NOTICE INVITING TENDER
Tender No: KSEDC/KCC/TSD/PUR/ENQ/CPD/004/13-14 dtd. 29-10-2013
1. Kerala State Electronics Development Corporation Limited (Herein as referred to as KELTRON)
invites e-tenders from Authorised Distributor/ Dealer for Rate Contract for Hearing Aids (As per
Annexure 5) as per the Schedule of Requirement given in the General Terms & Conditions of the
Tender, for supplying through:-
(i)
(ii)
(iii)
(iv)
(v)
The Vendors can quote appropriate suitable regions accordingly & should cover the respective
districts fully on the concerned regions.
2. The items shall be delivered our site at various Panchayaths/ Muncipalities/ Corporations in Kerala
State within 2 4 weeks after confirmation of P.O.
Schedule of Requirement
Sl.
No.
1.
Item Description
Quantity
Duration
----
1 Year
from the
date of
signing the
Rate
Contract
TENDER EMD
FEE
Amount
(Rs.)
(Rs.)
----
----
3. The tender document should be submitted as per formats along with all relevant documents in
support of qualifications and experience.
4.
Tender Notification
http://etenders.kerala.gov.in/nicgep/app
29-10-2013
KSEDC/KCC/TSD/PUR/ENQ/
CPD/004/13-14 dtd. 29-10-2013
Request for clarification, if any
from bidders.
Uploading of e-tender (both
Envelope 1 and 2)
Submission of Pre-Qualification
Cum Technical Bid in sealed
cover (Envelope-1)
Opening of Pre-Qualification
and Technical Bids
Opening of Sealed Commercial
Bid
Will be
intimated later
5. Tender Documents shall be available only on the Internet and shall not be available for sales elsewhere.
6. KELTRON reserves the right to amend or cancel the tender in part or in full without prior notice at any
point of time
7. Keltron reserves the right to reject the bid of parties who have failed to provide adequate after sales
support for the products supplied against various orders.
8. Supplier shall provide access to their Website so that Keltron can verify whether the warranty
and coverage / scope details are updated in the website as per the order.
9. In the event of failure to deliver the materials as per the agreed delivery schedule, we should be entitled
to recover a sum equivalent to 1% of the value of materials not supplied in time for every 15 days delay
or part thereof subject to a maximum of 10% value. Also if the supplies are not within control, the buyer
is entitled to cancel the order and make necessary alternative immediate arrangements. Furthermore, if
the delay exceeds 21 days after the scheduled date of supply, such suppliers will not be considered for
the subsequent tenders.
10. The Special Instructions to the Contractors/Bidders for the e-submission of the bids are given under
Help to Contractors in website http://etenders.kerala.gov.in/nicgep/app
Head Materials
Kerala State Electronics Development Corporation Ltd
Keltron Communication Complex
Monvila, Kulathoor.P.O.,
Thiruvananthapuram-695 583,
Kerala
Tel: 0471-2598948 Fax:0471-2598984
Email: kelkcc.pur@gmail.com
3
SECTION 2
INSTRUCTIONS TO BIDDERS
1. INTRODUCTION - DEFINITIONS
1.1 KELTRON / The Buyer means Kerala State Electronics Development Corporation Limited.
1.2 "The Bidder / Vendor" means the individual or firm or company who participates in this tender and
submits its bid.
1.3 "The Supplier / Contractor" means the individual or firm making up the supply / work defined in the
Notice Inviting Tender.
1.4 The Supply Order/Purchase Order" means the order placed for the Rate contract for Spectacles.
1.5 "The Contract Price" means the price payable to the Contractor under the Supply Order / Purchase Order
for the full and proper performance of its contractual obligations
1.6 Non-Responsive Bid means a bid, which is not submitted in line with the tender requirements Invitation to Bidders, General Terms and Conditions of the Tender, Special Terms and Conditions of the
Tender and other conditions in the tender documents, Tender Fee etc.
2
ELIGIBILITY CRITERIA
2.1 Eligibility for Pre-Qualification Cum Technical Bid of Tender submitted 2.1.1 Bidders who are black listed by State / Central Government departments and
organizations are not eligible to participate in this tender and such bids will be summarily
rejected.
2.1.2 Bids containing Products of black listed companies will also be rejected
2.1.3 Documents to be submitted along with the Pre-Qualification cum technical bid of
Tender Document.
2.1.3.1
Certificate of Incorporation or Registration of the Firm / Partnership
2..1.3.2
2.1.3.3
2.1.3.4
2.1.3.5
2.1.3.6
A declaration Letter on your Letter Head by confirming the acceptance of SECTION 1, 2, 3
& 4 of our Tender Document.
3
COST OF BIDDING
3.1 The Bidder shall bear all costs associated with the preparation and submission of the bid. The Buyer, will
in no case, be responsible or liable for these costs, regardless of the conduct or outcome of the bidding
process.
BID DOCUMENTS
4.1 The required materials, bidding procedures and contract terms are prescribed in the Bid Documents. The
Bid Documents include4.1.1 Section
4.1.2 Section
II
Instructions to Bidders
4.1.3 Section
III
4.1.4 Section
IV
4.2 The Bidder is expected to examine all instructions, forms, terms and specifications in the Bid Documents.
Failure to furnish all information required as per the Bid Documents or submission of bids nonresponsive to the Bid Documents in every respect will result in rejection of the bid.
5
Bid Submission
7.1 The bidder shall submit the above tender document online in PDF/xls/rar/dwf formats well in advance
before the prescribed time.
8.
BID PRICES
8.1
Prices in the Commercial bid format shall be entered in the following manner:
8.1.1 The Basic Unit Rate of the Item in Rs. and Kerala VAT amount / CST amount in Rs
shall be entered in the respective cells of the format. Since we are able to avail
KVAT Credit, weightage should be given - if your billing should be done from
inside Kerala. For CST billing C forms will be arranged by us. Hence the
quote should be on concessional tax rates only.
8.2
The rate quoted by the bidder shall be on F.O.R our Sites basis.
8.3
The bidder shall quote the rates in numerals. The rates shall be in whole numbers
8.4
All expenses incurred during delivery of the item at destination including unloading charges has to be
borne by the bidder
9.
9.1 The bidder shall furnish, as part of his bid, documents establishing the conformity of his bid to
the Bid document of all Items and services, which he proposes to supply under the Contract.
Submission shall be as follows:
9.1.1
Bidder must attach required technical brochures / literatures / data sheets for all the products
asked in the tender to ensure that compliance to all the specifications given in the tender
document can be verified. All the brochures/literature/datasheets shall be counter signed and
stamped by the vendor or authorized signatory of vendor. Non-availability of specifications (as
mentioned in the tender document) in the brochure/literature will be treated as non-compliance
and no clarifications shall be asked in this regard. If bidder fails to submit the required
brochures/literatures along with the tender document, it shall be treated as non-compliance and
may lead to outright rejection of bid submitted by bidder. No clarifications in this regard shall
be sought from the bidder.
9.1.2
Each specifications sought shall be marked or highlighted in the attached brochures / literatures
/ data sheets. The brochures / literatures / data sheets shall be superscripted with the Item
Number and shall be arranged sequentially. The supporting documents shall carry all the
required specifications and same shall be marked.
9.1.3
The compliance statement submitted shall be duly supported by technical literature, equipment
brochures & other related reports / documents from the OEM. The compliance statement not
supported by the documentary evidence shall not be considered. Such bids shall be considered
as non-responsive and may result in rejection on technical grounds.
12
12.1 The Buyer shall evaluate in detail the Technical Bids (Cover 1) and determine whether the bid complies with
all the Qualitative Requirements (QRs) and shall be treated at par for the purpose of financial comparison.
Only technically successful bids will be considered for Commercial Bid opening.
13
13.1 Commercial Bids (Cover 2) of those vendors who qualify technically shall be opened. The Opening date of
the Commercial Bids will be uploaded in the website.
13.2 On comparison of evaluation, CST amount will be added on the cost of the bid. Kerala VAT will be
deducted from total cost of the bid.
14
15
AWARD OF CONTRACT
15.1 The acceptance of the tender will be intimated to the successful bidder by the Buyer,
15.2 The Buyer shall be the sole judge in the matter of award of contract and decision of the Buyer shall be final
and binding.
15.3 The buyer reserves the right to accept or reject the tender in full or part.
15.4 The buyer reserves the right to cancel the contract either in part or full, if the contractor fails to deliver the
specified quantity of the item at the stipulated time, and award the same to the next successful bidder. LD
Clause will be imposing at the rates specified previously.
16
16.1 The right to accept the tender in full or in part/parts will rest with the Buyer. However, the Buyer does not
bind itself to accept the lowest tender and reserves to itself the authority to reject any or all the tenders
received without assigning any reason whatsoever.
16.2 Tenders not accompanied with prescribed information or are incomplete in any respect, and/or not meeting
prescribed conditions, shall be considered as non-responsive and are liable to be rejected.
16.3 The Buyer reserves the right to accept or reject any bid or a part of the bid or to annul the bidding process and
reject all bids, at any time prior to award of contract without assigning any reason whatsoever and without
thereby incurring any liability to the affected bidder or bidders on the grounds for the Buyers action.
16.4 Tenders that are not accompanied with Tender fee shall be rejected outright..
16.5 The specifications indicated in the Tender Notification are the minimum and bids of the firms not
complying with these minimum requirements or having deviations equivalent to the minimum
requirements shall be rejected. However, higher than the minimum requirements shall be technically
acceptable without any additional financial implication.
SECTION 3
GENERAL TERMS & CONDITIONS OF THE CONTRACT
1
Compliance
2.1 The unconditional acceptance of all the terms & conditions of the Tender Notification has to be
submitted through this website. The format of the letter is attached at Annexure-2.
2.2 The submission of the tender will imply acceptance of all the tender condition by the bidder laid in
tender document including all the Annexure(s) & schedules to the tender document.
2.3 The compliance to the terms & conditions should be supported by authenticated documentation
wherever required.
4.1.1.1 The Buyer or his representative shall have the right to conduct pre-dispatch inspection of
the Hardware and Accessories. Where the Buyer decides to conduct such tests on the premises
of the Original Equipment Manufacturer (OEM) or Supplier of the OEM, all reasonable
facilities and assistance like Testing Instruments and other test gadgets including access to
drawings and production data shall be furnished to the inspectors at no charge to the Buyer. The
schedule & procedure of testing shall be intimated to the bidder after the placement of the
Purchase Order. The successfully inspected / accepted items shall be sealed in the presence of
the Inspectors and signed by the inspectors accordingly.
4.1.1.2 Should any inspected or tested Items fail to conform to the Specifications the Buyer may
reject them and the Contractor shall either replace the rejected Items or make all alterations
necessary to meet Specification requirements free of cost to the Buyer.
4.1.2 Post receipt / pre-installation testing
4.1.2.1 This final testing / inspection shall be performed at the Customer site at the time of delivery
of the equipment and the Inspector shall inspect the goods. The inspector shall also check the
goods delivered against the models ordered. The inspector shall reject the items, which are not
delivered as per the contract or any subsequent modifications to the contract, in terms of the
Technical Specifications. The inspector shall also receive the goods after inspection.
Force Majeure
6.1 KELTRON may grant an extension of time limit set for the completion of the work in case the timely
completion of the work is delayed by force majeure beyond the contractors control, subject to what is
stated in the following sub paragraphs and to the procedures detailed their in being followed. Force
Majeure is defined as an event of effect that cannot reasonably be anticipated such as acts of God (like
earthquakes, flood, storms etc), acts of states, the direct and indirect consequences of wars (declared or
un-declared), hostilities, national emergencies, civil commotion and strikes (only those which exceed a
duration of ten continuous days) at successful Bidders factory. The successful bidders right to an
extension of the time limit for completion of the work in above-mentioned cases is subject to the
following procedures.
6.1.1 That within 7 days after the occurrence of a case of force Majeure but before the expiry of the
stipulated date of completion, the bidder informs the KELTRON in writing about the occurrence of
Force Majeure Condition (as per Annexure-3 to the tender document) and that the Bidder considers
himself entitled to an extension of the time limit.
6.1.2 That the contractor produces evidence of the date of occurrence and the duration of the force
majeure in an adequate manner by means of documents drawn up by responsible authorities.
6.1.3 That the contractor proves that the said conditions have actually been interfered with the carrying
out of the contract.
6.2 Apart from the extension of the time limit, force majeure does not entitle the successful bidder to any
relaxation or to any compensation of damage or loss suffered.
Settlement of Disputes
8.1 If a dispute of any kind whatsoever arises between the KELTRON and the Contractor in connection
with, or arising out of the Contract or the execution of the works, whether during the execution of the
Works or after their completion and whether before or after repudiation or after termination of the
contract, including any disagreement by either party with any action, inaction, opinion, instruction,
determination, certificate or valuation of the Project Leader or his nominee, the matter in dispute shall,
in first place be referred to the Executive Director, Keltron who shall act as the conciliator on the
matter. The disputes will firstly be settled by the Conciliator, failing which any party may invoke
arbitration clause.
8.2 Unless the Contract has already been repudiated or terminated or frustrated the Contractor shall in
every case, continue to proceed with the works with all due diligence and the Contractor and
KELTRON shall give effect forthwith to every decision of the Project Leader or his nominee unless
and until the same shall be revised, as hereinafter provided, by the Conciliator or in an Arbitral Award.
SECTION - 4
SPECIAL CONDITIONS OF THE CONTRACT
1
The supply should be completed 2 4 weeks after confirmation of Purchase Order. Items shall be
delivered F.O.R. our Sites at various Panchayaths/ Muncipalities/ Corporations in Kerala State in
good condition.
2
Payment Terms
No mobilization advance shall be paid.
95% payment on back to back basis after getting collection from the customer & successful
supplies of items. 5% against Performance Bank Guarantee for a period of 1 year w.e.f the date of
supply to the end user.
Guarantee / Warranty
Warranty: 1 Year
4.
Dispatch Documents
Delivery Challan, Original Commercial Invoice in Triplicate, Original Excise Invoice (Original for
Buyer & Duplicate for Transporter Copies). Warranty Certificate, Test Reports etc.
6. Change of Specifications
a. No change of specification after the placement of Order shall be entertained unless the
alternate model offered are equivalent or higher in specifications and approval of the
competent authority has been obtained in writing for such a change of model before the
delivery of the product. Delivery of the alternate product without such an approval shall not
be accepted and KELTRON shall not be responsible for any delay in delivery schedule on
this account.
7. INTELLECTUAL PROPERTY RIGHTS
a. KELTRON recognizes the intellectual property rights of the Original Equipment
Manufacturer.
11
ANNEXURE-1
To
Head-Materials,
Keltron Communication Complex,
Monvila,Kulathoor. P.O.,
Thiruvananthapuram-695 583.
Kerala, INDIA.
Signature of Bidder
(seal)
12
ANNEXURE-2
BID FORM
To,
Head-Materials,
Keltron Communication Complex,
Monvila,Kulathoor. P.O.,
Thiruvananthapuram 695 583.
Kerala, INDIA.
Sub: Bid Form
Ref. Tender No. KSEDC/KCC/TSD/PUR/ENQ/CPD/004/13-14 dated 29-10-2013
Dear Sir,
1.
2.
3.
4.
5.
6.
7.
Having examined the conditions of tender contract, the receipt of which is hereby duly acknowledged, I / We, undersigned, offer
to the Rate Contract for Spectacles and execute the P.O with tender specifications referred above and also to the said terms &
conditions of contract for the sum shown in the commercial bid(s) attached herewith and made part of this bid.
I / We undertake, if our Bid is accepted, to complete supplies 2 4 weeks from the date of confirmed P.O.
I / We agree to abide by this Bid up to 31st January 2014 and it shall remain binding upon us and may be accepted at any time
before the expiration of that period.
Bid submitted by us is properly sealed and prepared so as to prevent any subsequent alteration and replacement.
We understand that you are not bound to accept the lowest or any bid, you may receive.
I / We affirm that I / We have enclosed the acceptance of all terms and conditions and also all brochures detailing the technical
specification of the items quoted by me/us.
The
tender
document
for
the
works
mentioned
above
have
been
obtained
by
me
from
the
URL:
http://etenders.kerala.gov.in/nicgep/app, the official website of Govt of Kerala and I / We hereby certify that I / We have read
the entire terms and conditions of the tender document, which shall form part of the contract agreement and I / We shall abide by
the conditions / clauses contained therein.
8.
I / We hereby unconditionally accept the tender conditions of KELTRONs tender document in its entirety for the above
supplies.
Witness 2. -----------------Signature
13
ANNEXURE-3
Detail of
Incident
Activity
affected
We are entitled to an extension in the date of completion as requested above. Bar Chart with revised schedule of
activities is attached. Please approve the extension in the time. Evidence of the date of occurrence is also enclosed.
It is certified that performance of the Contract has been interfered with. It is also certified that the incident has not
occurred due to our own action and that there has not been any lack of action by us in preventing the occurrence.
We are only claiming the extension in the date of completion of the activity (ies) and not claiming the loss
incurred in the course of the incident.
Yours truly,
(Project Leader)/Contractor
Enclosures:
1.
2.
14
ANNEXURE-4
Specification as
per tender
Specification of Variation
the item offered
Cross reference to
attached
brochures/documents
Signature of Bidder
(seal)
15
ANNEXURE-5
Schedule of Requirement
Item Description
Spectacles as per the list given below
Quantity
------
Duration
1 Year from
the date of
signing the
Rate
Contract
Sl.
No.
1
ITEM DESCRIPTION
SPECTACLES: LIGHT WEIGHT HIGH QUALITY, METAL GOLDEN/ SILVER/ GUN METAL
FRAME WITH CONCEALED SPRING SUPPORT AND UNIFOCAL POWER GLASS
SPECTACLES: LIGHT WEIGHT HIGH QUALITY, METAL GOLDEN/ SILVER/ GUN METAL
FRAME WITH CONCEALED SPRING SUPPORT AND UNIFOCAL POWER GLASS
(RESILENSE UNBREAKABLE)
SPECTACLES: LIGHT WEIGHT HIGH QUALITY, METAL GOLDEN/ SILVER/ GUN METAL
FRAME WITH CONCEALED SPRING SUPPORT AND BIFOCAL POWER GLASS
SPECTACLES: LIGHT WEIGHT HIGH QUALITY, METAL GOLDEN/ SILVER/ GUN METAL
FRAME WITH CONCEALED SPRING SUPPORT AND BIFOCAL POWER GLASS
(RESILENSE UNBREAKABLE)
16
2. The Vendor shall deliver/ distribute all the spectacles required at the corresponding
Units/ FOR Site or other places as per the requirement of customers distribution
Schedule. The price basis shall be FOR Site.
3. The Vendor shall provide Guarantee for the spectacles for 12 months from the date of
distribution of items. Any defect noticed during the above period, such devices shall be
replaced by the Vendor free of cost at Site.
4.
Any unforeseen expenses in connection with screening camp and distribution camp shall to
be borne by the Vendor.