Sei sulla pagina 1di 4

CBM FIELD DEVELOPMENT PROJECT

TEST REPORT FOR SOLO RUN TEST FOR


MOTORS
Owner
: Reliance Industries Ltd
Contractor : L&T Hydrocarbon Engineering Limited

Sheet

Date of
Testing :
AC MOTOR CHECKOUT/NAMEPLATE DATA
Motor Tested
Serial Number:

Type:

KW:

Phase:

Voltage Rating:

Frequenc
y:
Class:

Current Rating:
Motor Speed:
Manufacturer:

1.

MECHANICAL PREPARATION/CHECKS

CHECK

1. Motor Bearings are greased.


OK
2. Conduit and cable work complete.
OK
3. Turn the motor/fan by hand and check for rubs.
OK
4. Motor GROUNDING is done
OK
5. Cable terminal block is sealed with compound filling material
OK

2.

ELECTRICAL TEST PROCEDURES.

1. Lock main circuit breaker in the OFF position. (Door open)

OK
2. Check for loose wires or damaged components.
OK
3. From the MCC, Megger the motor from phase to phase and phase to
ground
OK
4. Measure the resistance between motor phases.
OK
5. Check the rating of the overload and set to rated full load current of the
motor.
OK
6. Unlock the circuit breaker, switch the selector switch to OFF and close
the breaker.
OK
7. Bump test the motor by switching selector to HAND, and verify correct
rotation.
OK
8. When the rotation is correct run the motor and record current.
OK
Testing Engineer

L&T

RIL(Projects)

RIL(O&M)

Name:
Designation:
Signature & Date:
Format No :LT/RIL/CBM/ELEC/ITP/016

Page No: 1 of 3

CBM FIELD DEVELOPMENT PROJECT


TEST REPORT FOR SOLO RUN TEST FOR
MOTORS
Owner
: Reliance Industries Ltd
Contractor : L&T Hydrocarbon Engineering Limited

Sheet

9. Run for 4 hours and record the temperature, vibration levels, voltage and
current.
OK
10. Switch off and lock out motor after test.
OK

Motor winding resistance:


REF

Resistance Value

Inductance

U1 - U2
V1 - V2
W1 - W2

Motor Insulation resistance:


REF

Resistance Value

R-Y
R-B
Y-B
R - Earth
Y - Earth
B - Earth

Direction of Rotation:
________________________________________________
RUN TEST RESULTS

PHASE
CURRENT

PHASE
VOLTAGE

Parameters/Ti
me

R-Y

START

30 MIN

60 MIN

90 MIN

120
MIN

150
MIN

180
MIN

210
MIN

240
MIN

Y
B

Y-B
B-R

TEMPER
ATURE

RPM
NDE

Testing Engineer

L&T

RIL(Projects)

RIL(O&M)

Name:
Designation:
Signature & Date:
Format No :LT/RIL/CBM/ELEC/ITP/016

SAMPLE

Page No: 2 of 3

CBM FIELD DEVELOPMENT PROJECT


TEST REPORT FOR SOLO RUN TEST FOR
MOTORS
Owner
: Reliance Industries Ltd
Contractor : L&T Hydrocarbon Engineering Limited

Sheet

DE
AMBIENT
TEMP
WINDING
TEMP
*For motors with VFD, RPM of motor as per VFD output also shall be measured and recorded separately.

Details of test equipments used:


IR Tester
Make:
.

Range: ..V

Sl. No: ..

Cal due Date:

Range: ..V

Sl. No: ..

Cal due Date:

Range: ..V

Sl. No: ..

Cal due Date:

Range: ..V

Sl. No: ..

Cal due Date:

Clamp meter
Make:
.
Thermometer
Make:
.
Digital Multi meter
Make:
.
Micro ohm meter
Make:

Range: ..V

Sl. No: ..

Cal due Date:

Sl. No: ..

Cal due Date:

.
Digital tachometer
Make:

Range: ..V
.

Testing Engineer

L&T

RIL(Projects)

RIL(O&M)

Name:
Designation:
Signature & Date:
Format No :LT/RIL/CBM/ELEC/ITP/016

Page No: 3 of 3

CBM FIELD DEVELOPMENT PROJECT


TEST REPORT FOR SOLO RUN TEST FOR
MOTORS
Owner
: Reliance Industries Ltd
Contractor : L&T Hydrocarbon Engineering Limited

Sheet

*all testing equipment details shall be added at time of preparation of final reports and
reports to be attached

Testing Engineer

L&T

RIL(Projects)

RIL(O&M)

Name:
Designation:
Signature & Date:
Format No :LT/RIL/CBM/ELEC/ITP/016

Page No: 4 of 3

Potrebbero piacerti anche