OPS/RFP/SVRS/GHOH/2015/001
RFP No. (UNOPS/RFP/SVRS/GHOH/2015/001)
Section 1: Proposal data
RFP number:
Project:
Procurement officials name:
Email:
Telephone number:
Facsimile:
Issue date:
UNOPS/RFP/SVRS/GHOH/2015/001
UNOPS KETA Project Volta Region, KETA GHANA.
+233 244376328
N.A.
April 29, 2015
Proposal due
OFFERORS ARE RESPONSIBLE FOR THE TIMELY SUBMISSION OF THEIR PROPOSAL.
Proposed due Date:
Time:
within 30 days
This UNOPS RFP consists of six sections and a series of annexes that will be completed by offerors and
returned with their proposal.
RFP section 1:
RFP section 2:
RFP section 3:
RFP section 4:
Approved by:
Ary Bobrow
Director and Representative, GHOH
Date: 29 April, 2015
2 Cost of Proposal
The cost of preparing a proposal, attendance at any pre-proposal conference, meetings or oral
presentations shall be borne by the offerors, regardless of the conduct or outcome of the solicitation
process. Proposals must offer the services/goods for the total requirement; proposals offering only part
of the services/goods will be rejected unless the option of submitting a proposal for any or all lot/s of the
requirement has been expressly stated in the TOR/SOW.
3 Eligibility
Offerors must not be associated, or have been associated in the past, directly or indirectly, with a
firm or any of its affiliates which has been engaged by UNOPS to provide consulting services for the
preparation of the design, terms of references, and other documents used for the procurement of the
services/goods under this Request for Proposal.
All suppliers are expected to embrace the principles of the United Nations Supplier Code of Conduct,
given that it originates from the core values of the Charter of the United Nations. UNOPS also expects
all its suppliers to adhere to the principles of the United Nations Global Compact.
Offerors must not be under a declaration of ineligibility for corrupt and fraudulent practices published
by UNOPS on its website. Offerors must meet the eligibility criteria as published on the UNOPS
website.
6 Language of Proposals
The proposals prepared by the offeror and all correspondence and documents relating to the proposal
exchanged by the offeror and UNOPS, shall be written in English. Supporting documents and printed
literature furnished by the offeror may be in another language provided they are accompanied by an
appropriate translation of all relevant passages in English. In any such case, for interpretation of the
proposal, the translation shall prevail. The sole responsibility for translation and the accuracy thereof
shall be the responsibility of the offeror.
7 Submission of Proposal
7.1. Offerors have to submit their proposal in hard copies. Technical and financial proposals must
be submitted simultaneously but in separate sealed envelopes with the RFP reference and
the clear description of the proposal (technical or financial) by the date and time stipulated in this
document, Section 1.
7.2. Proposals must be sent ONLY to the address detailed below. Proposals sent to other addresses
or to individuals put offers proposal at risk of being rejected.
Page 5 of 33
8 Late Proposals
Any proposals received by UNOPS after the deadline for submission of proposals prescribed in
this document, may be rejected.
9 Clarification of Proposals
To assist in the examination, evaluation and comparison of proposals, UNOPS may, at its sole
discretion, ask the offeror for a clarification of its proposal. The request for clarification and the
response shall be in writing and no change in the price or substance of the proposal shall be
sought, offered or permitted. UNOPS will review minor informalities, errors, clerical mistakes,
apparent errors in price and missing documents in accordance with the UNOPS Procurement
Manual 8.9 Discussions with vendors.
10 Proposal Currencies
All prices shall be quoted in US$ (United States Dollar)
UNOPS reserves the right not to reject any proposals submitted in another currency than the
mandatory bidding currency stated above. UNOPS may accept proposals submitted in another
currency than stated above if the offeror confirms during clarification of proposals (8) in writing that
it will accept a contract issued in the mandatory proposal currency and that for conversion the
official United Nations operational rate of exchange of the day of RFP deadline as stated in the
RFP letter shall apply.
Regardless of the currency of proposals received, the contract will always be issued and
subsequent payments will be made in the mandatory bidding currency above.
11 Mandatory/Pre-qualification Criteria
11.1. The mandatory requirements/pre-qualification criteria have been designed to assure that, to the
degree possible in the initial phase of the RFP procurement process, only those offerors with
sufficient experience, the financial strength and stability, the demonstrable technical knowledge,
the evident ability to satisfy UNOPS requirements and superior customer references for
supplying the services envisioned in this RFP will qualify for further consideration. UNOPS
reserves the right to verify any information contained in offerors response or to request additional
information after the proposal is received. Incomplete or inadequate responses, lack of response
or misrepresentation in responding to any questions will affect your evaluation
Page 6 of 33
11.2. Offerors will receive a pass/fail rating in the mandatory requirements/pre-qualification criteria
section. In order to be considered for Phase I, offerors must meet all the mandatory
requirements/pre-qualification criteria described in this RFP. See Annex B
The UNOPS General Conditions of Contract for services/goods and the UNOPS contract, as part
of this RFP, contain mandatory terms and conditions for offerors review and acceptance.
UNOPS will not entertain any proposed changes to the Non-Negotiable Articles. Offerors are
expected to confirm in writing their acceptance of these conditions by completing the mandatory
requirements/pre-qualification criteria as provided in Annex B. There will be no negotiation of
terms and conditions and contract terms at contract award.
30 points
15 points
15 points
60 points
In case UNOPS will notice a significant deviation from the proposed format (see annex D.1) for
financial proposal (I.E. missing services), the Bidder will be notified to confirm the total (or the
lot) lump sum price. By not confirming the price he will be automatically disqualified.
In case there are three or more proposals fully technically compliant, the financial evaluation
will be made for the entire proposal (total lump sum), including the eventual discount proposed
by the Bidders. The price for each lot will be taken into consideration only for the section of the
contract (after applying proportionally on the total the eventual discount)
In case there are two or lower number (even none) of proposal fully technically compliant, the
financial evaluation will be made lot by lot (independently).
Also in case of partial awarding (by lots), the award might be done to a single Consultant in
case he results the best for every lot or if the total of awarding to different Consultants result
higher than the total proposed by a compliant offer including the discount.
In all other cases the award will be proposed to different Consultants.
The defect liability period services will not be part of the financial evaluation (it must not be
included in the total lump sum price).
12.2.1.1. Formula for computing points:
Points = (A/B) Financial Points
Example
:
13 Preparation of Proposal
13.1. The offeror is expected to examine all terms and instructions included in the solicitation
documents. Failure to provide all requested information will be at the offerors own risk, and may
result in rejection of the offerors proposal.
13.2. The offerors proposal must be organized to follow the format of this RFP. Each offeror must
respond to every stated request or requirement, and indicate that the offeror understands and
confirms acceptance of UNOPS stated requirements. The offeror should identify any substantive
assumption made in preparing its proposal. The deferral of a response to a question or issue to
the contract negotiation stage is not acceptable. Any item not specifically addressed in the
offerors proposal will be deemed as accepted by the offeror. The terms offeror and contractor
refer to those companies that submit a proposal pursuant to this RFP.
13.3. Where the offeror is presented with a requirement or asked to use a specific approach, the
offeror must not only state its acceptance, but also describe, where appropriate, how it intends to
comply. Failure to provide an answer to an item will be considered an acceptance of the item.
Where a descriptive response is requested, failure to provide the same will be viewed as nonresponsive.
13.4. The terms of reference/statement of work in this document provides a general overview of the
current operation. If the offeror wishes to propose alternatives or equivalents, the offeror must
demonstrate that any such proposed change is equivalent or superior to UNOPS established
requirements. Acceptance of such changes is at the sole discretion of UNOPS.
13.5. Proposals must offer services/goods for the total requirement, unless otherwise permitted in the
solicitation document. Proposals offering only part of the services/goods may be rejected unless
permitted otherwise in the solicitation document.
The offerors proposal shall include all of the following labelled annexes:
Page 8 of 33
Part of proposal
Part of proposal
Part of proposal
Part of proposal
If after assessing this opportunity you have made the determination not to submit your proposal, we
would appreciate if you could return this form indicating your reasons for non-participation.
Pre-submission:
Offerors shall complete and return the Proposal/no proposal confirmation form prior to the submission
deadline, indicating whether they do or do not intend to submit a proposal.
Stand-alone
document
15 Award
15.1. The Award will be made to the responsible and responsive offeror with the highest evaluated
proposal following negotiation of an acceptable contract. UNOPS reserves the right to conduct
negotiations with the vendor regarding the contents of their offer. The award will be in effect only
after acceptance by the selected offeror of the terms and conditions and the terms of
reference/statement of work. The contract will reflect the name of the firm whose financials
were provided in response to this RFP. Upon execution of the contract, UNOPS will promptly
notify the unsuccessful offerors.
15.2. The selected contractor is expected to commence providing services as of the date and time
stipulated in this RFP, or as agreed with UNOPS at the time of Award.
15.3. The Award will be for a contract with an original term of 1 years & nine (9) months with the
option to extend under the same terms and conditions for an additional period or periods or
periods as indicated by UNOPS.
15.4. The Contract(s) for services will be a Lump Sum.
Page 9 of 33
15.5. In any case (meaning if there are different Consultants or a single one) the Contract will be
divided, managed and paid by Lots.
15.6. Even if the Bidder shall bound their proposal for the entire period and the entire service(s)
foreseen, at the end of any stage (see above Chapter 4) UNOPS will evaluate the performances
of the Consultant and might decide, if they are not satisfactory or if it is not in the interest of the
project to continue, not to proceed for the following ones.
15.7. The sections/lots in which the contract will be in any case divided are the following:
a)
Structural design, up to the final revision (after ESIA) and issuance of the for construction
set of documents (LOT 1)
b)
Engineering, up to the final revision (after ESIA) and issuance of the for construction set
of documents (LOT 2)
c)
Tender dossier, up to the completion of the evaluation of the bids, including clarifications
and eventual revisions needed (LOT 3)
d)
e)
Defect liability period (might not be included in the initial contract) up to the final
acceptance. The Consultant will be bound to the prices indicated in his proposal
Page 10 of 33
A.
Background
UNOPS is implementing a Project, funded by Korean International Cooperation Agency (KOICA) that
is aimed to build the facilities to host the newly created Midwifery College in Keta, Volta Region,
Ghana. The Project is implemented in partnership with the Regional Health Directorate (Volta Region),
the Municipal Authority (Keta) and of course the Nursing and Midwifery College in Keta (NMCK).
The Local Authority selected a public reclaimed- land for the location of the Project, 6,2 Acres, located
in the outskirts of Keta town centre, where some other buildings, belonging to the same College, have
been already built (or are under construction). The project will include academic buildings, the
auditorium, offices and residences for the teacher, with a total surface of around 2,500 sqm, distributed
in one or two storey buildings, as well as some external arrangements and connection to the utilities.
Typology, finishing and standards will be simple and basic, aimed to ensure durability, functionality and
easy maintenance.
The Project, approved in December 2014, has started in February 2015 and it is supposed to last two
and half years, including defect liability period.
In this frame some engineering services are required, particularly the design and supervision of the
construction works.
Once the design process will be completed and approved by the Project Board, presumably in July
2015, UNOPS is planning to launch a tender for a lump sum contract, within the frame of the (attached)
UNOPS Short Form Contract, drafted on the basis FIDIC Green Book.
The supervision will then accompany all the construction process, planned to last around 15 months,
up to the commissioning and handing over stage.
The aim of this RFP is to select the Consultant(s) to be appointed for the implementation of these
services.
Introduction:
UNOPS plays a critical role in providing management services for our life-saving, peace
building, humanitarian and development operations.
-Ban Ki-moon, United Nations Secretary-General
UNOPS mission is to expand the capacity of the UN system and its partners to implement peace
building, humanitarian and development operations that matter for people in need.
Working in some of the worlds most challenging environments, our vision is to always satisfy
partners with management services that meet world-class standards of quality, speed and cost
effectiveness.
UNOPS provides services in sustainable infrastructure, sustainable procurement and sustainable
project management, with projects ranging from building schools, roads, bridges and hospitals to
procuring goods and services and training local personnel.
By assisting UN organizations, international financial institutions, governments and other
development partners, UNOPS makes significant, tangible contributions to results on the ground.
Requirement overview:
Design
The main objective of the design is to define in all needed details the project, from a technical point of view,
with reference to all disciplines involved, in order to guarantee that the facilities will be suitable for the
purpose they are built. The design documentation produced by the Consultant shall guarantee carrying out
a fair tender process (enabling Bidders to get acquainted of the project characteristics) and of course it is
has to make sure that the selected Contractor will have all data to carry out the works (allowing complete
and full understanding of technical details and standards to be applied).
Works Supervision (WS)
The aim of the WS is to guarantee that the Contractor is implementing the works in accordance with the
approved project, in a workmanlike manner, that all technical implication are considered, test and controls
procedures are strictly respected, quality of the results is ensured.
The WS shall also monitor that all contracts condition are respected all along the process.
Finally the WS is aimed to identify, to define and/or analysing changes that might be required during the
construction process.
Commissioning
The main objective of the commissioning phase is to certify the final results of the construction process,
ensuring the facilities are suitable for their safe use, legal implications have been met and technical
requirements fulfilled.
B.
Please refer to the Document Attached (see annex Z, X, Y and K for all details)
C. Performance
Please refer to the Document Attached (see annex Z, X, Y and K for all details)
D.
Sustainability
UNOPS is committed to progressively streamline sustainability in all its operations, with due considerations
for local market conditions and local capacity development. UNOPS expects its suppliers to adhere to the
principles of the United Nations Global Compact, and to continuously strive to improve their social and
environmental performance
Please refer to Annex X design brief for all details.
A.
Metrics
1 Contract documents
1.1
This Contract is subject to the UNOPS General Conditions for Professional Services, [insert the current
version number and date from the document library], attached hereto as Annex I. The provisions of such
Annex shall control the interpretation of this Contract and in no way shall be deemed to have been
derogated by the contents of this letter and any other Annexes, unless otherwise expressly stated under
section 4 of this letter, entitled "Special Conditions".
1.2
The Consultant and UNOPS also agree to be bound by the provisions contained in the following
documents, which shall take precedence over one another in case of conflict in the following order:
a) this letter;
b) UNOPS Request for Proposal, reference [insert reference number], dated, and subsequent
amendments and clarifications, assumed to be known to both parties, including the Statement of
Work / Terms of Reference, attached hereto as Annex II;
c) the Consultant's technical proposal [reference [insert reference number], dated [insert reference date],
as clarified by the agreed minutes of the negotiation meeting [dated [insert meeting date]], both
documents not attached hereto but known to and in the possession of both parties.
1.3
All the above shall form the Contract between the Consultant and UNOPS, superseding the contents of
any other negotiations and/or agreements, whether oral or in writing, pertaining to the subject of this
Contract.
2.2. The Consultant shall provide the services of the following key personnel:
Name
[insert name]
[insert name]
Specialization
[insert specialization]
[insert specialization]
Nationality
[insert nationality]
[insert nationality]
Period of service
[insert period of service]
[insert period of service]
2.3. Any changes in the above key personnel shall require prior written approval of the Director, [insert name of
Director] RO/OC UNOPS.
2.4. The Consultant shall also provide all technical and administrative support needed in order to ensure the
timely and satisfactory performance of the Services.
2.5. The Consultant shall submit to UNOPS the deliverables specified hereunder according to the following
schedule:
[LIST DELIVERABLES][INDICATE DELIVERY DATES]
e.g.
Progress report
...............
Final report
../../....
../../....
../../....
2.6. All reports shall be written in the English language, and shall describe in detail the services rendered under
the Contract during the period of time covered in such report. All reports shall be transmitted by the
Consultant by [MAIL, COURIER AND/OR FAX] to the address specified in 9.1 below.
2.7. The Consultant represents and warrants the accuracy of any information or data provided to UNOPS for
the purpose of entering into this Contract, as well as the quality of the deliverables and reports foreseen
under this Contract in accordance with the highest industry and professional standards.
Milestone
Amount
Target date
[insert milestone]
[insert milestone]
[insert amount]
[insert amount]
[insert date]
[insert date]
4 Special conditions
4.1. The advance payment to be made upon signature of the contract by both parties is contingent upon receipt
and acceptance by UNOPS of a bank guarantee for the full amount of the advance payment issued by a
Bank and in a form acceptable to UNOPS.
4.2. The amounts of the payments referred to under section 3.6 above shall be subject to a deduction of [insert
percentage that the advance represents over the total price of the contract] % (... percent) of the amount
accepted for payment until the cumulative amount of the deductions so effected shall equal the amount of
the advance payment.
UNOPS/RFP/SVRS/GHOH/2015/001 (RFP for Design & Supervision)
4.3. Owing to [insert reason], Article(s) [insert article number?] of the General Conditions in Annex I shall be
amended to read/be deleted.
OR
4.1. No special conditions shall apply.
5 Submission of invoices
5.1. An original invoice shall be submitted by mail by the Consultant for each payment under the Contract to the
following address:
[insert address]
[insert address]
[insert address]
5.2. Invoices submitted by fax shall not be accepted by UNOPS.
8 Modifications
8.1. Any modification to this Contract shall require an amendment in writing between both parties duly signed
by the authorized representative of the Consultant and the Director, [.....] UNOPS.
9 Notifications
9.1. For the purpose of notifications under the Contract, the addresses of UNOPS and the Consultant are as
follows:
For UNOPS:
[Insert name of RO/OC Director]
Director
[RO/OC.....]
UNOPS
Address
Ref.______/______/______
[Insert contract reference and number]
Phone: [Insert phone number]
Fax:
[Insert fax number]
Email: [Insert email address]
For the Consultant:
[Insert name, address, phone, and fax/email]
10 Good faith
10.1. The Parties undertake to act in good faith with respect to each other's rights and obligations under this
Contract and to adopt all reasonable measures to ensure the realization of the objectives of this Contract.
If the above terms and conditions meet with your agreement as they are typed in this letter and in the
Contract Documents, please initial every page of this letter and its attachments and return to this office one
original of this Contract, duly signed and dated.
Yours sincerely,
[Insert name of RO/OC Director]
Director
[......] RO/OC
____________________________
Title
____________________________
Date
____________________________
ANNEX A
Request For Proposal
Structural and Engineering Design, Technical Dossier for tendering
and Supervision
OPS/RFPRS/ /001
UNOPS
Email:
Angelika@unops.org
RFP (UNOPS/RFP/SVRS/GHOH/2015/001)
ANNEX B
Request For Proposal
Structural and Engineering Design, Technical Dossier for tendering
and Supervision
OPS/RFPRS/ 2015/001
Offerors response
Provide name, company and
contact information
Reference #1:
Reference #2:
Reference #3:
Reference #4:
Reference #5:
1.4.
Yes/No
1.5.
The consultant shall prove and demonstrate that the
company has been established by not later than 3 years (2011
or earlier)
Yes/No
Yes/No
1.6.
Full acceptance of UNOPS General Conditions (for
Professional Services / Goods) and UNOPS Contract forService
contract template (Annexes C and D)
ANNEX C
Request For Proposal
Structural and Engineering Design, Technical Dossier for tendering
and Supervision
OPS/RFPRSHOH/2015/001
b.
This Technical Proposal Submission Form consists of this cover page, the Certificate of the Offerors
Eligibility and Authority to sign the Proposal, and the Technical Proposal itself.
c.
The entire Technical Proposal and all required and optional documentation related to the technical
component of the proposal, must be placed in an envelope pre-addressed and marked:
10.1.1.
RFP No. UNOPS/RFP/SVRS/GHOH/2015/001 (description of requirement) Technical proposal(name and address of Offeror)
10.1.2. If submitted by email, the email subject line should read:
10.1.3. RFP No RFP (UNOPS/RFP/SVRS/GHOH/2015/001- (Name of Offeror) - Technical proposal
d.
The Technical Proposal envelope / the Technical Proposal email is herewith submitted in
accordance with the instructions given in the Request for Proposal.
e.
The completed and signed Technical Proposal Submission Form, together with the mandatory
requirements / pre-qualification criteria document completed by me (Appendix 1 to this offer),
together with any other supporting documentation submitted in accordance with this RFP and/or
voluntarily constitutes the offerors Technical Proposal and fully responds to the Request for
Proposal No RFP (UNOPS/RFP/SVRS/GHOH/2015/001
Offerors Response
4. Have you ever been terminated for non-performance on a contract? If YES, describe
in detail.
defines, for the purposes of this provision, the terms set forth below as follows:
Confirm
Yes _____; No ______
Offerors Response
(i)
corrupt practice is the offering, giving, receiving or soliciting, directly or indirectly,
of anything of value to influence improperly the actions of another party;
(ii) fraudulent practice is any act or omission, including misrepresentation, that
knowingly or recklessly misleads, or attempts to mislead, a party to obtain financial or
other benefit or to avoid an obligation;
(iii) collusive practices is an arrangement between two or more parties designed to
achieve an improper purpose, including to influence improperly the actions of another
party;
(iv) coercive practices is impairing or harming, or threatening to impair or harm, directly
or indirectly, any party or the property of the party to influence improperly the actions of a
party;
(v)
obstructive practice is
(aa)
deliberately destroying, falsifying, altering or concealing of evidence material to
the investigation or making false statements to investigators in order to materially impede
a Bank investigation into allegations of a corrupt, fraudulent, coercive, or collusive
practice; and/or threatening, harassing, or intimidating any party to prevent it from
disclosing its knowledge of matters relevant to the investigation or from pursuing the
investigation; or
(bb)
acts intended to materially impede the exercise of UNOPS inspection and audit
rights.
Confirm that the offeror and its sub-contractors have not engaged in any corrupt,
fraudulent, collusive, coercive or obstructive practices in competing for this solicitation.
7.
Officials not to benefit: Confirm that no official of UNOPS has received or will be
offered by the offeror or its sub-contractors, any direct or indirect benefit arising from
this solicitation or any resulting contracts.
8. Confirm that the offeror supports the principles of the United Nations Global
Compact, which includes respecting fundamental human- and labour rights and
advancing environmental responsibility.
9.
Confirm that the offeror is not engaged in any activity that would put it, if selected for
this assignment, in a conflict of interest with UNOPS.
Confirm
Yes _____; No ______
Confirm
Yes _____; No ______
Confirm
Yes _____; No ______
10. Confirm that the offeror and your sub-contractors have not been associated, or had
been involved in any way, directly or indirectly, with the preparation of the design,
terms of references and / or other documents used as a part of this solicitation.
Confirm
11. UNOPS policy restricts companies from bidding on or receiving UNOPS contracts if a
UNOPS staff member or their immediate family are an owner, officer, partner or board
member or in which the staff member or their immediate family has a financial
interest. Confirm that no UNOPS staff member or their immediate family are an
owner, officer, partner or board member or have a financial interest in either the
offeror or its sub-contractors.
Confirm
____________________
(Signature)
___________________________
(Name)
____________________
(Title)
________________
(Date)
Provide the name and contact information for the primary contact from your company for this quotation:
Name: ________________________________ Title: ________________________________
Mailing address (street name/number/city/town/province/state): __________________________
____________________________________________________________________________
Tel. no: _________________________ Fax no: ___________________________
Email address: _______________________________
Offer valid until: _____(date)_____ Must be at least 90 days
Currency of offer: (state currency) Payment terms 30 days accepted:
Are you a UNOPS registered vendor? Yes No If yes, provide vendor number: _______________
Offerors response
Completeness of the proposal
Demonstrate, by listing and describing the products you are going to provide,
that the services included in your proposal are achieving expected results
Structural design
Engineering design
Tender dossier
Works supervision and commissioning
Defect liability period follow up
Appropriateness of the methodology (design)
demonstrate with rational description and schedule that the methods proposed
for the implementation of the services is in line with the expected phases of the
process
Q2.1.
Q2.2.
Conceptual design
Q2.3.
Coordination workshop
Q2.4.
Final design
Q2.5.
3.
Weight 12.5
%
Q3.1.
Q3.2.
Q3.3.
Q3.4.
Q3.5.
4.
Weight 25 %
Section
Q4.1.
Q4.2.
Q4.3.
Q4.4.
Offerors response
LOGICAL RELATION BETWEEN DESIGN PRINCIPLE TO BE APPLIED
AND SOLUTION
PROCEDURES TO ADHERE THE MANUAL
MECHANISM OF SUPERVISION
Q4.5.
The bidder shall refer to Annex 4 (and annexes Z, X, Y and K) to draft and redact his proposal.
ANNEX D
Request For Proposal
Structural and Engineering Design, Technical Dossier for tendering
and Supervision
OPS/RFPRSHOH/2015/001
___________________________
(Name)
____________________
(Title)
________________
(Date)
Provide the name and contact information for the primary contact from your company for this quotation:
Name: ________________________________ Title: ________________________________
Mailing address (street name/number/city/town/province/state): __________________________
____________________________________________________________________________
Tel. no: _________________________ Fax no: ___________________________
Email address: _______________________________
Offer valid until: _____(date)_____ Must be at least _(90)_ days
Currency of offer: (state currency) Payment terms 30 days accepted:
Are you a UNOPS registered vendor? Yes No If yes, provide vendor number: _______________
ANNEX G
Request For Proposal
Structural and Engineering Design, Technical Dossier for tendering
and Supervision
OPS/RFPRSHOH/2015/001
___________________
Date (Day/Month/Year)
ANNEX E
RFP (xx-xxx)
ANNEX I
UNOPS General conditions of contract for professional services
https://www.unops.org/SiteCollectionDocuments/Procurement/GCCs%20For%20Professional%20Services.pdf
ANNEX E
RFP (xx-xxx)
ANNEX E
Request For Proposal
Structural and Engineering Design, Technical Dossier for tendering
and Supervision
OPS/RFPRSHOH/2015/001