Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
4/10/2009 – 5/10/2009 To learn about painting. The painting is applied at equipment G2-101A
(Feed Gas Filter - sweating surface) and G2-301B (Mercury Removal Filter
– dry surface)
1
DETAIL REPORT
In every activity, the most important document is the Code & Standards which is needed for engineering
reference. In painting activity, these three documents are mandatory:
a) PTS 30.48.00.31 – PETRONAS Technical Standards for Protective Coatings and Linings
b) SSPC – Steel Structures Painting Councils’ Specification
c) NACE – National Association of Corrosion Engineers
Generally, painting activity will involved surface preparation, painting application and inspection
activities. The procedure is prepared by contractor and approved by owner (PGB). Before proceed further,
I would like to introduce some basic terms and the apparatus used throughout the painting procedure.
TERMS:
a) Surface Profile – The shape of a cross-sectioned power-tool-cleaning finish
b) DFT – Dry film thickness – The thickness of dried painting film
c) WFT – Wet film thickness – The thickness of wet painting film
d) RH – Relative humidity – A term used to describe the amount of water vapor exists in a gaseous
mixture of air and water
e) DP – Dew point – The temperature of metal surface that will be sweating
f) Wet Bulb Temperature – Lowest temperature that can be reached by the evaporation of water only
g) Dry Bulb Temperature – Normal air temperature
2
APPARATUS:
a) Power Brush (grinding machine)
b) Paint Thickness Gauge
c) Hygrometer (Relative Humidity Gauge)
d) Paint Brush
e) The Paint
Painting
How do select painting process? How do we determine whether it is SSPC-SP3 or SSPC-SP2?
1) The painting is applied at the external side of pipe, we shall use PTS 30.48.00.31 Section 6.2,
Painting and Coating System Schedules For External Application.
2) Check the material of the surface that will be painted. In this case, the material is SA-234 and SA-
106-B. Referring to ASME VIII Division 1, Table UCS-23 (Carbon and Low Alloy Steel) these
2 materials are carbon and low alloy steel. (please see drawing)
3) Check the insulation. The pipe is non insulated.
3
4) Check the design temperature. The design temperature is 50oF (10oC). Now the only scope left is
PTS 30.48.00.31 Section 6.2.1, Carbon Steel Design Temperature < 110 oC NON
INSULATED in the Atmospheric Zone. (please see drawing)
5) Check whether this painting is the initial or maintenance painting. This is the maintenance
painting.
6) Check the compatibility of the surface preparation. Since blast cleaning is not compatible in the
plant, we shall choose PTS 30.48.00.31 Section 6.2.1.3 Coating System No. 1C: Maintenance
Painting for Power Tool Cleaned Surface.
4
G2-301B, before cleaning G2-301B, during cleaning
This painting project requires special coating as the part that will be painted is sweating line. Proper
coating type as well as adequate ventilation is needed to achieve the desired DFT. This equipment is using
5
modified epoxy. The product use is Interzone 954. The DFT that shall be achieved is 400µ. The
specification is as below:
COAT DESCRIPTION PRODUCT COLOUR VOLUME DFT OVER THINNER
TYPE NAME GROUP SOLID (µ) COATING
(VS) % INTERVAL AT
40OC MIN-MAX
Full coat Modified epoxy Interzone Pearl Grey 85 400 3Hr – 5D International
954 GTA220
As mentioned by the Manufacturer, Interzone 954 has the specialty to cure when immersed in water.
Surface preparation is as SSPC-SP2. The surface to be coated is cleaned and freed from contamination.
Also, the application of painting is done 2 days as the painting work is using paint brush. As mentioned
by Manufacturer;
a) When applied by paint brush, typically 100µ to 150µ of DFT is achieved
b) When applying Interzone 954 by brush or roller, it may be necessary to apply multiple coas to
achieve the total specified DFT.
However, practically, it will depend on the calculation of the Painting Inspector. In this case,
minimum DFT 400µ had been achieved after painting work is carried out twice.
6
G2-101A, after painting
As per PTS 30.48.00.31 Section 5.2, painting is not permissible to be applied when the following
conditions occur unless recommended by Manufacturer and accepted by Owner:
a) The surface temperature is less than 3oC above the dew point
b) The surface temperature is below 5oC
c) When the relative humidity is above 85%
d) The metal surface temperature is higher than that recommended by Manufacturer
e) Surface preparation has not been completed
f) Poor weather condition for painting exist within 2 hours of application
INSPECTION:
As per PTS 30.48.00.31 Section 8.2.2, Painting Inspector is the one that is responsible to ensure the
quality of all aspects of painting is in accordance with the painting specification. Painting Inspector is
responsible to witness, verify, and document the various inspection points:
a) Pre-surface preparation inspection
b) Measurement of environmental conditions
c) Evaluation of compressor and surface preparation equipment
d) Determination of surface preparation cleanliness and profile
e) Inspection of application equipment
f) Witnessing paint mixing
g) Determination of wet film thickness (WFT)
h) Determination of dry film thickness (DFT)
7
i) Evaluating cleanliness between coats
j) Pinhole and holiday testing
k) Adhesion testing
l) Evaluating the curing of applied paints
m) Any other coating related activities
To determine the Dew Point and the percentage of Relative Humidity, the steps are as below:
1) Using Hygrometer, measure the dry bulb and wet bulb temperature.
2) After getting both reading, find the difference to get wet-bulb depression.
3) Using Psychrometric Chart to get the RH and DP.
For example:
Surface Temperature = 26oC
8
Referring to the Psychrometric Chart, the value of RH=71% and DP=20oC
Therefore, the minimum surface temperature allowed to be painted is 20oC + 3oC = 24oC
The RH is 71%, which is less than 85%
9
Table 19.4: Table UCS-23 – Carbon and Low Alloy Steel, extracted from ASME VIII, Division 1 (2007)
10
Table 19.5: Psychrometric Chart
11
Verified by (Plant Supervisor): SHAHRULLIZAM SHAHID
Initial:
12