Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Fall 2012
Pg.
Pg.
Pg.
Pg.
Pg.
Pg.
Pg.
Pg.
Pg.
Pg.
Pg.
Pg.
Pg.
Pg.
Pg.
Pg.
Pg.
3
3
3
3
4
5
5
5
5
5
6
6
6
6
6
6
7
Table 1.1
List of Tables
Weight of Popsicle Sticks .... Pg. 7
Figure 1
Figure 2
List of Figures
Final chosen design...... Pg. 8
Alternative design... Pg. 8
Fall 2012
Fall 2012
were allowed, but they had to be only for the roadway and they were required to be
perpendicular to the length of the bridge. The bridge was allowed a maximum of 6 sticks stacked
on top of each other at any point on the bridge and stacks of sticks were required to be a
minimum of 1 inch apart from each other. Load supports were 29 inches apart, no more than
inches wide and inches high, and were 5 inches long. The bridge was required to be selfsupporting and had to be able to stand freely on its own. For the load testing a gap in the deck
was required exactly 10 inches from where the end supports would be assuming the span of 29
inches with the width of one Popsicle stick roughly 3/8 inches.
2.3 Quality Control Testing.
Weight of Popsicle Sticks - Table 1.1
Weight dry
(g)
2.6
5.4
8.0
11.0
13.7
16.5
19.1
21.7
24.4
27.1
# Sticks
2
4
6
8
10
12
14
16
18
20
y = 1.3785x - 0.0333
R = 0.9998
25.0
Weight (g)
20.0
15.0
linear
10.0
5.0
0.0
0
10
15
20
25
Number of Sticks
Our group purchased 300 Popsicle sticks for this project. By applying the equation
obtained through a series of data, the weight of 300 glued Popsicle sticks is expected to be
413.51 g. In fact, a total of 290 Popsicle sticks were used in building the bridge, the estimated
glued weight is 399.73. However, the final weight on the balance is measured to be 403 g, which
is heavier than the calculated weight.
Fall 2012
2.4 Aesthetics.
The final bridge was eye pleasing in general. It was symmetrical and had a smooth
continuous flow to it. The only part of it that was a little rocky was the actual roadway deck
because of a slight flaw in the cross beams under it the deck had a weird construction and had
some areas of overlap that caused it to be slightly bumpy. In general our bridge got an average
rating.
2.5 Economics.
There were three types of materials and costs for the construction of the bridge. The
first of them was the cost of the Popsicle sticks. In the initial bid the Popsicles cost $1,000 per
stick. Our initial bid was for 200 popsicle stick so we estimated a total expense for Popsicle
sticks to be $200,000. During construction we ran out of Popsicle sticks and were forced to
purchase more, but this time the cost per stick was $2,000. We bought 100 more sticks costing
our group another $200,000. Total expenses for only Popsicle Sticks turned out to be $400,000.
The next material we had to bid for was glue. Our group estimated we would need roughly 20
grams of glue. The glue itself went for $5,000 per gram. Our team spent $100,000 on glue. Total
expenses for just the Popsicle Sticks and glue came out to be $500,000 in the end because of our
error in guessing during the initial bid. The final coast was labor hours. We estimated that it
would take us 4 hours to build the whole bridge, but we were off by roughly 6 hours.
Fall 2012
(390/20)*(27.4-27.1) = 395.2 g. For the entire project, the total man-hours spent are 13.5 hours,
which means in average, 3.375 hours was spent on each person
6.0 Estimated Load Capacity.
Our design team estimated that the constructed bridge would be able to withstand roughly
35lbs of weight added to it. The end results were better than we had expected. Our bridge
withheld 56lbs of added weight which when converted to grams comes out to be roughly
25401.2g. Our failure load to bridge weigh ratio was 63:1.
7.0 Prototype Load Testing.
In order to test the bridge, the bridge was placed in between two tables edges, which is 43 inches
apart. A hole (testing spot) was made 10 inches away from the edge on the bridge. A chain was hung
down from the hole. And then, a bucket was attached to the chain and placed right below the bridge.
Below the bridge, sand and 15 pound weights were added into the bucket to increase the weight. .
Fall 2012
12.0 References.
12.1 ANGEL/Lessons/Design Project #1/Final Design Report/EDSGN100_Bridge
Building_SOW_F2012+.doc.
12.2 ANGEL/Lessons/Design Project #1/Final Design Report/EDSGN100_Bridge
Building_Specifications_F2012+.doc.
12.3 ANGEL/Lessons/Design Project #1/Final Design Report/EDSGN100_Stick
Weights_F2012+.xlsx.
12.4 ANGEL/Lessons/Design Project #1/Final Design Report/EDSGN100_Bridge
Competition_F2012+.xlsx.
12.5 West Point Bridge Designer (2011). Developed by Colonel Stephen Ressler,
Department of Civil and Mechanical Engineering, U.S. Military Academy, West Point, NY
<http://bridgecontest.usma.edu/download2011.htm>.
12.6 Virtual Laboratory: Bridge Designer. Johns Hopkins University, Baltimore, MD
<http://www.jhu.edu/virtlab/bridge/bridge.htm>.
<Compile a list of references if you used any outside resources and mentioned them in this
report, Referencing should follow a format like you may encounter in your textbooks.>
TABLES
Weight of Popsicle Sticks - Table 1.1
Weight dry
# Sticks
(g)
2
2.6
4
5.4
6
8.0
8
11.0
10
13.7
12
16.5
14
19.1
16
21.7
18
24.4
20
27.1
Fall 2012
y = 1.3785x - 0.0333
R = 0.9998
25.0
Weight (g)
20.0
15.0
Series1
10.0
linear
5.0
0.0
0
10
15
20
25
Number of Sticks
FIGURES
Figure 1: Chosen Final Design
Fall 2012
Fall 2012
10
Fall 2012