Sei sulla pagina 1di 19

CS-OHS-32

(11/05)

CS ENERGY PROCEDURE FOR

MAINTENANCE AND TESTING OF ENTITY WORKS, ELECTRICAL


INSTALLATIONS AND ELECTRICAL EQUIPMENT
CS-OHS-32
Responsible Officer: Health and Safety Manager

Approved: General Manager Operations

Contents
1.0 Purpose....................................................................................................................2
2.0 Scope .......................................................................................................................2
3.0 Definitions ................................................................................................................2
4.0 Maintaining Entity Works ..........................................................................................3
4.1 General .................................................................................................................3
4.2 Safety and clearance requirements design/construction/maintenance work ....... 3
4.3 Earthing and protection .........................................................................................4
4.4 Construction or excavation work in proximity to overhead or underground
electrical lines .................................................................................................................4
4.5
Vegetation Management ......................................................................................4
5.0 Maintaining Electrical Installation/Equipment Requirements ..................................... 5
5.1 General .................................................................................................................5
5.2 Electrical Contractor Licensee...............................................................................6
6.0 Specific AS/NZS 3000 Testing .................................................................................6
6.1 Earth Resistance Test (Test 3)..............................................................................6
6.2 Equipotential Bonding Conductor Test (Test 4) .....................................................8
6.2 Fault Loop Impedance Test (Test 8) .....................................................................8
6.3 Inspection and maintenance of integrity of insulation ............................................ 9
7.0 Recording Inspections and Testing ..........................................................................9
7.1 General .................................................................................................................9
8.0 Legislative and CS Energy References ....................................................................9
9.0 Associated Documentation .....................................................................................10
Attachment 1 Visual Inspection Check Sheets ........................................................... 11
Attachment 2 Electrical Tests Check Sheet ............................................................... 17
Attachment 3 Electrical Installation/Electrical Equipment Certificate of Testing and
Compliance ..................................................................................................................19
Issue Date
08/11/2005

Nature of Changes
Original Issue

C:\Documents and Settings\lwhite\Local Settings\Application Data\TOWER Software\TRIM5\TEMP\CONTEXT.5048\B D 11 30958


Procedure - H&S - CS-OHS-32 - Maintenance and Testing of Entity Works, Electrical ~ CS Energy Registered.DOC

THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT

Page: 1 of 19

1.0

Purpose

The purpose of this procedure is to detail specific electrical entity, installation and
equipment compliance, inspection, testing and maintenance requirements. The procedure
provides guidance and check sheets that are to be used to document the inspection and
testing of modified or new electrical installations and provide evidence of compliance with
AS/NZS 3000 Electrical Installations and AS301 Electrical Installations Testing and
Inspection Guidelines.

2.0

Scope

This procedure is applicable to all electrical installations and equipment that are part of CS
Energy Power Stations and workplaces, and all CS Energy employees and any other
persons working at these locations.
This Procedure is to be used in conjunction with Power Station specific Modification
Procedures and AS/NZS 3000, Section 6 requirements.
This Procedure does not address the specific inspection and testing frequencies of
portable electrical equipment or the inspection and testing frequencies of residual current
devices. Refer to CS Energys Maintenance and Testing of Portable Electrical Equipment,
RCDs and Tools procedure.

3.0

Definitions

Electrical contractor licensee


is a person nominated on CS Energys Electrical Contractors License responsible for
inspection and testing of electrical installations.
Electrical equipment
is any apparatus, appliance, cable, conductor, fitting, insulator, material, meter or
wire:

used for controlling, generating, supplying, transforming or transmitting


electricity at a voltage greater than extra low voltage, or

operated by electricity at a voltage greater than extra low voltage, or

that is, or that forms part of, a cathodic protection system.

Note:

electrical equipment does not include any apparatus, appliance, cable, conductor, fitting,
insulator, material, meter or wire forming part of a vehicle if
it forms part of a unit of the vehicle that provides propulsion for the vehicle, or

its source of electricity is a unit of the vehicle that provides propulsion for the vehicle.

Electrical installation
is a group of items of electrical equipment, if:

all the items are permanently electrically connected together, and

the items do not include items that are works of an electricity entity, and

electricity can be supplied to the group from the works of an electricity entity or
from a generating source.

Note:

an item of electrical equipment can be part of more than 1 electrical installation and for
item one above:
an item of electrical equipment connected to electricity by a plug and socket is not
permanently electrically connected, and

connection achieved through using works of an electricity entity must not be taken
into consideration for deciding whether items of electrical equipment are
electrically connected.

C:\Documents and Settings\lwhite\Local


Settings\Application Data\TOWER
Software\TRIM5\TEMP\CONTEXT.5048\B D 11
30958 Procedure - H&S - CS-OHS-32 - Maintenance
and Testing of Entity Works, Electrical ~ CS Energy
Registered.DOC

[Document no]

Page: 2 of 19

Modification procedures
are procedures, established at each CS Energy Power Station, that detail specific
process, documentation and approval requirements for undertaking modifications to
plant and equipment.
Residual current device (RCD)
a mechanical switching device designed to make, carry and break currents under
normal service conditions and to cause the opening of the contacts when the
residual current attains a given value under specified conditions.
Works of an electricity entity (entity works)
means the electrical equipment, and electric line associated equipment, controlled or
operated by the entity to generate, transform, transmit of supply electricity.
Note:

4.0

electrical equipment for circulating water pumps, conveyors, chemical plant,


etc on site are works of an electricity entity, whereas appliances or fixed
wiring in an electricity entitys workshop or office areas is not

Maintaining Entity Works

4.1
General
CS Energy entity works, electrical installations, electrical equipment and associated
equipment essential to generate and supply electricity:

are to be electrically safe, and

are to be operated in a way that is electrically safe.

The requirements for maintaining electrical installations as detailed in this procedure and
the specific requirements as detailed in the Electrical Safety Regulation Part 7: Works of
an Electricity Entity, are to be complied with. Provisions within this procedure address the
following:

Electric lines and control cables,

Clearance of overhead electric lines from ground,

Clearance of overhead electric lines from structures,

Building or adding to structure near electric line,

Maintenance of works,

Maintenance of integrity of insulation, and

Trimming of trees near overhead electric line.

4.2

Safety and clearance requirements design/construction/maintenance


work
CS Energy entity works, electrical installations, electrical equipment and associated
equipment essential to generate and supply electricity are to:

be designed, constructed and maintained to ensure they are electrically safe,

be operated in a way that is electrically safe,

meet thermal capacity to pass the electrical load for which they are designed,

have the capacity to pass short circuit currents to allow protective devices to operate
correctly,

have enough mechanical strength to withstand anticipated mechanical stresses


caused by environmental, construction or electrical service conditions,

C:\Documents and Settings\lwhite\Local Settings\Application Data\TOWER Software\TRIM5\TEMP\CONTEXT.5048\B D 11 30958


Procedure - H&S - CS-OHS-32 - Maintenance and Testing of Entity Works, Electrical ~ CS Energy Registered.DOC

THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT

Page: 3 of 19

restrict unauthorised access by persons to live exposed parts.

CS Energy power station sites must ensure the design, construction, operation and
maintenance records necessary for the electrical safety of the works are be kept in an
accessible form. Electrical equipment must undergo commissioning tests to verify the
equipment is suitable for service and can be operated safely when initially installed or
altered. Labels are to clearly identify parts of the works whose identity or purpose is not
obvious and are to be updated after any changes are made.
Lines and cables are to be maintained so that clearances from the ground/roads and
structures for low and high voltage cables are in accordance with the requirements of the
Electrical Safety Regulations Schedule 4 and 5.
4.3
Earthing and protection
Each power station site is to incorporate and maintain an earthing and protection system
(to stop, as far as is practicable, a person suffering electric shock) capable of the
following:

Reliable passage of fault current and operation of circuit protection devices,

Safe step, touch and transfer potentials for all electrical equipment,

Appropriate coordination with the earthing and protection systems of other


entities,

Protection against likely mechanical damage, inadvertent interference and


chemical deterioration,

Mechanical stability and integrity of connections,

Effective earthing of neutral conductors (MEN system), and

Earthing of each non current carrying exposed conductive part of the


generating plant

4.4

Construction or excavation work in proximity to overhead or underground


electrical lines
Where building, construction or excavation work is proposed to be done, or a change to a
building or structure is to occur within the clearance requirements for overhead or
underground cables (exclusion zones) a Permit to Work/Permit to Dig or Access Permit is
to be obtained by the OIC for the work from CS Energy. The Permit is to outline the
measures taken to protect workers and the electrical works while the activities are being
performed and to ensure the requirements for exclusion zones are complied with.
4.5
Vegetation Management
Vegetation management is to be taken into account for trees and shrubs that are located
at CS Energy Power Station sites and within close proximity of any overhead power lines
associated with adjoining switchyards. Vegetation growth and work on or near the
vegetation is to be monitored so that at any time, the growth of the trees or shrubs and/or
a part of any persons body or anything they are holding or that is attached to their body, or
anything they are using - in association with the vegetation - does not come within the
exclusion zones.

A person is not to undertake tree trimming or vegetation management where any


part of the tree or vegetation to be treated or cut or otherwise worked with is within
the exclusion zones.

A person should not undertake tree trimming or vegetation management where


any part of the tree or vegetation could fall or otherwise be carried within the safe
approach distances.

A formal documented inspection is to be undertaken of all site vegetation every six


months to check if growth is within the exclusion zones.

C:\Documents and Settings\lwhite\Local Settings\Application Data\TOWER Software\TRIM5\TEMP\CONTEXT.5048\B D 11 30958


Procedure - H&S - CS-OHS-32 - Maintenance and Testing of Entity Works, Electrical ~ CS Energy Registered.DOC

THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT

Page: 4 of 19

A Permit to Work is required for any work on or near vegetation that may be within
the exclusion zones.

Hazard Identification: before carrying out any vegetation management work, a JSEA is
required to identify potential hazards and suitable control measures. Hazards to be
considered include, but are not limited to, the following:

Proximity of vegetation and proposed work activity to electric lines (e.g. if the
vegetation involved is located within exclusion zones).

The vegetation or part of the vegetation may fall or otherwise be carried into the
area within exclusion zones.

Carrying out the task would cause a person or anything a person may be holding,
or in contact with, to intrude into exclusion zones.

Wind causing intermittent encroachment of vegetation into the exclusion zone or


wet weather making the situation more dangerous.

Fires and smoke associated with the vegetation may cause trips or damage to the
overhead wires, towers and insulators.

Operational characteristics of equipment eg length of boom and speed of


movement of an elevating work platform (EWP). Some examples of operational
characteristics that may present a hazard are: knuckle boom EWPs where
convenient placement of the basket can have part of the boom intruding into
roadways or other hazardous areas;

Cutting equipment such as chain saws, which may "kick back", causing equipment
to move inadvertently; or

Site conditions such as weather (wind), terrain, vehicular and other traffic. For
example, heavy traffic on an adjacent roadway could prevent safe access to
vegetation.

5.0

Maintaining Electrical Installation/Equipment Requirements

5.1
General
A licensed electrical worker who performs electrical work on an electrical installation or
electrical equipment is to ensure that the installation or equipment, to the extent it is
affected by the electrical work, is in accordance with AS/NZS 3000 Electrical
Installations.
Where CS Energy, as a holder of an electrical contractor license, engages contracted
electrical workers to perform such work, CS Energy must ensure the electrical installation
or equipment complies with AS/NZS 3000 by:

ensuring that only licensed electrical contractors perform such work, and

ensuring that test certificates are received stating that the electrical
installation or equipment satisfies AS/ZNS 3000 requirements.

Persons in control of low voltage electrical installations at each Power Station are not to
allow the earthing for the installations to be inconsistent with the earthing system
requirements for the entity works.
A modification officer or equivalent, as defined within the site Power Station specific Plant
Modification Procedure is to ensure:

that a competent electrician or electrical engineer designs the new or


modified electrical installation or equipment,

that the Electrical Contractor Licensee documents the inspections and


tests required by this procedure, and

C:\Documents and Settings\lwhite\Local Settings\Application Data\TOWER Software\TRIM5\TEMP\CONTEXT.5048\B D 11 30958


Procedure - H&S - CS-OHS-32 - Maintenance and Testing of Entity Works, Electrical ~ CS Energy Registered.DOC

THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT

Page: 5 of 19

5.2

the resulting inspection and test documentation is filed within the


relevant modification and or maintenance site file.

Electrical Contractor Licensee

The Electrical Contractor Licensee is to inspect and test the electrical installation and
ensure compliance to AS/NZS 3000 where modification work has been performed. The
Electrical Contractor Licensee may allow another competent electrician to perform the
inspection and tests, providing the Licensee coordinates such tasks and also endorses
the result sheets.
Note: If the work is maintenance work (i.e. removal and replacement of a motor) the maintenance electrical
worker is to ensure compliance and sign the test certificate. No further signature is required by the Licensee.

The requirements to ensure for visual inspection in accordance with AS/NZS 3000,
Section 6.2.2, are summarised in Attachment 1 Visual Inspection Check Sheet.
The requirements for tests on the installation are to be in accordance with AS/NZS 3000,
Section 6.3, and are summarised in Attachment 2 Electrical Tests Check Sheet. Test
methods are further defined in AS/NZS 3017 and the sequence of electrical testing is
described in the Flow Chart below.
Chart 5.2 Electrical Testing Flow Chart
1. Earth Resistance Test
Continuity of Main Earthing
Conductor

2. Insulation Resistance Test of


Installation

3. & 4. Earth Resistance Test for


Other Earthed and Equipotential
Bonded Parts

5. Consumers Mains Test


Polarity

6. Sub-mains Tests Polarity

7. Final Sub-circuit Test Polarity


8. Final Sub-circuit Test
Connections

9. Fault Loop Impedance Test

6.0

10. Verification of Operation of


Residual Current devices

Specific AS/NZS 3000 Testing

6.1
Earth Resistance Test (Test 3)
As AS/NZS 3000 does not specifically state a required impedance limit for earth
conductors other than the main earth, the following method based on the required fault
loop impedance is to be used. This method is derived from Appendix B of AS/NZS 3000.
The disconnection time required for each protective device is to be determined.
230/240 Volts, AS/NZS 3000, Section 1.7.4.3.4 requires these to be:

C:\Documents and Settings\lwhite\Local Settings\Application Data\TOWER Software\TRIM5\TEMP\CONTEXT.5048\B D 11 30958


Procedure - H&S - CS-OHS-32 - Maintenance and Testing of Entity Works, Electrical ~ CS Energy Registered.DOC

THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT

For

Page: 6 of 19

0.4 seconds for socket outlets <63A, hand held Class I equipment, and
portable equipment intended for manual movement during use

5 seconds for sub-main and final sub-circuits supplying fixed or


stationary equipment.

The circuit breaker type or fuse type and rating are to be determined.
The following table is to be used to determine the required value of earth resistance (for
415/240 volts only). This can then be used as the pass criteria for the test method of
protective earthing conductors in AS/NZS 3017.
Earth Resistance Testing Test 3
Conductor Size

Protective
Device
Rating

Circuit Breakers
Type B

Type C

Fuses

Type D

Disconnection Times
Active

Earth

0.4 s

0.4 s

5s

mm2

mm2

3.96

2.12

1.28

4.75

5.14

10

2.38

1.28

0.77

2.66

3.08

1.5

1.5

10

2.28

1.22

0.73

2.53

2.94

1.5

1.5

16

1.43

0.76

0.46

1.22

1.66

2.5

2.5

16

1.30

0.69

0.42

1.11

1.51

2.5

2.5

20

1.04

0.55

0.33

0.76

1.05

2.5

25

1.03

0.55

0.33

0.73

1.03

2.5

32

0.80

0.42

0.25

0.57

0.82

2.5

40

0.73

0.39

0.24

0.49

0.69

10

50

0.59

0.31

0.19

0.37

0.55

16

63

0.48

0.26

0.15

0.29

0.43

16

80

0.38

0.20

0.12

0.20

0.30

25

80

0.42

0.22

0.14

0.22

0.34

25

100

0.33

0.18

0.11

0.16

0.26

35

10

100

0.32

0.17

0.10

0.15

0.25

35

10

125

0.26

0.14

0.08

0.12

0.19

50

16

125

0.25

0.13

0.08

0.11

0.18

50

16

160

0.20

0.10

0.06

0.09

0.15

70

25

160

0.19

0.10

0.06

0.09

0.15

70

25

200

0.15

0.08

0.05

0.07

0.10

Maximum Protective Earth Impedance

C:\Documents and Settings\lwhite\Local Settings\Application Data\TOWER Software\TRIM5\TEMP\CONTEXT.5048\B D 11 30958


Procedure - H&S - CS-OHS-32 - Maintenance and Testing of Entity Works, Electrical ~ CS Energy Registered.DOC

THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT

Page: 7 of 19

6.2
Equipotential Bonding Conductor Test (Test 4)
The following table below is to be used as part of equipotential bonding conductor testing.
Equipotential Bonding Conductor Test 4
Required Resistance

Equipotential Bonding - mm2


(AS/NZS 3000 Section 5.8.3.2)
1

Multiply length (m) of cable by 0.0233 (/m)

1.5

Multiply length (m) of cable by 0.0149 (/m)

2.5

Multiply length (m) of cable by 0.00814 (/m)

4 other than consumer mains


support

Multiply length (m) of cable by 0.00506 (/m)

Consumer mains support

Refer to AS/NZS 3000 5.8.3.2 (c) and calculate required


resistance from conductor tables in AS/NZS 3008

6.2
Fault Loop Impedance Test (Test 8)
The maximum allowed fault loop impedance for 230/240 volts (400/415 volts 3 phase) is
defined in Table B 4.1 of AS/NZS 3000 and listed in the following table. Other voltage
levels require design calculations in accordance with AS/NZS 3000, Section 5.
The following table below is to be used as part of fault loop impedance testing.
Maximum Values of Fault Loop Impedance (Zs)
Protective Device
Rating

Circuit Breakers
Type B

Type C

Fuses
Type D

Disconnection Times
0.4 s
A

0.4 s

5s

Maximum Fault Loop Impedance Zs

9.58

5.11

3.07

11.5

15.33

10

5.75

3.07

1.84

6.39

9.20

16

3.59

1.92

1.15

3.07

5.00

20

2.88

1.53

0.92

2.09

3.59

25

2.3

1.23

0.74

1.64

2.71

32

1.8

0.96

0.58

1.28

2.19

40

1.44

0.77

0.46

0.96

1.64

50

1.15

0.61

0.37

0.72

1.28

63

0.91

0.49

0.29

0.55

0.94

80

0.72

0.38

0.23

0.38

0.68

100

0.58

0.31

0.18

0.27

0.48

125

0.46

0.25

0.15

0.21

0.43

160

0.36

0.19

0.12

0.16

0.30

200

0.29

0.15

0.09

0.13

0.23

C:\Documents and Settings\lwhite\Local Settings\Application Data\TOWER Software\TRIM5\TEMP\CONTEXT.5048\B D 11 30958


Procedure - H&S - CS-OHS-32 - Maintenance and Testing of Entity Works, Electrical ~ CS Energy Registered.DOC

THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT

Page: 8 of 19

6.3
Inspection and maintenance of integrity of insulation
The integrity of the insulation of an electric line forming part of the power station site
electrical works (entity works) is to be inspected and maintained at periodic intervals. The
person performing the inspections and maintenance work is to check the integrity of the
electrical insulation where the line:

forms parts of the entity works,

is adjacent to a roof or structure, and

is in a position where it is likely that a person could come into contact with the
line (eg. cooling tower fan motor cables, EFP motor cables, ID fan motor
cables, persons painting near cables, sections of conduit from underground
cables to electric motors, sections of cable trays that are accessible).

Maintenance practices are to include visual inspections and megger testing of cables at
regular intervals such as during an overhaul. A compliant testing and maintenance
routine/plan is to be implemented in SAP to reflect this requirement.

7.0

Recording Inspections and Testing

7.1
General
The person performing the tests is to use the check sheets provided in Attachments 1 & 2.
Site-specific check sheets may also be utilised (e.g. for each motor, incomer, feeder etc.
for the 440V system).
Once the inspection and testing tasks are completed, the Electrical Contractor Licensee is
to sign the Certificate of Testing and Compliance a certificate is provided in Attachment
3.
Power Station specific cable schedule records are to be updated as appropriate and
circuit schedules on switchboards are to be updated in a legible way. Consideration is to
be given to re-typing circuit schedules on switchboards where a number of modifications
have been made.
The certificate of testing and compliance is to be filed in the site CS Energy file for that
particular modification and/or in the site maintenance files.
Note: a second copy of the certificate may be stored in the sites central register for audit
purposes.

8.0

Legislative and CS Energy References

QLD Electrical Safety Act 2002


QLD Electrical Safety Regulation 2002
AS/NZS 3000 Electrical Installations
AS/NZS 3008 Electrical Installations: Selection of Cables
AS/NZS 3017 Electrical Installations: Testing Guidelines
AS/NZS 3760 In-service Safety Inspection and Testing of Electrical Equipment
CS Energy Electrical Safety Procedure
CS Energy Maintenance of Electrical Safety Equipment and Clothing (PPE) Procedure
CS Energy Site-specific Plant Modifications Procedure

C:\Documents and Settings\lwhite\Local Settings\Application Data\TOWER Software\TRIM5\TEMP\CONTEXT.5048\B D 11 30958


Procedure - H&S - CS-OHS-32 - Maintenance and Testing of Entity Works, Electrical ~ CS Energy Registered.DOC

THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT

Page: 9 of 19

9.0

Associated Documentation

To provide the reader with additional information as referred to within this procedure, the
following documentation has been attached. This includes:
Attachment 1 Visual Inspection Check Sheet,
Attachment 2 Electrical Tests Check Sheet, and
Attachment 3 Certificate of Testing and Compliance.

C:\Documents and Settings\lwhite\Local Settings\Application Data\TOWER Software\TRIM5\TEMP\CONTEXT.5048\B D 11 30958


Procedure - H&S - CS-OHS-32 - Maintenance and Testing of Entity Works, Electrical ~ CS Energy Registered.DOC

THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT

Page: 10 of 19

Attachment 1 Visual Inspection Check Sheets


Description of Installation:
Modification Number:
Inspection Item (AS/NZS 3000-2000)

Not Applicable

AS/NZS 3000-2000
Clause Reference

(Inspectors Initials)

Complies
(Inspectors Initials)

General
i) Protection against direct contact
with live parts eg- insulation and
enclosure

1.7.2 & 1.7.3

ii) Protection against indirect contact


with exposed conductive parts egdouble insulation or isolating
transformers

1.7.2, 1.7.4 & 2.3

iii) Protection against hazardous parts


eg- enclosure, guarding or screening
of flammable materials, hot surfaces
and parts that may cause physical
injury

1.7.11, 4.2 & 4.3

iv) Protection against spread of fire


eg- penetration of fire barriers

3.9.10

v) General condition of the electrical


equipment eg- signs of damage that
could impair safe operation,
disconnection of unused electrical
equipment
Page 1 of 6
Inspector (where not the licensee):
Name:

Signature:

Certificate of Competency Number:

Date:

Electrical Contractor Licensee:


Name:

Signature:

Contractors Licence Number:

C:\Documents and Settings\lwhite\Local Settings\Application Data\TOWER Software\TRIM5\TEMP\CONTEXT.5048\B D 11 30958


Procedure - H&S - CS-OHS-32 - Maintenance and Testing of Entity Works, Electrical ~ CS Energy Registered.DOC

THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT

Date:

Page: 11 of 19

Description of Installation:
Modification Number:
Inspection Item (AS/NZS 3000-2000)

Not Applicable

AS/NZS 3000-2000
Clause Reference

(Inspectors Initials)

Complies
(Inspectors Initials)

Consumers Mains
i) Current carrying capacity

3.4
AS3008.1

ii) Voltage drop

3.6, 1.8.4
AS3008.1

iii) Underground installation conditions


e.g. enclosure, depth of burial,
mechanical protection

3.11
3.7
2.9, 5.5.4

iv) Aerial installation conditions

3.12, 3.8.4
5.5.4

v) Connection of wiring

3.7

vi) Protection against external


influences

1.9.3, 1.8.6
Page 2 of 6

Inspector (where not the licensee):


Name:

Signature:

Certificate of Competency Number:

Date:

Electrical Contractor Licensee:


Name:

Signature:

Contractors Licence Number:

C:\Documents and Settings\lwhite\Local Settings\Application Data\TOWER Software\TRIM5\TEMP\CONTEXT.5048\B D 11 30958


Procedure - H&S - CS-OHS-32 - Maintenance and Testing of Entity Works, Electrical ~ CS Energy Registered.DOC

THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT

Date:

Page: 12 of 19

Description of Installation:
Modification Number:
Inspection Item (AS/NZS 3000-2000)

Not Applicable

AS/NZS 3000-2000
Clause Reference

(Inspectors Initials)

Complies
(Inspectors Initials)

Switchboards
i) Location e.g. access and egress

2.9.8

ii) Protective devices e.g. overload


and residual current rating, fault
current rating

2.3, 2.4
2.6.2, 2.7.2
4.3.9.2.2
7.10.4.4

iii) Isolating devices, e.g. main


switches

2.8

iv) Connecting devices e.g. neutral


bars, earth bars and active links

2.9

v) Connection and fixing of wiring and


switchgear

2.9

vi) Identification and labelling of


electrical equipment

2.9.4

vii) Protection against external


influences

1.9.3, 1.8.6

5.6
3.7

Page 3 of 6
Inspector (where not the licensee):
Name:

Signature:

Certificate of Competency Number:

Date:

Electrical Contractor Licensee:


Name:

Signature:

Contractors Licence Number:

C:\Documents and Settings\lwhite\Local Settings\Application Data\TOWER Software\TRIM5\TEMP\CONTEXT.5048\B D 11 30958


Procedure - H&S - CS-OHS-32 - Maintenance and Testing of Entity Works, Electrical ~ CS Energy Registered.DOC

THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT

Date:

Page: 13 of 19

Description of Installation:
Modification Number:
Inspection Item (AS/NZS 3000-2000)

Not Applicable

AS/NZS 3000-2000
Clause Reference

(Inspectors Initials)

Complies
(Inspectors Initials)

Wiring Systems
i) Conductor size e.g. current carrying
capacity and voltage drop

1.8.4
3.4, 3.5
AS3008.1

ii) Identification of cable cores

3.8

iii) Adequate support and fixing

3.9

iv) Connections and enclosures

3.7, 3.10

v) Particular installation conditions


e.g. underground, aerial, emergency
systems

3.11, 3.12
3.13, 3.14
3.15, 3.16

vi) Segregation from other services


and electrical installations

3.9.9.4
7.10.8
1.7.2
7.7.4
1.10.4

vii) Protection against external


influences e.g. enclosure

1.9.3, 1.8.6
Page 4 of 6

Inspector (where not the licensee):


Name:

Signature:

Certificate of Competency Number:

Date:

Electrical Contractor Licensee:


Name:

Signature:

Contractors Licence Number:

C:\Documents and Settings\lwhite\Local Settings\Application Data\TOWER Software\TRIM5\TEMP\CONTEXT.5048\B D 11 30958


Procedure - H&S - CS-OHS-32 - Maintenance and Testing of Entity Works, Electrical ~ CS Energy Registered.DOC

THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT

Date:

Page: 14 of 19

Description of Installation:
Modification Number:
Inspection Item (AS/NZS 30002000)

Not Applicable

AS/NZS 3000-2000
Clause Reference

(Inspectors
Initials)

Complies
(Inspectors
Initials)

Electrical Equipment
i) Isolation and switching
devices for protection against
injury by Mechanical Movement

4.2

ii) Isolation and switching


devices for protection against
thermal effects

2.8

iii) Switching devices for


particular electrical equipment,
socket outlets, cooking
appliances

4.9.4

iv) Particular installation


conditions e.g. locations
affected by water, explosive
atmospheres, extra low voltage,
high voltage

7.1 Baths Showers and Sinks

2.8.5

4.3

4.3.11

7.2, 7.3 Pools and Saunas


7.4 Refrigeration Rooms
7.5 Where Hosing Occurs
7.6 Fountains
7.7, 3.9.9.3, 4.9.1.3.1 ELV
7.8 High Voltage
7.9, 4.4 Hazardous Areas
7.10 Emergency Systems
7.11 Specific Installations

v) Compliance with required


Standard (for specific device)

Device:

vi) Connection, support, fixing

4.11

vii) Protection against external


influences

1.9.3, 1.8.6

Standard:

Page 5 of 6
Inspector (where not the licensee):
Name:

Signature:

Certificate of Competency Number:

Date:

Electrical Contractor Licensee:


Name:

Signature:

Contractors Licence Number:


C:\Documents and Settings\lwhite\Local Settings\Application Data\TOWER Software\TRIM5\TEMP\CONTEXT.5048\B D 11 30958
Procedure - H&S - CS-OHS-32 - Maintenance and Testing of Entity Works, Electrical ~ CS Energy Registered.DOC

THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT

Date:
Page: 15 of 19

Description of Installation:
Modification Number:
Inspection Item (AS/NZS 3000-2000)

Not Applicable

AS/NZS 3000-2000
Clause Reference

(Inspectors Initials)

Complies
(Inspectors Initials)

Earthing
i) MEN connection

5.6.5, 5.3

ii) Earth electrode

5.6.2

iii) Earthing conductors e.g. size,


identification

5.6.7

iv) Equipotential bonding conductors,


e.g. size, identification

5.8

v) Connections, joints and


terminations

3.7

vi) Protection against external


influences

1.9.3

vii) Connection to earthing


arrangements for other systems

5.10

viii) Creation of earthed situation that


may require earthing of additional
electrical equipment

5.7

5.6.3

5.6

7.8.10
5.4

Circuit and Cable Schedules


Check cable and circuit schedules
have been updated legibly
Page 6 of 6
Inspector (where not the licensee):
Name:

Signature:

Certificate of Competency Number:

Date:

Electrical Contractor Licensee:


Name:

Signature:

Contractors Licence Number:

C:\Documents and Settings\lwhite\Local Settings\Application Data\TOWER Software\TRIM5\TEMP\CONTEXT.5048\B D 11 30958


Procedure - H&S - CS-OHS-32 - Maintenance and Testing of Entity Works, Electrical ~ CS Energy Registered.DOC

THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT

Date:

Page: 16 of 19

Attachment 2 Electrical Tests Check Sheet


Description of Installation:
Modification Number:
Test Item (AS/NZS 3000-2000)

AS/NZS 3000-2000

(For test methods refer to AS 3017)

Pass Criteria

Tested
Value

Test OK
(Inspectors
Initials)

Mandatory Tests
1) Main Earthing Conductor
Continuity 1.11.2, 5.6.3, 6.3.3.2

No more than 0.5 M

2) Insulation Resistance

Not less than 1 M

1.11.2, 6.3.3.3

Can be as low as 0.01 M for sheathed


heating elements in appliances

(Where multiple items test, attached a


separate list initialled)

Can be reduced of the particular


appliance standard allows a lower value

3) Protective Earth Conductors


1.11.2, 6.3.3.2, Appendix B4

See Section 5.1 of this procedure

(Where multiple items test, attached a


separate list initialled)

Circle CB Type

Clearance time:
B C D Fuse
CB/Fuse Rating:
Size of Active:
Size of Earth:
Required value of resistance from Table
within S 5.1:

4) Equipotential Bonding
Conductors
1.11.2, 6.3.3.2, 5.8.3

See Section 5.2 of this procedure


Length of cable (m):
Size of cable:
Required Resistance:

5) Polarity Check of Consumer


Mains
1.11.2.4, 6.3.3.4, AS 3017

No transposition of conductors

6) Polarity Check of Submains

No transposition of conductors

1.11.2.4, 6.3.3.4, AS 3017

No switches or protective devices that


operate independently in the neutral or
earthing conductor

(Where multiple items test, attached a


separate list initialled)

7) Polarity Check of Final


Subcircuit
1.11.2.4, 6.3.3.4, AS 3017
(Where multiple items test, attached a
separate list initialled)

No switches or protective devices that


operate independently in the neutral or
earthing conductor

No transposition of conductors

N/A

N/A

No switches or protective devices that


operate independently in the neutral or
earthing conductor

8) Correct Circuit Connections


of Final Sub-circuit

No short circuit between active, neutral


and earth (other than MEN or ESR)

1.11.2.5, 6.3.3.5, AS 3017

No transportation that would energise


exposed conductive parts

(Where multiple items test, attached a


separate list initialled)

N/A

N/A

No interconnection of conductors
between different circuits

Page 1 of 2

C:\Documents and Settings\lwhite\Local Settings\Application Data\TOWER Software\TRIM5\TEMP\CONTEXT.5048\B D 11 30958


Procedure - H&S - CS-OHS-32 - Maintenance and Testing of Entity Works, Electrical ~ CS Energy Registered.DOC

THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT

Page: 17 of 19

Test Item (AS/NZS 3000-2000)


(For test methods refer to AS 3017)

AS/NZS 3000-2000
Pass Criteria

Tested
Value

Test OK
(Inspectors
Initials)

Optional Tests Performed


Once Installation is Made Live
9) Fault Loop Impedance

See Section 5.3 of this Procedure)

Measured at farthest practicable


point in circuit from supply
1.11.2, 6.3.4.2, Appendix B

Clearance Time:

(Note Test method for this test


is not covered by AS 3017
1996, later editions may
however cover it.

CB/Fuse rating:

(Where multiple items test, attached a


separate list initialled)

Circle CB Type:
B C D Fuse
Required value of Zs from Table:
Value:
Test passes of RCD trips while fault loop
impedance tester is measuring
impedance.

10) Operation of Residual


Current Devices
6.3.4.3, AS 3760

RCD Operates correctly when tested


with (circle one below):

See also CS Energys


Maintenance of Electrical Safety
Equipment & Clothing (PPE)
Procedure

Integral Test Device

Or circle:
RCD
Tripped

N/A
Unless special
test equipment
used

or
Special Test Equipment

Inspector (where not the licensee):


Name:

Signature:

Certificate of Competency Number:

Date:

Electrical Contractor Licensee:


Name:

Signature:

Contractors Licence Number:

Date:
Page 2 of 2

C:\Documents and Settings\lwhite\Local Settings\Application Data\TOWER Software\TRIM5\TEMP\CONTEXT.5048\B D 11 30958


Procedure - H&S - CS-OHS-32 - Maintenance and Testing of Entity Works, Electrical ~ CS Energy Registered.DOC

THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT

Page: 18 of 19

Attachment 3 Electrical Certificate of Testing and Compliance


"B/D/12/7183" - Form - S1975 - Electrical Certificate of Testing and Compliance (COT)

C:\Documents and Settings\lwhite\Local Settings\Application Data\TOWER Software\TRIM5\TEMP\CONTEXT.5048\B D 11 30958


Procedure - H&S - CS-OHS-32 - Maintenance and Testing of Entity Works, Electrical ~ CS Energy Registered.DOC

THIS DOCUMENT IS UNCONTROLLED IN HARD COPY FORMAT

Page: 19 of 19

Potrebbero piacerti anche