Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
A Study on
Six Sigma Techniques
And
Its application in reduction of seat rejection
At BOSCH LTD.
Submitted by
Ankur Bhaskar Ghosh(11FN-013)
Saurabh Bakshi(11IB-052)
Chandra Shekhar L(11DM-031)
Pankhuri Agrawal(11FN-071)
Hitesh Kothari(11IB-025)
Pranjal Singh(11DM-107)
Literature Survey
Case study of manufacturing Industry
Identification of problem
Industry
Data Collection
Identify Specific problem
Define
Measure
Analyze
Improve
Control
Improvement Results
Conclusions
Scope of future work
Fig 2:
PPM Defectives
Sigma level
6,91,000
3,09,000
67,000
6,200
230
3.4
Product Definition:
Dowel hole
drilling
Shoulder
Turning
Step Turning
Seat
Profile
Grinding
Guide Bore
Drilling
Inlet hole Drilling
Pressure Chamber
machining
Fig 5: Body of DSLA type nozzle
Sack Hole
Seat
Surface
Seat- seen under Microscope
DEFINE PHASE:
1. Why the project? (The Business case) DSLA nozzle parts are hardened at UDA (Hardening
process) and after subsequent chamfer grinding they come at UVA (High precision internal grinding)
machines for Guide bore and Seat grinding. The seat and guide bore surface grinding is done on UVA
and then they are sent to inspection for seat visual checking. At seat visual checking section the no. of
parts getting rejected are quite high. From Jan08 to July08 average 22600 ppm (parts per million)
were rejected due to Bad seat problem (Rejection due to other reasons are not included in the scope
of the project).
Due to these rejections the first pass yield and type wise fulfillment of parts decreases. Also Due to
added seat repair operation at UVA the m/c utilization decreases and at the same time it increases
the defect cost associated with it. By successfully implementing the project we can save up to 1, 50
TINR.per month.
2. SIPOC (Supplier-Input-Process-Output-Customer):
SIPOC is a six sigma tool. The acronym SIPOC stands for Suppliers, inputs, process, outputs, and
customers. A SIPOC is completed most easily by starting from the right ("Customers") and working
towards the left.
Suppliers to UVA process are Company, TEF1, TEF2, PLP, and MSEB.
Inputs to UVA process are Man, Machine, Electricity, Drawings, and H.T. over parts, Gauges, Tooling
Compressed air, JML, Cutting oil, Check list , Instruction charts, Program etc.
Process taking place at UVA process is Internal grinding of seat surface.
Output of the UVA process are Seat Grinding over parts, Worn out tooling, Grinding muck, PMI chart,
Re-release chart.
Customers of the UVA process are Inspection, Repair process, Stores, Scrap yard, Etamic check,
Honing, Profile Grinding.
Using this data a SIPOC diagram is created.
SUPPLIER
Company
Electricity
Maintenance
TEF1
Purchase
Soft Stage
Operations
INPUT
Man
Machine
Electricity
Drawings
H.T. over parts
Gauges, Tooling
Compressed air
JML ,Cutting oil
Check list
Instruction charts
Program
Hardening
PROCESS
OUTPUT
CUSTOMER
UVA
process
High
Precision
Internal
Grinding
Process
Inspection
Repair process
Stores
Scrap yard
Etamic check,
Honing
Profile Grinding
UVA process
(High Precision
Internal Grinding)
Seat Visual
Inspection
Profile
Grinding
Taper repair
Guide bore repair
To reduce
UVA
process
Repair
Repair
Seat repair
Scrap
Pareto Analysis:
The Pareto chart was introduced in the 1940s by Joseph M. Juran, who named it after the Italian
economist and statistician Vilfredo Pareto, 18481923. It is applied to distinguish the vital few from
the trivial many as Juran formulated the purpose of the Pareto chart.
From this Analysis we clearly see that Seat repair is the most critical of all rejections.
Attractive
One-Dimensional
Must-Be
Indifferent
As per Kano model of Quality A CTQ specification table is generated for giving the specifications of
rejections.
CTQ
MEASURE
SPECIFICATION
G.B. Repair
Monthly PPM
--
Seat Repair
Monthly PPM
Taper bad
Seat Damage/
Finish Bad
Monthly PPM
--
G.B. Scrap
Monthly PPM
--
Seat Scrap
Monthly PPM
Seat Damage
Repair
DEFECT DEFINITION
specification
G.B. size out of
specification
Seat visually not O.K.
KANO STATUS
Must Be
MEASURE PHASE:
Collect baseline
data on defects &
possible causes
Develop a
sampling
strategy
Validate your
measurement
system using
Gauge R & R.
Analyze
patterns
in data
Determine
process
capability
Creating a data collection plan: As per the approach specified a plan for collecting the base line
data is created. It is given below.
What
Seat defects
Measure type/
How
data type
measured
Discrete data
visually
How/where
Sampling
conditions to
recorded
notes
record
lot wise
(Attached form)
100%
--
Date
Qty.
Inspected
Name_________________________
Shift
Qty.
OK
Qty
Rejected
Item
No.
Bad
Rings
Finish
Token No:
Patches
Seat Defects
Rubbing at
sack hole
No sack
hole
Type
Patches
Unground
seat
No sack
hole
277
182
93
172
0
6
1
5
1
1
Rubbing at sack
hole end
due to burr
0
1
174
100
63
10/8/2008
1114
646
440
12
12
12/8/2008
13/08/08
14/08/08
17/08/08
607
47
163
416
20
80
90
165
24
78
293
25
2
4
57
0
0
0
0
1
0
0
8
0
1
1
2
18/08/08
19/08/08
20/08/08
22/08/08
23/08/08
25/08/08
26/08/08
270808
28/08/08
30/08/08
1/9/2008
2/9/2008
46
85
170
214
308
189
2
20
74
115
204
113
43
56
95
90
90
70
0
0
0
8
12
6
0
0
0
0
0
0
0
2
1
0
0
0
1
7
0
1
2
0
192
82
94
16
119
101
163
99
78
32
38
32
12
31
86
63
55
37
43
1
0
9
48
4
0
0
66
1
0
0
0
1
0
0
0
0
0
0
0
5058
2566
2150
219
79
27
16
Total no. of
Bad finish
parts checked (rough surface)
Day count
Date
Day-1
Day-2
6/8/2008
7/8/2008
372
367
Day-3
8/8/2008
Day-4
Day-5
Day-6
Day-7
Day-8
Day-9
Day-10
Day-11
Day-12
Day-13
Day-14
Day-15
Day-16
Day-17
Day-18
Day-19
Day-20
450
5000
100
4000
80
3000
60
2000
40
1000
20
Percent
Count
0
i
fi n
Defect
h
ug
Ro
Count
Percent
Cum %
2566
50.7
50.7
sh
ng
Ri
2150
42.5
93.3
es
t ch
Pa
ds
un
gr o
Un
219
4.3
97.6
ea
79
1.6
99.1
he
Ot
rs
43
0.9
100.0
Measuring Table-20249
Measuring Table-19389
Gage R & R
18.82
13.23
10
10
If GRR <10
If 10<GRR<30
If 30<GRR
Gauge is acceptable
Gauge is conditionally acceptable
Gauge is unacceptable & must be replaced/modified.
Binomial P lot
P r opor tion
0.024
Expected Defectives
U C L=0.026045
0.026
_
P =0.022624
0.022
0.020
LC L=0.019202
1
10 13 16 19
Sample
22 25
425
400
375
350
360
390
420
O bser ved Defectives
28
C umulative % Defective
Dist of % Defective
Tar
8
S ummary S tats
(using 95.0% confidence)
% Defective
2.30
% Defectiv e:
Low er C I:
U pper C I:
Target:
P P M Def:
Low er C I:
2.28
2.26
2.24
2.22
5
10
15
20
Sample
25
30
U pper C I:
P rocess Z:
Low er C I:
U pper C I:
2.26
2.22
2.30
0.00
22624
22217
6
4
2
23035
2.0024
1.9947
2.0100
0.
00
0.
35
0.
70
1.
05
1.
40
1.
75
2.
10
2.
45
Sigma level
6,91,000
3,09,000
67,000
6,200
230
3.4
11
UVA PROCESS
REPAIR &
SCRAP
Seat
repair
Rough finish,
Rings, Patches,
No sack hole,
Rubbing at sack hole,
Unground seat
Chamfer height
variation.
Jet broken,Pump
pressure less
Uneven chamfer
band
Guide to shaft TR
not checked after
TBT as per freq.
Vibrations &
chatter marks on
seat in soft stage
Roundness, Straightness,
Guide bore to seat TR
No specification in
drawing
Possibility of poka
yoke failure
Type Mix-up ( P
type in DSLA &
vise versa
Manual element
more than 70
microns
specification 58.8
(+/- 0.2)
Chamfer mandrel
angle in hard
stage
I/P parts
TR more
than 100
microns
More/less
than spec.
Fig 16: Tree diagram created from brainstorming session for Input part parameters
12
Measure
by gauge
Vibration
RPM
value-2250
Consult Mr.Kumavat
Workhead
Loading/
Unloading
Spindle height
Repeatability
Below 20
Female center
Grinding
Decide freq.
Once in a month
Loading alignment
of component
Visual check
OK/ Not OK
Loading cylinder
Air leakage
Cylinder swing
In / Out positions
Changing freq.
To be decided
Once in
2 months
As per freq.
Angle master
Checking
bench
UVA
process
repair
Seat
Rejections
Visual inspection
microscopes
M/C
parameters
Seat profile
To be studied
Alignment of both
eyes
Scope condition
to be studied
Prepare
schedule
Frequent checking
by associates
RPM
value-60,000
spindle cooling
To be asked
to maintenance
Initial setting
Height gauge to
check height diff.
4,600 mm
After dressing
spindles
Setting
parameters
Adaptor
TR < 10
Dressing ring
coolant
systems
4,300 mm
confirmation of poka
yoke once in a shift
Grinding wheel
Dressing freq.
6 parts
Feed rate
Details to be taken
Grinding
From two tree diagrams created above it is clear that there are 7 parameters related to input part
parameters & 23 machine related parameters. To know the impact of each parameter on seat
rejections it was necessary to validate each parameter using statistical methods. In Six Sigma method
used for root cause validation is Hypothesis testing.
13
sub cause
Suspected sources
of variations
(SSV's)
Uneven
chamfer
band
End
date
Test used Results obtained
Conclusions
2
proportions
test
49 bad in 50 with The impact of drill
chatter marks, 1 damage in soft stage
bad in 50 without on Seat rejections is
16-Dec8-Jan-08
chatter marks
Significant.
08
16-Dec8-Jan-08
08
12 parts bad in
The impact of
Take 50 parts with TR more
2
50 TR bad parts Uneven chamfer band
than 85 & put them on UVA also 3-Mar-09 3-Mar-09 proportions
1 bad in 50 TR ok on Seat rejections is
process 50 normal parts
test
parts
Significant
Guide to shaft TR is
not
checked in soft
stage
Guide to shaft
TR not ok
Start date
0 bad parts in
Take 275 parts with cleaning & 25
The impact of aqueous
2
275 ok parts
parts without cleaning & process
cleaning on chamfer
8-Nov-08 8-Nov-08 proportions 0 bad parts in 25
them on same chamfer grinding
height variation is
test
without cleaning
m/c & same UVA m/c.
Insignificant.
parts
Trial taken
Actions taken
Sr.N Root
o.
cause
14
Poka yoke
failure on
Retco machine
Poka yoke
failure on
spinner
machine
sub cause
Chamfer
mandrel
angle
in soft
stage
More or
less than
specification
Actions taken
Trial taken
Start date
End
date
Test used
Results obtained
Conclusions
Chamfer mandrel
Chamfer mandrel 4 mandrels given to
angles checked
angle to
tool room
25-Nov- 25-Decby Sine bar method
be verified in tool for chamfer angle
08
08
& Microscope
room
verification
method
No
variation
in output
As there in no
variation in
output statistical
test cannot
be performed
The impact of
chamfer mandrel
angle on seat
rejections is
Insignificant
Suspected sources of
variations
(SSV's)
80% on
75% Benzinger,
10% on ECM.
Part type Possibility on Manual element
5
mix up all operations may be present,
Elevator condition
in soft stage is
poor
Angle not
checked as per
Seat angle On spinner
frequency/Drill life
6
in soft
& Retco
over, Drill
stage
machines
resharpening
improper
Parts
without
4 sack hole
from soft
stage
Sr.
Root cause
No.
15
RPM
Trial taken
Start date
End
date
Female
center
Job
Air supply to job clamping
Chuck clamp
clamping
is varied to different levels
grinding
pressure
& it's effect was observed
2 proportions
test
conclusions
Results obtained
No variation
output
observed
Test used
Check repeatability<20,
50 parts each were processed
Repeatability take trial with processing
with repeatability of 10 &
12-Mar-09 12-Mar-09
below 20
parts with different
at20.
repeatability values.
Actions taken
Spindle
height
Workhead
Earlier not
known
Vibration
value-1800
rpm
Suspected
sources of
variations
(SSV's)
Sr.
Root cause sub cause
No.
16
Changing
freq.
Loading
spring
wornout
11
Checking
bench
Air supply
for parts
cleaning
Visual
inspection
microscope
Angle master
10
Loading
cylinder
No supply
provided
A workshop on microscope
handling to be arranged
18-Dec-08 18-Dec-08
30-Jan-09 30-Jan-09
Associates awareness
about microscope
adjustment to be done.
Check requirement of
frequent verification of
microscope condition
Alignment
of both eyes
not there
Frequent
checking by
associates
Checking freq. to be
reduced
Master
showing
wrong
reading
30-Jan-09 30-Jan-09
30-Jan-09 30-Jan-09
30-Jan-09 30-Jan-09
End
date
Start date
Trial taken
Actions taken
Loading
Loading /
alignment of Visual check
Unloading
component
Suspected
sources of
variations
(SSV's)
sub cause
Sr.
Root cause
No.
2 proportions
test
conclusions
GRR found to be ok
Results obtained
No test
performed
No hypothesis
test performed
2 proportions
test
2 proportions
test
Test used
17
Adaptors
Dressing
ring
17
Setting
parameters
16
15
14
13
To be asked to
maintainance
30-Jan-09
30-Jan-09
30-Jan-09
Adaptor Tr checked
take 50 parts with adaptor
If TR out of
every time machine is
TR<10
specification seat disturbed & it's impact
30-Jan-09
& again take 50 parts with
bad comes
on seat rejections
adaptor TR>10
observed
30-Jan-09
30-Jan-09
30-Jan-09
30-Jan-09
End
date
Ensure positive
cutting
after dressing
If dressing ring is
worn out, the
Trial taken which
Periodic
grinding wheel
involves placing a worn
replacement
form gets
out ring on Machine &
& TR
damaged. Due to
taking parts
which part comes
seat bad.
TR<10
New seat
wheel
setting
Spindle
cooling
Start date
Trial taken
12
Grinding
spindles
value to be
60,000 RPM
RPM
Actions taken
Suspected
sources of
variations
(SSV's)
Sr.
Root cause sub cause
No.
Results obtained
2 proportions
test
2 proportions
test
2 proportions
test
No test
performed
Test used
conclusions
18
6 parts
Dressing freq.
21
Incorrect decision
due to fear
of getting rejected
from assembly.
Lack of
operator
equalization
23
Operator
Manual knob
present
Feed rate
22
Grinding
program
3 microns
30-Jan-09
30-Jan-09
30-Jan-09
30-Jan-09
30-Jan-09
30-Jan-09
Start date
Confirmation of
poka yoke once
in a shift
Tip breakage
sensing poka
yoke
20
Grinding
wheel
Check pressure,
temperature
of coolant system
The dressing/
Grinding
pressure varies
Trial taken
3.5 to 4 bar
grinding/
dressing
coolant
Actions taken
Suspected sources
of variations
(SSV's)
sub cause
Dressing
depth of cut
19
18
Coolant
systems
Sr.
Root cause
No.
30-Jan-09
30-Jan-09
30-Jan-09
30-Jan-09
30-Jan-09
30-Jan-09
End
date
Results obtained
0 bad in 50 with 3
depth of cut.
0 bad in 50 with 2
depth of cut.
conclusions
Due to continuous
The impact of Operator
rejections from
2 proportions
equalization on seat
assembly section fear
test
rejections is
is set in visual
Significant.
operators.
2 proportions
test
2 proportions
test
2 proportions
test
Test used
19
Method
Dirt
accumulates on
part as it is near
to window
Material
Gauges not
calibrated on
elevator getting
jammed
Work
Instructions are
Complex
procedures
Frequent breakdowns
Drill Breakage
In coming quality
bad
Rough
Checking freq. is
Finish &
less
Motivation less
Rings
formation
on Seat
New operator
Detection is poor
Negligence
Tool Quality
Awareness
Man
20
Machine:
No Poka Yoke present to detect Drill breakage which causes ring formation
Material:
In coming quality of parts not ok (Part bend which causes drill breakage)
Method:
Elevator which lifts the part to chuck gets jammed causing part damage
Environment:
Machine is near to open window which causes dirt accumulation on part which damages
surface during grinding.
Bar chart
The ideas generated during Brainstorming session were verified by Process Experts and the causes
having positive impact on rejections were listed out. Bar chart analysis was performed on these
parameters to know the causes which have significant impact on rejections.
% Rejections
50
45
40
35
30
25
20
15
10
5
0
21
15
8
11
% wise causes
Drill overuse
No Poka
Gauges not
Yoke present calibrated on
to detect Drill
time
breakage
Coolant
pressure
varies
Others
Causes
21
% Rejections
45
21
15
8
11
% wise causes
Drill overuse
No Poka
Gauges not
Yoke present calibrated on
to detect Drill
time
breakage
Coolant
pressure
varies
Others
Causes
Fig 12: Tool breakage sensing Poka Yoke with OK drill mounted on machine
Fig 21: Tool breakage sensing Poka Yoke when tip of drill is broken
After successfully implementing this on one pilot machine, there was horizontal deployment of this
Poka yoke on all 8 machines.
22
were
given
clear
instructions
about
drill
records
maintenance.
Accurate
drill
Window responsible for dirt accumulation was permanently closed & one exhaust fan was
installed at that place.
For new operator coming in area training sessions & supervision by skilled operators was
made compulsory.
CONTROL PHASE:
This phase defines control plans specifying process monitoring and corrective actions. It ensures that
the new process conditions are documented and monitored. All possible causes of specific identified
problems from the analysis phase were tackled in the control phase. Control solutions to identified
problems have been prepared in sequence to the improvements as explained above. This will prevent
the problems from recurring. The proposed control solutions to improve the previous solutions are
listed in sequence as follows.
A) Drill breakage Poka Yoke:
A Poka yoke monitoring sheet is maintained by shop. One shop Forman daily checks that all Poka
Yoke are working correctly & records it on a check sheet. A clear escalation model for problem
reporting is prepared for Poka Yoke failure.
B) Drill overuse by operators:
As weekly drill quantity top-up is done, it automatically ensures that every week drill quantity is verified
for shortage. A record sheet is maintained to keep all drills records.
C) Gauges calibration:
This issue was taken seriously by quality department & they have assigned special audit team to
ensure that gauges are calibrated on time.
23
D) Coolant pressure:
For all hydraulic circuits in shop, one preventive maintenance program is prepared. Operators are
given authorities to stop machine if leakage is found on it.
E) Operator related issues:
All operator related issues were taken to Worker Union and after their consent it is decided to take
strict action against the operator negligence is company.
RESULTS:
After completing the DMAIC methodology of Six Sigma, again the process capability Analysis was
done to know the improvement in Sigma level. One month data on Control phase was taken for the
Analysis.
Capability Analysis of Seat Visual Process
Binomial P lot
0.020
Expected Defectives
P C har t
1
P r opor tion
1
1
0.015
U C L=0.01344
_
P =0.01104
0.010
1
11
10 13 16 19
Sample
22 25
LC L=0.00864
300
250
200
150
160
240
320
O bser ved Defectives
28
C umulative % Defective
Dist of % Defective
S ummary S tats
(using 95.0% confidence)
% Defective
1.2
% Defectiv e:
Low er C I:
U pper C I:
Target:
P P M Def:
Low er C I:
1.1
1.0
5
10
15
20
Sample
25
U pper C I:
P rocess Z:
Low er C I:
U pper C I:
30
1.10
1.08
1.13
0.00
11039
10754
11330
2.2890
2.2791
2.2989
Tar
12
9
6
3
0
0.0 0.3 0.6 0.9 1.2 1.5 1.8
Figure 22: Process capability of seat visual process after applying DMAIC methodology
From the Minitab output it is clear that PPM defect level is reduced from 22,624 ppm to 11,031 ppm.
And Sigma level is Improved from 3.5 to 3.79 .
Rejections in PPM
25,000
22,624
Sigma level-3.5
PPM level
20,000
Sigma level
improved to 3.79
15,000
11039
10,000
5,000
Rejections in PPM
0
PPM rejections before Project
A few more agreed recommendations are still to be implemented during plant shut down. The
estimated savings from the project after the implementation of all recommendations are expected to
be 1, 50,000Rs per Annum.
24
CONCLUSIONS:
The immediate goal of Six Sigma is defect reduction. Reduced defects lead to yield improvement;
higher yields improve customer satisfaction. The ultimate goal is enhanced net income. The money
saved is often the attention getter for senior executives. It has a process focus and aims to highlight
process improvement opportunities through systematic measurement. Six Sigma defect reduction is
intended to lead to cost reduction. Six sigma is a toolset, not a management system and can be used
in conjunction with other comprehensive quality standards present in the industry. The application of
Six Sigma technique for this project shows that company has taken a small step towards Six Sigma
Implementation on Company wide basis. Once Six Sigma finds its rightful place in the minds of higher
management, enormous gains can always be expected from its application. It is clear that the Six
Sigma methodology is highly beneficial to improve the performance of any manufacturing plant.
25
References
1) Kumar, P. (2002) Six Sigma in manufacturing, Productivity Journal, Vol. 43, No. 2, pp.196
202.
2) Harry, M.J. and Schroeder, R. (1999) Six Sigma: The Breakthrough Management Strategy
Revolutionizing the Worlds Top Corporations, New York, NY: Double Day.
3) Henderson, K.M. and Evans, J.R. (2000) Successful implementation of Six Sigma:
benchmarking: General Electric Company, Benchmarking: An International Journal, Vol. 7,
No. 4, pp.260281.
4) Mathew.H, Barth.B, and Sears.B, (2005) Leveraging Six Sigma discipline to drive
improvement, Int. J. Six Sigma and Competitive Advantage, Vol. 1, No. 2, pp.121133.
5) Park, S.H. (2002) Six Sigma for productivity improvement: Korean business corporations,
Productivity Journal, Vol. 43, No. 2, pp.173183.
26