition Displays. Additionally as part of
the Display requirements as stated in Section 14.18.2 of this Standard
appropriate peripherals (e.g. Keyboards/Mice, KVM switches etc.) shall be
supplied and installed by the SOLUTION PROVIDER .
14.18.4
One (1) Color Laserjet printer which can print both A4 sized and A3
sized color documents. The Color Laserjet printer will generally be
used for printing display images from the various workstations as part
of the SAS (e.g. station one-lines, bay one-lines, some alarm/event
indications, etc). The Color Laserjet printer shall be able to operate
from a network (LAN) connection with required NIC cards/ports
installed inside the printer to allow Ethernet Communication to SAS
computers to SAS computers through an RJ-45 connection. The Color
Laserjet printer shall be a branded industrial grade printer, with
consumables/spare parts for the printer readily available for the
Alarm/Event Printer within Saudi Arabia.
Finally, as part of the supply of the Color Laserjet Printer, three (3)
years worth of estimated consumables (paper, laserjet cartridges and
other consumables to support 3 years operation).
TESP10701R0/KSB
PAGE 93 OF 119
TES-P-107.01, Rev. 0
14.19 Engineering Workstation and Operator's Workstation requirements for the SAS
14.19.1
14.19.2
14.19.3
14.19.4
All the other external standalone systems such as TFR (Transient Fault
Recorder)/DFR (Digital Fault Recorder) and possibly other external
equipment which the SOLUTION PROVIDER will propose during the Base
Design Stage of the project, require dedicated Ethernet connection for
communication with their respective remote master workstations (located
outside the substation).
14.19.5
The stand-alone Engineering Workstation shall be provided with remoteaccess Ethernet connection.
14.19.6
The Operator's workstations shall provide for full operation of the Station
HMI platform to allow for full SAS Control (when the Operator's workstation
is selected for this control), and will provide for retrieval of alarms/events
and other data from the Station HMI Front End Computers.
14.19.7 For both the Engineering Workstation and the Operator's Workstation the
computers, displays and peripheral equipment provided by the SOLUTION
PROVIDER shall be industrially hardened computers suitable for use in a
substation environment (with substations up to an operating voltage of 380
kV) and shall be fully in compliance with the SAS equipment manufacturer's
recommendations, as well as other requirements of this Standard. The
TESP10701R0/KSB
PAGE 94 OF 119
TES-P-107.01, Rev. 0
b.
c.
d.
14.20.4
TESP10701R0/KSB
PAGE 95 OF 119
TES-P-107.01, Rev. 0
c.
d.
PAGE 96 OF 119
TES-P-107.01, Rev. 0
14.22
a.
b.
For all SAS equipment items using Ethernet connections (except for
the Ethernet switches) plug-in Ethernet Communications Port/NIC
cards (with a maximum of two (2) Ethernet Communications
(Transmit/Receive) Ports per plug-in module (card)
c.
d.
e.
MTBF (Mean Time Between Failures) for critical non-redundant SAS equipment
14.22.1 For critical non-redundant SAS equipment which will impact on the overall
availability of the provided SAS (e.g. Control IEDs, Protection IEDs,
combined Control/Protection IEDs, Bay-oriented Local Control Panels with
Mimic Diagram, etc.), National Grid Saudi Arabia requires that a very high
reliability and availability must be provided for this equipment. Due to this,
the National Grid Saudi Arabia requires a minimum MTBF period of 20
years for this critical non-redundant SAS equipment.
14.22.2 The SOLUTION PROVIDER, as part of the design and construction of this
equipment should provide that, as part of the overall design and construction
that the National Grid Saudi Arabia required MTBF period of a minimum of
twenty (20) years be provided for each critical non-redundant SAS
TESP10701R0/KSB
PAGE 97 OF 119
TES-P-107.01, Rev. 0
equipment item. Where needed to meet the National Grid Saudi Arabia
preferred minimum MTBF period, the SOLUTION PROVIDER shall
consider such measures as providing internal redundancy of certain
components which have a high probability of failure (such as internal power
supplies and other components) which can be used to increase the MTBF
period requirement to the National Grid Saudi Arabia required minimum of
twenty (20) years.
14.22.3 As part of the SOLUTION PROVIDER's Bid Proposal, the SOLUTION
PROVIDER shall identify each critical non-redundant SAS equipment item,
and provide his minimum MTBF period for each critical non-redundant SAS
equipment item.
14.23 Additional Features and Functions of the Bay-oriented Local Control Panel with
Mimic Diagram and Alarm/Annunciator facilities and other LCC/Low Voltage
Compartment Requirements
14.23.1
TESP10701R0/KSB
b.
c.
d.
PAGE 98 OF 119
TES-P-107.01, Rev. 0
f.
g.
TESP10701R0/KSB
PAGE 99 OF 119
TES-P-107.01, Rev. 0
TESP10701R0/KSB
h.
i.
For the LCC Control Switch inside the LCC Panel(s) for High
Voltage in lieu of the requirements of the applicable switchgear
Materials Standard (32-TMSS-02 for 69 kV up to 380 kV), the
Control Switch shall be a four position switch with each position of
the Control Switch corresponding to the functionality as described in
Section 4.2.3.b and its subsections of this Standard.
j.
For the Low Voltage Compartment Control Switch inside the Low
Voltage Compartment(s) for Medium Voltage in lieu of the
requirements of the applicable switchgear Materials Standard (32TMSS-01 for 11 kV, 13.8 kV, 33 kV and 34.5 kV), the Control
Switch shall be a four position switch with each position of the
Control Switch corresponding to the functionality as described in
Section 4.2.3.2 and its subsections of this Standard).
k.
l.
TES-P-107.01, Rev. 0
14.24
n.
For the High Voltage, the Bay-oriented Local Control Panel with
Mimic Diagram, related emergency alarm/annunciator panels, lamps,
physical switches, Synchroscope, and Digital Meters shall be
integrated into the LCC Cubicle for the specific Bay, and will be
combined with the Control IED and other related equipment for that
Bay.
o.
14.24.2
Where the non-SAS routers/switches have fiber optics ports available for
connection with the SAS, National Grid Saudi Arabia requires that the
cabling which is to be provided, installed and connected by the
SOLUTION PROVIDER between the redundant Communications
Gateways and the non-SAS routers/switches shall be fiber cabling and
shall be MM or SM cabling (non-SAS router/switch ports which the
14.24.3
TESP10701R0/KSB
TES-P-107.01, Rev. 0
14.24.4
14.25
In terms of the use of either IEC-101 or IEC-104 or both for the SCADA
and SOE connections for each Communications Gateway, this decision
will be made by the National Grid Saudi Arabia at the time of
commissioning of the Substation.
14.25.2
14.25.3
14.25.4
All tests per Table 3 and Table 4 (including optional tests) of IEC 620403 or equivalent international standard to be indicated by Solution provider
shall be performed. Load test shall cover both manual and automatic,
transfer, and retransfer characteristics between UPS inputs and alternate
supply, In addition the following tests shall be performed: no load test,
forced air cooling tests (if applicable) and surge withstand capability.
14.25.5
TESP10701R0/KSB
TESP10701R0/KSB
TES-P-107.01, Rev. 0
TES-P-107.01, Rev. 0
TESP10701R0/KSB
TES-P-107.01, Rev. 0
14.25.6
TESP10701R0/KSB
b.
c.
d.
e.
14.25.7
14.26
TES-P-107.01, Rev. 0
National Grid Saudi Arabia notes that the Control IEDs, Protection IEDs,
combined Control/Protection IEDs and Ethernet Switches (used in the
Inter-Bay Bus and Station Bus) contained in the SAS shall NOT be
provided AC power as a primary power source, but instead, be provided
power from each substation's DC battery source (which is generally 125
VDC, but NOT the -48 VDC Communications Battery Source) as a
primary power source.
14.27
14.28
The supplied software shall have provision for the National Grid Saudi
Arabia to expand the Single Line diagram, Mimics and database to
accommodate future additions, without the involvement of the SAS
supplier.
14.28.2
The redundant computers used as part of the Station HMI Front End shall
be provided with full capability to provide simultaneous full updates of
TESP10701R0/KSB
TES-P-107.01, Rev. 0
all databases of the redundant Station HMI Front End computers. As part
of this full updating capability, the databases of the redundant Station
HMI computers shall be identical at all times.
14.28.3
14.28.4
14.28.5
14.28.6
TESP10701R0/KSB
TES-P-107.01, Rev. 0
14.28.7
14.28.8
14.28.9
TESP10701R0/KSB
a.
b.
c.
Anticipated
software/firmware
upgrades
and
software/firmware "fixes" which will be performed for a two
year period under the software maintenance and software
upgrade agreement plus
d.
Storage of all alarm, event and other data which will be stored
in the Station HMI for a period of three years after National
Grid Saudi Arabia final acceptance of the SAS plus
e.
f.
In the event that the IEDs are not able to interface and communicate with
the Station HMI equipment, the IEDs shall have sufficient buffering
capability to store normal quantities of alarms, values and events for a
minimum period of 24 hours without having alarms, values and events
Date of Approval: February 26, 2013
TES-P-107.01, Rev. 0
data erased or overwritten inside each IED. Also, upon the restoral of the
communications between the Station HMI equipment and the IEDs, each
IED shall provide an automatic transfer of alarms, values and events date
from each IED to the Station HMI equipment without disrupting SAS
operations, which will clear the IED buffers of backlogged alarms, values
and events.
14.28.10
14.28.11
14.28.12
National Grid Saudi Arabia notes that it will NOT accept the combined
functions of a Communications Gateway and Station HMI Front End
Computer in the same computer hardware unit. As such, physically
separate computers shall be provided for the separate functions of Station
HMI Front End and Communications Gateway.
14.28.13
TESP10701R0/KSB
14.28.14
14.29
14.30
TES-P-107.01, Rev. 0
For all computers used in the SAS installation for the substation which
the SOLUTION PROVIDER will be providing, the computer equipment
shall NOT use Manufacturer discontinued/obsolete processors and other
items inside the computer equipment that are no longer supported by
spare parts on the open market. Some examples of this include obsolete
microprocessors installed in the computer equipment, low capacity hard
disk drives which are no longer market supported low
capacity/obsolete/discontinued memory, obsolete video ports and other
items/factors.
For the alarms/events reporting related to the SOE functions, the Station
HMI shall provide a filtering capability to report SOE alarms/events on
the Station HMI which will display these SOE alarms/events with a
similar "look and feel" which currently exists on stand-alone SOE RTU
HMI equipment which the National Grid Saudi Arabia currently uses.
14.29.2
For the SOE Functional Display for the SAS, this "look and feel" shall be
similar and compatible with the current features of existing stand-alone
SOE Recorder products within the National Grid Saudi Arabia
14.29.3
14.29.4
14.30.2
TESP10701R0/KSB
14.30.3
14.31
TES-P-107.01, Rev. 0
14.32
14.33
TESP10701R0/KSB
TES-P-107.01, Rev. 0
14.35
Minimizing SAS Shutdown Time and Outage Coordination during future SAS
Upgrades/Reconfigurations
14.35.1
TESP10701R0/KSB
b.
c.
d.
14.35.2
14.35.3
14.35.4
Minimizing
Outage
Time
during
actual
upgrades/reconfigurations of SAS installations
performance
of
a.
In
cases
where
this
Contract
requires
an
upgrade/reconfiguration of the SAS to meet project
requirements (as identified in this standard), the SOLUTION
PROVIDER shall identify what items of the SAS will require
an outage, and perform all steps/activities, and equipment
necessary (as part of any upgrades/reconfigurations of the
SAS) to minimize such outage time.
b.
c.
b.
Development/Testing of SCD Files, CID Files and GOOSE CrossReferences for ultimate configuration of each substation
a.
TESP10701R0/KSB
TES-P-107.01, Rev. 0
As one step in minimizing the outage time in the future for the
SAS for each substation, the SOLUTION PROVIDER shall
Date of Approval: February 26, 2013
TES-P-107.01, Rev. 0
TESP10701R0/KSB
b.
c.
d.
e.
f.
TES-P-107.01, Rev. 0
Identification of connections between SAS and external SCADA Master Stations &
SOE Master Stations under standard.
14.36.1
14.36.2
14.36.3
14.37
For the hardware connection requirements (to SCADA and SOE Master
Stations), the boundary of the SAS portion will be at the substation
Communications equipment. However the SOLUTION PROVIDER
shall provide and perform the extension of double shielded CAT5
enhanced and/or SM/MM fiber optic cabling and its termination by
providing the necessary fiber optic transceivers on the router/switch
equipment in the substation communication room. SOLUTION
PROVIDER will be required to fully integrate all SCADA and SOE
functionality (at the SAS level) with the external SCADA and SOE
Master Stations and fully test these functionalities in coordination with
National Grid Saudi Arabia personnel who will be located at the
respective Master Stations
TESP10701R0/KSB
TES-P-107.01, Rev. 0
required to provide additional LCC/Control IEDs for the future bays/diameters for the
substation.
14.38
TESP10701R0/KSB
TES-P-107.01, Rev. 0
14.38.6 Points lists for the SCADA shall be established by SOLUTION PROVIDER
using one line diagrams provided in the main SOW/TS and applicable tables of
points, other guideline provided in latest revision of TES-P-119.27, Supervisory
Control and Data Acquisition. Finalization of all point lists shall be done during
base design stage subject to approval of National Grid Saudi Arabia.
14.38.7 The SAS upgrade/modifications/additions provided by the SOLUTION
PROVIDER shall be designed and configured in a manner such that, outage time
shall be minimized to the maximum extent possible. The section 13.35 above
shall also be applicable as necessary for minimizing the outage time
requirements.
14.38.8 SOLUTION PROVIDER shall prepare and/or revise the SCADA drawings, SAS
System Block Diagram, SCADA Tele-Information Plan sheets and all other
related drawings of the substations and submit to the National Grid Saudi Arabia
for review and approval before finalizing.
14.38.9 SOLUTION PROVIDER shall implement the SCADA Tele-Information plan
requirement for the substations in this project.
14.38.10 SOLUTION PROVIDER shall prepare procedures and conduct installation
check-out and performance testing in coordination with NATIONAL GRID
SAUDI ARABIA REPRESENTATIVES, which shall include, but not limited to
the following:
a.
b.
c.
d.
e.
TESP10701R0/KSB
TES-P-107.01, Rev. 0
TESP10701R0/KSB