Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1. Introduction
As a part of development of National Roads in Eastern Indonesia ( Eastern Indonesia
National Road Improvement Project : EINRIP ), selected road links have been developed
in the Island of Sulawesi ( South Sulawesi, North Sulawesi, Central Sulawesi and South
East Sulawesi ), Kalimantan ( West Kalimantan and South Kalimantan ), NTB ( Island of
Sumbawa ) and NTT ( Ende ). They include development of roads and bridges in 18 No.
Packages and 2 No. packages are planned for development soon ( ESS 05 and ESS 06 ).
The Total Loan given by AusAID for above development is about Aus$ 300 million
( AusAID Loan No. AIPRD L002 ).
2. Project Data
a. Province : South Sulawesi. Kabupaten : Kab. Bantaeng and Kab. Bulukumba
b. Project Limits : Starting Point : KM 122+000 from Mks and Ending Point : KM
148+875 from Mks.
c. Total Project Length : 26,875 km.
d. Width ( Urban areas ) : 7.00 m
Width ( Rural areas ) : 6.00 m.
Width ( Bantaeng City areas ) : 11.00 m
e. Topography : The entire road length is located in flat terrain, where part of the
road is located adjacent to the coastal region. In general there are paddy fields
and shrimp ponds located on the land side of the road. There are many bridges
long and short, of which at 5 No. locations, the existing bridges have been
replaced. In addition to above 13 No. new box-culverts have been constructed.
f.
Climatic Condition :
The project area is generally warm and has been
experiencing monsoon rainfall, which was quite intense during the peak rainy
season experienced in the project area.
g. Economic Condition and Economic Potential : The main occupation of the local
population is paddy cultivation, shrimp ponds and fishing industry in areas
adjacent to the coast. Apart from that, development of seaweed is being carried
out in large scale. In the stretch between Jeneponto and Bantaeng, there are
salterns over large area. Apart from above, tourist industry is booming in the
beaches of Bira and new such development is being made in between Bantaeng
and Bulukumba. Development of exotic plant is being made in the mountains
adjacent to the project area, which includes strawberry.
1
(j)
(k)
5. Major Works
The major works executed in the project, in general are as follows :
(a) Pavement construction composed of aggregate layers and asphalt layers
(b) Shoulder construction composed of paved sidewalks and penetration
macadam.
(c) Bridges and Box-culverts
(d) Pipe Culverts and Slab Culverts ( New and extension )
(e) U ditches ( Open and Covered type )
(f) Retaining Walls
(g) Gabion Construction
(h) Guard Rails
(i) Road Markings
(j) Traffic Signs
6. Aggregate and asphalt construction
(a)
(b)
(c)
(d)
1.500 km
17.675 km
1.900 km
5.800 Km
(c) Padangloang : Crushing & Blending plants and AMP were erected at this camp,
where materials were produced and used until completion of works. Though
essential laboratory equipment were available in the above camp for quality
control, major quality control works were performed at the camp at
Pajukukang.
8. Bridges and Culverts
Bridges :
(a) Pile Construction : There were 45 No. Bridges located in the project of which 5
No. bridges had to be replaced with new bridges. 5 No. bridges which were
relatively short had to be replaced with box-culverts ( either one, two or three
cells ) and at 13 No. Bridges no treatment whatsoever was planned except for
very minor repairs.
At 2 No. bridges for replacement, the foundation structure consisted of precast
concrete driven piles whereas in 3 No. bridges it consisted of bored piles. Pile
construction was made with relative ease, except at 1 No. bridge where, when
piles were driven, 2 No. piles could not be driven beyond shallow depth, due to
the presence of rock.
Hence, soil investigation was made by boring at two positions, and it was
determined that rock boulders were present and hence excavation was made
and the boulders were removed ( relatively shallow depth ) and construction
was completed conforming to drawings. Pile Load Test ( PDA Test ) was
performed as required and was found that the constructed piles were adequate
to carry load during service period.
(b) Bearing at Abutments and Piers : The bridge abutments contain composite
structure at the abutments, where the curtain wall at the abutment and slab in
deck are constructed monolithically. The design assumes that there will be no
relative rotation between the slab and the curtain wall and hence there will be
no need to provide elastomeric / rubber bearings at the abutments. Instead
fiber cement pad has been placed as bearing. Whereas at Piers, elastomeric
bearings have been placed and the design has been made, such that the deck
could be slightly lifted and the bearing could be replaced, without damaging
and without endangering the safety of the structure.
Whereas at the piers, continuous linking slab and elastomeric bearing pads
have been used. When during service period, replacement of bearings will be
necessary, the linking slab could be lifted along with the beams and the
bearings could be replaced, without the need to damage the slab or the beams.
(c) Detour and Temporary Bridge
4
At all locations ( 5 No. ) where new bridges are constructed, detour and
temporary bridges were required. Where as at locations where new boxculverts were constructed, detour and temporary bridges too were considered.
(d) Box culvert construction
At locations where detour could not be constructed due to difficulties in
acquiring land, construction is made in halves, i.e. one-half of the bridge is
demolished and reconstructed, while the remaining half is used by traffic. On
completion, the traffic is diverted on to the completed half and the remaining
half is constructed, thus the entire structure is replaced.
9. Coastal erosion :
During the months of March in 2012, the coast in the stretch Km : 124+250 to Km.
124+500 was affected by coastal erosion, including erosion / removal of the banks,
which were about 2 m. high above the sandy floor of the coast. As the result of it the
edges of the shoulder / verge were eroded and hence had to be protected.
Since, the above work was not anticipated, there were no pay items available in the
contract and hence temporary protection was made by placing large boulders and the
work was performed on day work basis. However, it should be noted that currently
most of the placed boulders are not visible and have sunk into the sand available at
that position.
We were informed by the project personnel that as a part of coastal protection the
Provincial / Kabupaten Government will soon construct protection along all areas
subject to erosion, including at the above position.
10. Sta : 23+600 Torele Bridge
At the above location 9.00 m long simple span bridge exists, and as per contract plan
the above bridge had to be replaced with 3 Barrel Box culvert. The existing structure
was investigated and load tests were performed to determine its suitability. It was
determined that the existing structure will be adequate to carry project load and the
width was sufficient. It was felt that it will be wise to retain the existing bridge.
The above question was brought to the attention of Bintek Officials, who made
intensive observation and analysis and it was decided to retain the bridge as it is, but
to provide gabion protection of the river bank both in upstream and downstream
directions to prescribed lengths.
Based on the above recommendations, the required gabion protection was
constructed in place and the existing bridge has been retained.
5
12. Utilities
At many locations in the project area, utilities such as telegraphic and electricity
poles, embedded water lines and embedded optic cables were available. The electric
and telephone poles were relocated by the relevant authorities. Whenever buried
optic cables were encountered, personnel from the relevant authorities were present
at site assisting construction, thus damage to them could be avoided. Similarly
assistance was sought from water authorities when works were carried out.
use in asphalt and the skid resistance will be reduced. Hence, the above matter
should be made clear and construction should be correctly implemented.
(e) 5 No. cold bins
The specification requires that 5r No. cold bins be used when asphalt base is
produced. The requirement should be checked and if possible it should be
avoided since in Indonesia AMP with 5 No. cold bins is not produced. There
are different opinions expressed in relation to use of 5 No. cold bins i.e. even if
5 No. bins will be used the materials will be mixed in the dryer and will be
separated in the hot bins before actual use. The same process occurs whether
4 No. cold bins or 5 No. cold bins will be used i.e. the real advantage of using 5
No. cold bins cannot be clearly understood.
There are quarters who claim that the above arrangement is most suitable if
continuous asphalt mixing plant will be used. Since in this project batching
type AMP is used, there will be need for 5 No. cold bins.
During construction of pavement, when the existing pavement was removed, telford
was determined at many locations, where the surface was not smooth and in some
locations, soft material was discovered under the telford and had to be removed and
replaced with suitable materials before construction could be continued.
At a very small section, the soft layer encounter4ed undermeath was relatively deep
and hence timber piles were driven to strengthen the surface before the required
materials could be placed and construction continued.
10
11
32. Bus-Bays
The contract requires bus-bays be constructed at several locations, for which
necessary land has to be acquired. The local government reported that no additional
land as required will be acquired and hence bus-bays were not constructed. However,
at new market in Lampucha, since land was not available for construction of bus-bay,
parking area has been developed inside the market area, with the hope to lure the
vehicles to park inside and not to cause difficulties on the road.
34. Trees
All trees as required have been removed and new trees have been planted as
specified. The works were carried out in association with the relevant department in
the Kabupaten to ensure their desires too are fulfilled.
The contract plans require that the trees within the city limits be removed and paved
sidewalks constructed. The City Government instructed that no trees be removed and
that no additional land will be made available for construction of sidewalk to required
width. Hence, the trees were retained and sidewalk with paving blocks were
constructed only over available width.
35. Environment
Environmental issues were checked and controlled in this project which included air
pollution by AMP and crushing plants, dust pollution, pollution of waterways, removal
of trees and all other features considered harmful to environment. Necessary
precautions were enforced, and were monitored very frequently ans required reports
were submitted.
37. Conclusion
Works were completed as required and PHO was made on March 12, 2012. However,
as recommended by the Safety Audit Consultants, additional works need to be
performed. Since, the Contractor has partly demobilized and the tendered price is
high, it is planned that the above works will be carried out by Contractor for ESS 01.
V.Thiagarajah : CSE A3
13