Sei sulla pagina 1di 49

CXPS 24-2T 24Vdc Power System

053-390-B0

The following documents and drawings are included in this manual to provide the necessary information required for
routine installation of the unit:

• Specifications: 053-390-B1
• Warranty Policy: 048-507-10
• Important Safety Instructions
• Installation and Operation Instructions: 053-390-C0
• Schematic: 053-390-05
• Outline Drawing: 053-390-06
• Customer Connections: 053-390-08
• Factory Service Information: 048-527-10

Manuals to be included in the documentation package for this product:

• Cordex Controller (CXC) Software: Current Version

Argus Technologies Ltd. 053-390-B0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved.
Specifications for Argus’ CXPS 24-2T 24Vdc Power System

Output
Voltage: 21 to 29Vdc within rated limits

Current: System: 1200A maximum (distribution limited)


Rectifier Module: 115A @ 27Vdc nominal (130A max.)

Power: System: 28800W maximum @ 24V (distribution limited)


Rectifier Module: 3100W maximum

Heat Dissipation (per rectifier): <1176 BTU per hour

Static Load Regulation: Better than ±0.5% for any load change within rated limits

Dynamic Load Regulation: Better than ±4% for 40% - 90% load step
(output shall recover to static limits within 30ms)

Static Line Regulation: Better than ±0.1% for any change in input voltage within rated limits

Electrical Noise: <32dBrnC (voice band)


<20mVrms 10kHz to 10MHz (wideband)
<100mVp-p 10kHz to 100MHz
<1.0mV (psophometric)

Acoustic Noise: <60dBa @ 1m (3ft.) @ 30°C (86°F)

Input
Voltage: 208, 220, 230, 240, 277Vac nominal

Operational Range: 176 to 320Vac

Extended Operation: Low: 176 to 90Vac (derated power)

Frequency: 45 to 66Hz

Current: 14.6A @ 240Vac


16.9A @ 208Vac
20.2A @ 176Vac (maximum)

Recommended Feeder Breaker


Single Phase: 30A, #10 AWG (for a single rectifier module)
Three Phase: 50A, #6 AWG delta connection (for three rectifier modules)
30A, #10 AWG wye connection (for three rectifier modules)

Power Factor: >0.99 at nominal conditions and 50-100% load

Protection: 10kA-interrupting capacity fuses in active and neutral lines

Efficiency: >90% at nominal conditions and 50-100% load

Argus Technologies Ltd. 053-390-B1 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 1 of 3
Specifications for Argus Technologies’ CXPS 24-2T 24Vdc Power System Continued

Connections
Load Connections: AM breakers (1-pole): 1/4” holes on 5/8” centers
AM breakers (multiple pole): 3/8” holes on 1” centers
GMT fuses: screw terminals 0.25mm2 to 2.5mm2 (#24 to #14 AWG)

Battery Terminations: 3/8” holes on 1” centers, 4 sets per polarity

Rectifier Terminations: 3/8” holes on 1” centers

Alarm Connections: 0.081mm2 to 0.55mm2 (#28 to #20 AWG)

Cable Access: Top and/or bottom

Environmental
Operating Temperature: -40 to +75°C, power derated above 65°C (149°F)
(-40 to 167°F)

Storage Temperature: -40 to +85°C


(-40 to 185°F)

Humidity: 0 to 95% non-condensing

Elevation: -500m to 2800m; to 4000m with temperature derated to 40°C


(-1640 feet to 9186 feet; to 13124 feet with temperature derated to 104°F)

Miscellaneous
Maximum Number of Rectifiers: Up to eleven (11) Cordex 24-3.1kW modules
#010-601-20 (pre-RoHS #010-572-20);
NOTES: One rectifier space is occupied by the CXCM4
#018-586-20 (pre-RoHS #018-574-20),
Distribution tiers limit the system output to 1200A

Distribution Capacity: Tier 1: Up to twenty (20) 24V, AM plug-in style breakers, 600A maximum

Tier 2: Up to eighteen (18) 24V, AM plug-in style breakers, 600A maximum


NOTE: Tier 2 may be factory or field configured for eight (8) 24V breaker
positions and ten (10) 48V breaker positions for an optional 24V-48V DC-DC
converter installation

Up to ten (10) 24V, GMT fuse positions


NOTE: Maximum 30A per GMT fuse assembly

Dimensions: 584mm W x 755mm H x 477mm D


(23” W x 29.7” H x 18.8” D)
[for additional options see outline drawings at the rear of this manual]

MTBF (rectifier module): >350,000 hours ground benign @ 30°C (86°F)

Argus Technologies Ltd. 053-390-B1 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 2 of 3
Specifications for Argus Technologies’ CXPS 24-2T 24Vdc Power System Continued

Safety
NOTE: Safety certifications performed at rectifier level only.
EN 60950 Rectifier output shall be rated SELV suitable for connection to TNV-1 circuits

UL 60950

CSA C22.2 No. 60950

CE EN 60950, CB Scheme
73/23/EEC Low Voltage Directive with amendment 93/68/EEC

Telcordia (Bellcore) GR-1089-CORE (requirements applicable to rectifier)

Other Referenced Standards


EN 300 386-2 EMC and ERM; Telecommunication Network Equipment

EN 55022 (CISPR 22) Information Technology Equipment – Radio Disturbance Characteristics – Limits
and Methods of Measurement

EN 61000-3-2 Harmonic Current Emissions

EN 61000-3-3 Voltage Fluctuations and Flicker

EN 61000-4-2 ESD Immunity

EN 61000-4-3 Radiated Electromagnetic Immunity

EN 61000-4-4 Electrical Fast Transient/Burst Immunity

EN 61000-4-5 Power Line Surge Immunity

EN 61000-4-6 Conducted Electromagnetic Immunity

EN 61000-4-11 Voltage Dips, Short Interruptions and Variations

ETS 300 019-1-1 Environmental Conditions; Storage

ETS 300 019-1-2 Environmental Conditions; Transportation

ETS 300 132-2 Power Supply Interface at the Input to Telecommunications Equipment;
Operated by Direct Current (DC)

ETS 300 753 Acoustic Noise Emissions

IEC 60950 Safety of Information Technology Equipment, Including Electrical Business


Equipment (UL/CSA 60950)

The above information is valid at the time of publication. Consult factory for up-to-date ordering information.
Specifications are subject to change without notice.

Argus Technologies Ltd. 053-390-B1 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 3 of 3
WARRANTY AND REPAIR INFORMATION
Warranty Policy Factory Service Centers
Canada and International
Argus Technologies Ltd. warrants all equipment manufactured by it to be free from defects in parts Argus Technologies Ltd.
and labor, excluding third party OEM materials (example: air conditioners, batteries), for a period of ATTN: RMA Returns
7033 Antrim Avenue
two years from the date of shipment from the factory. For third party products the OEM’s warranty Burnaby, BC, V5J 4M5 Canada
shall apply. The liability of Argus applies solely to repairing, replacing or issuing credit (at Argus’ sole Tel: +1 604 436 5900
discretion) for any equipment manufactured by it and returned by the customer during the warranty Fax: +1 604 436 1233
Email: returns@argusdcpower.com
period. The terms of the warranty are Ex Works (EXW) from Argus’ factory service location.
USA
Argus Technologies Inc.
Argus reserves the right to void the warranty if: ATTN: RMA Returns
3116 Mercer Avenue
(1) identification marks or serial numbers are removed or altered in any way, Bellingham, WA, 98225 USA
(2) invoice is unpaid, or Tel: +1-360 756 4904
(3) defect is the result of misuse, neglect, improper installation, environmental Fax: +1-360 647 0498
Email: returns-usa@argusdcpower.com
conditions, non-authorized repair, alteration or accident.
Asia-Pacific
PCM Electronics (Dong Guan) Co., Ltd.
Argus shall not be liable to the customer or other parties for any loss of profits, loss of use, costs for Hongli Industrial Area, Miaobian, Liaobu Town,
Dongguan City, Guangdong Province,
removal or installation of defective equipment, damages or consequential damages based upon 523400 China
equipment failure during or after the warranty period. There shall be no other obligations either Tel: +86 755 8895 3310
expressed or implied. Argus will not honor warranties for batteries and other third party products Fax: +86 755 8895 3307
without prior written Argus authorization. Authorized Service Center
Argentina
Argus Technologies de Argentina
Belen 315, Capital Federal, Buenos Aires,
1407l Argentina
Freight Policy Tel: +54 (11) 4672 4821
Customer is responsible for all shipping and handling charges (COD and freight collect will not be Fax: +54 (11) 4504 4698
Cell: +54 9 (11) 4993 9996
accepted without prior approval from Argus Technologies). Email: lkleiman@argus.ca
Asia
Argus Technologies Asia Pte Ltd
Blk 6 Tagore Lane #160
Terms of Payment (North America) Singapore 787570
Payment terms are net 30 days subject to prior credit approval. All other orders require payment Tel: +65 6458 8900
before shipping. Fax: +65 6458 2122
Australia
CPS National
8/376 Newbridge Rd
Moorebank, NSW, 2170 Australia
Terms of Payment (International) Tel: +61 02 9822 8977
Payment terms are subject to prior approval and are typically through Tele-Transfer. Fax: +61 02 9822 8077
Australia/New Zealand
Alpha Power Systems Pty Ltd
Unit 3, 30 Heathcote Road
Moorebank, NSW, 2170 Australia
Return Material Policy Tel: +61 02 9602 8331
Our RMA policy is designed to ensure prompt, efficient and high quality factory service. A Return Fax: +61 02 9602 9180
Material Authorization (RMA) number must be obtained before products can be accepted for Canada
servicing by the Argus factory. For returns to an authorized service center (refer to “Authorized Compower Systems Inc.
118 Tiffield Road
Service Centers” for locations), please consult the individual service center for specific return policies Toronto, ON, M1V 5N2 Canada
and instructions. Tel: +1 416 293 3088
Fax: +1 416 293 0671

To obtain a RMA number for a factory return, customers must call the appropriate location with the Europe
Alpha Technologies Europe Ltd.
product serial and model number, as well as a brief description of the problem, shipment instructions Cartel Business Estate
and billing details. Edinburgh Way
Harlow, Essex, CM20 2DU UK
Tel: +44 1279 422110
The original packing container should be used whenever possible. Both the shipping documents Fax: +44 1279 423355
and the outside of the box must have the RMA # clearly marked and the product shipped prepaid to Mexico & Central America
the Argus factory service center. Argus will endeavor to repair products within five working days of Technologies Argus First De Mexico SA de CV
Anatole France No. 17
receipt. Repairs to the returned product are warranted for a period of six months. A service charge Col. Polanco
may be applied if no fault is found in the returned product. Argus will not accept products without an Mexico City, 11560 Mexico
RMA number. Tel: +52 55 5280 6990
Fax: +52 55 5280 6585
South America
Argus Technologies Argentina
Santo Tome 2573, Capital Federal
Business Hours Buenos Aires, 1416 Argentina
Argus North American office hours are 7:30 am to 5:00 pm (Pacific Standard Time) Monday to Friday. Tel: +54 11 4504 4698
Cell: +54 9 11 4993 9996
E-pager: 541149939996@nextel.net.ar
Turkey
IPC Enerji Elk San ve TIC AS
Inonu cad. Kanarya sok. No:20
Yenisahra - Kadikoy
Istanbul, Turkey
Tel: +90 216 317 41 42
Fax: +90 216 472 90 66

048-507-10-I1 Rev R (08/2007)

Canada and USA toll free 24 hour emergency technical support: +1 888 GO ARGUS (462 7487) Outside North America: +1 604 436 5547
IMPORTANT SAFETY INSTRUCTIONS
SAVE THESE INSTRUCTIONS

This section contains important instructions that should be followed during the installation and maintenance of
equipment and batteries. Please read all of the instructions before operating the equipment, and save this
manual for future reference.
A licensed electrician MUST perform connections to the branch circuit of service feed. Installation of the power
supply and batteries must be performed by, or under the direct supervision of service personnel knowledgeable of
the required electrical and battery safety precautions.
If instructions in this manual conflict with local electrical codes, those instructions shall be superseded by the local
code.
The following safety symbols will be found throughout this manual, carefully read all information and abide by the
instructions:

DANGEROUS VOLTAGE
This symbol indicates a dangerous voltage
exists in this area of the product.

GAS HAZARD
This symbol indicates a gas hazard
exists in the area of vented batteries.

NO MATCHES OR OPEN FLAMES


This symbol indicates a fire or explosive hazard
exists in the area of the product.

The following levels of warning will be used with the above symbols:
DANGER: You WILL be KILLED or SERIOUSLY INJURED if instructions are not followed closely.
WARNING: You CAN be KILLED or SERIOUSLY INJURED if instructions are not followed closely.
CAUTION: You CAN be INJURED or equipment can be DAMAGED if instructions are not followed closely.

Mechanical Safety
Keep hands and tools clear of fans. Fans are thermostatically controlled and will turn on automatically.
Power supplies can reach extreme temperatures under load.
Use caution around sheet metal components and sharp edges.
Electrical Safety
WARNING
Hazardous voltages are present at the input of a power system. The DC output from rectifiers and
batteries, though not dangerous in voltage, has a high short-circuit current capacity that may
cause severe burns and electrical arcing.
Before working with any live battery or power system, follow these precautions:
• Remove all metallic jewelry; e.g., watches, rings, metal rimmed glasses, necklaces.
• Wear safety glasses with side shields (and prescription lenses if necessary) at all times during installation.
• Use tools with insulated handles.

Lethal voltages are present within a power system. Never assume that an electrical connection or conductor is not
energized. Check the circuit with a voltmeter with respect to the grounded portion of the enclosure (both AC and
DC) prior to any installation or removal procedure.
Do not work alone under hazardous conditions.
A licensed electrician is required to install permanently wired equipment. Input voltages can range
up to 240Vac. Ensure that utility power is disabled before beginning installation or removal.
Ensure no liquids or wet clothes contact internal components.
Hazardous electrically live parts inside this unit are energized from batteries even when the AC input power is
disconnected.

Battery Safety
Servicing and connection of batteries shall be performed by, or under the direct supervision of, personnel
knowledgeable of batteries and the required safety precautions.
Always wear eye protection, rubber gloves, and a protective vest when working near batteries. Remove all
metallic objects from hands and neck.
Use tools with insulated handles; do not rest tools on top of batteries.
Batteries contain or emit chemicals known to the State of California to cause cancer and birth defects or other
reproductive harm. Battery post terminals and related accessories contain lead and lead compounds; wash hands
after handling (California Proposition 65).

WARNING
Follow battery manufacturer’s safety recommendations when working around battery systems.

WARNING
Do not smoke or present an open flame when batteries (especially vented batteries) are on
charge. Batteries vent hydrogen gas when on charge, which creates an explosion hazard.

Batteries are hazardous to the environment and should be disposed of safely at a recycling facility. Consult the
battery manufacturer for recommended local authorized recyclers.
TABLE OF CONTENTS
1 INTRODUCTION ............................................................................................................................................................. 1
1.1 Scope of the Manual ..................................................................................................................................... 1
1.2 Product Overview.......................................................................................................................................... 1
1.3 System Configurations .................................................................................................................................. 2
1.4 Part Numbers and List Options..................................................................................................................... 2

2 FEATURES ................................................................................................................................................................... 3
2.1 System Overview .......................................................................................................................................... 3
2.2 Tiered Distribution Features.......................................................................................................................... 3
2.3 Cordex System Controller (CXC).................................................................................................................. 4
2.4 Cordex 24-3.1kW Rectifiers .......................................................................................................................... 7

3 INSPECTION................................................................................................................................................................ 11
3.1 Packing Materials........................................................................................................................................ 11
3.2 Check for Damage ...................................................................................................................................... 11
3.3 General Receipt of Shipment...................................................................................................................... 11

4 INSTALLATION ............................................................................................................................................................ 12
4.1 Safety Precautions ...................................................................................................................................... 12
4.2 Tools Required............................................................................................................................................ 12
4.3 Power System Assembly and Mounting ..................................................................................................... 13
4.4 Rectifier Module Insertion/Removal ............................................................................................................ 13
4.5 Battery Installation....................................................................................................................................... 14

5 WIRING ...................................................................................................................................................................... 16
5.1 Grounding ................................................................................................................................................... 16
5.2 AC Feeder Protection/Sizing....................................................................................................................... 16
5.3 AC Input Connections ................................................................................................................................. 16
5.4 DC Output Connections .............................................................................................................................. 17
5.5 DC-DC Converter Connections................................................................................................................... 19
5.6 Controller I/O Connections.......................................................................................................................... 25
5.7 Network Connection and Remote Communications via CXC..................................................................... 27

6 SYSTEM STARTUP ...................................................................................................................................................... 28


6.1 Check System Connections........................................................................................................................ 28
6.2 Verify AC and Power the Rectifier Shelf ..................................................................................................... 28
6.3 Check Battery Polarity and Connect ........................................................................................................... 28
6.4 CXC Reset .................................................................................................................................................. 28

7 OPERATION ................................................................................................................................................................ 29
7.1 Main Rectifier States ................................................................................................................................... 29
7.2 Main Rectifier Modes .................................................................................................................................. 29
7.3 Factory Ranges and Defaults ..................................................................................................................... 30

8 MAINTENANCE ........................................................................................................................................................... 31
8.1 Fan Replacement........................................................................................................................................ 31
8.2 MOV Replacement...................................................................................................................................... 32

9 ARGUS CONVENTIONS ................................................................................................................................................ 33


9.1 Numbering System...................................................................................................................................... 33
9.2 Acronyms and Definitions ........................................................................................................................... 33

i
This page intentionally left blank.

ii
1 Introduction

1.1 Scope of the Manual


This instruction manual covers the features and installation of Argus Technologies’ CXPS 24-2T 24V 1200A
Power System.
For advanced detail on the system components used in the CXPS 24-2T, please refer to the following manuals:
• Cordex 24-3.1kW Rectifier Module: 010-601-B2 [This manual also provides CXCM4 (controller) installation details.]
• Cordex Controller (CXC) Software: 034-109-B2 or latest revision of software.

NOTE: To aid the user with installation, frequent reference is made to drawings located at the rear of this manual.

1.2 Product Overview


The CXPS 24-2T is a complete integrated 24Vdc power system with 1200A capacity. The system utilizes the
advanced Cordex controller and 24V 3.1kW rectifier modules. The two-tier (Vista II series) distribution center
provides front access for DC distribution, site controller, and battery connections.
Cordex rectifier modules use a high frequency, switched mode conversion technique to provide a fully regulated
and isolated DC output from the AC mains. The rectifier input is wide range to allow use on 208/220/240Vac
50/60Hz electrical service.
Rectifier power modules are “hot swappable” meaning they can be inserted or removed from the shelf without
cutting power to or from the system or the load.

NOTE: Rectifier modules are not included with the base system,
but may be purchased along with the system at the time of
ordering or added after the shelf has been installed.

The shelf rectifier system is designed to operate with the


Argus Cordex System Controller (CXC).
This system uses the CXCM4 modular version of the
controller which plugs directly into the Cordex rectifier
system shelf. The rectifier/shelf manual provides CXCM4
installation details.
The CXC allows the user to configure, monitor and control
the entire DC power system from its touch screen display
similar to that used in a personal digital assistant (PDA).
Other features of the unit include temperature
compensation, auto equalization, remote access, dial out
on alarm, battery diagnostics, as well as web server and
SNMP support for configuration and monitoring.
Details of controller operation are provided in the
current version software manual.

Figure 1–Front angle view of the 053-390-20-000


rail mount CXPS 24-2T configuration

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 1 of 33
1.3 System Configurations
The system is available to order in the following configurations:
Description Part Number
CXPS 24-2T, Cordex base 24V 1200A power system, 23” rail mount .............................................. 053-390-20-000
CXPS 24-2T system with 22RU relay rack, battery mount ................................................................ 053-390-20-010
CXPS 24-2T system with 7 foot Z4 relay rack ................................................................................... 053-390-20-020
CXPS 24-2T system with 7 foot Z4 relay rack and 3x battery trays (6x strings) ............................... 053-390-20-030

1.4 Part Numbers and List Options


This product is available to order with the following options and accessories:
Description Part Number
Cordex 24-3.1kW rectifier power module (pre-RoHS 010-572-20).................................................... 010-601-20-040
CXPS 24V-48V converter integration kit, CSM01 6-module converter shelf............................................038-275-20
CXPS 24V-48V converter integration kit, CSM11 4-module converter shelf............................................038-277-20
Rack, relay, 7 foot, 23", seismic zone 4 ............................................................................................. 030-638-20-023
Rack, battery mount, half-height, 23", 22RU ..................................................................................... 030-694-20-042
Breaker, AM-type mid-trip plug-in, 1A........................................................................................................470-300-10
Breaker, AM-type mid-trip plug-in, 3A........................................................................................................470-301-10
Breaker, AM-type mid-trip plug-in, 5A........................................................................................................470-302-10
Breaker, AM-type mid-trip plug-in, 10A......................................................................................................470-303-10
Breaker, AM-type mid-trip plug-in, 15A......................................................................................................470-304-10
Breaker, AM-type mid-trip plug-in, 20A......................................................................................................470-305-10
Breaker, AM-type mid-trip plug-in, 25A......................................................................................................470-306-10
Breaker, AM-type mid-trip plug-in, 30A......................................................................................................470-307-10
Breaker, AM-type mid-trip plug-in, 35A......................................................................................................470-308-10
Breaker, AM-type mid-trip plug-in, 40A......................................................................................................470-309-10
Breaker, AM-type mid-trip plug-in, 45A......................................................................................................470-310-10
Breaker, AM-type mid-trip plug-in, 50A......................................................................................................470-311-10
Breaker, AM-type mid-trip plug-in, 60A......................................................................................................470-312-10
Breaker, AM-type mid-trip plug-in, 70A......................................................................................................470-313-10
Breaker, AM-type mid-trip plug-in, 80A......................................................................................................470-314-10
Breaker, AM-type mid-trip plug-in, 90A......................................................................................................470-315-10
Breaker, AM-type mid-trip plug-in, 100A....................................................................................................470-316-10
Breaker , AM-type mid-trip plug-in, 110A (2-pole) .....................................................................................747-220-20
Breaker, AM-type mid-trip plug-in, 125A (2-pole) ......................................................................................747-147-20
Breaker, AM-type mid-trip plug-in, 150A (2-pole) ......................................................................................747-148-20
Breaker, AM-type mid-trip plug-in, 175A (3-pole) ......................................................................................747-149-20
Breaker, AM-type mid-trip plug-in, 200A (3-pole) ......................................................................................747-150-20
Breaker, AM-type mid-trip plug-in, 225A (3-pole) ......................................................................................747-200-20
Breaker, AM-type mid-trip plug-in, 250A (3-pole) ......................................................................................747-221-20
GMT fuse, 0.5A ..........................................................................................................................................460-004-10
GMT fuse, 1A .............................................................................................................................................460-006-10
GMT fuse, 1.3A ..........................................................................................................................................460-081-10
GMT fuse, 1.5A ..........................................................................................................................................460-082-10
GMT fuse, 2A .............................................................................................................................................460-083-10
GMT fuse, 3A .............................................................................................................................................460-013-10
GMT fuse, 4A .............................................................................................................................................460-085-10
GMT fuse, 5A .............................................................................................................................................460-084-10
GMT fuse, 7.5A ..........................................................................................................................................460-105-10
GMT fuse, 10A ...........................................................................................................................................460-069-10
GMT fuse, 15A ...........................................................................................................................................460-150-10

The above information is valid at the time of publication. Consult factory for up-to-date ordering information.

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 2 of 33
2 Features

2.1 System Overview


The basic system configuration is called out by Argus part number 053-390-20-000 (Figure 1); which includes:
• 1200A Two-Tier Distribution Center (Vista II Two-Tier UDC)
• Cordex System Modular Controller 4RU (CXCM4)
• Two (2) Cordex 24-3.1kW 6-module rectifier shelves
• Kydex rear cover
• 23” rack mount rails
• System integration cabling and bus work.
Optional system configurations are available as:
053-390-20-010: basic configuration factory installed into a 22RU battery mount 23” relay rack.
053-390-20-020: basic configuration factory installed into a 7 foot 23” zone 4 relay rack.
053-390-20-030: basic configuration factory installed into a 7 foot 23” zone 4 relay rack and three (3) battery
trays with cabling and 100A battery disconnects for up to six (6) 24V VRLA strings.

2.2 Tiered Distribution Features


2.2.1 Overview (Vista II Two-Tier)
The 1200A Two Tier Distribution Center is a modular, front access system that provides DC distribution, rectifier
and battery connections. Coupled with Argus Cordex system controller, rectifiers and converters, it provides a
complete solution in a compact integrated package.
The distribution center in the CXPS 24-2T is configured at the factory with:
• 24V, 20-position breaker tier with 600A low voltage disconnect (LVD)
• 24V, 18-position split-breaker tier with 600A LVD (can also be configured for split 24V/48V voltage
applications)
• 10-position, 30A GMT fuse assembly
• Load shunts for current measurement.
The modular distribution center allows customization of integrated power systems; perfect for space-restricted
installs. The system provides front access to controller interface and I/O connections, load breakers & fuses, and
battery connections.

2.2.2 DC Distribution Installed

2.2.2.1 Tier 1 (Upper)


The upper distribution tier in the CXPS 24-2T has support for twenty (20) AM-type plug-in
breaker positions for 24Vdc distribution. The tier contains a 800A load shunt and a 600A LVD.

2.2.2.2 Tier 2 (Lower)


The lower distribution tier in the CXPS 24-2T has support for eighteen (18) AM-type plug-in
breaker positions with a 800A shunt and 600A LVD. This option is a split-tier design – factory
configured – with a jumper to support eighteen (18) 24Vdc breaker positions.
The jumper is removable for future system installation / upgrade of 24V-48V converters.
Removing the jumper will change the tier capacity to eight (8) 24Vdc breaker positions and ten
(10) 48Vdc breaker positions.
NOTE: When implementing the 24/48V split distribution configuration, the LVD will only be series with the 24V distribution side.
LVD for the 48V loads will be performed via the 24V input to the converter or via software at the converter level. For split
voltage modification of Tier 2, please reference the installation section of this manual.

2.2.2.3 GMT Fuse Block


A 10-position GMT fuse block is also factory installed and is configured for additional primary
voltage (24V) distribution. The GMT fuse block has a total capacity of 30A.

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 3 of 33
2.3 Cordex System Controller (CXC)

2.3.1 CXCM4 Overview


The CXCM4 (Cordex Controller, Modular, 4RU) is mounted in the rectifier system shelf and brings advanced
monitoring technology to the Cordex series of rectifiers. This compact system controller is designed for seamless
operation and set up of Argus power systems and is equipped with the complete range of Cordex software
features, including the following:
• Designed to communicate directly with Cordex rectifiers
• Includes battery temperature compensation charging
• Battery performance diagnostics
• Provides local and remote communications
• User definable alarms
• Daily logging of power system events and system statistics.
Behind the CXCM4’s front panel lies the main controller motherboard, which contains a microprocessor, memory,
as well as numerous other electronic components.
The CXCM4 includes a web server providing easy set up and monitoring using an Internet connection with the
standard Windows Internet Explorer browser.
The data logging feature allows the user to capture data from multiple inputs, for AC/DC voltages, load/battery
current, cell voltages & temperatures (automatically for up to 16 user defined logs). Typical applications of the
CXCM4 logging include power system details, thermal performance of outdoor enclosures, battery cell specifics,
or mains variations captured by an AC voltage watchdog.
A built-in audio speaker sounds an intermittent tone during active alarms.
The input/output (I/O) board houses a series of terminal connections.

2.3.2 Front Panel

2.3.2.1 Display
Located on the front panel is a 160 x 160-pixel graphical LCD with touch screen similar to those
used in PDAs. This graphical user interface (GUI) allows the operator to interact with screen
selectable items using a fingertip.

Touch screen

RS-232 (craft port)

Reset (RST) button


Ethernet port

System status LEDs

Figure 2–Cordex CXCM4 model system controller front panel (shown with optional gray finish)

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 4 of 33
2.3.2.2 LEDs
The CXCM4 has three LEDs located on the front panel. These are used to display the alarm
status of the power system, CXCM4 progress and status during startup, file transfers and lamp
tests.

Alarm Conditions
The CXCM4 illuminates the LED that corresponds to the system alarm status. The following
show the corresponding alarm status for each LED color:
Green – OK, no alarms present
Yellow – Minor alarm is present (no major alarms)
Red – Major alarm is present.
Only one LED is illuminated at a time during alarm conditions.

Progress and Status Indication


The LEDs are also used in the following situations:
Base unit validation – all three LEDs are on at the same time.
File transfer – when recovering from invalid firmware application – the red LED is
illuminated.
Lamp Test – all three LEDs flash on and off at the same time for 2 seconds.

2.3.2.3 Reset
A reset button is located on the front panel for restarting the CXCM4’s microprocessor. It takes
approximately 15 seconds before the display reappears after pressing the reset button.
NOTE: Refer also to the software manual – always select the shutdown menu item before pressing the reset
button.

2.3.2.4 Ethernet Port


The Ethernet port is designed for CXCM4 connection to a user supplied network (TCP/IP
secured by user) via a front panel RJ-45 jack and a standard network cable.
Local access (e.g. laptop computer) is also possible from the Ethernet port connection using a
standard network crossover cable.

2.3.2.5 RS-232 Serial (Craft) Port


Local access to the CXCM4 is possible through a front panel RS-232 serial port; using a null
modem cable. The communication protocol supports a web interface (via Microsoft® Internet
Explorer 6 or greater). The remote screen display is an enhanced version of the CXC’s front
panel display.

2.3.3 Analog Input Channels


The CXCM4 has analog input channels for voltage, current, and temperature.

2.3.3.1 Voltage Inputs


Two voltage input channels, V1 and V2, provide monitoring of discharge and charge voltage.
The CXCM4 software is pre-configured to monitor V1 for load voltage and V2 for battery
voltage. V2 is used as the system reference for rectifier float voltage, low voltage disconnect
(LVD), system high voltage alarm, and system low voltage alarm.

2.3.3.2 Current Inputs


The CXCM4 software is pre-configured to monitor for load current using an external 50mV
current shunt.

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 5 of 33
2.3.3.3 Temperature Inputs
Two temperature input channels, T1 and T2, provide monitoring of battery temperature and
temperature compensation (temp comp) or room/ambient temperature. A voltage is supplied to
these terminals to power the temperature sensors.

2.3.4 Digital Input Channels


The CXCM4 can accommodate up to four channels and can monitor digital alarm/control signals from rectifiers,
converters and many other types of equipment.

2.3.5 Alarm and Control Output Relays


The CXCM4 contains eight Form C digital alarm output relays to extend alarms and control external apparatus.
Each internally generated alarm or control signal may be mapped to any one of the relays, or, several signals may
be mapped to just one relay or none at all.

2.3.5.1 LVD Control (External Option)


The LVD Control functions can be hardwired directly from the assigned relay output to an
optional LVD override control and distribution alarm card. This provides a safety measure to
protect against load disconnect during CXCM4 reset or replacement; e.g. when the controller is
off-line. Operators may also perform test and maintenance procedures on the CXCM4 without
disturbing the load.

2.3.6 System Fail Alarm/Relay


The CXCM4 system fail alarm activates because of a major internal failure. During such a condition, the unit will
attempt to reset, but if this fails, an alarm condition will be extended to a relay and the red LED on the front panel
will illuminate. This is a fail-safe signal to the remote monitoring equipment; i.e. alarm will be extended even if
power to the unit is interrupted.

2.3.7 Network Connection and Remote Communications


The Cordex system can be set up, monitored and tested via ETHERNET 10/100 Base-T serial data connection.
The communication protocol supports a web interface. All alarming and control of Cordex rectifiers is
accomplished with a CXC via a CAN bus.
A step-by-step connection wizard – provided to establish remote communications with your CXC – is available via
the Argus website (www.argusdcpower.com).
When connected to the CXC remotely, an online help guide is provided to supplement the software manual with
regard to the features of the web interface.

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 6 of 33
2.4 Cordex 24-3.1kW Rectifiers

2.4.1 Rectifier Overview


The CXPS 24-2T system is provisioned for use with the high-density Cordex 24V-3.1kW rectifier system. The
system ships complete with two (2) 23” 6-module rectifier shelves installed. Individual 3.1kW (130A) rectifiers are
ordered separately.
NOTE: The two (2) installed 6-module shelves with one CXCM4 (controller) allow for up to eleven (11) 3.1kW modules in
a single system, however distribution and buswork capacity limits the total system load capacity to 1200A.

2.4.2 Remote Control


All alarming and control of Cordex rectifiers is accomplished with a CXC via a CAN bus. The Cordex rectifier
shelves provide connections for serial communications with other rectifier shelves as well as supervisory and
control panels.

2.4.3 Rectifier Front Panel

LEDs

Thumbscrew

Figure 3–Cordex 24-3.1kW modular switched mode rectifier


2.4.3.1 LEDs
The front panel LEDs provide:
• Rectifier status summary,
• Rectifier software upgrade in progress indication,
• Locate module pattern.

Rectifier status summary will show the rectifier alarm status, communication fail status and
rectifier on/off status.

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 7 of 33
AC ON
The top LED (green) is on when AC is within valid range. The LED will flash (~2Hz) when AC is
outside the nominal range – AC voltage is invalid if the AC Mains Low or AC Mains High
alarm is active. The LED turns off when AC has failed.

DC ON
The middle LED (green) is on when the rectifier is delivering power to the load. The LED will
flash when communication is lost. The LED turns off when the rectifier is off; e.g., when
commanded via the CXC.

ALARM
The bottom LED (red) is on continuously in the event of an active Module Fail alarm; if the
module is unable to source power as a result of any of the following conditions:
Output fuse blown AC Mains Input Fail Module fail (ramp test fail)
High voltage (OVP) shutdown Thermal shutdown Local shutdown
UPF fail No output power Fan (1 and 2) fail.

The LED will flash (~2Hz) when a minor alarm is detected; if the modules output capability has
been reduced or a minor component failure is detected during the following conditions:
VAC meter fail AC foldback Remote equalize
Fan (1 or 2) fail Low output voltage High output voltage
Current limit (programmable option) Power limit (programmable option) High temperature foldback
Temperature sense fail Soft start operation Communications lost.

The LED remains off in the absence of an alarm. If the unit output is not connected to a battery
or parallel rectifier, the LED will extinguish if no AC power is present.

LED Activity During Software Upload


When a rectifier software upload is in progress, the LEDs will behave in a distinctly different way
to indicate new rectifier software is being transferred from the CXC.
When a rectifier data transfer is in progress, all three LEDs will flash in a sequence lasting 1.5
seconds. When the last LED is lit, the sequence is repeated beginning at the first LED.

LED Activity During ‘Locate Module’ Command from CXC


When the ‘locate module’ command has been received from the CXC, the LEDs will behave in
another distinct fashion so that the rectifier is easier to visually identify among adjacent
rectifiers.
This state is entered when commanded via the CXC. The LEDs will flash in a ping-pong pattern
repeating every 2 seconds.
The ping-pong pattern lights each LED sequentially. After the last LED is lit, each LED is lit in
reverse sequence. When the first LED is lit, the pattern repeats. The effect makes it appear as if
the light is bouncing between the first and last LED.

2.4.3.2 Mechanical
A thumbscrew is provided to secure the rectifier into the shelf. During normal operation the
rectifier shall be locked into position. A handle (or grip) is incorporated into the front panel to
facilitate the removal of the rectifier from the shelf. No special tools are required.

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 8 of 33
2.4.4 Rectifier Rear Panel
Located on the rear panel of the rectifier is a single connector for shelf power and communications.

2.4.5 True Module Fail Alarm


The power modules have a “true” fail alarm. This provides a true indication of the power module’s ability to source
current. When the module’s output current drops below 2.5% of the rated output a low output current condition is
detected and the Module Fail detection circuit is activated. This circuit momentarily ramps up the output voltage to
determine if the module will source current. If no increase in current is detected, the Module Fail alarm is
activated. The module will test once every 60 seconds for the condition until current is detected. Output voltage
ramping will cease upon detection of current1. A minimum 2.5% load is required to avoid the Ramp Test Fail
alarm; this can typically be provided with the parallel system battery. Activation of this alarm could indicate a failed
module or a failed load.
NOTE: For Cordex rectifier systems without batteries (or with a very light load; below 2.5% of rated output) it is
recommended that the ramp test be disabled to avoid nuisance alarms. The Ramp Test feature is
enabled/disabled via the CXC menu item: Rectifiers, Configure Settings.

2.4.6 Heat Dissipation


Each rectifier module is equipped with at least one front-mounted fan. The fan operates at temperatures above
0°C (32°F). Cooling of the module is front-to-rear with the exhaust air exiting at the back. The fan is variable
speed; which is determined by heatsink temperature and load.

2.4.7 Over Temperature Protection


Each rectifier module is protected in the event of an excessive increase in temperature due to component failure
or cooling airflow blockage. During over temperature conditions, the rectifier limits the output power as well as the
output current. If temperature continues to increase, a shutdown of the rectifier is initiated. The rectifier shall
restart automatically if the temperature has returned to a safe level.

2.4.8 Wide AC Range


A minor alarm is generated when the AC input voltage drops below specification. Rectifier output power is
reduced linearly between 176Vac and 150Vac to 75% of the rated output power (the unit will deliver derated
output power down to 90Vac).
At 90Vac, the module will shut down and will not restart until the AC is greater than or equal to 150Vac; however,
the restart voltage depends on the load current. At reduced load current the unit may restart with the input voltage
as low as 100Vac.
For voltages above 277Vac, power factor and total harmonic distortion may be derated. Up to 320Vac, the
rectifier will be operational and shall not suffer any damage.

2.4.9 AC Inrush/Transient Suppression


The inrush current of the rectifier module is limited to the full load steady state line current to prevent surge on the
AC line. Modules are also protected from input lightning and transient surges in accordance with IEEE/ANSI
C62.41 Category B3.

2.4.10 Soft Start


To eliminate an instantaneous demand on the AC source, a soft start feature is employed. Soft Start, sometimes
referred to as “current walk-in”, works by gradually (up to five seconds) ramping the current limit up from zero to
the actual or defined customer setting. The rectifier output voltage is ramped up from the minimum voltage to the
float voltage.

1
Under normal conditions, a battery connected to the output of the rectifier will draw current when the voltage ramp occurs. Therefore the rectifier fail
alarm will not be generated with a battery connected.

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 9 of 33
2.4.11 Start Delay
The rectifier modules are equipped with a delay timer in order to stagger start a series of modules to prevent
excessive loading of generators upon start up. The built-in timer delays the turn on of the module depending on
the value selected (up to 120 seconds) via the CXC. A minimum one-second delay is preset to allow charging of
the input capacitors.

2.4.12 Current Limit/Short Circuit Protection


The current limit function determines the maximum output current limit of the rectifier module, regardless of output
voltage or power. Maximum output current is limited to a constant value down to short circuit condition. Current
limiting can be used to mate the rectifier output current ampacity to the needs of the load and parallel battery to
minimize excessive battery recharge current.
The rectifier will sustain a short circuit at the output terminals indefinitely. The maximum short circuit current shall
not exceed 105% of the rated full load current.

2.4.13 Power Limiting


Each rectifier module is designed to limit power output to the module specification. This enables more current to
be supplied at lower output voltages, and allows matching of output to the demand of constant power loads,
normally seen with telecom equipment.
This feature may also be used for a faster recharge of flooded batteries paralleled with the load.
NOTE: Current limiting overrides the power-limiting feature.

2.4.14 High Voltage Shutdown (HVSD)


This feature provides protection to the load from over voltage conditions originating from the rectifiers. It operates
by shutting down the offending rectifier module when a high output voltage condition occurs. Indication is through
the red Alarm (Module Fail) LED. Modules will restart automatically; however, if more than three over voltage
conditions occur in one minute, the module will latch off and remain shut down until it is reset (by restarting the
rectifier) via the CXC.

2.4.15 Battery Eliminator Operation


Rectifier modules maintain all specifications (except where indicated) with or without a battery attached in parallel
to the output; however, if a battery or another module supplying DC voltage in parallel is not present, there will be
no monitoring or control activity if there is an AC power failure or input fuse failure.

Please see our website at www.argusdcpower.com for details on other custom products from Argus Technologies.

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 10 of 33
3 Inspection

3.1 Packing Materials


All Argus products are shipped in rugged, double walled boxes and suspended via solid inserts to minimize shock
that may occur during transportation. Packaging assemblies and methods are tested to International Safe Transit
Association standards. Power systems are custom packaged in heavy-duty plywood crates.
Products are also packaged with Cortex. This plastic wrap contains a corrosive-inhibitor that protects the product
from corrosion for up to two years.
NOTE: Rectifiers and batteries are shipped on individual pallets and are packaged per manufacturer’s guidelines.

3.1.1 Returns for Service


Save the original shipping container. If the product needs to be returned for service, it should be packaged in its
original shipping container. If the original container is unavailable, make sure the product is packed with at least
three inches of shock-absorbing material to prevent shipping damage.
NOTE: Argus Technologies is not responsible for damage caused by the improper packaging of returned products.

3.2 Check for Damage


Prior to unpacking the product, note any damage to the shipping container. Unpack the product and inspect the
exterior for damage. If any damage is observed contact the carrier immediately.
Continue the inspection for any internal damage. In the unlikely event of internal damage, please inform the
carrier and contact Argus Technologies for advice on the impact of any damage.

3.3 General Receipt of Shipment


NOTE: The inventory included with your shipment is dependant upon the options you have ordered. The options are
clearly marked in the bill of materials at the back of this manual and on the labels on the shipping containers.

3.3.1 Racks
Consult the packing slip and power system bill of materials to verify that you have the correct number of racks per
your order.

3.3.2 Rectifiers (Purchased Separately)


Consult the packing slip to verify that you have the correct number of rectifiers per your order.

3.3.3 Miscellaneous Small Parts


Review the packing slip and bill of materials to determine the part number of the “configuration kits” included with
your system; e.g., 053-390-20-010 for CXPS 24-2T system with 22RU battery-mount relay rack.
Review the bill of materials (per the configuration kits that you determined above) to verify all the small parts are
included.

3.3.4 Batteries (Purchased Separately)


Verify that you have the correct number of batteries (if applicable). Refer to packing list.

Verify that you have all the necessary parts per your order for proper assembly.
Call Argus Technologies if you have any questions before you proceed: 1 (888) 462-7487

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 11 of 33
4 Installation
This chapter is provided for qualified personnel to install and interconnect the power components within the Argus
power system. Regarding battery installation, refer primarily to the manufacturer’s guidelines for more specific
information.
NOTE: To aid the user with installation, frequent reference is made to drawings located at the rear of this manual.

4.1 Safety Precautions


Refer to the Important Safety Instructions near the front of this manual.

4.2 Tools Required


Various insulated tools are essential for DC power system installation. Use this list as a guide:
• Battery lifting apparatus (as required)
• Electric drill with hammer action, 1/2" capacity
• Various crimping tools and dies, to match lugs used in installation
• Load bank of sufficient capacity to load largest rectifier into current limit
• Digital voltmeter equipped with test leads
• Cable cutters
• Torque wrench: 1/4” drive, 0-150 in./lb.
• Torque wrench: 3/8” drive, 0-100 ft./lb.
• Insulating canvases as required (2’ x 2’, 1’ x 1’, 3’ x 3’, etc.)
• Various insulated hand tools (see Figure 4) including:
-Combination wrenches -Ratchet and socket set
-Various screwdrivers -Electricians knife
• Battery safety spill kit (required for wet cells only) including:
-Protective clothing -Face shields
-Gloves -Baking soda
-Eye wash equipment
• Cutters and wire strippers (#14 to #22 AWG) [2.5 to 0.34mm2].

Figure 4–Example of an insulated tool kit

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 12 of 33
4.3 Power System Assembly and Mounting
The power system must be mounted in a clean and dry environment. Sufficient free space must be provided at
the front and rear of the power system. This is to meet the cooling requirements of the rectifiers utilized in the
power system and to allow easy access to the power system components.

4.3.1 Rack Mounted Systems


Attach the power system to the customer-provided relay rack using mounting screws and star washers to ensure
an electrical bond between system chassis and relay rack.

4.3.2 Floor Mounted Systems


Secure the system to a concrete floor utilizing either heavy duty anchors (1/2” x 2-1/2”) or, for wooden floors,
heavy-duty lag screws (5/8” x 2-1/2”). Use appropriately-sized flat washers.
Use isolating kits if required to isolate system from the floor.
It is recommended that the relay rack be secured to the overhead cable tray. Argus does not supply the
mechanical details necessary for overhead support.

4.3.3 Half-Rack/Battery Mounted Systems


Obtain the appropriate battery to power system adapter plate. Secure the plate to the battery stack using heavy
duty hardware.
Secure the power system to the adapter plate using heavy duty hardware.
It is recommended that the power system be secured to the overhead cable tray. Argus does not supply the
mechanical details necessary for overhead support.

4.4 Rectifier Module Insertion/Removal


Insert by placing the rectifier module on the shelf bottom and sliding the module into the rear connector (inside of
the shelf). Apply pressure on the module handle to engage the rear connector in the shelf receptacle.
NOTE: It is recommended that the first module be inserted into the front leftmost position using the side of the shelf as a
guide. Subsequent modules may be inserted using the previous module as a guide.
Tighten the screw on the bottom of the faceplate to secure the module to the shelf.
NOTE: Do not force a module into position if it does not seat properly. All modules are keyed to ensure that the correct
module (voltage/polarity) type is used.
To remove a module, loosen the screw on the bottom of the faceplate. Grasp handle and pull out, sliding the
module away from the rear connector and out of the shelf.

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 13 of 33
4.5 Battery Installation
This information is provided as a guideline and is not meant to imply that batteries are part of this power system.
WARNING
Follow battery manufacturer’s safety recommendations when working around battery systems
and review the safety instructions provided in this manual.

4.5.1 Preparation/Mounting
Batteries should be located in a temperature-controlled environment. The temperature should be regulated at
approx. 25°C (77°F). Significantly lower temperatures reduce performance and higher temperatures decrease life
expectancy.
Provide adequate ventilation. VRLA batteries, though not requiring the special ventilation requirements of a
flooded battery, should not be installed in an airtight enclosure. Hydrogen gas may be vented in a fault condition;
i.e., failed battery.
Before assembly, clean cells (where applicable) as per the battery manufacturer's recommendations.
First neutralize any acid with a baking soda and water solution. Then wipe the cells with clean water.

4.5.2 Installation of Batteries


Verify that all battery breakers, DC circuit breakers, and fuses on the distribution panels are either
in the OFF position or removed.
Use a corrosion-inhibiting agent such as NO-OX or NCP-2 on all battery terminal connections.
1. Assemble battery rack (if required) and the cells or mono-blocks as per the
installation instructions supplied with the batteries.
2. Ensure that the battery output cabling will reach the [+] and [–] terminals of the series
battery string and that the batteries are oriented correctly for easy installation of the
inter-unit “series” connectors.
3. Remove any no-oxide “A” grease from battery terminals.
4. Burnish terminal posts with a non-metallic brush, polishing pad or 3M-type scotch pad.
5. Apply a light coating of no-oxide “A” grease to the terminal posts.
6. If lead plated inter-unit connectors are used, they should also be burnished and no-
oxide “A” grease applied as above. Install the inter-unit connectors.
7. After all battery connections are completed, torque per battery specifications
(typically 100 in-lbs).

NOTE: See system startup procedure before connecting batteries online.

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 14 of 33
After assembly, batteries should be numbered and “as received” readings taken, including specific gravity, cell
voltage and temperature. One cell will be designated as the pilot cell; this is usually the cell with either the lowest
specific gravity or voltage. Refer to manufacturer's literature for guidelines. See following table for typical
maintenance report:

Company: ________________________________________________ Date: ____________________


Address:____________________________________________________________________________
Battery location and/or number:__________________________________________________________
No. of cells: _______________ Type: __________________________ Date new: ________________
Date installed: _____________ Float voltage: ____________________ Ambient temp.: ____________

Cell Readings

Cell # Serial # Voltage Specific Ohms Mhos Observations


Gravity
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24

Remarks and recommendations: _________________________________________________________


__________________________________________________________________________________
__________________________________________________________________________________

Readings taken by: _________________________________________

Table A–Typical VRLA battery maintenance report

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 15 of 33
5 Wiring
This chapter provides cabling details and notes on cable sizing for DC applications with respect to the product.
WARNING
Ensure that power is removed by turning off rectifiers and removing battery line fuse or
connection before attempting work on the wiring connections. Use a voltmeter to verify the
absence of voltage. Clearly mark the correct polarity of the battery leads before commencing work
on DC connections.
Refer to the previous (Installation) chapter for safety precautions and tools required.

5.1 Grounding
The isolated power system battery return bus (BRB) should be connected to the building master ground bus
(MGB) or floor ground bus (FGB) in a larger building. This acts as a system reference and as a low impedance
path to ground for surges, transients, noise, etc. The MGB or FGB should have a direct low impedance path to
the building grounding system. The cable from the power system to the MGB or FGB should be sized to provide
sufficient ampacity to clear the largest fuse or breaker on the power system, excluding the battery protection fuse
or circuit breaker. 750MCM is recommended. This is the minimum requirement; other factors including length of
cable and special grounding requirements of the load should also be factored in. The insulated cable should be
equipped with two-hole crimp type lugs and should not have any tight bends or kinks.
Power System Ampacity Ground Reference Conductor Size
< 30A #10
30 – 100A #6-2
100 – 400A 0000
400 – 800A 350 MCM
> 800A 750 MCM

Table B–Typical ground reference conductor selection


The power system frame must also be connected to the MGB or FGB. This is done for personnel safety and to
meet many Telco grounding requirements. Each bay should have its own frame or site ground connection (see
Figure 5). Refer also to the Customer Connections drawing at the rear of the manual.

5.2 AC Feeder Protection/Sizing


To maximize system reliability, each power module should be fed from a dedicated protection feeder breaker
located at the AC distribution panel. The feeder breaker can also act as the disconnect device for the connected
module. Refer to the specifications at the front of this manual for Argus recommendations.

5.3 AC Input Connections


CAUTION: AC input wires should be routed in flexible or rigid conduit as far away as possible
from the DC power wires to minimize EMI disturbances.
Ensure all modules are removed from the shelf and refer to the Customer Connections drawing at the rear of the
manual for AC terminal block location.
Remove the metal covers (2 places) from the rear of the shelf to expose the AC input terminal blocks, L1 and L2
for each rectifier. Each terminal pair relates to an individual power module as marked.
The wireway is designed for two customer-supplied 1” conduit fittings for AC supply located one on each side of
the shelf. Attach the conduit retainers to the wireway hole(s) and route the AC cables through. Secure the wires to
the AC input and chassis ground terminals as required. Tighten the cable connector to the AC cable (conduit
similar).
Replace rear cover(s) once all connections have been completed.

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 16 of 33
5.4 DC Output Connections
WARNING
Leave cables or bus bars disconnected at battery and verify output polarity using a voltmeter.
Make battery connections only after all other wiring is completed.
DC output wire shall be UL approved XHHW or RHH/RHW (for Canadian users, RW90 Type). Control and sense
wires shall be UL approved Style 1015 (for Canadian users, TEW type).
The common output leg of the rectifier system should be connected to ground. This is typically done at the load
common termination point.

5.4.1 Battery Connections


Battery cables should be sized for a 0.25 V drop from battery to the power system at full load including anticipated
growth. The cables should also meet ampacity requirements. Cables terminating directly on battery posts or
connection details should be secured so that there is no stress on the battery posts. Lead plated lugs and lead
plated or stainless steel hardware should be used on all terminations at vented batteries to reduce corrosion.
Prepare, route and connect cables from power system to battery termination details. Terminating points should be
burnished and a corrosion-inhibiting agent, such as NO-OX-ID “A”™, should be applied to all battery terminal
connections.
The 1200A Two Tier Distribution Center (Vista II Two-Tier UDC) allows for (4) sets of battery connections for both
hot and return. Connections allow for 3/8” on 1”C lug connections.
Hot Return Site Ground

Optional Alarm
Wire Connection

Figure 5–Vista II two-tier battery connections (hot and return)


NOTE: Final connection to battery live should not be made, insulate and leave disconnected or remove the battery fuses.
Switch battery contactors off (if used). See system startup procedure before connecting batteries online.

5.4.2 Load Distribution


Refer to guidelines supplied with the load equipment. Typically distribution cables are sized to provide a 0.5 V
loop drop at full load as well as meeting ampacity requirements of the protection fuse or circuit breaker.

5.4.2.1 AM Breakers
The CXPS 24-2T is factory configured with (38) total single-pole AM-type plug-in breaker
positions for 24V load distribution. The breakers have bullet terminals which plug into the
breaker tier for simple installation and removal. Each distribution tier has a 1/4” – 5/8”C hole set
for the breaker output and on the ground bar located directly above the breaker panel.
• 1 to 100 amp breakers require 1 position.
• 110 to 150 amp breakers require 2 positions*.
• 175 and 200 amp breakers require 3 positions*.

* 2-position and 3-position breakers have an output adapter that provides a single 3/8" hole on a 1" center output.
The return must use one of the battery or rectifier terminations.

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 17 of 33
Figure 6–Front view of the 2-Pole and 3-Pole output adapters
It is recommended to install the largest capacity circuit breakers on the top distribution tier to
optimize cable management. It is imperative to plan circuit breaker installation to allow for
proper cable management and to not overload the capacity of a single tier (600A LVD
limitation).
TPS fuses may be used instead of breakers via a plug-in breaker cartridge which installs into
any AM-type plug-in breaker panel configuration. See Figure 7 below:

Figure 7–Plug-in breaker/fuse cartridge

5.4.2.2 GMT Fuses


The CXPS24-1200 is factory configured with (10) GMT type fuse positions for additional 24V
load distribution. The fuse assembly is rated for maximum capacity of 30A.
Connections for hot and return are made via screw terminal connections on the assembly.

Figure 8–GMT fuses

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 18 of 33
5.5 DC-DC Converter Connections
The CXPS 24-2T is factory configured as a 24Vdc power system. A dual 24/48V output option is available via
factory or field upgrade with DC-DC converters.
Reference the DC-DC converter manual for full installation and operation procedures.

5.5.1 Re-Configure Split Tier Distribution


1. Remove the copper jumper bridging the 8-position and 10-position breaker rows.
2. Locate the alarm card on the left hand side of the internal wall of the distribution
center. Reference the Customer Connections drawing at the rear of the manual.
3. Locate the terminal blocks. The 10-position breaker alarming – factory configured for
24V distribution – is wired to TB12-42 “Pri Alm In.” Refer to the system schematic
located at the rear of this manual for terminal block location and factory wiring.
4. Remove the alarm wire and re-terminate to TB12-43 “Sec Alm In.”

5.5.2 Argus CSM01 Six-Module Converter Shelf Installation Method Of Procedure (MOP)
The CSM01 six-module converter shelf kit, # 038-275-20, includes a cable kit for integration into a CXPS 24-2T
power system. Please reference CSM01 manual # 012-501-B2 for drawings, specifications, and operation of
converter system. Please also reference schematic included with 038-275-20 kit for detailed wiring instructions.
NOTE: Rear access to CXPS system is required for this installation.
The kit includes:
• One six-module CSM01 23” converter shelf
• One 100A plug-in feeder breaker
• Two converter input cables (+/–), #2 AWG flex cable, pre-terminated with 1/4”-5/8”C
lugs on converter shelf end (un-terminated on other)
• Two converter output cables (+/–), #6 AWG flex cable, pre-terminated with 1/4”-5/8”C
lugs on converter shelf end (un-terminated on other)
• Two loose 1/4”-5/8”C lugs for terminating #2 AWG converter input cabling to Vista II
UDC (requires customer supplied crimp tool)
• Two loose 3/8”-1”C lugs for terminating #6 AWG converter output cabling to Vista II
UDC (requires customer supplied crimp tool)
• Hardware for attaching +GND converter output cable to Vista II UDC busbar
• Three #18 AWG signal cables for connecting converter fail alarm (digital) signal to
controller.

5.5.2.1 Installation Procedure

Preparation
Mount converter shelf into 23” rack channels below the CXPS power system leaving 1 RU
space between converter shelf and bottom of rectifier shelf for cooling.
Remove the rear panel of the converter shelf.
Insert the pre-terminated lug ends of the two #6 AWG cables into the converter output wireway
on the right hand side of the shelf.
Insert the pre-terminated lug ends of the two #2 AWG cables into the converter input wireway
on the left hand side of the shelf.

Converter Output Cabling (+GND Connection)


Terminate the #6 AWG cable with pre-terminated 1/4”-5/8”C lug (with wire marker #43) to the
+GND output terminal labeled “E4” using hardware supplied with shelf.
Route the un-terminated wire end up to the system return bus, cut wire to size, strip cable
sheath, crimp supplied 3/8”-1”C lug.
Attach to system return bus bar as per Figure 9 using hardware supplied with kit.

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 19 of 33
Converter output (-48V)
wire routing location

Converter output (+GND)


wire connection location

Figure 9–Rear of CXPS 24-2T system showing converter +GND output connection
and –48V wire routing location

Converter Output Cabling (–48V HOT Connection)


Terminate the #6 AWG cable with pre-terminated 1/4”-5/8”C lug (With wire marker #44) to the –
48V (hot) output terminal labeled “E3” using hardware supplied with shelf.
Route the un-terminated wire end up in between the system bus bars towards the front of the
distribution center (Reference Figure 9 for routing location).
Fish the wire through the existing hole in the glastic insulator of the bottom distribution tier
(Reference Figure 10 for routing location).
Cut wire to size, strip cable sheath, and crimp supplied 3/8”-1”C lug. Note: This lug must be
crimped after it has been routed through the distribution tier.
Attach lug to input bar using the hardware originally used for attaching copper jumper bar.

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 20 of 33
Upper distribution tier (2-tier
model) for converter input feeds

Converter output (-48V)


wireway

Converter output (-48V)


wire connection
(jumper bar removed)

Figure 10–Connection points and wire routing for –48V input into split tier distribution

Converter Input Cabling (–GND Connection)


Terminate the #2 AWG cable with pre-terminated 1/4”-5/8”C lug (with wire marker #46) to the –
GND input terminal labeled “E2” using hardware supplied with shelf.
Route the un-terminated wire end up behind the CXPS system over the top of the distribution
center.
Cut wire to size, strip cable sheath, and crimp supplied 1/4”-5/8”C lug.
Attach lug to distribution tier return bar. It is recommended to utilize the top distribution tier for
feeder breaker installation. Use the hardware supplied with the CXPS system for attaching lug
(Reference Figure 10 for breaker locations in 2-tier UDC).

Converter Input Cabling (+24V Connection)


Terminate the #2 AWG cable with pre-terminated 1/4”-5/8”C lug (with wire marker #45) to the
+24V (hot) input terminal labeled “E1” using hardware supplied with shelf.
Route the un-terminated wire end up behind the CXPS system over the top of the distribution
center.
Cut wire to size, strip cable sheath, and crimp supplied 1/4”-5/8”C lug.
Attach lug to breaker output terminal. It is recommended to utilize the top distribution tier for
feeder breaker installation. Use the hardware supplied with the CXPS system for attaching lug
(Reference Figure 10 for breaker locations in 2-tier UDC).

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 21 of 33
5.5.2.2 Converter Fail Alarm

Locate #18 AWG wire with tag #42.


Attach end with ring lug to +GND output terminal on converter shelf (E4).
Attach unterminated wire end to TB #8 “Conv Fail” on alarm connection at rear of CSM01 shelf.

Locate #18 AWG wire with tag #41.


Attach unterminated wire end to TB #7 “Conv Fail” on alarm connection at rear of CSM01 shelf.
Attach other unterminated wire end to TB11-38 “Conv Fail” on internal alarm board with Vista II
UDC (reference Figure 11 for alarm board details as well as -08 connection drawing at rear of
this manual).

Locate #18 AWG wire with tag #40.


Attach unterminated wire end to TB11-37 “Conv Fail” on internal alarm board with Vista II UDC
(reference Figure 11 for alarm board details as well as -08 connection drawing at rear of this
manual).
Attach end with ring lug to an available screw terminal input on the +24V bus bar inside the
Vista distribution center (reference Figure 5 for alarm connection locations).

5.5.2.3 Final Steps


Reattach back cover to converter shelf.
Install breakers as needed in 10 position breaker tier for required 48V distribution.
Cable from 48V loads to distribution as required.
Plug in 100A 24V feeder breaker into upper distribution tier.
Switch 100A feeder breaker to “ON” position to supply power to converter shelf.
Refer to Cordex Controller Software manual for custom alarming options using the two new
digital alarms (-48V distribution and converter fail).

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 22 of 33
5.5.3 Argus CSM11 Four-Module Converter Shelf Installation MOP
The CSM11 four-module converter shelf kit, # 038-277-20, includes a cable kit for integration into a CXPS 24-2T
power system. Please reference CSM11 manual # 012-548-B2 for drawings, specifications, and operation of
converter system. Please also reference schematic included with 038-277-20 kit for detailed wiring instructions.
NOTE: Rear access to CXPS system is required for this installation.
The kit includes:
• One 4-module CSM11 23” converter shelf
• Four 80A plug-in feeder breakers
• Eight converter input cables (+/–), #2 AWG flex cable, pre-terminated with 1/4”-5/8”C
lugs on converter shelf end (un-terminated on other)
• Two converter output cables (+/–), #2 AWG flex cable, pre-terminated with 3/8”-1”C
lugs on converter shelf end (un-terminated on other)
• Eight loose 1/4”-5/8”C lugs for terminating #2 AWG converter input cabling to Vista II
UDC (requires customer supplied crimp tool)
• Two loose 3/8”-1”C lugs for terminating #6 AWG converter output cabling to Vista II
UDC (requires customer supplied crimp tool)
• Hardware for attaching +GND converter output cable to Vista II UDC busbar
• Three #18 AWG signal cables for connecting converter fail alarm (digital) signal to
controller.

5.5.3.1 Installation Procedure

Preparation
Mount converter shelf into 23” rack channels directly below the CXPS power system.
Remove the cover for the DC input cable wireway (via front access to shelf).
Remove the cover for the DC output cable wireway on rear of shelf.

Converter Output Cabling (+GND Connection)


Route the #2 AWG cable with pre-terminated 3/8”-1”C lug (With wire marker #43) through the
rear entry hole on right side of shelf (as seen from front).
Terminate cable to the “+” output terminal (top hole set on DC output connection at rear of
shelf).
Route the un-terminated wire end up to the system return bus, cut wire to size, strip cable
sheath, crimp supplied 3/8”-1”C lug.
Attach to system return bus bar as per Figure 9 using hardware supplied with kit.

Converter Output Cabling (-48V HOT Connection)


Route the #2 AWG cable with pre-terminated 3/8”-1”C lug (With wire marker #42) through the
rear entry hole on right side of shelf (as seen from front).
Terminate the cable to the “–” output terminal (lower hole set on DC output connection at rear of
shelf).
Route the un-terminated wire end up in between the system bus bars towards the front of the
distribution center (Reference Figure 9 for routing location).
Fish the wire through the existing hole in the glastic insulator of the bottom distribution tier
(Reference Figure 10 for routing location).
Cut wire to size, strip cable sheath, and crimp supplied 3/8”-1”C lug. Note: This lug must be
crimped after it has been routed through the distribution tier.
Attach lug to input bar using the hardware originally used for attaching copper jumper bar.

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 23 of 33
Converter Input Cabling
Identify the eight cables provided for installation on the following connection points:
Wire Tag 48 = “+” Terminal 1, Wire tag 47 = “–” Terminal 1;
Wire Tag 50 = “+” Terminal 2, Wire tag 49 = “–” Terminal 2;
Wire Tag 52 = “+” Terminal 3, Wire tag 51 = “–” Terminal 3;
Wire Tag 54 = “+” Terminal 4, Wire tag 53 = “–” Terminal 4.

The CSM11 shelf configuration has individual feed inputs for each of the four module positions.
Repeat the following steps four times for each of the module input terminals “1” through “4”
starting with module “1” being the leftmost terminal position (as seen from front).
• For a module input, route a set (“+” and “–”) of #2 AWG cables with pre-
terminated 1/4”-5/8”C lugs into the wireway on the leftside of the
converter shelf (as seen from front).
• Terminate the “–” cable connection to the lower hole set.
• Terminate the “+” cable connection to the upper hole set.
• Route the un-terminated wire ends up behind the CXPS system over the
top of the distribution center.
• Cut wires to size, strip cable sheath, and crimp supplied 1/4”-5/8”C lugs.
• Attach lugs to distribution tier return bar for “–” cable connection and to
the breaker output terminal for the “+” cable connection. It is
recommended to utilize the top distribution tier for feeder breaker
installation. Use the hardware supplied with the CXPS system for
attaching lugs. (Reference Figure 10 for breaker locations in 2-tier UDC).

5.5.3.2 Converter Fail Alarm

Locate #18 AWG wire with tag #42.


Attach end with ring lug to +GND output terminal on converter shelf (top hole set).
Attach unterminated wire end to TB6-4 “Mod Fail Minor” on alarm connection at rear of CSM11
shelf.

Locate #18 AWG wire with tag #41.


Attach unterminated wire end to TB6-3 “Mod Fail Minor” on alarm connection at rear of CSM11
shelf.
Attach other unterminated wire end to TB11-38 “Conv Fail” on internal alarm board with Vista II
UDC (reference Figure 11 for alarm board details as well as -08 connection drawing at rear of
this manual).

Locate #18 AWG wire with tag #40.


Attach unterminated wire end to TB11-37 “Conv Fail” on internal alarm board with Vista II UDC
(reference Figure 11 for alarm board details as well as -08 connection drawing at rear of this
manual).
Attach end with ring lug to an available screw terminal input on the +24V bus bar inside the
Vista distribution center (reference Figure 5 for alarm connection locations).

5.5.3.3 Final Steps


Reattach front (input) cover and rear (output) cover to converter shelf.
Install breakers as needed in 10-position breaker tier for required 48V distribution.
Cable from 48V loads to distribution as required.
Plug in four 80A, 24V feeder breakers into onto upper distribution tier.
Switch four 80A, 24V feeder breakers to “ON” position to supply power to converter shelf.
Refer to Cordex Controller Software manual for custom alarming options using the two new
digital alarms (-48V distribution and converter fail).

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 24 of 33
5.6 Controller I/O Connections
WARNING
Ensure that input power and output power is removed before attempting work on the
CXC’s wiring connections.
System integration cabling is utilized to bring the controller I/O connections to the front (left side) of the distribution
center:

Relay outputs

Analog inputs AUTO IN (green) LED

LVD control switch


Digital inputs
OVERRIDE IN or Inhibit
(amber) LED

Figure 11–Controller I/O connections and LVD control card


(illustration only and may not match your installation)

5.6.1 Analog Inputs


WARNING
Ensure the correct polarity is used for all input cable terminations.
The analog input channels are used to monitor various types of electrical signals. Some of the analog channels
are reserved for specific signals, while others are designated as general-purpose inputs, which accommodate
various types of analog signals. The input cables should be bundled together and routed through the entry holes,
if applicable.
Default configurations and terminal numbers described below have been summarized in the
foldout drawings located at the rear of this manual.

CAUTION: to reduce risk of fire, use only 0.129mm2 (#26 AWG) or larger wire.

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 25 of 33
5.6.2 Digital Inputs
The digital input channels are used to monitor various alarm and control signals. All input channels are voltage
activated and accept a bipolar (i.e. negative or positive) DC signal directly.

5.6.2.1 Connection Method


Typical Argus systems use the “reset with Hot and trigger with Ground” connection. The digital
input is wired in such a way that the Hot is wired directly into one of the input terminals; e.g.,
positive input for +24V systems. The other input terminal is wired to the Ground (common) of
the system through a relay (dry contact – usually located on the equipment requiring
monitoring). This method (see Figure 12) allows the digital input to receive (or not receive) a
Ground signal on an alarm.

Figure 12–Showing digital input connection method

5.6.2.2 Programming the Digital Input


The digital input channels can be programmed for “active high” or “active low.” Active high
indicates “alarm on the presence of a ground signal” and active low indicates “alarm on the
removal of a ground signal.” See CXC Software manual for detailed instruction on
programming.

Voltage Level (VDC) Voltage Level (VDC)


Voltage Range (VDC)
Considered As “0” (Off) Considered As “1” (On)
0—60
0—3 18—60
(system voltage setting)

Table C–Voltage level definitions for digital inputs

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 26 of 33
5.6.3 Relay Outputs
Terminals provide contacts for extending various alarm or control signals. Each relay output can be wired for NO
or NC operation during an alarm or control condition. See Figure 13.

Figure 13–Showing relay connections in the de-energized state


Relays can be programmed to energize or de-energize during an alarm condition (see CXC Software manual).
When the CXC reset button is pressed or power is lost, all relays de-energize.

5.6.3.1 System Fail Relay


System Fail output relay (K0) is fail-safe and will de-energize during an alarm condition.

5.6.3.2 LVD Control


The LVD Control functions can be hardwired directly from the assigned relay output to the LVD
contactor panel. See Controls Menu Defaults in the CXC Software manual.

5.6.4 CAN Port


The CAN port or “CAN bus” allows communications between the CXC and Cordex series rectifiers or other CXC
system peripherals. These are located on the left side of the rectifier shelf (as viewed from the front).

5.7 Network Connection and Remote Communications via CXC


The Cordex system can be set up, monitored and tested via ETHERNET 10/100 Base-T serial data connection.
The communication protocol supports a web interface.
Some standard scenarios are described below:

5.7.1 Ethernet Port for Network Connection (Standard Network Cable)


The Ethernet port is designed for CXC connection to a user supplied network (TCP/IP secured by user) via a front
panel RJ-45 jack. Connect to the Cordex shelf using a standard network cable.

5.7.2 Ethernet Port for Local Connection (Crossover Cable)


Local access (e.g. laptop computer) is also possible from the Ethernet port connection using a standard network
crossover cable.

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 27 of 33
6 System Startup
Visually inspect the installation thoroughly.
After completing the system installation and power system wiring, perform the following startup and test
procedure to ensure proper operation:

6.1 Check System Connections


• Ensure ac is off, battery is disconnected, and all power modules are removed from the shelf.
• Triple-check the polarity of all connections.

6.2 Verify AC and Power the Rectifier Shelf


• Install one power module.
• Verify ac input voltage is correct and turn on the corresponding feeder breaker.
• The power module OK LED should illuminate after a preset start delay.
• Using the CXC, test functionality of various module alarms and controls.

6.3 Check Battery Polarity and Connect


• Verify correct battery polarity using a voltmeter (ensuring no cells or batteries are reversed).
• Connect battery as required to the output of the system.
• Install remaining power modules.
• In the adjustments menu of the CXC, set float and equalize voltage to the levels specified by the battery
manufacturer.
• Using the CXC, test functionality of various module alarms and controls. In addition, perform a load test with
the system using a resistive load box as needed.
• Enable the temperature compensation (temp comp) feature (Batteries menu) and program the settings for
slope and breakpoints (upper and lower) with respect to the specific batteries used.

6.4 CXC Reset


The reset button located on the front panel of the optional CXC is for restarting the microprocessor. When
pressed momentarily, the unit beeps twice then resets. The front-panel LED’s will illuminate temporarily, but will
extinguish after the system has finished its 15-second self-test.
WARNING
Before removing a CXC from a live system, or performing controller maintenance, an external LVD
override is required to avoid a disruption of service.
The LVD Control functions are hardwired directly from the assigned relay output to the LVD override control and
distribution alarm card (Figure 11).
Place the LVD Control switch to the OVERRIDE IN position to keep the LVD contactor engaged.
NOTE: The single LVD Control switch will override both upper and lower tier LVD’s when placed in the OVERRIDE IN
position.
WARNING
Do not leave the switch in the OVERRIDE IN position. Doing so may result in a complete discharge
of the batteries during a power failure situation.
To allow the CXC to resume automatic control of the LVD contactor, check that the AUTO IN (green) LED is lit
confirming that the CXC will keep the LVD contactor engaged. Then you may return the LVD Control switch
to the AUTO IN position.

Canada and USA toll free 24 hour emergency technical support: +1 888 GO ARGUS (462 7487).

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 28 of 33
7 Operation

7.1 Main Rectifier States


Rectifier operation can be broken up into five main states:
1. Off,
2. Start delay,
3. Soft start,
4. Normal operation,
5. Turning off.

Each state is characterized as being distinct and necessary for the operation of the rectifier. These states are
briefly described below.

7.1.1 Off State


The rectifier will be in the Off state immediately after power is applied to the rectifier or after a rectifier shutdown.
The shutdown source may be remote or local shutdown, AC shutdown, OVP or thermal shutdown.
When the rectifier is in this state the DC-DC converter is turned off and the CXC will be monitoring its inputs for
the proper conditions to begin the start up sequence.
When the conditions have been met for the rectifier to start up, it will transition to the Start Delay state.

7.1.2 Start Delay State


When the rectifier is in the Start Delay state, the DC-DC converter is held off and still not sourcing power and is
waiting for a given amount of time before transitioning to the next state.
When in this state, the CXC continues to monitor its inputs.
After the Start Delay state the rectifier will transition to the Soft Start state.
NOTE: Soft start, or current walk-in, gradually increases the voltage and current output of the rectifier upon startup. This
is done to reduce the instantaneous load on the AC source.

7.1.3 Soft Start State


When the Soft Start state is entered, the rectifier will be turned on and the output voltage and output current will
be gradually increased. If a load is present, the rectifier will begin to source power.
When the voltage and current limit ramps have finished, the rectifier will transition to the Normal Operation state.

7.1.4 Normal Operation State


The Normal Operation state is the state that the rectifier will be in performing all of the rectifier functions and
features specified herein.
From this state, the only valid transition is to the Turning Off state. This transition will happen if the rectifier is
required to shut down.

7.1.5 Turning Off State


The Turning Off state is entered because a short delay is required before the rectifier actually turns off to take
care of any initialization requirements.
When this short delay has elapsed, a transition to the Off state is made.

7.2 Main Rectifier Modes


In addition to Main Rectifier States, there is a set of Main Rectifier Modes. These modes can be divided into two
categories as follows:

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 29 of 33
7.2.1 Output Voltage Modes
Voltage modes can be thought of as modes that, under software control, can directly adjust the output voltage.
The qualification of ‘under software control’ is made because there are processes that occur in the rectifier that
can change the output voltage that do not adjust the output voltage directly (such as the rectifier being in current
limit).
The following table lists four Output Voltage Modes and a description of when they are active:
Output Voltage Modes Active when…
Float Output voltage is set to the float voltage setting.
Equalize Output voltage is set to the equalize voltage setting.
Battery Test Output voltage is set to the battery test voltage setting.
Safe Output voltage is set to the safe mode voltage setting.

Table D–Output voltage modes

7.2.2 Output Current/Power Modes


These modes directly affect the output current and power.
The following table lists the four Output Current/Power Modes and a description of when they are active:
Output Current/Power Mode Active when…
Temperature foldback mode Output current and power limit have been reduced due to high temperature of the
heatsink or internal ambient temperature sensor.
AC foldback mode Output current and power limit have been reduced due to low AC input voltage. Note:
this will reduce the risk of tripping an AC breaker due to increased AC current draw as
the AC voltage decreases.
Short circuit foldback mode Output current limit has been reduced due to a short circuit at the output.
Internal fault foldback mode Output current limit has been reduced due to an internal fault.

Table E–Output current/power modes

7.3 Factory Ranges and Defaults


The following table lists the rectifier settings/ranges/defaults; changes are made via the CXC:
Setting Range (minimum to maximum) Default
Float (FL) Voltage 23.75 – 29.1V 27V
Equalize (EQ) Voltage 24.9 – 30.1V 27.5V
Battery Test (BT) Voltage 22 – 26V 23V
OVP See note below – 31.5V 28.5V
Current Limit (CL) 23 – 100% 100%
Power Limit (PL) 0 – 100% 100%
Module Start Delay 0 – 250s 1s
System Start Delay 0 – 600s 0s
Low Voltage Alarm (LVA) 21 – 26V 22V
High Voltage Alarm (HVA) 26 – 31.5V 27.75V
EQ Timeout 1 – 2399h 30h
BT Timeout 1 – 250h 8h
Softstart Ramp-rate Normal/Fast Normal
CL/PL Alarm Enable/Disable Enable
Remote Shutdown Enable/Disable Enable
Ramp Test Enable/Disable Enable

Table F–Cordex 24-3.1kW factory ranges and defaults


NOTE: OVP cannot be set below the present system/FL/EQ/BT voltage setting or the safe mode voltage of 25.7V.

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 30 of 33
8 Maintenance
Although very little maintenance is required with Argus systems, routine checks and adjustments are
recommended to ensure optimum system performance. Qualified service personnel should do repairs.
The following table lists a few maintenance procedures for this system. These procedures should be performed at
least once a year.
WARNING: HIGH VOLTAGE AND SHOCK HAZARD.
Use extreme care when working inside the unit while the system is energized.
Do not make contact with live components or parts.
Circuit cards, including RAM chips, can be damaged by static electricity. Always wear a grounded
wrist strap when handling or installing circuit cards.
Ensure redundant modules or batteries are used to eliminate the threat of service interruptions
while performing maintenance on the system’s alarms and control settings.
Procedure Date Completed
Clean ventilation openings
Inspect all system connections (re-torque as necessary)
Verify alarm/control settings
Verify alarm relay operation

Table G–Sample maintenance log

8.1 Fan Replacement

Figure 14–Fan replacement

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 31 of 33
1. Shut off the unit and unscrew the front fastener that secures the power module to the shelf.
2. Slide the module 10 cm (4”) out of the shelf and wait two minutes for module capacitors to discharge.
3. Remove the four screws (two each side) that secure the front panel to the module chassis.
4. Slide the front panel out.
5. Disconnect the fan power lead wires (one set per fan) and front panel ribbon cable from the module.
6. Remove the screws that secure the fans to the front panel.
7. Note the direction of airflow and remove the fans from the front panel.
8. Install the replacement fans following the preceding steps in reverse order.

8.2 MOV Replacement

Figure 15–MOV replacement


The MOVs (metal oxide varistor) are used to protect the power modules from power line surges and the surges
caused by lightning strikes. High capacity surges may permanently damage MOVs but they are easily replaced in
the field using the following procedure:
1. Shut off the unit and unscrew the front fastener that secures the power module to the shelf.
2. Slide the module 10 cm (4”) out of the shelf and wait two minutes for module capacitors to discharge.
3. Turn the module around to face the back of the unit and remove the one screw (module bottom toward the
rear) securing the MOV cover.
4. Remove the cover and locate the MOV printed circuit board (PCB).
5. Remove the three screws that secure the MOV PCB.
6. Decontaminate the area and unit with flux remover or a similar cleaning compound. This is to remove any
metallic particles or carbon, which may have been deposited when the MOV failed.
7. Install the replacement MOV PCB following the preceding steps in reverse order.

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 32 of 33
9 Argus Conventions

9.1 Numbering System


Argus Technologies uses an eight-digit drawing number system, which is broken into three blocks. The first three
digits describe the category of the product; e.g., rectifier or fuse panel. The next three digits indicate the sequence
in which the product number was allocated in a particular category. The last two digits indicate the type of
drawing, for example:
“-05” Schematic
“-06” Outline Drawing
“-20” Main Assembly
Argus uses an eight-digit part numbering system for all components and sub assemblies. Each part is covered by
its own unique number. Due to the quantity, categories will not be listed within this manual.

9.2 Acronyms and Definitions


AC Alternating current
ANSI American National Standards Institute
AWG American Wire Gauge
BTU British thermal unit
CAN Controller area network
CEC Canadian Electrical Code
CSA Canadian Standards Association
CX Cordex™ series; e.g., CXC for Cordex System Controller
DC Direct current
DHCP Dynamic Host Configuration Protocol
EIA Electronic Industries Alliance
EMC Electromagnetic compatibility
EMI Electromagnetic interference
ERM Electromagnetic Compatibility and Radio Spectrum Matters
ESD Electrostatic Discharge
FCC Federal Communications Commission (for the USA)
GSM Group Speciale Mobile (global system for mobile communications)
HVSD High voltage shutdown
IEC International Electrotechnical Commission
IEEE Institute of Electrical and Electronics Engineers
IP Internet Protocol
LED Light emitting diode
LVD Low voltage disconnect
MIL One thousandth of an inch; used in expressing wire cross sectional area
MOV Metal oxide varistor
MTBF Mean time between failures
NC Normally closed
NEC National Electrical Code (for the USA)
NO Normally open
OSHA Occupational Safety & Health Administration
OVP Over voltage protection
RAM Random access memory
RU Rack unit (1.75”)
TCP/IP Transmission Control Protocol / Internet Protocol
THD Total harmonic distortion
UL Underwriters Laboratories
VRLA Valve regulated lead acid

Argus Technologies Ltd. 053-390-C0 Rev A WC


Printed in Canada. © 2007 Argus Technologies Ltd. ARGUS and CORDEX are trademarks of Argus Technologies Ltd. All Rights Reserved. Page 33 of 33
REVISIONS
LTR DESCRIPTION REV BY DATE APPD

18.8 477.13

018-574-20 7.3 186.30

29.710 754.63
020-419-20
27.735 704.47

24.235 615.57

21.235 539.37

17.235 437.77

13.735 348.87

10.235 259.97

7.235 183.77

3.235 82.17
0.235 5.97
0

22.312 566.73 6.0 153.10


23.000 584.21

THESE DESIGNS AND SPECIFICATIONS ARE THE PROPERTY OF


030-736-20 ARGUS TECHNOLOGIES AND SHALL NOT BE COPIED OR USED
FOR MANUFACTURING WITHOUT ITS WRITTEN CONSENT.

DESIGN BK 2007/06 MATERIAL


DRAWN RP 2007/06 SEE B.O.M.

010-572-20 CHECKED
APPROVED
RP
GS
2007/06
2007/06 FINISH
TOLERANCES PER P.O. and
[X] 1mm Doc. 070-024-83
CXPS 24-2T X.X
X.XX
0.04"
0.02" [X.X] 0.5mm

BASE SYSTEM CONFIGURATION 053-390-20-000 SHOWN X.XXX 0.01" [X.XX] 0.25mm SCALE NTS
TITLE
(INCLUDES 23" MOUNTING BRACKETS) OUTLINE, CXPS 24-2T
CORDEX POWER SYSTEM
O
c 2005 ARGUS TECHNOLOGIES ISSUE
SHEET 1 OF 2
DATE
DIMENSIONS ARE IN INCHES WITH METRIC (mm) IN BRACKETS: INCHES [mm] SIZE TYPE DWG NO. REV
B D2 053-390-06 A
REVISIONS
LTR DESCRIPTION REV BY DATE APPD

20.3 516.70
018-574-20
020-419-20
018-574-20

020-419-20

20.3 516.70

40.5 1028.70

84.0 2133.60

030-736-20

030-736-20

030-694-20

010-572-20

31.6 802.64 23.6 599.44 28.6 726.44


010-572-20

8.0 203.20

11.0 279.40
25.6 649.27 19.8 502.19 16.5 419.10 7.0 177.80
CXPS 24-2T
SYSTEM CONFIGURATION 053-390-20-010 SHOWN
(INCLUDES 1/2 HEIGHT RACK (030-694-20))
THESE DESIGNS AND SPECIFICATIONS ARE THE PROPERTY OF
ARGUS TECHNOLOGIES AND SHALL NOT BE COPIED OR USED
FOR MANUFACTURING WITHOUT ITS WRITTEN CONSENT.

SCALE NTS
TITLE

11.3 286.29 OUTLINE, CXPS 24-2T


030-638-20 CORDEX POWER SYSTEM
CXPS 24-2T
SYSTEM CONFIGURATION 053-390-20-020 SHOWN c 2006 ARGUS TECHNOLOGIES
ISSUE
DATE
SHEET 2 OF 2
(INCLUDES 7 FT SEISMIC RACK (030-638-20)) SIZE TYPE DWG NO. REV
DIMENSIONS ARE IN INCHES WITH METRIC (mm) IN BRACKETS: INCHES [mm] B D2 053-390-06 A
REVISIONS
LTR DESCRIPTION REV BY DATE APPD

BATTERY RETURN
4 X 3/8"-16 HARDWARE ON 1" CENTERS
SITE GROUND
BATTERY HOT 1 X 3/8"-16 HARDWARE
4 X 3/8"-16 HARDWARE ON 1" CENTERS ON 1" CENTER

CIRCUIT BREAKER
RETURNS
1/4"-20 HARDWARE
ON 5/8" CENTERS

CIRCUIT BREAKER
OUTPUTS
1/4"-20 HARDWARE
ON 5/8" CENTERS

SEE DETAIL D
SEE DETAIL A (SHT2)

SEE DETAIL C 037-163-20 JUMPER KIT


(SHT2) REMOVE WHEN USING FOR 48V DISTRIBUTION WITH OPTIONAL CONVERTORS

SEE DETAIL B DETAIL A


(SHT3)
(DOOR NOT SHOWN)
TOP TIER E/W 20 POS'N "AM" BREAKER MODULE W/600A LVD THESE DESIGNS AND SPECIFICATIONS ARE THE PROPERTY OF

BOTTOM TIER E/W 8/10 SPLIT POS'N "AM" BREAKER MODULE W/600A LVD ARGUS TECHNOLOGIES AND SHALL NOT BE COPIED OR USED
FOR MANUFACTURING WITHOUT ITS WRITTEN CONSENT.

DESIGN BK 2007/06 MATERIAL


DRAWN RP 2007/06 SEE B.O.M.
CHECKED RP 2007/06

053-390-20-000 APPROVED GS 2007/06 FINISH


PER P.O. and
TOLERANCES
O
c 2005 ARGUS TECHNOLOGIES X.X
X.XX
0.04"
0.02"
[X]
[X.X]
1mm
0.5mm
Doc. 070-024-83
X.XXX 0.01" [X.XX] 0.25mm SCALE NTS
PART IDENTIFICATION TITLE
This part must be identified in accordance CONNECTION, CXPS 24-2T
with Argus document #071-014-10 by: CORDEX POWER SYSTEM
STAMPING TAGGING PEN LABELING
PART BOX PART
ISSUE
DATE
SHEET 1 OF 3
DIMENSIONS ARE IN INCHES WITH METRIC (mm) IN BRACKETS: INCHES [mm] SIZE TYPE DWG NO. REV
X B D2 053-390-08 A
REVISIONS
LTR DESCRIPTION REV BY DATE APPD

COMMON
F1

F2
F1
F2
F3
CXCM4 INTERFACE F3
CONNECTIONS F4
F4
F5
F5

COMMON
F6

F7
F6
F8 F7
F8
F9 F9
F10
F10

DETAIL C DETAIL D
CXCM4 I/O PCB GMT FUSE PCB THESE DESIGNS AND SPECIFICATIONS ARE THE PROPERTY OF
ARGUS TECHNOLOGIES AND SHALL NOT BE COPIED OR USED
FOR MANUFACTURING WITHOUT ITS WRITTEN CONSENT.

SCALE NTS
TITLE

CONNECTION, CXPS 24-2T


CORDEX POWER SYSTEM
c 2006 ARGUS TECHNOLOGIES
ISSUE
DATE
SHEET 2 OF 3
SIZE TYPE DWG NO. REV
DIMENSIONS ARE IN INCHES WITH METRIC (mm) IN BRACKETS: INCHES [mm] B D2 053-390-08 A
REVISIONS
LTR DESCRIPTION REV BY DATE APPD

THESE DESIGNS AND SPECIFICATIONS ARE THE PROPERTY OF


ARGUS TECHNOLOGIES AND SHALL NOT BE COPIED OR USED
FOR MANUFACTURING WITHOUT ITS WRITTEN CONSENT.

SCALE NTS
DETAIL B TITLE

030-736-20 SHELF WIRING CONNECTION, CXPS 24-2T


CORDEX POWER SYSTEM
c 2006 ARGUS TECHNOLOGIES
ISSUE
DATE
SHEET 3 OF 3
SIZE TYPE DWG NO. REV
DIMENSIONS ARE IN INCHES WITH METRIC (mm) IN BRACKETS: INCHES [mm] B D2 053-390-08 A
FACTORY SERVICE INFORMATION
Technical Support Factory Service Centers
Canada and International
Technical support staff are available for answering general questions related to installation, operation Argus Technologies Ltd.
and maintenance of Argus products. In Canada and the USA, call Argus toll free 7:30 am to 5:00 pm ATTN: RMA Returns
7033 Antrim Avenue
Pacific Standard Time at: Burnaby, BC, V5J 4M5 Canada
Tel: +1 604 436 5900
Fax: +1 604 436 1233
+1-888 GO ARGUS Email:
USA
returns@argusdcpower.com

(+1-888-462-7487) Argus Technologies Inc.


ATTN: RMA Returns
3116 Mercer Avenue
For emergencies, call +1-888-GO-ARGUS 24 hours a day, seven days a week. Bellingham, WA, 98225 USA
Customers outside Canada and the USA, call +1-604-436-5547 for technical support. Tel: +1-360 756 4904
Fax: +1-360 647 0498
Email: returns-usa@argusdcpower.com
Asia-Pacific
PCM Electronics (Dong Guan) Co., Ltd.
Training Hongli Industrial Area, Miaobian, Liaobu Town,
Argus offers various levels of product and technical training. These workshops provide a mix of Dongguan City, Guangdong Province,
523400 China
theory and hands on application for qualified customers. Please consult your sales representative for Tel: +86 755 8895 3310
course schedules, locations and costs, or visit our website at www.argusdcpower.com. Fax: +86 755 8895 3307
Authorized Service Center
Argentina
Argus Technologies de Argentina
Belen 315, Capital Federal, Buenos Aires,
Factory Repair and Servicing 1407l Argentina
All service, beyond initial adjustments, should be carried out by qualified factory service personnel. Tel: +54 (11) 4672 4821
Fax: +54 (11) 4504 4698
For these procedures, please contact Argus Technologies at the locations listed to the right. Cell: +54 9 (11) 4993 9996
Email: lkleiman@argus.ca
Asia
Argus Technologies Asia Pte Ltd
Product Returns Blk 6 Tagore Lane #160
Singapore 787570
Before returning any product for service, please obtain a Return Material Authorization (RMA) number Tel: +65 6458 8900
from an Argus factory service representative. The representative will require the model and serial Fax: +65 6458 2122
number, as well as a brief description of the problem prior to issuing the RMA number. All material Australia
must be pre-authorized before being returned. CPS National
8/376 Newbridge Rd
See document 048-507-10 “Warranty and Repair Information” for more details. Moorebank, NSW, 2170 Australia
Tel: +61 02 9822 8977
Fax: +61 02 9822 8077
Australia/New Zealand
Moving and Storage Alpha Power Systems Pty Ltd
Unit 3, 30 Heathcote Road
Units must be suitably packed in the original shipping container (or equivalent) prior to re-shipping. Moorebank, NSW, 2170 Australia
The box should be completely enclosed and constructed of wood or double-wall, corrugated Tel: +61 02 9602 8331
Fax: +61 02 9602 9180
cardboard. At least 3” of foam or shock absorbing packing material must surround the unit.
Canada
Compower Systems Inc.
118 Tiffield Road
Toronto, ON, M1V 5N2 Canada
Tel: +1 416 293 3088
Fax: +1 416 293 0671
Europe
Alpha Technologies Europe Ltd.
Cartel Business Estate
Edinburgh Way
Harlow, Essex, CM20 2DU UK
Tel: +44 1279 422110
Fax: +44 1279 423355
Mexico & Central America
Technologies Argus First De Mexico SA de CV
Anatole France No. 17
Col. Polanco
Mexico City, 11560 Mexico
Tel: +52 55 5280 6990
Fax: +52 55 5280 6585
South America
Argus Technologies Argentina
Santo Tome 2573, Capital Federal
Buenos Aires, 1416 Argentina
Tel: +54 11 4504 4698
Cell: +54 9 11 4993 9996
E-pager: 541149939996@nextel.net.ar
Turkey
IPC Enerji Elk San ve TIC AS
Inonu cad. Kanarya sok. No:20
Yenisahra - Kadikoy
Istanbul, Turkey
Tel: +90 216 317 41 42
Fax: +90 216 472 90 66

048-527-10-I1 Rev K (08/2007)

Canada and USA toll free 24 hour emergency technical support: +1 888 GO ARGUS (462 7487) Outside North America: +1 604 436 5547

Potrebbero piacerti anche