Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
and Evaluation
G.R. MacDougall, SPE, Chevron Canada Resources Ltd.
Summary. Recent wellsite disasters have led to an increased emphasis on properly sized mud/gas separators. This paper reviews
and analyzes existing mud/gas separator technology and recommends separator configuration, components, design considerations, and
a sizing procedure. A simple method of evaluating mud/gas separation within the separator vessel has been developed as a basis for
the sizing procedure. A mud/gas separator sizing worksheet will assist drilling personnel with the sizing calculations. The worksheet
provides a quick and easy evaluation of most mud/gas separators for a specific well application. A brief discussion of other mud/gas
separator considerations is provided, including separator components, testing, materials, and oil-based-mud considerations.
Introduction
The mud/gas separator is designed to provide effective separation
of the mud and gas circulated from the well by venting the gas and
returning the mud to the mud pits. Small amounts of entrained gas
can then be handled by a vacuum-type degasser located in the mud
pits. The mud/gas separator controls gas cutting during kick situations, during drilling with significant drilled gas in the mud returns,
or when trip gas is circulated up.
This paper discusses design considerations for mud/gas separators. The purpose of this paper is to allow drilling rig supervisors
to evaluate mud/gas separators properly and to upgrade (if required)
the separator economically to meet the design criteria outlined in
this paper, and to provide office drilling personnel with guidelines
for designing mud/gas separators before delivery at the drillsite.
Principle of Operation
The operating principle of a mud/gas separator is relatively simple. The device is essentially a vertical steel cylindrical body with
openings on the top, bottom, and side, as shown in Fig.!. The
mud and gas mixture is fed into the separator inlet and directed
at a flat steel plate perpendicular to the flow. This impingement
plate minimizes the erosional wear on the separator's internal walls
and assists with mud/gas separation. Separation is further assisted
as the mud/gas mixture falls over a series of baffles designed to
increase the turbulence within the upper section of the vessel. The
free gas is then vented through the gas vent line, and mud is returned
to the mud tanks.
Operating pressure within the separator is equal to the friction
pressure of the free gas venting through the vent line. Fluid is maintained at a specific level (mud leg) within the separator at all times.
If the friction pressure of the gas venting through the vent line exceeds the mud-leg hydrostatic pressure within the separator, a blowthrough condition will result sending a mud/gas mixture to the mud
tanks. As one can readily see, the critical point for separator blowthrough eXists when peak gas flow rates are experienced in the separator. Peak gas flow rates should theoretically be experienced when
gas initially reaches the separator.
Types of Mud/Gas Separators
Three types of mud/gas separators commonly are used today: closed
bottom, open bottom, and float type. The principle of mud/gas separation within each type of vessel is identical. Differences can be
found in the method of maintaining the mud leg, as discussed
below.!
The closed-bottom separator, as the name implies, is closed at
the vessel bottom with the mud return line directed back to the mud
tanks, as shown in Fig. 1. Mud leg is maintained in the separator
by installation of an inverted V-shaped bend in the mud return line.
Fluid level can be adjusted by increasing/decreasing the length of
the V-shaped bend.
Commonly called the poor boy,2,3 the open-bottom mud/gas
separator is typically mounted on a mud tank or trip tank with the
bottom of the separator body submerged in the mud, as shown in
Copyright 1991 Society of Petroleum Engineers
~
I:.::.:.:::.::J MUD & GAS MIXTURE
MUD
GAS
IMPINGEM ENT
PLATE
MUD
GAS
IMPINGEMENT
PLATE
SEPARATOR INLET
MUD TANK
must exceed vent-line friction pressure to prevent a separator blowthrough condition. Minimum mud-leg hydrostatic pressure would
occur if an oil/gas kick was taken and the mud leg was filled with
0.26 psi/ft oil. 8 This minimum condition mayor may not occur,
depending on the well location. Offset well data should be evaluated to establish a minimum mud-leg fluid gradient. For example,
the 0.26-psi/ft mud-leg gradient would be considered extremely conservative if dry gas were expected for the sample problem. A more
realistic estimate would approach the gradient of whole mud for
the dry-gas case. A realistic mud-leg gradient for a gas/water kick
would be the gradient of native salt water.
In this paper, a worst-case scenario is considered with a mudleg fluid gradient of 0.26 psi/ft. If we assume a 7-ft mud leg,
PmZ=h mzg mZ =7xO.26=1.8 psi, ...................... (6)
.....................................
(7)
r:;::::::::I
GAS
MUD
IMPINGEMENT
PLATE
BAFFlES
We find that the gas migration rate is greater than the liquid velocity in the separator, 8.4>4.8 ft/min. Therefore, a blow-through
condition caused by insufficient separator cut does not exist.
Note that a separator cut < 100% frequently exists with mud/gas
separators, and under some conditions, is not a major concern. As
stated earlier, the mud/gas separator is designed to provide effective separation of mud and gas with small amounts of entrained
gas handled by a vacuum-type degasser located in the mud pits.
Therefore, large active pit volumes may tolerate < 100% separator cut.
Sizing Conclusion. Having evaluated sizing criteria for the mud/gas
separator (Fig. 4), we may conclude that the separator is sized sufficiently to handle our worst-case kick properly.
OIIBasedMud Considerations
The effects of oil-based mud on the operation of the mud/gas separation can signifiantly affect sizing and design requirements. l
These concerns are currently being evaluated. However, some conclusions can be made at this stage. 10
MIXTURE
MUD
Well Data :
4'
GAS
27'
Kick Data :
7 O' VENT LINE
I':':':':j
.... .
~
SOURCE
SKETCH
EQUIV. LENGTH
BEND ACUTE,
ROUND
rr=====:::::-
BEND ACUTE,
SHARP
fr=:::::::-
150
BEND RIGHT,
ROUND
BEND RIGHT,
SHARP
BEND OBTUSE,
ROUND
BEND - OBTUSE,
SHARP
CONTRACTION,
GRADUAL
CONTRACTION,
ABRUPT
((
II
70
~
~
(FT)
15
-------------~
10
----r-
--
-------
...
....
.
friction
(pol)
~2'
t.
to
" OM
_*kin
012*4,'7"
282
10
18
1.4
16
mud 16 Ibmlgal
1.2
mud 14 Ibmlgal
14
mud 12 Ibm/gal
12
10
ml
(pel)
(pol)
0.8
-~--,-
. -' --
0.6
.... -
---
0.4
0.2
2
0
10
12
14
16
18
TroubleShootlng an Insufficiently
Sized Separator
Frequently, the situation arises where a mud/gas separator is picked
up with the rig contract, and the drilling rig supervisor and engineer must evaluate the suitability of the separator for the welliocation. This evaluation typically should be conducted during the rig
bid analysis process. If the separator is insufficient or marginal,
it may be more economical to upgrade the existing separator to meet
the sizing criteria as an alternative to renting or building a suitable
one.
Small Vessel ID. We frequently do our calculations and determine
that our vessel ID is too small. Reducing the kill rate will improve
this situation; e.g., if the kill rate for the previously sized separator were reduced from 3 to 1.5 bbl/min, then from Eq. 7:
[(2 x 1.5)/36 2 ]/1,029 =2.4 ft/min.
Thus, reducing the kill rate also reduces the liquid velocity rate
in the separator, which increases the mud/gas retention time and
improves the efficiency of mud/gas separation.
Also note that a gas migration rate of 500 ft/hr (8.4 ft/min) is
a worst-case scenario and values could be higher. Therefore, when
vessel ID is considered, a marginal separator probably would be
sufficient because of this built-in safety factor. Higher gas migration rates may also be used in the sizing procedure, as previously
discussed. Fig. 7 shows the effect of kill rate on the calculation
of minimum separator ID for different gas migration rates.
Vent-Line Friction Pressure Exceeds Mud-Leg Hydrostatic Pressure. Another area of concern is vent-line friction pressure exceeding mud-leg hydrostatic pressure, Pj > Pml' Several options exist
to help alleviate this problem.
1. Reduce the circulating kill rate. As discussed previously, a
reduction in the circulating kill rate may improve a separator's operation when vessel ID is considered and also when excessive ventline friction pressures are considered. This reduction in kill rate
may be the most economical solution to the sizing concern. For
SPE Drilling Engineering, December 1991
E_l.engtlt{n)
vL =
20
10
~
(pol)
.
..
10
11
12
example, if the kill rate for the previously sized separator were reduced from 3 to 1.5 bbl/min, the peak gas flow rate would decrease.
Combining Eqs. 1 and 3 and converting, we obtain
(=75.9/1.5=50.6 min
and qmax=9,036/50.6=1,443,903 ft31D.
This decrease in peak gas flow rate would significantly decrease
the excessive vent-line friction pressure and improve the operation
of the separator (Eq. 4).
Pj(5.0X 10- 12 x410x 1,443,903)217.0 5 =0.25 psi.
Fig. 8 shows the effect of kill rate on the calculation of vent-line
friction pressure for the previously sized separator.
2. Increase the mud leg. Another solution may be to increase the
height of the mud leg. For example, if we increased the previously
sized separator from a 7-ft mud leg to alOft mud leg, the mud-leg
hydrostatic pressure should increase (Eq. 6).
Pml=lOxO.26=2.6 psi.
Thus, the mud-leg hydrostatic pressure increased from 1.8 to 2.6
psi, allowing the separator to operate more efficiently.
Fig. 9 shows the effect of mud-leg height on the calculation of
mud-leg hydrostatic pressure for different mud-leg gradients. Note
that the mud-leg height cannot exceed the separator height. The
mud leg may also be restricted by bell-nipple elevation. If the mud
leg is higher than the bell nipple, additional surface equipment may
be required to permit the separator to operate when drilling with
significant gas in the mud returns.
3. Adjust vent-line bends. As shown in Table 1, the type and
number of bends in the vent line significantly affect the effective
vent-line length, which in turn affects the calculation for vent-line
friction pressure. If we were to replace the targeted T-bends on
the previously sized separator with right-rounded bends, the cal283
Author
G.R. MacDougall Is a drilling engineer
at Chevron Canada Resources Ltd. In
calgary. Previously, he was an engineer
at Chevron Services' Drilling Technology cantre. He holds a BS degree In minIng engineering from the Technical U. of
Nova Scotia.
s =
culations for the effective length (Eq. 5) and vent-line friction pressure (Eq. 4) would change:
L e =200+(3 X 1)=203 ft
and PI =(5.0x 10- 12 x203x2,887,806)217.0 5 =0.5 psi.
Hence, a vent-line friction-pressure decrease from 1.0 to 0.5 psi
increases the efficiency of the separator for a given mud leg. In
addition, the vent-line friction pressure increases proportionally to
the effective length (Fig. 10).
4. Increase vent-line ID. Increasing the vent-line ID is generally
the most expensive alternative but may be the only adjustment possible to increase separator efficiency. Larger-ID vent lines will
decrease the vent-line friction-pressure calculation. For the previously sized separator, if an 8.0-in.-ID vent line were used, the calculation for vent-line friction pressure (Eq. 5) would change to
PI =(S.Ox 10- 12 X41OX2,887,806)217.0 5 =O.S psi.
Again, a vent-line friction-pressure decrease from 1.0 to 0.5 psi
will increase separator efficiency for a given mud leg. Fig. 11 shows
the effect of vent-line ID on the calculation of vent-line friction pressure for the previously sized separator.
Conclusions
1. The principle of mud/gas separation within most commonly
used mud/gas separators is identical. Differences can be found in
the method of maintaining the mud leg.
2. A closed-bottom mud/gas separator is the preferred configuration. Open-bottom and float-type separators work well but are
subject to limitations and prone to failure.
3. Sizing of a mud/gas separator should be specific to individual
well conditions.
4. Modeling of gas flow through a mud/gas separator can be approximated by a simple procedure in a limited time.
S. A complete list of mud/gas separator components and considerations was compiled to assist with the design of mud/gas separators.
6. A trouble-shooting guide was developed to address economical upgrading of an existing insufficiently sized separator to meet
sizing guidelines as an alternative to building or renting a new
separator.
Nomenclatu...
A = cross-sectional area of gas vent line, ft2
CqJ = separator capacity, bbl/ft
d j = gas vent-line ID, in.
d s = separator ID, in.
t=
Vcmax =
Acknowledgments
I thank Chevron Services Co., Chevron Canada Resources, and
Chevron's Drilling Technology Centre for their assistance and permission to write and publish this paper.
References
1. Turner, E.B.: "Well Control When Drilling With Oil-Based Mud,"
Offshore Technology Report OTH86260, U.K. Operations & Safety,
Dept. of Energy, London (Oct. 1986).
2. Butchko, D. et al.: "Design of Atmospheric Open-Bottom Mud/Gas
Separators," paper SPE 13485 presented at the 1985 SPEIIADC Drilling
Conference, New Orleans, March 5-8.
3. Grigg, P.C.: "The Poor Boy Degasser as a Well Control TooI,'~ paper
presented at the 1980 IADC/CAODC Drilling Technology Conference,
Dallas, March 17-20.
4. Swaco Mud-Gas Separator Operation and Service Manual. Report No.
0380-0250, Dresser Industries Inc. (April 1982).
5. Brewton, I., Rau, W.E., and Dearing, H.L.: "Development and Use
of a Drilling Applications Module for a Programmable Hand-Held Calculator," paper SPE 16657 presented at the 1987 SPE Annual Technical Conference and Exhibition, Dallas, Sept. 27-30.
6. Engineering Data Book, ninth edition, Gas Processors Suppliers Assn.,
Tulsa (1979) Chap. 16, 1-41.
7. Hartman, H.L.: Mine Ventilation and Air Conditioning, John Wiley
& Sons Inc., New York City (1982) 131-61.
8. Spec. 121, Specificationfor Oil and Gas Separators, sixth edition, API,
Dallas (June 1, 1988).
9. Rader, D.W., Bourgoyne, A.T., and Ward, R.H.: "Factors Affecting
Bubble-Rise Velocity of Gas Kicks," JPT (May 1975) 571-84.
10. O'Bryan, P.L. and Bourgoyne, A.T.: "Methods for Handling Drilled
Gas in Oil-Based Drilling Fluids," SPEDE (Sept. 1989) 237-46.
11. Boiler and Pressure Code, Section Vlll Div. 1, Pressure Vessels, ASME,
Dallas (Dec. 1989) 101-36.
12. Standard MROl-75-84, Material Requirement, Sulfide Stress Cracking
Resistant Metallic Materials for Oil Field Equipment, NACE, Houston
(Jan. 1984).
284
t =
=
Vc =
vL
E-Ol
E-Ol
E-02
E-03
E+OO
E-Ol
E+OO
m3
m
m3
m3
cm
kg
kPa
SPEDE
Original SPE manuscript received for review Sept. 2, 1990. Paper accepted for publication
Sept. 30, 1991. Revised manuscript received Sept. 12, 1991. Paper (SPE 20430) first
presented at the 1990 SPE Annual Technical Conference and Exhibition held in New
Orleans, Sept. 23-26.