NDE in ASME

NDT Related Clauses in Section - I


PG 78

: Repairs of Defects In Materials

May be, provided acceptance by the Inspector is first


obtained for the method and extent of repairs

PG 90

: Inspection and Test (General)

During Construction and After Completion by AI

PG 91

: Qualification of Inspectors

Qualification of AI

PG 93
: Examination and Repair of Flat Plate in
Corner Joints
For More than 14 mm, LPT and MT to be used
NDT in General Requirement
Presentation title - 12/05/2015 P 7
ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

NDE in ASME
NDT Related Clauses in Section - I
PW 11 : Volumetric Examination of Welded Butt Joints
Table PW 11
Either RT or UT until PW -11 restricts for any method

PW 40 : Repair of Defects
PW 46 : Inspection and Tests
PW 50 : Qualification of Nondestructive Examination
Personnel
Written Practice must be written by employer

Presentation title - 12/05/2015 P 8


ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

NDE in ASME
Radiographic Examination
PW 51 : Radiographic Examination
PW 51.1 : RT as per Section V
PW 51.2 : Permission for Backing Strip
PW 51.3 : Acceptance Standard
51.3.1 : Unacceptance of LOF, Crack, and LOP
51.3.2 : Unacceptance for Other Elongated Indication
51.3.3 : Aligned Indications ( L in 6L distance)
51.3.4 : Round Indications A 250

PW 5.4

: Retention of radiograph and record for 5 years

Radiography Reference in Section - I


Presentation title - 12/05/2015 P 9
ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

NDE in ASME
Ultrasonic Examination
PW 52 : Ultrasonic Examination
PW 52.1 : UT as per Section V, Article 4
PW 52.2 : Report Retention for 5 years
PW 52.3 : Acceptance Standard
52.3.1 : Unacceptance of LOF, Crack, and LOP
52.3.2 : Unacceptance for Other Elongated Indication
t mentioned in 52.3.2 is thinner for 2 joints

Ultrasonic Reference in Section - I


Presentation title - 12/05/2015 P 10
ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

Potrebbero piacerti anche