Date:
29.12.2014
Prepared By
HS
Checked By
LR
Version No.
Date
Description
Prepared By
Checked By
Version No.
Date
Approved By
LR
Approved By
Description
Prepared By
Checked By
Approved By
CONTENTS
1.0.
INTRODUCTION.....................................................................................................4
2.0.
3.0.
METHODOLOGY....................................................................................................7
4.0.
5.0.
FINDINGS............................................................................................................. 12
6.0.
SIGNOFF .............................................................................................................. 13
1.0.
INTRODUCTION
1.1 The Fans commissioning work shall be taken up after completion of installation, ,
associated ductwork and necessary electrical cabling works.
1.2 The fansshall be tested for various performance parameters such as air flow, static
pressure, noise vibration etc.,
1.3 Operation of the starters through BMS system shall alsotested.
1.4 The HRW units, Kitchen exhaust fan, Battery exhaust fan, Pantry exhaust are also be
tested in similar fashion.
1.5 All instruments, documents, tools, tackles, ladders, access platforms, personnel,
required for the purpose of testing are to bemade available by the vendor.
2.0.
2.1 Documents:
a.
b.
c.
d.
e.
f.
Multimeter
Clamp on Meter
Digital
Thermometer
Vane Type
Anemometer
Pitot Tube
Static measuring
probe.
Digital
Non-Contact Sound Level Meter
Tachometer
Sling Psychrometer
Vibration Meter
3.0.
METHODOLOGY
3.1 The Fans have to be commissioned after completion of installation, necessary ducting
connections, electrical work and pre-commissioning checks.
3.2 Pre-Commissioning checks included:
a. Checking that the Fan is installed as per the room layout.
b. The Fan has been fitted out with pre-commissioning filters(if required).
c. Ductwork with outlet damper and flexible connections is completed.
d. Pulley diameters are as per design.
e. Motor and fan blower rotate freely without touching any unintended surfaces.
f. All clearances for accessing the filters, motors, damperselectrical panels exist as
per manufacturers recommendations.
g. Starter panel with bypass is installed.
h. Over load current settings are made appropriately in the starter.
i. Cabling and earthing for the motor, bulkhead lamp, control wiring for door limit
switch is completed(for cabinet type fans).
4.0.
Yes/No
Vendors Comments:
Prepared By:
Date:
Signature:
Motor
W1 W2
W2-W3
W3-W1
W1-E
W2-E
W3-E
Vendor:
PMC:
Testing Consultant
Value
Vendor:
PMC:
Testing Consultant:
10
Value
Testing Consultant
Value
Testing Consultant
PMC
11
5.0.
FINDINGS
Testing and Commissioning has to be carried out on the HRW , Fans and the major findings
of the tests are furnished below:
FINDINGS
ACTION PROPOSED
VENDOR
PMC
TESTING CONSULTANTS
12
6.0.
SIGNOFF
We hereby confirm that this report is a true record of the testing and commissioning activity
carried out on the system:
Testing
Consultant
Organisation
Name
HVAC
Consultant
Project
Management
Consultant
HVAC Vendor
Witnessed By:
Signature
Date