00/141017 Lummus-I & II Shutdown

Jobs List for Lummus Shutdown


October 2014
HEATER H-01 & H-101:
Cleaning of both heaters tubes
H-01 necessary refractory repair (if required)
Hydro Testing of both heater coils
External cleaning of both heater tubes
Cleaning of fuel oil/gas burners
Overhauling/adjustment & greasing of louvers of both heaters
Damper operation checking & rectification
Fuel gas/fuel oil/atomizing steam valves checking and replacement (if required)
HEAT EXCHANGERS:
Inspection, Cleaning & Hydro-testing of following Heat Exchangers:
E - 1 (Naphtha/Crude Heat Exchanger)
E-2A (Naphtha condenser)
INSTRUMENT JOBS:

Calibration of pressure/temperature gauges and replacement of Faulty gauges


Calibration of PI-410 (flash zone vacuum)
ESD checking of both heaters
Installation of thermocouples for stack temperatures of both heaters
Rectification of draught gauges of both heaters
Calibration & servicing of FCV-107 (atmos. HSD) and LCV-308 (OHD to storage)
Installation of new cut-4 control valve (FCV-119)

INSPECTION JOBS:
Inspection of both heaters refractory & tube thickness/hardness
Inspection of both heaters steam super heater coils
Inspection/replacement of corrosion probes (if any)
Inspection of vacuum overhead line to V-104
MISCELLANEOUS:

6/7/2015

New electric driven vacuum charge pump tie-in connections


Replacement of leaky valve in vacuum overhead line
Removal of chocking in flash zone vacuum gauge tapping (new gate valve required)
Line modification for injection of Tk 74 through new electric driven vacuum charge pump
Replacement of 2 globe valve in steam line near P-101
Removal of chocking from FT-120, FT-121, FT-127

5:41 A6/P6

Page 1 of 2

OP/lu/6,211.00/141017 Lummus-I & II Shutdown

Replacement of 3 gate valve with 3 globe valve at V-01 bottom injection line to vacuum
charge pump
Replacement of 2 globe valve at P-4 discharge line
Connection of super heated steam line (vacuum side) with saturated steam line
Cleaning of nozzles/lines for Filmer/Neutralizer injection
Rectification of Steam leakages in live steam line near PI-412, steam emergency line near V-2,
steam line near H-101, steam line from H-01 to V-1 (FT-120) and pump P-3 steam inlet line
Gland packing of different valves at plant

LIST OF BLINDS TO BE INSERTED & REMOVED


1. LP-to-export line
2. Main fuel gas line to unit
3. Flare line at knockout vessel
4. Naphtha product line, east side battery limit
5. LWK product line, east side battery limit
6. HSD product line, east side battery limit
7. DFO product line, east side battery limit
8. Residue product line, east side battery limit
9. Fuel oil lines at battery limit supply & return
10. Superheated steam line at battery limits
11. Heater blow down
12. Heater Inlet / outlet of both heaters