Contractor:
ESNAAD
AEGIS CONTRACTING LLC
Document Title:
Project Title:
Date:
Rev. No. 00
Page 1 of 9
Project Title
ESNAAD Main Gate Complex
Document Title
Method Statement for Cable Pulling & Termination of MV Cables
Re
v.
No.
Date
Descripti
on /
Remarks
Reviewe
d
Approve
d
Approved
Approva
l Status
Employer
Contractor:
ESNAAD
AEGIS CONTRACTING LLC
Document Title:
Project Title:
Date:
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 DEFINITIONS
5.0 RESPONSIBILITIES
6.0 EQUIPMENT
7.0 HEALTH AND SAFETY ARRANGEMENTS
8.0 PROCEDURE
8.3 CABLE TERMINATION & INSTALLATION
8.4 TESTING & COMMISSIONING
9.0 DOCUMENTATION
Rev. No. 00
Page 2 of 9
Employer
Contractor:
ESNAAD
AEGIS CONTRACTING LLC
Document Title:
Project Title:
Date:
Rev. No. 00
Page 3 of 9
1.0 PURPOSE
This method statement is applicable for laying & termination of MV Cables
for ESNAAD MAIN GATE TRUCK X-RAY COMPLEX in accordance with the
specified standards and regulations in project specifications.
2.0 SCOPE
The Scope of works includes the delivery to site, installation, precommissioning, testing, commissioning and guarantee of the system as
described in the specification/contract documents and drawings.
3.0 REFERENCES
3.1
3.2
3.3
3.4
3.5
3.6
4.0 DEFINITIONS
:
ATS Group/Advanced
(ATS/AIS)
Customer
CICPA
Operating Company
Contractor/Contractor
:
:
ESNAAD
Aegis Contracting L.L.C. (Aegis).
Subcontractor/Subtiers
Supplier
IR
Inspection Request
Employer/ Client
Integrated
Systems
Employer
Contractor:
ESNAAD
AEGIS CONTRACTING LLC
Document Title:
Project Title:
Date:
HSE
Rev. No. 00
Page 4 of 9
5.0 RESPONSIBILITIES
5.1 The Project Manager is over all responsible for implementation of
this Method Statement and to ensure that his site team of
Engineers and Foremen are aware of this Method Statement and all
resources, manpower, material and equipment are available to
carry out the work as planned and without any delay.
5.2 The Construction Manager/Site Engineer will co-ordinate with the
MEP Sub contractors and the Safety Officer, Foreman for a safe and
proper execution of works.
5.3 The Site Supervisor/General Foreman along with Foreman will
ensure that, the installation is carried out according to the
Specifications/Drawings and the Method Statement.
5.4 Lead QA/QC Engineer, in close interaction with MEP Site personnel,
will ensure that, the works are carried out as per the project
requirements. He is also responsible for the implementation of
QA/QC related to works as detailed in this procedure and for
completing Quality Documents for the Installation works.
5.5 Lead Safety Engineer will ensure implementation of all safety
procedures, Safety measures related to the nature of works being
carried out in accordance with Project HSE Plan EMG-HSE-01
Rev.00
6.0 EQUIPMENT
Cable Rollers
Cable Pulling Grip
Hand Cable cutter
Manual Cable Crimpers
Hacksaw blade
Power Tools
Tool Box
Measuring Tape
Ladders / Scaffoldings/Platform
Hand tools Hilti Drill Machine
Employer
Contractor:
ESNAAD
AEGIS CONTRACTING LLC
Document Title:
Project Title:
Date:
Rev. No. 00
Page 5 of 9
Ensure the working area at any confined space is free from any
Hazardous Gas by proper Gas testing using the Gas testing
instrument.
8.1.2 Materials
Employer
Contractor:
ESNAAD
AEGIS CONTRACTING LLC
Document Title:
Project Title:
Date:
Rev. No. 00
Page 6 of 9
After the test, the end of the cable shall be sealed to prevent
the ingress of moisture.
Cable laying will generally start from one end of the route
length or at any suitable point, as necessary.
Employer
Contractor:
ESNAAD
AEGIS CONTRACTING LLC
Document Title:
Project Title:
Date:
Rev. No. 00
Page 7 of 9
Suitable jacks shall be placed firmly on the ground and jackedup to allow clearance from the ground depending on the size of
the cable drum.
The entire body of the cable must enter the gland. The cable
shall be on a straight axis from a point at least six diameter
before entering the gland. Seals shall be checked for correct
size at the point of application.
Employer
Contractor:
ESNAAD
AEGIS CONTRACTING LLC
Document Title:
Project Title:
Date:
Rev. No. 00
Page 8 of 9
Unused cable entries shall be closed with plug suitable for the
degree of protection classification.
Employer
Contractor:
ESNAAD
AEGIS CONTRACTING LLC
Document Title:
Project Title:
Date:
Rev. No. 00
Page 9 of 9
9.0 DOCUMENTATION
9.1 Request of Inspections will be issued for all hold and witness points
as indicated on the Quality Control Plans
9.2 QC Forms will be jointly completed and signed off at the end of
Inspection.
9.3 Attachment:
Quality Checklist - Cable Pulling & Termination of MV
Cables Inspection
Risk Assessment