Sei sulla pagina 1di 5

FEDERAL INLAND REVENUE SERVICE

QTY

UNIT

RATE

MAIN BUILDING
DEMOLITION AND ALTERATION WORKS
WINDOWS
A

Carefully remove existing 1nr Aluminium


sliding window size 2100 x 1600mm high
and keep in FIRS store

nr

3,500

3,500.00

Carefully remove existing 1nr steel burglar


proofing for sliding window size 2100 x
1600mm high and keep in FIRS store

nr

3,500

3,500.00

m2

7,000

21,000.00

BLOCKWORK
C

Carefully demolish existing 230mm block


wall and dispose debris offsite and make
good all works affected
Allow a provisional sum of N 10,000.00 to
prepare surfaces for new works to be
expended as directed.

sum

Demolition and Alterations Carried to Summary

KAD/FIRS/1

10,000.00

38,000.00

FEDERAL INLAND REVENUE SERVICE

QTY

UNIT

RATE

CIRCULAR STAIRCASES
EXCAVATION AND EARTHWORK
G

Excavate pit for column bases starting from


stripped level and not exceeding 1.50m
deep.

m3

1,500.00

3,000.00

Remove surplus excavated material from


site

m3

1,500.00

1,500.00

Return, fill and consolidate selected


excavated material around foundation

m3

1,000.00

1,000.00

Approved rock hardcore filling well rammed


and consolidated, including blinding top with
fine ash in layers not exceeding600mm
thick

m3

3,200.00

3,200.00

m2

Damp proof Membrane


Guage 1000 polythene damp proof
membrane lapped 450mm at all welted
joints, laid on blinded hardcore

300.00

600.00

CONCRETE WORK
Plain insitu vibrated Concrete Grade 15 in:
A

50mm blinding under bases

m2

1,250.00

2,500.00

150mm Bed

m3

25,000.00

25,000.00

Reinforced insitu Vibrated Concrete grade


D

Column bases and Circular Column

m3

28,000.00

28,000.00

Steps

m3

28,000.00

28,000.00

landing

m3

28,000.00

28,000.00

450

kg

240.00

108,000.00

Reinforcement (Provisional)
High yield deformed bars to BS 4449 in
F

column bases, columns and steps


8-16mm diametre bars in concrete steps,
slab projection and column
Formwork
Sawn formwork to:

Sides of Circular Columns

m2

2,200.00

8,800.00

Sides and soffits of steps

19

m2

2,200.00

41,800.00

Sides and Soffits of landing

m2

2,200.00

8,800.00

Carried to Collection

288,200.00

KAD/FIRS/2

FEDERAL INLAND REVENUE SERVICE

QTY

UNIT

RATE

Circular Staircases Continued


FINISHES
Rendering
15mm thick rendering finished fair and
smooth on
A

Sides of Circular Columns

m2

600.00

1,800.00

Ditto sides and soffits of steps

19

m2

600.00

11,400.00

Sides and Soffits of landing

m2

600.00

2,400.00

Painting and Decoration


Prepare and apply one coat primer and two
finshing coats of vinyl mat portland gloss
paint on:
A

Sides of Circular Columns

m2

600.00

1,800.00

Ditto sides and soffits of steps

19

600.00

11,400.00

Sides and Soffits of landing

m2

600.00

m2

4,500.00

2,400.00

FLOOR FINISHES
Terrazo Flooring
Insitu Terrazo Paving laid in 600x600mm
bays with and including ebonite dividing
strip on screeded bed
(measured
separately)
B

25mm thick flooring


CARRIED TO COLLECTION

13,500.00
44,700.00

CIRCULAR STAIRCASES

COLLECTIONS

Page

Page

KAD/FIRS/2

288,200.00

KAD/FIRS/3

44,700.00

STAIRCASES CARRIED TO SUMMARY

332,900.00

KAD/FIRS/3

FEDERAL INLAND REVENUE SERVICE

QTY

UNIT

RATE

Danpalon Skylight Roofing


Structural Steel Framing
Structural steel curved built up roof trusses
and built up girders; top and bottom booms,
all properly framed and welded together
comprising of hollow circular steel sections
as designed finished in one coat of red
oxide paint after fabrication and two
finishing coat of approved gloss paints in:
A
B

75mm diameter hollow circular pipes

26

kg

240.00

6,240.00

Ditto 50mm diameter

37

kg

240.00

8,880.00

m2

25,000.00

225,000.00

DANPALON ROOFING SHEETS


Danpalon proprietary system; danpalon
arched canopy mechanically locked with
polycarbonate or powder coated aluminium
connectors
C

Danpalon arched canopy 3000 X 3000mm


wide installed with hangers to Steel trusses
(measured separately);

DANPALON SKYLIGHTS CARRIED TO SUMMARY

KAD/FIRS/4

240,120.00

FEDERAL INLAND REVENUE SERVICE

S/NO

GENERAL SUMMARY

TOTAL FOR THE PROPOSED


CONSTRUCTION OF STAIRCASE FOR FIRS
BUILDING KADUNA

DEMOLITIONS AND ALTERATIONS

38,000.00

STAIRCASES

332,900.00

DANPALON SKYLIGHT ROOFING

240,120.00

611,020.00

ADD VAT & TAX (10%)

TOTAL FOR THE PROPOSED CONSTRUCTION OF


STAIRCASE FOR FIRS BUILDING KADUNA

KAD/FIRS/5

61,102.00

672,122.00