1 Introduction
14-2
14-2
14-3
14-10
14-8
14.1
Introduction
14.2
Safety Precautions
Danger 1
Danger 2
Warning 1
Warning 2
14.3
Power Cabling
General
Power Distribution Frame
Cable Routing
Two-Wire Configuration
Note
Power Unit
Caution Before connecting the power cables, make sure that the
circuit breakers for BAT-A and BAT-B are switched off.
Remove the safety cover; see Figure 14-5: loosen the two screws and remove the
safety cover.
Figure 14-5 Mounting of power cable shoes
Remove the nuts from the power terminals; see Figure 14-5.
Guide the power cables through the cable guide and connect them to the power
terminals as follows; see Figure 14-6:
Note The power cable nuts should be tightened with a torque of 1.52.0 Nm
Place the safety cover back in its location and fasten it with the 2 screws (maximum
torque: 0.3 Nm).
Note When the power cable is connected to BAT A and the power is
on and below -40.5V dc, the green LED BAT A at the right bottom of
the FX-4 subrack is on, showing the availability of power (even when the
circuit breaker is in the standby position); see Figure 14-6.
The same applies for BAT B.
14.4
Cable Type
Figure 14-7 Grounding Cable Lug
Route the grounding cable to the right side of the subrack and to the middle of the
subrack.
Connect the double lug to the grounding cable connection point as shown in
Figure 14-8.