Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
FHWA-KS-01-1 _
FINAL REPORT
OCTOBER 2001
7. Anthor(s)
Performing Organization
Report No.
FHWA-KS-OI-I
10 Work Unit No. (TRAIS)
15 Snpplementary Notes
Prepared in cooperation with the U.S. Department of Transportation,
Federal Highway Administration
16 Abstract
From 1990 to 1995 a total of 13 projects were constructed using crumb tire rubber. These projects
were built in responses to a legislature request to evaluate the feasibility of the use of crumb tire rubber in
highway construction. Six projects were changed ordered and seven were administrated through nonnal bid
procedures. The high-density mixes, recycle mixes, and the open graded mixes were employed in the
experiment. Five were the modified dry process and eight were of the wet process. A total of approximately
2637 tons or crumb tire rubber were used in all of the 13 projects.
A rating system was established to evaluate the effectiveness of each project. Almost all of the crumb
tire rubber came from outside of the state and very little was used from Kansas generated sources.
The report concluded that the use of crumb tire rubber in hot mix asphalt was possible but not
economically feasible. Therefore, if the use of crumb tire rubber is mandated in the state of Kansas, it is
recoriunended that another use be tried such as asphalt-rubber seals or buming the tires as a fuel source.
17 Key Words
18 Distribntion Statement
20 Security
C1assificatiou (of this
page)
Unclassified
21 No. of pages
82
22 Price
Prepared by
Glenn A. Fager, P.E.
Kansas Department of Transportation
October 200 I
ABSTRACT
From
to
1990
constructed using
1995
crumb
total
of
13
tire rubber.
projects
were
of
construction.
the
use
of
crumb
tire
rubber
in
highway
The high-
density mixes, recycle mixes, and the open graded mixes were
employed
in
process
the
and
experiment.
eight
were
of
Five
the
were
wet
the
process.
modified
dry
A total
of
rating
system
was
established
to
evaluate
the
hot
mix
Therefore,
feasible.
mandated
asphalt
in
the
state
was
if
of
possible
the use
Kansas,
but
of
it
not
economically
crumb tire
is
rubber is
recommended
that
11
TABLE OF CONTENTS
DESCRIPTION
PAGE
Abstract. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..
i
Table of C o n t e n t s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . i i
List of Tables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . i i i
List of Figures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. i v
Acknowledgements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..
v
Notice....... . . . . . . . . . . . . . . . . ... . . . . . . . .... .. . . . . . . . . . . .
v
Disclaimer. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..
v
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ~. . . . . . . . . . . ..
1
History...... . . . . . . . . . . . . . . . . ... . . . . . . . ... . .. . . . . . . . . . . .
2
Wet. Process. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..
3
Dry Process (Modified)..................................
5
Project Evaluation Criteria . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6
1990 Hot Mix Proj ects. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..
8
No.I-1990/US-75/Wet................................
8
NO.2-1990/K-2/Wet. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
9
Results (No. 1 & 2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
1991 Hot Mix Projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
No. 3-1991/US-24/Wet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Resul ts (No.3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
No.4-1991/US-24/Dry . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Results (No.4) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
No. 5-1991/US-59/Dry . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
Results (No.5) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
1992 Hot Mix Projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
No.6-1992/US-54/Wet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
Results (No.6) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
No. 7-1992/K-16/Dry . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
Results (No.7) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
No. 8-1992/I-70/Dry . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
Results (No.8) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
1994 Hot Mix Projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
No. 9-1994/US-54/Wet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
Results (No 9) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
No. 10 & 11-1994 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
Results (No. 10 & 11) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
No. 12-1994/I-135/Wet/NEPT KS 9401 (Final Report) .. 26
Resul ts (No. 1 2 ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
1995 Hot Mix Projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
No. 13-1995/US-75/Dry . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
Resul ts (No. 1 3 ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . : . . .. 45
Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
References. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 47
iii
LIST OF TABLES
PAGE
No.
DESCRIPTION
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
lV
LIST OF FIGURES
PAGE
No
DESCRIPTION
1.
2.
3.
4.
5.
6.
7.
8.
9.
67
68
69
70
71
72
73
74
75
ACKNOWLEDGEMENTS
Department
of
Transportation
(KDOT) ,
and
was
manufacturers.
This
information
formats.
available
in
alternative
accessible
Department
Information,
Office
is
Transportation,
Office
of
Transportation
Building,
296-3585 (Voice)
Topeka,
Kansas
66612-1568
or phone
(785)
(TDD).
DISCLAIMER
the
data
presented
herein.
The
contents
do
not
state of
Kansas
does
at
the
time of publication.
This
report
not
INTRODUCTION
In response to a State Legislature request,
Department
of
(KDOT)
Transportation
incorporate
ground
overlays.
There
tire
were
rubber
three
started
into
the Kansas
in
1990
experimental
basic
reasons
why
to
hot
mix
KDOT
was
from
old
Portland
Cement
Concrete
or
bituminous pavements.
2.
To
determine
if
it
would
reduce
the
amount
of
pavement rutting.
3. To address the environmental concerns over what could
be done with old tires.
Over
five-year
construction
period
(1990-1995),
been
of
the
wet
process.
through
sections
were
change
orders
planned
on
and
eight
have
negotiated
of
been
the
13
prices.
projects.
several
different
new gap
mix
graded mixes,
variations.
and
even
Standard
recycle
virgin
mixes
were
At that time,
this was the official mix design method for KDOT, and the one
most familiar by the field personnel.
A total of approximately 2637 tons of rubber were used
Very little crumb
shipped
from
outside
the
state.
map
of
the
proj ect
KDOT's
previous
experience
with
asphalt
rubber
dates
1978,
and 1979.
had fewer cracks than the control section, but on the other
three proj ects,
the control
performed
best.
performance
sections.
the
was
section without
On
the
measured
for
fifth
both
asphalt rubber
project
the
control
the
same
and
test
However,
were
two
Numerous
study.
of
the states
asphalt
throughout
the United
issued by
the
FHWA
rubber
helping to
projects
in
September
finance
1986,
Iowa
the
constructed
A report (2),
concluded
that
the
on
the
results
of
our
sections
and
the
test
rubber.
asphalt
The
process.
wet
process
Crumb rubber
is
the
already
(Type II or III)
familiar
MacDonald
is shipped in 22.68
kg
(50 Ib)
facility.
at approximately 204 C
typical blending ratio of 18% rubber and 82% AC-5 was used,
The combined
the material
At no time were
was
accomplished
by
normal
self-propelled,
It was capable of
(drums).
A minimum
asphalt-rubber binder.
DRY PROCESS (MODIFIED)
The modified dry process was the only process that KDOT
elected to try as
an alternate
to
the more
expensive and
It is applicable
To date,
all
of
constructed
rubber or what
is
through
feeder
is
also
attached
to
the
bottom of
the
weigh
After
rubber out
of
the
vane
feeder
the weigh
has
container,
metered
the
the
ultra
fine
conveyor or auger
The rubber is
drum
plant.
There
is
no
reaction
in
that
the
four
(highest)
performance.
crack surveys or by
Each
to
zero
(lowest)
based
on
its
field
(somewhat)
But,
subjective
that opinion
skid numbers,
results or conclusions.
grade
(four to
receive
zero).
formal
in detail
evaluation.
Very
little
testing
was
These
overall
calculated.
number,
rating
for
all
of
the
13
projects
was
therefore,
the
following
range
would
be
used
to
LEVEL OF PERFORMANCE
- 0.5
Marginal
(Below satisfactory)
1.5 - 2.5
2.5 - 3.5
3.5 - 4.0
1990
projects
located on US-75
The
Wichita.
to
south of
Topeka
be
constructed
Topeka
project
in
and on K-2
(Figure
1,
Kansas
were
southwest
No.
1-1990)
of
was
did
Inc.,
the
of Phoenix, Arizona,
preliminary
mix
International
design.
The
sections
were
The test
0.8 km
(0.5 miles)
course lifts of 44 mm
(1.
long and
(0.75 ") BM-1T, for a total of 108 mm (4.25") thick over the
old PCCP.
(0.75")
BM-1T,
(1.
75")
total thickness of
64 mm
(2.5").
The
(2.5")
thick as
predominately a
crushed
limestone mix that has been used for the previous two years
to reduce rutting.
approximately 38 mm
surface
course
overlay
projects
vehicles
per
(1. 5")
is
thick.
normally
for
used
roadways
It
day.
The 19 mm
for
with
contains
skid
placed
contractor had a
using
new pipe
than
approximately
drum
mix
installed
50%
on
5,000
crushed
BM-1T
resistance
greater
rubber
(1. 5")
plant,
in the
which
the
of
the
Wichita.
Shown
in
Figure
are
typical
sections
for
total
of
76
consisted of 38 mm (1.5")
mm
(3.0")
The
thinner
sections
of BM-
existing
bituminous
longitudinal,
pavement
and block
cracks.
had
Many
numerous
of
the
10
transverse
were
cracks
slight
secondary
depressions
Most
cracks.
had
cracks.
associated
Generally,
with
these
there
secondary
straight alignment
in Tables
mixes
will
It
and 3.
cost
is
obvious
substantially
that
more
the asphalt-rubber
than
the
asphalt
only
mixes.
quantities.
They
were
also
experimental
with
several
calculated and payments were made under change orders and not
under
low
bid
expected
that
section
would
price
cost
be
conditions.
for
quite
Therefore,
constructing an
high.
Later
it
would
be
asphalt-rubber test
proj ect
studies
did
Tables 2
respectively.
three
the
asphalt
only
section.
For
the
next
three
Both the
11
Final
rut
measurements were
only sections.
It appears
collected
numbers,
it
was
determined
that
Based on the
there
was
no
pavement
and
those
taken
on
an
asphalt-rubber
pavement.
Based on the less than satisfactory performance of all
of the
test
sections
2.4
km
(1.5
mile)
test
larger
and
asphalt-rubber
principal
was
complete
overlay
sections,
constructed.
The
would
12
The
wet
(Interna tional
The
process
was
Surfacing
sub-contractor
used
Inc.)
and
the
again completed
accomplished
also
sub-contractor
the
the
design.
blending
and
However/
The aggregate
with a
as
the
binder.
Table
binder content,
miles)
gives
description
of a 25 mm
(In)
of
the
The
(No.
aggregate,
But, as of June 5,
13
cost for this particular project was 2.75 times higher than a
normal asphalt overlay, the increase in cost may be justified by
the increase in service life.
undetermined what the actual life of the asphalt rubber gap graded
mix would be as the whole project had to be overlaid.
The factors
used to determine the timing of the new overlay came from the
condition of the pavement from outside the asphalt rubber gap
graded test section.
Based on the unusually high field performance of no cracking
or rutting in the gap graded test section, this experiment was
given the highest rating of a four.
A noise study was completed on the US-24, US-75, and K-2
projects. The study was conducted in 1991, which was one year
after construction had been completed on both projects.
The
peak
individual
or
highest
vehicle
operating modes
were
passing
noise
by
levels
at
generated
controlled
obtained on the
test
by
speeds
sections.
an
and
All
14
sections.
three
passes
cruising,
at
55
m.p.h.
accelerating,
in
three
modes
and rolling.
of
operation:
interval
January 1992.
report
of
the
results
were
published
in
on the US-75
and K-2
sites.
An
average
of
the
overall data indicates a noise level of 69.73 dB for asphaltrubber and 72.04 dB for the asphalt only pavement.
2.31
dB
decrease
in noise
level
of
high
This is a
density
asphalt-
on
produced
the
the
US-24
project,
highest
the
readings
asphalt
with
the
rubber
car
and
slight decrease.
(84.2 vs.
84.9);
however,
cruise
and
accelerating
data
for
larger
heavy
truck
the
best
indication of
In fact,
the
pavement-tire
interaction
15
would
still
be
generating
an
uncertain
amount
of
noise.
Costs
still
remain
high
for
the
wet
process
and
mix,
proposal
Therefore,
in order to
from
contractor
was
approved
to
rubber was
plant silo.
and
The ultra
stored in a
plant.
Three
test
sections
and
one
control
section
were
of
A 10%
it was designed as
16
over lay.
(2")
KDOT BM-2A
(low
excluding mobilization.
If the
cost
the
of
significant.
(Also,
indirect
such
costs
mobilization
in
as
Table
would
7,
tack coats,
the
have
mix
been
cost
stripping,
less
excluded
etc.)
The
Table
8 presents the
measurement data.
rubber
section
did
perform
However,
slightly
better
than
the
rutted.
Based on the crack surveys and the apparent inability of
the rubber to reduce the cracking to any appreciable extent,
the performance of this experimental project was rated as a
one.
17
that was started in 1991, but not finished until 1992 (Figure
1,
No.
5-1991).
This was
the
first
attempt
using
the
fine
rubber
to
introduce
Previous KDOT
involved virgin
aggregates
both
30%
Reclaimed
Asphalt
Virgin
Both mixes
as
percentage
added plus
asphalt
of
the
total
in the RAP).
liquid
This
binder
calculation
A 10% asphalt-
rubber mix blend ratio was computed as ten parts rubber (by
weight)
to
90 parts
asphalt-rubber
asphalt.
recycle
mixes,
Using this
the
90
example
parts
for
asphalt
the
would
then more
18
AC-5
additives
was
used
were
in
used for
the
30/70
the
mix,
two different
and
RA-100
mixes.
asphalt
(1.5").
fall
of 1991.
The
Bi tuminous
shoulders
were
extended
0 .46
')
but a 38 mm
(l.5")
was due to
the
lift,
but
Severe
it was uncertain
the
winter,
decision
to
Also
construction
would
increase
the
binder
first
be
completed
on
other portions of the project so that the top and final lift
would be constructed during warmer months of the construction
season.
19
ravel.
difficul t
somewhat
to compact.
looked
asphalt
substantially
blend ratio.
would
not
occurred in the
was
increased,
increased
in
order
SO/50
mix.
the
rubber
had
to
maintain
the
When
the
to
be
overall
to
the
aggregates.
Apparently
the
it
The
percent
new
asphalt
could
then
be
changed
20
The crack
finished.
Three additional
were also
The
sixth
competitive
bids
project
were
was
the
received
on
wet
a
process
29.8
km
(Figure 1,
in
which
(18.5
mile)
No.
6-1992).
This proj ect did not contain any test or control sections.
The mix on this
wet process
project
was
Costs were
21
cement.
some
rubber
from a
Kansas
necessary
after
approximately
two
Extensive repairs
years.
Water
was
entering the mix and causing deterioration in the asphaltrubber and the base mix.
life of only
seventh
The
incorporating
gap-graded
(Figure
mix
and
No.
1,
BM-IB
mix,
7-1992)
used
the
content
on
this
proj ect
was
control
section
and
based
on
changed
of
the
BM-IB
mix
were
built
with
control
km
(0.5
mil
control
section
contained asphalt
The
without
rubber.
asphalt
only
aggregates
mix.
and
The
stick to
asphalt
the
would
drain
truck beds.
down
from
the
22
This
(SMA)
mix very
closely resembled a
mix gradation.
stone
Mastic
This allowed a
lists
the
mix
and
cost .data
of
the
control
Table
and
test
sections.
Results (No.7)
No formal crack surveys were conducted on the project.
However,
informal
site
inspections
were
completed
on
the
following dates:
1)
2)
3)
Aug. 7, 1995
-BM-1B Mix
No
rutting
but
some
cracking in all sections.
Bleeding
in
the
high
asphalt-rubber sections.
-Gap Graded Mix
No rutting or bleeding.
Raveling and cracking in
the lower asphalt-rubber
section.
4)
July 3, 1997
-BM-1B Mix
No rutting but some
cracking.
Starting to
form potholes on the low
asphalt-rubber section.
-Gap Graded Mix
Some raveling in the low
asphalt-rubber section. A
few spot bleeding areas in
the high asphalt-rubber
sections. Cracking in all
areas.
concluded
that
the
asphalt-rubber
sections
would
be
Some of the
test sections looked good at the time of the overlay and they
would probably last
longer
than
six years.
It
should be
the
short
test
section.
The
rating of this
r-70 / Dry
24
fed
from
silo,
but
air blown
Rubber was
into
coater
not introduced into the mix inside the drum dryer where the
hot
gases
could
remove
the
fine
rubber
from
the
mixing
chamber.
Results (No.8)
No formal crack and rut surveys were conducted on this
project.
rubber could be
added to a
drum feed
of a two.
At the end of 1992,
that
full
depth
serviceable
Up
until
life
1993,
asphalt-rubber pavements
than conventional
all
whether
the
of
the
may
asphalt
rubber
proj ects
have
longer
only pavements.
had been
thin
cracking performance
of
the
asphalt-rubber
It wasn't until
25
Three
test
sections were
were
built
several
other
These test
different
were
designed
(International
and
Surfacing
reacted
Inc) .
by
the
The
test
These wet
subcontractor
main
contractor
40mm ARS
240mm BM-2C
40mm ARS
60mm ARB
200mm DGAB
40mm ARS
60mm ARB
200mm BM-2C
Resul ts (No.9)
By 1996, major rutting had occurred in all of the rubber test
sections.
the
results
concluded
the
rutting
was
due
to
both
mix
Due to the
26
(Figure 1,
No.
10
11-
&
received.
mixes
and
designed
the
(International
in
these
binder
Surfacing,
wet
process
reacted
Inc.).
by
proj ects
subcontractor
Mix cost
were
was
still
high
The second
(No.
10 and 11)
providing
service
As of May 2000,
to
traffic
although
maintenance
the Kansas City area, the project on US-56 was given a rating
of a three.
No. 12-1994 / I-135 / Wet / NEPT KS 9401 (Final Report)
In 1994, a 15.25 km full depth asphalt-rubber project was
constructed
NO.12-1994) .
on 1-135
An
in McPherson County,
adjoining
16.22 km full
Kansas
(Figure
1,
depth conventional
There were
27
1.
pavement rutting.
To
3.
address
the
environmental
concerns
over
the
will
Surface
comply
with
Section
1038
mixes,
of
the
and procedures
1991
(ISTEA),
Intermodel
but produce a
construction equipment,
cost effective.
methods,
In May 1990,
Life cycle
(overlays)
time.
major
Most
Portland
Bituminous
Cement
occurring
at
reconstruction
Concrete
(PCC)
estimated
projects
pavement
intervals
would
and
include
Full
of
a
Depth
28
However;
field
FDBIT
Therefore,
pavements.
the
preferred
construction
KDOT
1992,
reduction
of
early
asphalt-rubber
hot
had
attained
transverse
mix.
cracking
There
was
itself
to
limited
reduced prices
success
with
also
the
some
in
gap
the
graded
interest
in
on the
cost
of
the
asphalt-
rubber.
An
initial
cost analysis
There was
also
some
interest
in determining
FDBIT
pavement
(without
rubber)
was
not
five
strategies
were
reduced
to
three
plans
as
Initial
three plans.
The construction
29
Table
11.
actions,
The
present
worth
cost
of
these
10
and
20
year
cost.
Strategy C was approved as the most feasible construction
option.
Some
necessary
at
reconstruction
five
bridge
into
locations
the
in
subgrade
order
would
to
be
maintain
Type
III
reacted
bituminous pavement.
(wet
committed
to letting in
process)
crumb
rubber
modified
in
the
pugmill
mixer)
time,
of
batch
or
continuous
flow
plant
(drum
it
was
expected
that
some
of
the very
fine
alternate
was
considered as
dry process.
(Ultra Fine)
The
the
dry process
of
adding
possibility of
using
Type
VI
considered,
it
If
this
cost
30
and
been
already
had
used
on
pavement
construct
to
(3 )
previous
KDOT
projects
as
using
either
one
of
the
two
used
on
the
alternatives.
Two
project.
aggregate
different
One would be
asphalt-rubber
mixes
would
be
an asphalt-rubber base
(ARS) .
surface
Both
of
(ARB)
these
and an
aggregate
(VMA).
This
for
alternate
#2
(Ultra
Fine
Dry
(Wet process)
process).
and two
Table
12
The wet
process was approximately $2/ton less than the ultra fine dry
process.
However/
for
comparison
purposes
only,
it
was
Control
and
Test
constructed in the
Sections
northbound
were
lanes.
was a
treated
also
laid
Figures 4
and
360
mm
asphalt
rubber
and
through 7
Test Section #1
out
(Figure
150 mm lime
mix
(320
mm
These
31
overpasses
in
Therefore,
order
test
to
provide
section
from
proper
this
bridge
particular
clearances.
design
was
(Figure 5)
was a
were
accumulated
added
in
the
to
remove
rubblized
any
water
that
concrete.
The
was
Edge
trapped or
shoulders
were
thickness
reduction
in
the
asphalt
rubber
would
perform
(Figure 6).
only
is
that
shoulders
section #3
were
also
is
45 mm thicker.
built
to
normal
The
design
(Figure 7)
32
The mixes that were used in the control and test sections
are characterized in Table 13.
u.s.
Corp
content.
blows
Gyratory
(GTM)
were
used
select
the
binder
used
for
the
shoulders.
volumetric
The
paving
did
not
start
until
early
April
1994.
The
the
Once
northbound
the
lanes
were
built
including
the
the
former
driving
surface
into
fairly
large
size
edge
rubblized
of
the
section.
The
small
areas
that
were
33
spread and
Only one drum mix plant was used on the proj ect.
compacted.
The
reacted,
plant
could
accommodate
either
asphalt
only
or
asphalt
to
build
an
asphalt
rubber
reaction
mixing plant.
The major
Originally,
transported
system.
to
rubber was
shipped in large
the
tank
mixing
kg bags and
elevator/conveyor
through an
900
and
handle
moisture contamination.
rubber
with
little
danger
from
at the bottom of the silo would weigh the rubber and then feed
it into a pneumatic line that would
mixing/reaction tank.
34
2.
Rubber that was fed into the mixing and reaction tank was
reacted for 45-90 minutes with AC-I0.
supplied from a
was
periodically
checked
Once a
viscosity of 1000-4000
with
cps was
Haake
viscosimeter.
attained,
the
reaction
was considered complete and the reacted asphalt rubber was then
pumped
into
liters
of AC-I0
rubber
for
an
Later in the
The
68,137
asphalt
was
liter
storage
reacted
with
approximate
project,
rubber
the
16/84
tank.
3.67
was
metric
tons
rubber/asphalt
blend ratio
reaction
Typically,
was
"batch"
of
blend
reduced
22,712
crumb
ratio.
to 13/87.
process,
but
the
The
purpose
of
the
storage
tank
was
to
keep
the
mixer
process.
the
to
complete
the
asphalt
rubber
storage
tank
to
be
charged
9.4
bituminous
mix
times
(with
the
22,712
Probably
one
of
the
more
important
components
of
the
A special circulating
35
storage
tanks.
Addi tionally,
the
hot
oil
circulated
the oil was returned to the oil heater to begin the circulation
process
over again.
The
heated oil
never came
asphalt
into direct
asphalt
rubber.
kept
project.
hot
until
the
asphalt
The AC-10
was
then pumped
mixing/reaction
tank.
Rubber
rubber
was
was
into
than
needed
the
on
It
the
34,069
liter
pneumatically
added
Samples were
After transfer or
36
the
asphalt
rubber
could
be
reacted.
The
production
this
project
typically varied
from
Rubber contents
16/84
down
to
13/87
shutdown,
but was
finished
in
1995.
Laboratory Testing
Almost
all
of
the
research
laboratory
testing
was
Gyratory
Compactor
rutting potential.
(GTM)
could
possibly
The U.S.
address
the
37
is
GTM
the
both
test,
compactor
specimens
are
and
testing
clamped
in
machine.
the
To
mold chuck.
Vertical
pressure
is
Gyratory motion is
the top surface of the chuck flange and the other around the
lower surface.
to
allow
strain.
setting
The
of
any gyratory
interaction
of
the
angle
or
vertical
degree
of
pressure
shear
and
the
movement of the rollers around the chuck flange gives the mold
and its test specimen the rolling undulating motion that kneads
the test materials in ways that closely approach the pressures
and wear of highway use.
and
this
material.
motion
is
affected
In other words,
shear tester.
by
the
plasticity of
the
test
Test
gyrograph
data
from the
chart.
oscillating pattern,
The
GTM are
read out
gyrograph
shows,
in the
in
form of
close-spaced
38
of
revolutions.
On most
Kpa
Ram pressure
interstate projects
75-blow Marshall.
traffic
at
60
hot
(KDOT)
1 initial
gyratory angle.
revolutions have
the
For
roads use
50
blow Marshall
to
select
the
asphalt
upon
the
anticipated
densities
that
these
mixes
would
be
to
establish
compactions.
can
viscosi ty
of
expect
lower
angle.
It
design
densities
for
future
GTM
densities
the
be
the
is
used
asphalt
"design"
for
design
purposes.
rubber mixes,
revolution
anticipated
that
the
it
and/or
is
Due
to
reasonable
initial
design density
the
to
gyratory
for
the
39
in
1. 00
excess
of
indicates
A GSI
progressive
An
increase
in
mixture
for
any
particular
pressure,
angle,
and
Equilibrium
gyrograph
where
compaction
the
rate
is
of
defined
change
in
as
point
density
on
reaches
the
16
revolutions,
A least
increased,
and
40
specimens
that
All of the
the
field
rubber mixes
that
were
strength
and
temperature
had been
recompacted
to various
at
fracture
of
compacted
Kansas
cm
(both
asphalt
and
asphalt
rubber)
are
11,
12,
15,
and
16
list
most
of
the
cost
(reacted)
41
rubber.
This
cost
comparison
is
applicable
only
to
large
each mix showed that the asphalt-rubber mix would cost 45% to
56% more than an asphalt only mix.
that
the
total
cost
per kilometer
percentage increase.
In Table 16,
be
to
directly
compared
an
may
result
less
of
"equal"
asphalt-rubber
For comparison,
in
27%
section,
increase in
be
slightly
less
than
the
asphalt
only
control
section.
There were two cost effective strategies for this project
when
asphalt-rubber was
compared
to
asphalt
only pavements.
in
order
for
asphalt-rubber pavements
to
become
the
Second,
life
the
of
the
cost
asphalt-rubber
effectiveness
should
could be
last
applied
27%
to
A reduction
42
result
in
asphalt
an
only
equal
cost
of
the
section.
In
this
asphalt-rubber
case,
the
asphalt-rubber section
life
of
section
to
the
mm
185
12)
was
after
were
six
137,000
Equivalent
cracks/
raveling,
months,
one
cored
flushing,
indicate
satisfactory.
Core
that
analysis
location
1.00.
rut
of
Under
until
Whether
after
the
or
rutting.
the
pavement
indicates
the
traffic ESAL' s.
order.
and a
(including the
However,
no
visual
permeabilities
be
On Figure 9,
indicates
the pavement
exceed at
exceeded
experienced
can
least
only
GSI
the
of
should not
2100
be
considerable
kg/m3.
determined
number
of
starting to
became concerned,
road
has
were
performing
is
(IWP)
kg/m3)
(2073
densities
kg/m3 will
pavement
pavement was
density
pavement
There
that
1995.
approximately
All
(WP)
12,
the
2100
WP
and
(ESAL's).
on June
winter,
observations
remain high,
surveyed and
test
monitoring
of
The
applied to
through
the
field personnel
test
the whole
an emergency work
section
continued
43
Table
17 reveals
year period.
test
thick
modulus.
ARB
The
over
test
lime
treated
section
(FWD)
with
subgrade
the
has
reduced
the
lowest
thickness
has
(See Figure 1,
No.
13-1995).
(GTM)
were used
was
9.53% and the VMA was 22.15% at the design asphalt content of
9.0%.
44
An
investigation
changed
revealed
and
this
that
the
gradation
caused part
of
the
aggregate
had
problem.
the
of
bleeding
Conversations
path.
It
was
obvious
that
some
form. of
action was
higher
skid
numbers.
severely bleeding,
Even
though
the
wheel
paths
were
surface
and
additional
lightweight
was
added
to
the
surface.
improved
to
an
exceptable
level.
Due
the
immense
safety
45
SUMMARY
1.
On large projects,
cost estimates of
asphalt-rubber
the
However,
state.
asphalt-rubber
will
Unless
pavements.
be
cost
more
estimates
also
indicate
that
expensive
than
asphalt
only
the performance of
asphalt-rubber can be
proj ect"
might
be
to
"asphalt
an
longer
performance
life,
which
could
make
the
Asphalt-rubber
projects
are
more
expensive
than
the increased
cost for the wet process will remain approximately 50% higher
than conventional mixes.
3.
mixes
The
can be
thermal
fracture
compared to
temperature
of
asphalt-rubber
conventional AC-5
or AC-IO mix.
This will
allow thick film on the aggregates and help retard the tendency
of the mix to stick to truck beds, etc.
46
5.
An AC-5 with
However,
Based on the
condition surveys,
be
these
made
from
study
(approximately nine)
specific
For
every
unsuccessful disaster.
a
fuel
source
implemented.
in
13
projects.
Several
action could be
success.
of
determined
successful
as
proven method
attempt,
there
was
for
an
kiln
may
be
more
successfully
47
REFERENCES
"Investigation of Materials
3.
Fager,
G.,
"Use
of
Rubber
in Asphalt
Pavements:
Kansas
48
TABLE l. Mix & Cost Data, US-75, Osage County, No. 1-1990
l\1JX
BM-IB
DESCRIPTION
Asphalt Only
BINDER
CONTENT
(AGGREGATE
BASED)
(%)
(%/TON)
4.75% AC-IO
17.09
6.16%ACR
46.18
COST DATA
(MIX)
BM-IB
BM-IT
Asphalt Rubber
85% Crushed Limestone
15% Sand
Asphalt Only
47% Crushed Limestone
5.5% AC-lO
19.97
6.3%ACR
49.22
BM-IT
Asphalt Rubber
47% Crushed Limestone
40% Chat (Mine Tailings)
13% Sand
TABLE 2.
THICK OVERLAY
CONTROL SECTION
(Asphalt Only)
19mm Surface BM-lT
44111111 Base BM-1B
TEST SECTION
(Asphalt-Rubber)
19111111 Surface BM-l T
44111111 Base BM-IB
CONTROL SECTION
(Asphalt Only)
19111111 Surface BM-lT
89111111 Base BM-1B
TEST SECTION
(Asphalt-Rubber)
19111111 Surface BM-lT
89111111 Base BM-1B
612011990
0
(Construction)
0
(Construction)
0
(Construction)
0
(Construction)
1010411990
01/1711991
05/0211991
10/0311991
05/2111992
10106/1992
0411611993
0411811994
05/0211995
05/22/1996
0
31
34
31
50
39
58
61
98
218
0
47
62
62
62.3
58.5
70.7
75
81
90
0
1
5
3
4
3
23
41
87
198
0
10
27
25
39
34
40
42
51
SURVEY DATE
(Mo/DaylYr)
-'"
<.0
64
WHEEL PATH
1.43 111111
0.86111111
1.05 111m
1.32111m
RUTTING
ESD=.52 mm
ESD=0.76mm
ESD=0.89 mm
ESD=1.17 mm
__~(~A=s~o~f~5/~22~/~96~)__________~N~=~8~____________~N~=~8______________N~=8~____________~N~=~8~_____
4,
"
50
TABLE 3.
MIX
BM-1B
Asphalt Only
BINDER
CONTENT
(AGGREGATE
BASED)
(%)
COST DATA
(%/TON)
5.0% AC-20
17.60
6.6%ACR
44.64
(MIX)
75% Crushed
Limestone
25% Sand
BM-IB
Asphalt Rubber
75% Crushed
Limestone
25% Sand
BM-IT
Asphalt Only
5.75% AC-20
19.64
Asphalt Rubber
7.4%ACR
36% Crushed
49.45
36% Crushed
Limestone
BM-lT
Limestone
TABLE 4. Crack & Rut Survey, K-2, Sedgwick County, No. 2-1990
TRANSVERSE CRACKlNG (PERCENT OF ORIGINAL)
THICK OVERLAY
THIN OVERLAY
CONTROL SECTION
(Asphalt Only)
19mm Surface BM-1T
38mm Base BM-1B
TEST SECTION
(Asphalt-Rubber)
19mm Surface BM-1T
38mm Base BM-IB
CONTROL SECTION
(Asphalt Only)
19mm Surface BM-IT
57mm Base BM-1B
TEST SECTION
(Asphalt-Rubber)
19mm Surface BM-1T
57mm Base BM-IB
8/2911990
0
(Construction)
0
(Construction)
0
(Construction)
0
(Construction)
10/3111 990
0111811991
10/0211 991
05/0111992
12/0211992
05/0411 993
0711811995
0511611 996
0
0
0
.4
3.4
28.5
41.8
75.9
0
0
0
5.6
6.4
32.1
31.2
37.5
0
0
0
0
.4
10.2
31.0
63.1
0
.4
.2
1.6
2.9
24.8
24.4
32.7
WHEEL PATH
RUTTING
(As of 511 6/96)
6.71 mm
ESD=1.27 mm
N=40
3.70 mm
ESD=3.33111111
N=24
6.61 111111
ESD=I.53 m111
N=24
3.33 mm
ESD=2.81 111111
N=20
SURVEY DATE
(MolDaylYr)
c.n
t,
'"
52
TABLE 5. Mix & Cost Data, US-24, Jefferson County, No. 3-1991
MIX
DESCRJPTION
BINDER
CONTENT
(AGGREGATE
BASED)
(%)
COST DATA
(MIX)
($/TON)
BM-IT
Asphalt Only
45% Crushed
Limestone
40% Chat (Mine
tailings)
15% Sand
5.25% AC-lO
21.05
BM-IT
Asphalt-Rubber
45% Crushed
Limestone
40% Chat (Mine
tailings)
15% Sand
6.9
18% Type II
Rubber
82% AC-5
48.97
BM-Gap Graded
Asphalt-Rubber
60% Crushed
Limestone
40% Chat (Mine
Tailings)
8.9% AC-lO
18% Type II
Rubber
82% AC-5
57.71
TABLE 6 Crack & Rut Survey, US-24, Jefferson County, No. 3-1991
TOTAL CRACKING (PERCENT OF ORIGINAL)
SURVEY DATE
(Mo/DaylYr)
CONTROL SECTION
(5.25% Asphalt Only)
25111111 Surface BM-lT
TEST SECTION
(6.9% Asphalt-Rubber)
25n1111 Surface BM-lT
TEST SECTION
(8.9% Asphalt-Rubber)
25111111 Surface Gap
Graded
05/30/1991
0
(Construction)
0
(Construction)
0
(Construction)
.7
18.7
15.4
71.3
49.2
82.8
96.2
124.6
(Maintenance Patch)
0
3.0
2.8
30.9
12.8
30.4
(Maintenance Patch)
0
0
0.3
0
0
0
0
0
0.5
0.8
0.05"
0.07"
0.15"
.10/0311991
05/2111992
10/0611992
0411911993
10/2711993
05/05/1994
09/27/1994
05/09/1995
05/23/1996
06/05/1997
RUTTING DEPTH
(As of 5/23196)
1" = 25.4111111
Ul
l;
'"
54
TABLE 7.
MIX
DESCRIPTION
BINDER
CONTENT
(AGGREGATE
BASED)
COST DATA
(MIX)
(%)
(%/TON)
BM-2A
Asphalt Only
66% Crushed
Limestone
34% Sand
5.25% AC-IO
20.22
BM-2A
(3 Binder Contents)
Asphalt Rubber
66% Crushed
Limestone
34% Sand
5.5%ACR
5% Ultra Fine
Rubber
95% AC-lO
21.96
5.5%ACR
7.5% Ultra Fine
Rubber
92.5% AC-lO
22.70
5.5% ACR
10% Ultra Fine
Rubber
90% AC-lO
23.44
TABLES.
TEST SECTION
(95% Asphalt)
(5% Fine Rubber)
CONTROL SECTION
(92.5% Asphalt)
(7.5% Fine Rubber)
TEST SECTION
(90% Asphalt)
(10% Fine Rubber)
05/28/1991
0
(Construction)
0
(Construction)
0
(Construction)
0
(Construction)
12/05/1991
07/30/1992
07/19/1993
08/0111994
38.5
47.7
91.4
112.1
87.8
87.4
131.1
133.1
70.4
73.5
99.6
100.6
21.3
41.7
119.0
138.0
SURVEY DATE
(Mo/DaylYr)
U1
U1
t.
'"
TABLE 9.
SURVEY DATE
(Mo/Day/Yr)
CONTROL SECTION
(0% Rubber)
(30% RAP)
(70%AGG)
TEST SECTION
(10% Rubber)
(30% RAP)
(70% AGG)
CONTROL SECTION
(12.5% Rubber)
(30% RAP)
(70%AGG)
0412011993
04/27!l994
05/1511995
04/30!l996
0510911997
1.4
0.6
1.1
24.0
72.9
9.6
7.3
'17.9
184.2
184.5
4.2
2.7
8.1
69.6
112.9
U1
0)
t,
,I
57
TABLE 10.. Mix & Cost Data, K-16, Jackson County, No. 7-1992
MIX
DESCRIPTION
BINDER
CONTENT
(AGGREGATE
BASED)
(%)
(%/TON)
COST DATA
(MIX)
BM-lB
Asphalt Only
80% Crushed
Limestone
20% Sand
5.5% AC-I0
17.67
BM-IB
Asphalt Rubber
80% Crushed
Limestone
20% Sand
5.0% AC-I0
1.0% Ultra Fine
Rubber
24.27
6.0% AC-I0
1.0% Ultra Fine
Rubber
24.79
7.0% AC-IO
1.0% Ultra Fine
Rubber
25.29
BM-Gap Graded
Asphalt Only
100% Crushed
Limestone
6.0% AC-IO
20.55
BM-Gap Graded
(3 Binder Contents)
Asphalt-Rubber
100% Crushed
Limestone
8.0% AC-IO
1.0% Ultra Fine
Rubber
28.30
8.0% AC-IO
1.5% Ultra Fine
Rubber
31.59
8.5% AC-lO
1.5% Ultra Fine
Rubber
31.80
58
COST
INITIAL
Complete Reconstruction
360 rum Asphalt-Rubber
250 rum Fly Ash Treated
Subgrades
($/Km)
30 YEAR
LIFE CYCLE
($/Km)
731.250
987,500
768,750
1,006,250
600,000
850,000
Complete Reconstruction
250 rum Portland Cement
Concrete Pavement
(PCCP)
100 rum Portland Cement
Treated Base
250 rum Fly Ash Treated
Subgrade
20 Years @ 100 rum Overlay
. Rubblized PCCP
Under Overpass
355 rum Asphalt-Rubber
150 rum Lime Treated
Subgrade
10 Years@75rumOveriay
20 Years@50rumMill
follow by a
75 mm Overlay
25.4mm-1 in
llan = 0.6 mi
59
Contractor
#1
$/Metric
Ton
Contractor
#2
$lMetric
Ton
Contractor
#3
$lMetric
Ton
20.00
18.52
19.10
25.00
22.90
21.90
128.34
900.00
l30.00
840.00
33.87
33.76
170.00
31.15
Table 13. Marshall Mix Design Parameters, 1-135, McPherson County, No. 12-1994
Mix
Description
Binder
Marshall Parameters
Content
Thea.
Density
YMA
Air
Voids
VFA
Densi~
(%)
Stability
(KliM )
2386
2357
( KliM')
2218
2184
(% )
(% )
(% )
(N)
7.0'
8.0'
19.69
21.65
7.0
7.4
64.0
66.0
5089
7.0'
2383
2220
18.23
6.8
64.2
7353
Sandstone
Sand
5.0
AC-I0
2462
2347
14.82
4.7
68.5
4844
35%
40%
25%
Limestone
Sandstone
Sand
5.0
AC-IO
2441
2338
13.86
4.2
69.7
8372
ASPHALT
BASE
COURSE
83%
17%
Limestone
Sand
5.5
AC-I0
2368
2233
14.52
5.7
60.8
6966
ASPHALT
SHOULDERS
50%
50%
Limestone
Sand
5.5
AC-10
2432
2323
14.65
4.5
69.46
5298
30%
60%
10%
Limestone
55%
30%
15%
Limestone
ASPHALT
SHOULDERS
50%
50%
ASPHALT
SURFACE
COURSE
ARS
ARB
Sandstone
Sand
Sandstone
Sand
IN
= 16.019 Ib/ft'
= 0.2251b
m
C)
1,
"
61
DESCRlPTION
(% )
7-8
AVERAGE
FRACTURE
TEMPERATURE
(C)
-29
ARS (Field)
135-59 K-3450-01
(87% AC-IO)
(13% Type III
Rubber)
ARB (Field)
135-59 K-3450-01
(87% AC-lO)
(13% Type III
Rubber)
-29
ARS (Lab)
Wet
(82% AC-5)
(18% Type II Rubber)
8.5-10
-29
ARS (Lab)
Dry
(82% AC-5)
(18% Ultra Fine Rubber)
8.5-10
-28
Surface
Course
(Lab)
AC-5
4-6
-29
Surface
Course
(Lab)
AC-IO
4-6
-28
Surface
Course
(Lab)
AC-20
4-6
-24
Surface
Course
(Lab)
PG 64-34
4-6
-34
NO
ASPHALT
CONTENT
62
TABLE 15.
Description
39.40 (+56%)
25.30
32.90 (+45%)
25.30
63
TABLE 16. Actual Control and Test Section Cost, 1-135, McPherson County,
No. 12-1994
Description
Section
~(~$0Cm~)~----------
Control
(Rubblized PCCP/Asphalt Only)
164,000
317,000 (+93%)
150,000 (-9%)
208,000 (+27%)
1 Km=0.6Mi
64
TABLE 17. Crack & Rut Survey, 1-135, McPherson County, No. 12-1994
TOTAL CRACKING (Meters)
TEST SECTION # 1
Reconstruction
40mmARS
320mmARB
150mmLTS
TEST SECTION # 2
Reduced Thickness
40mmARS
140mmARB
Rubblized PCCP
TEST SECTION # 3
Full Thickness
40rrunARS
185rrun ARB
Rubblized PCCP
0
(Construction)
0
(Construction)
0
(Construction)
(Slurry Seal)
(Slurry Seal)
(Slurry Seal)
6112/1995
2/18/1998
511211999
5/12/2000
RUTTING DEPTH
(As of 5/15/2000)
5.6mm
2.3 rrun
4.8mm
SURVEY DATE
(Mo/Day/Yr)
1994
65
TABLE 18. Test Section Elastic Modulus, 1-l35, McPherson County, No. 12-1994
After Overlay ofRubblized Layer
Elastic Modulus for Rubblized Layer (psi)
Section
Description
1.5" ARS +
12.5" ARB +
6" LTSG
1.5" ARS +
5.5" ARB +
9" Rubblized
PCCP
1.5" ARS +
7.5" ARB
9" Rubblized
PCCP
I" BM-IT +
8" BM-2C +
9" Rubblized
PCCP
1994
1995
1996
1997
1998
1999
N/A
N/A
NlA
N/A
N/A
N/A
944,902
418,132
378,798
363,660
332,158
282,427
2,032,622
814,423
550,311
505,313
390,254
405,536
354,418
395,776
1,044,755
1,747,792
2,113,850
2,938,597
Description
1994
1995
1996
1997
1998
1999
472,173
194,028
125,346
125,938
145,823
121,830
657,879
268,861
501,418
555,920
378,010
533,638
672,968
264,579
506,689
555,920
395,331
511,998
604,105
186,698
407,086
490,997
361,274
398,865
1.5" ARS +
12.5" ARB +
6" LTSG
IS' ARS +
5.5" ARB +
9" Rubblized
PCCP
IS'ARS+
7.5" ARB +
9" Rubblized
PCCP
I" BM-IT :
8" BM-2C +
9" Rubblized
PCCP
A slurry seal was placed in 1995 after the 1995 FWD testing was completeD
-C"-!_
...,
66
TABLE 19. Summary of Projects
NO.1 -1990IUS-7510sage
FORMAL
CRACK
SURVEYS
Yes
NO.2 -19901K-2/Sedgwick
PROJECT
TEST SECTIONS
OR FULL PROJECT
CURRENT
STATUS
RATING
High=4
Low~O
Overlaid in
1996
Yes
Overlaid in
1996
NO.3 -1991IUS-24/Jefferson
Yes
Overlaid in
1996
NO.4 -1991IUS-24IMitchell
Yes
Overlaid in
1998
NO.5 -1991IUS-59/Allen
Yes
Overlaid in
1998
NO.6 -1992IUS-54IKingman
No
No Test Sections
Full Project &
Competitive Bidding
Overlaid in
1995
NO.7 -1992/K-16/Jackson
No
Overlaid in
1998
NO.8 -199211-70
No
No Test Sections
Change Order
NO.9 -1994IUS-54IKiowa
No
Emergency
Maintenance
Patch in 1996
NO. 10-1994IUS-56/Johoson
No
No Test Sections
Full Project &
Competitive Bidding
(In Active
Service)
NO. 11-19941K-32IDouglas
No
No Test Sections
Full Project &
Competitive Bidding
(In Active
Service)
NO. 12-1994/I-135IMcpherson
Yes
(In Active
Service)
NO.13-1995IUS-75IBrown
No
No Test Sections
Full Project &
Competitive Bidding
Emergency
Double Seal in
1995
AVERAGE RATING
1.53
(Low
Average)
(1990 = 1995)
TEST SECTIONS
No.4 - 1990
No.12-1994
~. T
"'k I'"
f;1
II
I I II I
r- ~
.....
II
~I
I
I
-<"
'""
~"
1'-.
I I
rLl\.
l/1
"1
.c
"l--
hL.
.....
1
f
tf~~ ~ ~
No.6 -1992
No. 2
No.1O-1994
~
~ -;rs
W
i.J
"'I
~ I'L
.~
Y~
~--=
I- -
en
'-J
~..,J '~rJ k(
1'-\1
'\
I"n:"
No.9 -1994
,L
/'
--=:J
:1 \l-' ~
" , ( 1-'.
K'-
\"
"
J y,,_P.).~
~
--J---"
'"
L
+
r
~.
I I -,.t
"
" -_1"1
' " , - : -1*-",.
If
~ .J
t:
I '>t:rizj ,
~
r~
I n
l:::. ___~ - , -1-.
/U
1
I
/'
~
1 "~
L~../It"
~
/-1
I"-
No. 11 - 1994
I I I\ .
I'-.
~ -
f'.
""
I"
I \
""I. ""
II
1"-.
---;..
.-V
~~~. 7-1992~
No. '-1992
"S;v
/'-'
No.13 -1995
.
No.3 _ 1991
No.1 - 1990
'.c
~~" k
' . - . . , .,/
...
.-'t==
-199~
H "'!"'F\
-"-
"""::H
l..:::t"
!;
o
No.5-1991
TEST
SECTION
TEST
SECTION
CONTROL
SECTION
CONTROL
SECTION
Asphalt - Rubber
Asphalt-Rubber
Asphalt Only
Asphalt Only
19mm Surface
19mm Surface
89mm Bose
89mm Bose
I
19mm Surface
19mm Surface
44mm Bose
44mm Bose
Existing Pavement
_._--_
1"
152mm
..
_._---
Existing Pavement
'"CD
---
----
--
---
---
---
25.4mm
"
TEST
SECTION
TEST
SECTION
CONTROL
SECTION
CONTROL
SECTION
Asphal t - Rubber
Asphalt - Rubber
Asphalt Only
Asphalt Only
102mm
57mm Base
'"
co
Existing Pavement
~~--
1"
25.4mm
t,
'"
TEST SECT/ON #/
(Reconstruction Section)
_ ..-
225mm
Asphalt
Shoulder
150mm
US
40mm
320mm
ARS
ARB
225mm Asphalt
Shoulder
150mm US
150mm US
1.85m
l.4m
"o
3.1m
"
TEST SECTION #2
(Reduced ThIckness Asphalt-Rubber Sect1on)
180mm
Asphalt
Shoulder
EdgeQ
40mm
ARS
140mm
ARB
RUBBLIZED PCCP
DrOin
1.85m
180mm Asphalt
Shoulder
"
QEdqe
Drain
7.4m
3.1m
'"
TEST SECTION #3
(Normal Asphalt-Rubber Section)
--
40mm
225mm
Asphalt
Shoulder
EdqeQ
Drain
1.85m
--
ARS
185mm ARB
225mm Asphalt
Shoulder
RUBBLIZED PCCP
.....,
QEdg.e
Drain
7.4m
3.1m
CONTROL SECTION
25mm Asphalt Surface
225mm
Asphalt
Shoulder
Edae
Drain
1.85m
200mm
D..
Asphalt Bose
RUBBLIZED PCCP
225mm Asphalt
Shoulder
D.. Edqe
9.
.....
w
Drain
7.4m
3.1m
'"
Hot Oil
Heater
"
"""
Asph
Heater
75,708 liter (Asphalt Only) Tank
\..- 37,854 liters (Asphalt Only) Tank
11- Valve
-Pump
t,
Figure 8.
"
75
-"
A~HAlu=~UBBE~
U~FACE
(135-59 K-3450-0 1)
7 & 8%
1.15 , - - - - - - - - - - - - - - - - - - - - - ,
!J)
(j
~
0
Z
1.10
>-
f-
-~
CO
f-
!J)
>-
IT
1.05
f-
IT
>-
(j
0
1.00
2000
:
2100
2200
GSI
DENSITY, 1-135,
No. 12-1994
VS.
2300