SONATRACH

SKIKDA NEW LNG TRAIN PROJECT


SKIKDA, ALGERIA
ALGERIAN REGULATORY AUTHORITY (ARA - DPEM & ONML)
REQUIREMENTS AND COORDINATION PROCEDURE
BETWEEN ARA, PURCHASER (KBR) & SUPPLIER
Document NO. PR101

JOB NO.: J6404


5

17 Apr 08

Issued for Implementation

D. Perry

L. Albrecht

I. Smith

3 Mar 08

Issued for Implementation

D. Perry

L. Albrecht

I. Smith

8 Oct 07

Issued for Implementation

L. Albrecht

D. Perry

I. Smith

24 July 06

IFD

Al
Tansiongco

I. Mahmud

B.
Bradfield

6 Jun 06

IFD

A.
Tansiongco

I. Mahmud

B.
Bradfield

23 Jan 06

IFD

Al
Tansiongco

J. Britton

T. G.
Jayanth

Rev.

Date

By

KBR

KBR

CLIENT

Chkd

App

App

Description

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

CONTENTS

FRONT PAGE AND DOCUMENT REVISION RECORD


ABBREVIATIONS.................................................................................................... 3
ALGERIAN REFERENCE DOCUMENTS.......................................................................3
1.0

PURPOSE..................................................................................................... 4

2.0

GENERAL..................................................................................................... 4

3.0

TYPE OF EQUIPMENT SUBJECT TO DPEM CONTROL........................................4

4.0

DEFINITIONS................................................................................................ 5

5.0

RESPONSIBILITIES........................................................................................6

6.0

ITEMS SUBJECT TO INVOLVEMENT OF DPEM / ONML......................................8

7.0

DOCUMENTATION SUBMITTALS...................................................................15

8.0

SCOPE OF DPEM INSPECTION (CIRCULAR 02 AND 04)..................................21

9.0

NAMEPLATES.............................................................................................24

10.0

DOCUMENT QUANTITY & FORMAT...............................................................24

11.0

NOTICE OF INSPECTION & TEST..................................................................26

12.0

EQUIPMENT RELEASE CERTIFICATES............................................................26

13.0

ATTACHMENTS........................................................................................... 26

ATTACHMENT 1: PRELIMINARY DOSSIER FORMS, DOCUMENT 1 8........................28


ATTACHMENT 2: FINAL DOSSIER FORMS, DOCUMENTS 10 24..............................38
ATTACHMENT 3: DPEM DOCUMENTATION TRANSLATION CHECKLIST......................53
ATTACHMENT 4: FAX REQUEST FOR PRESENCE OF DPEM/ONML INSPECTOR..........57
ATTACHMENT 5: ARA / DPEM DOCUMENTATION & ACTIVITIES...............................58
ATTACHMENT 6: FLOWCHART PRELIMINARY DOSSIER.........................................59
ATTACHMENT 7: EQUIPMENT LISTINGS................................................................60

Page 2 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

ABBREVIATIONS
ARA
DPEM

SH
KBR

Algerian Regulatory Authority


Direction du Patrimoine Energtique et Minier du Ministre de l Energie et des
Mines
Office National de la Mtrologie Lgale (National Organization for Legal
Measurements
Sonatrach, the Client/Owner
Kellogg Brown & Root International, Inc., the Purchaser/Contractor

ITP
LNG
PSV
QCP
SDR

Inspection and Test Plan


Liquefied Natural Gas
Pressure Safety Valves
Quality Control Plan
Supplier Document Requirements

ONML

ALGERIAN REFERENCE DOCUMENTS


DPEM Circular No. 2 Technical Control Regulations for Installations for the Treatment
and Storage of Hydrocarbons and Electric Power Generating Stations
DPEM Circular No 4 - Technical Inspection Regulations for Installation for Export of Liquid
Hydrocarbons, Liquefied Hydrocarbons and Gasses Under Pressure and
Associated Works
Decree 90-245 - Statutory Regulations for Gas Pressure Equipment
Decree 90-246 Statutory Regulations for Steam / Vapour Pressure Equipment
Decree 88-35 Statutory Regulations for Pipelines and Auxiliary Facilities Related to the
Production and Transportation of Hydrocarbons and Applicable Procedures

Page 3 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

1.0

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

PURPOSE
The purpose of this document is to define the Skikda New LNG Train Project
responsibilities for the coordination of all parties involved in the inspection and test
activities, at fabrication shops and jobsite that are subject to the approval and
acceptance of the Algerian Regulatory Authority (ARA), through agencies Direction du
Patrimoine Energie et des Mines (DPEM), and National Office of Legal Metrology
(ONML).

2.0

GENERAL
The requirements of this procedure apply to the equipment, devices and material that
are subject to ARA control. These requirements do not have any effect on the
inspections required by Purchaser and any waiver by ARA is not to be construed as a
waiver of any other requirements for inspection by Purchaser or any other obligation of
the Supplier noted elsewhere in the Purchase Order.
Supplier and Suppliers sub-suppliers will be subject to inspection of all materials and
equipment being manufactured or supplied.
The Supplier shall pass on the
requirements of these DPEM inspections to all of the Suppliers contracts (purchase
orders) to its sub-suppliers. These inspections are in addition to any other inspection
or testing requirements noted elsewhere.
The Supplier will undertake to facilitate all inspections made by ARA, Client personnel,
or other third parties related to ARA or Owner, under authority of ARA, on the premises.
The Supplier further undertakes to facilitate ARAs attendance at all inspection or
acceptance tests planned or required by contract to be conducted by the Supplier or
Sub-supplier.
REFERENCE: DPEM Circular No. 2 & 4, Algerian Decrees 90-245, 90-246 & 88-35

3.0

TYPE OF EQUIPMENT SUBJECT TO DPEM CONTROL


The following types of equipment are generally subject to DPEM regulations and
testing when they meet the criteria detailed below.

Pressure equipment, with conditions.


Safety systems such as CO2, fire water pump and foam extinguishing systems.
Fire fighting gas bottles and mass-produced pressure bottles of ASME UM design
(stamped or not)
Electrical equipment rated at 5.5 kV or higher.
Pressure Safety Valves, with conditions.
Valves (Control Valves, and other valves meeting piping criteria)
Gas or vapour compressors, with conditions.
Instrument Air Compressors- air compressor casing
Fire extinguishers whose capacity exceeds five (5) Litres, with conditions.
Auxiliary Systems for Packaged Equipment
Filters, fuel gas filters.
Lifting device above 5 tons. (ex: Overhead Crane and Man Lifts)
Page 4 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

Shop Fabricated & Field-Erected Tanks (see paragraph 6.2.4)

A Preliminary and a Final Dossier are required for all the equipment and material falling
within DPEMs scope.
For off-the-shelf, (stock) items of piping materials safety systems components,
electrical power cables or other electrical items (5.5 Kv and higher) that fall under the
DPEM criteria, the supplier shall submit a Technical File
The contents of the dossiers above are detailed in Sections 7.4, 7.5 and 7.7 of this
procedure.
All documents must be provided In French & English and in quantities shown in Section
10, and as summarized in Attachment 3.
4.0

DEFINITIONS
The definitions below refer to terms used in this procedure and are used for
convenience of reference in this procedure only. Contractual terms shall be as defined
in the Project Terms and Conditions of Purchase.
Preliminary & Final Dossier: A compilation of mandatory documents which provides a
record of quality checks performed by the Supplier throughout the design and
manufacture of the item. The Dossiers require Algerian Regulatory Authority
approval.
Direction du Patrimoine Energie et Mines (DPEM): An Algerian Regulatory Authority
Agency responsible for compliance with applicable decrees and regulatory technical
controls, and for performing independent Inspection and Witness of Equipment Test
at fabrication locations and Algerian construction Sites.
National Office of Legal Metrology (ONML): An Algerian Regulatory Authority Agency
responsible for compliance with applicable decrees and regulatory technical controls,
and for performing independent Inspection and Witness Testing of Fiscal Metering
Package at Suppliers location and Algerian construction Sites.
Quality Control Plan (Inspection & Test Plan): Purchase Order specific document that
clearly identifies in chronological and sequential order all manufacturing Inspection &
Testing requirements performed by the Supplier / Sub-supplier with facility for all
parties to indicate proposed Quality Control activities. The Quality Control Plan
identifies the witness and hold points for the Supplier, Purchaser, Owner and ARA.
Owner and ARA witness and hold points will be provided by Purchaser
Supplier Document Requirements (SDR): A listing of documents required to be
submitted to Purchaser including document submittal codes and target dates for
submittal.
Inspection and Test Plan (ITP): A Purchasers quality control form contained in
requisitions.
Page 5 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

Originals: The supplier document that contains wet stamp, signatories and endorsed
original from which copies are made. The originals of the Dossiers shall be delivered
to the Purchaser.
5.0

RESPONSIBILITIES

5.1

Purchaser
The Purchaser (KBR) is responsible for the following:

Facilitating the service agreement between Purchaser and the relevant ARA.
Advising the Supplier of relevant ARA involvement by including this procedure in the inquiry
(request for quotation) documents.
Ensuring Purchaser Inspector performs a review of Preliminary & Final Dossier at Supplier
location prior to submittal to Purchasers home office for processing and forwarding to
ARA.
Controlling and expediting the submission and distribution of the Suppliers Preliminary and Final
Dossier to the relevant ARA and Owner.
Ensuring the Purchasers inspector performs the required activities prior to the ARA Inspection.
Issuing all inspection and test notifications to relevant ARA per Section 11.0, and confirmation of
ARA inspection activities to the Supplier.
5.2

Supplier
The Supplier is responsible for the following:

5.2.1

Identifying, in the Bid, all items, components and/or appurtenances in the scope of
supply that meet the criteria of paragraph 6.0 and, hence, are subject to ARA
involvement. This is particularly important for equipment such as compressors, control
valve actuators, hydraulic power supplies and the like that contain piping,
accumulators, filters and other components and appurtenances that are dependant on
the Suppliers design.

5.2.2

Submitting to Purchaser an overall schedule, including tests, within the time shown
after receipt of Purchase Order in the Purchasers SDR included in the Purchase Order.

5.2.3

Ensuring that Attachment 1 Document 2, Certification by the Chamber of Commerce


of the Fabricator Signatures Algerian Consulate Stamp and Document 3 Certificate
of Conformity and of Internal and External Inspections, Attesting that the Equipment
Constructed Conforms to the Country of Origin is completed and fully signed by all
parties, including the Fabricators local Chamber of Commerce (as applicable).

5.2.4

Ensuring Certificate of Conformity and of Internal and External Inspection (Attachment


1 - Document 3) are stamped by the Algerian Consulate.

Page 6 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

5.2.5

Compiling the Preliminary Dossier and submitting it to the Purchaser preferably 6


weeks after purchase order / sub-order placement (but not less than 50 calendar days
prior to commencement of fabrication) for items relevant to DPEM / ONML involvement.
See Attachment 1 for Contents of this Dossier.

5.2.6

Issuing to the Purchaser all inspection notifications for DPEM / ONML activities as
indicated in the agreed Quality Control Plan. Notifications shall be made at least 45
days in advance the tests in accordance with the production and testing schedule.
(See Section 11.0)

5.2.7

Ensuring the applicable documentation is prepared and available for DPEM inspectors
review prior to test, per Section 8.1.

5.2.8

Submitting Final Dossier to Purchaser within thirty (30) calendar days after successful
completion of scheduled works and prior to shipment.

5.2.9

Ensuring a French and English copy of each approved Preliminary Dossier is retained
for DPEM Inspectors review per paragraph 8.1.

5.3

DPEM / ONML
The DPEM/ONML is responsible for the following:

5.3.1

Approving the Preliminary and Final Dossier of designated equipment and materials as
indicated in the Convention (Contract).

5.3.2

Reviewing and approving Preliminary Dossier and issuing approval consent within forty
five (45) calendar days of submission.

5.3.3

Confirming attendance or non-attendance by their representative at the indicated


inspection activity, per Suppliers Quality Control Plan (Inspection and Test Plan).

5.3.4

ONML is responsible for the Independent Inspection and Witness calibration of Fiscal
Metering packages.

5.3.5

Endorsing all relevant Final Dossier documents at Suppliers facility (Documents 19, 20
& 22) during their visit.

Page 7 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

6.0

ITEMS SUBJECT TO INVOLVEMENT OF DPEM / ONML

6.1

General:
If a device (pressure container) or material is within the DPEM scope as defined below,
the supplier is notified by the inclusion of this procedure in the procurement package.
Members of DPEM will conduct an inspection or witness testing. If DPEM does not
attend, they may request the Purchaser to assign a third party to inspect or witness on
their behalf.

6.2

Detailed Requirements and Criteria

Pressure Devices (Reference: Algerian Decree 90-245, Gas Pressure Equipment)


The following items are some examples that are considered as pressure devices:
Furnaces
- C02 Bottles (and other gasses)
Reactors
- N2 Fire Extinguishers
Columns
- Compressor
Heat Exchangers
- Piping
Air Coolers
- Pressure Vessels
Separators
- Filters
Please see Attachment 7 for Equipment Listings that require DPEM presence. For
detailed information see the individual Articles

6.2.1

Other Gas Pressure Devices (Pressure Containers)


Gas Pressure Devices that are not steam or hot water vessels come within DPEM
scope when they are handling liquid hydrocarbon, compressed gas, liquefied or
dissolved gas and pressurized overheated liquids, and if the following conditions are
simultaneously met (Decree 90-245, Article 2, Item 1):

6.2.2

The design pressure exceeds 4 BarG

The characteristic number; i.e. the product of the design pressure expressed in
BarG, multiplied by the capacity expressed in Liters, exceeds the number 80.

Steam Pressure Devices (Reference: Algerian Decree 90-246, Steam Pressure


Equipment)
This portion of the Algerian Regulations is not applicable to this procedure for the
Skikda New LNG Train Project.

6.2.3

Storage Tanks
The hydrocarbon, hazardous product and fire water storage tanks are within the scope
of DPEM.
The water storage tanks (other than fire water) are not subject to DPEM inspection

Page 8 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

Tanks operating at atmospheric pressure, with direct access to the atmosphere, are
generally excluded from the scope of DPEM. Supplier is required to notify and obtain
the advice of the Purchaser for any tank designed to contain hazardous liquids which
could, under maximum overfill conditions, be subject to a hydrostatic pressure such that
the stress in any member is equal to, or exceeds, five eighths (5/8) of the elastic limit of
the material being used.
6.2.4

Pumps (Decree 90-245, Article 2, Item 1)


Pumps, except firewater pumps, are generally excluded from the DPEM scope but
Supplier / Sub-supplier shall notify and obtain advice from Purchaser for any pump
which has a fabricated casing or body. In that case, the criteria for gas pressure
devices, paragraph 6.2.2, shall apply.

6.2.5

Turbines
DPEM does not witness the testing of the turbines but will witness its components that
are under DPEM jurisdiction (e.g. lube oil systems/piping systems).

6.2.6

Compressors (Decree 90-245, Article 1, Item 3)


Compressors of gases or vapors other than steam are within the DPEM inspection
scheme if the following two conditions are simultaneously met for the fluids specified.
A.

Delivery pressure exceeds 10 BarG

Characteristic Number, i.e., the product of the maximum delivery pressure


(expressed in BarG), multiplied by the maximum design flow rate under delivery
conditions (expressed in cubic meters per minute), exceeds the value 50.

B.

Hazardous liquids (Explosive, flammable, toxic or corrosive)

Delivery pressure exceeds 4 BarG

Characteristic Number exceeds the value 20.

C.
6.2.7

Non hazardous liquids

DPEM shall attend hydrostatic testing of casting or body.

Appurtenances
Supplier is reminded that electrical ancillaries, instruments, filters and interconnecting
pipe work will be subject to DPEM scrutiny if they exceed the characteristics defined in
the relevant paragraphs of this procedure.

6.2.8
5

All Gas Pressure Devices (Pressure Containing Equipment)


Supplier shall ensure that the equipment is designed for hydrotest at 1.5 times the design
pressure in the installed condition. Further, under a pressure equal to the design pressure, the
stress in the metal in the wall under pressure is less than the lower of the following two values:
One third (1/3) of the tensile strength of the metal at normal temperature

Page 9 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

Five eights (5/8) of the yield stress (0.2% permanent elongation) of the metal at maximum
operating temperature.

If the operating conditions are likely to cause creep of the metal, the work rate must also be
limited according to the specified temperature and service life.
6.2.9

Motors and Engines


Low voltage utility Motors and Engine drivers are not normally subject to DPEM
scrutiny. High voltage and fire or emergency service motors and engines may come
under their scrutiny. If an item comes within the DPEM scope, a Preliminary Dossier is
required to be submitted for DPEM review and approval.
A.

6.2.10

Motors are subject to DPEM inspection if:

The maximum voltage rating is equal to or exceeds 5.5 kV

The motors drive fire pumps or other essential or emergency services

DPEM shall attend routine and final acceptance tests of motors.

B.

Engines are not normally subject to DPEM scrutiny unless they drive, either directly
or indirectly, fire pumps or other essential or emergency service. In these cases
Preliminary and Final Dossiers shall be submitted.

C.

Appurtenances: Electrical ancillaries, instruments, fuel / oil filters, pneumatic and


hydraulic accumulators, and interconnecting pipe work will be subject to DPEM
scrutiny if they exceed the characteristics defined in the relevant paragraphs of this
procedure.

Mechanical Handling, Passenger Lifts / Man-riding Hoists, Overhead Cranes,


For Mechanical handling equipment where the designed safe working load equals, or
exceeds, 5 metric tons, DPEM require that one of its accredited Algerian third party
inspection agencies (like ENACT) attend load testing.
For items deemed within the scope above, a Technical File will be submitted for the
inspection agency for review and approval.

6.2.11

Electrical (Reference: DPEM Circular No. 2)


Electrical equipment may be subject to DPEM scrutiny. For items deemed within the
scope, a Preliminary Dossier, containing design premises etc., is to be submitted for
DPEM review and approval.
The following electrical equipment and material are within the DPEM scope if the
voltage rating is equal to or exceeds 5.5 kV.
A.

Transformers

B.

MCC

C. Switchgears
Page 10 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

D. Switches (Large transition switching units)


E.

Generators

F.

Motors

G. Cables
DPEM retains an interest in emergency power supplies and other safety related
aspects such as grounding arrangements, lightning protection, interlocks etc. Details of
emergency switchboards and safety related aspects may be required.
DPEM shall attend final acceptance tests of electrical appliance to confirm compliance
with IEEE, IEC and NEMA regulations
6.2.12

Instruments
With the exception of Pressure Safety valves, instruments and instrument material are
not normally subject to DPEM inspection.
A second Algerian Authority ONML (National Office of Legal Measurement) will be
concerned only with legal measuring components or systems, such as Fiscal Metering
devices.
A.

Pressure Safety Valves & Control Valves

Pressure Safety Valves are within the scope of DPEM. These valves need to be
checked for opening and closing pressures and tightness. Their primary concerns will
be the disposition of PSVs within a system, the witnessing of off-line tests and correct
installation. Design appraisal and witnessing of tests of individual PSVs in the factory
will, if at all, be limited to large, novel or particularly critical applications. Supplier shall
notify Purchaser of any non -standard items and obtain advice. The valve body shall
be classified by the criteria shown for piping materials.
Control valves that will contain potentially hazardous gasses or liquids under pressure
may also be within the scope of DPEM, in which case the above requirements for
design appraisal and testing shall apply.
DPEM shall attend hydrostatic testing of Pressure Safety Valves and Control Valves.
(Functional Test, Pressure Setting, Leak Test).
B.

Legal Measuring Instruments

Instruments concerned with measurement of physical properties of a product for


custody transfer are subject to approval, calibration and certification by ONML. A
Preliminary Dossier shall be prepared for each type of instrument, such as LACT,
MPFM, or other fiscal metering device.
C. General Instruments
All instruments and instrument material shall be selected and /or designed such that
they are suitable for the purpose for which they are intended to be used. Instruments
with an electrical content that could therefore be spark or heat-generating shall be
Page 11 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

suitable for use in the area specified and defined by the Hazardous Area drawings, and
as stated in the Purchase Order or Subcontract and its attachments.
D. Certifications
Suitable internationally recognized Hazardous Area Certification shall be submitted to
PURCHASER for all explosion proof electrical instruments intended to be located in
hazardous areas.
6.2.13

Piping, Process Piping and Pipeline System


Piping material may be subject to DPEM control. For items deemed within the scope, a
Preliminary Dossier, containing design premises etc. is to be submitted.
A.

Process Piping (Ref: Decree 90-245, Article 2, Item 4)


The piping for plant is subject to DPEM inspection if the following three (3)
conditions are simultaneously met:

The design pressure exceeds 10 BarG

The internal diameter exceeds 80 mm

The Characteristic Number, i.e., the product of the design pressure expressed
BarG, multiplied by the internal diameter expressed in mm, exceeds the number
1500.

B.

Piping for Flowlines and Export Pipeline (Ref: Decree 88-35)


This portion of the Algerian Regulations is not applicable to this procedure for the
Skikda New LNG Train Project.

6.2.14

Valves
Valves, other than control valves and PSVs, made in accordance with internationally
recognized Codes and Standards are considered by DPEM as pipe fittings.
For non-standard valves, the criteria laid down for Pressure Vessels in Section 6.2.2 will
apply.
DPEM shall attend hydrostatic testing of valves within its scope (body hydro and leak
test).

6.2.15

Process Pipe & Pipe Fittings (Supplier shop fabrication and field fabrication)
Pipe and pipe fittings for use in services other than steam and water are within the
DPEM inspection scope if the following three (3) conditions are simultaneously met:
A.

Non-hazardous gases and liquids other than steam or water

Inside Diameter > 80mm

Design Pressure > 10 BarG

Page 12 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

B.

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

Characteristic Number > 1500 (the product of the design pressure expressed in
BarG multiplied by the internal diameter expressed in mm, exceeds the number
1500)
Explosive, flammable, corrosive or toxic gases or liquids

Inside Diameter > 80mm

Design Pressure > 4 BarG

Characteristic Number > 1000

C. Requirements for Steam and Super-heated water pipes are not applicable to the
Skikda New LNG Train Project due to the diameter of the pipe.
NOTE: Cold water pipes are not within the DPEM inspection scope.
6.2.16

Piping Specialties
Piping specialties are considered by DPEM as pressure retaining items. The criteria
laid down for pressure vessels in paragraph 6.2.2 of this procedure apply.

6.2.17

A.

Loss Prevention Systems and Equipment


Loss prevention systems and equipment are normally subject to DPEM control. For
items deemed within the scope, a Preliminary Dossier, containing design premises etc
is to be submitted for DPEM review and approval before manufacture starts. (Ref:
Circular No. 2).
Fire Fighting

Fire fighting systems are within the scope of DPEM. DPEM will appraise firewater
distribution, drawings, firewater demand calculations, the positions of hydrants,
monitors, hose-reels etc.

Foam, powder and inert gas systems will similarly be examined.

Fire extinguishers and other mobile or portable fire fighting devices shall also be
examined for suitability of design and construction as well as their disposition on site.

DPEM shall attend hydrostatic testing and functional testing for all fire fighting
equipment.

Pressure retaining items shall be considered as pressure vessels as defined in


paragraph 6.2.2 of this procedure. Supplier shall notify and obtain the advice of
Purchaser regarding the inclusion of any pressure retaining item within the DPEM
scope.

B.

Bottles of Carbon Dioxide, Nitrogen and other gasses are within the DPEM scope if the
following two conditions are simultaneously met:

Design pressure greater than 4 BarG

The product of the design pressure expressed in BarG multiplied by the capacity
expressed in Liters; exceeds the number 10.
Page 13 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

NOTE: CO2 and N2 gas bottles are typically supplied to the Supplier direct from their
Sub-supplier, under the Suppliers responsibility, in accordance with the specification
provided. Supplier shall submit Preliminary and Final Dossiers in accordance with this
procedure. When the DPEM Engineer visits site and reviews the dossiers, they will
stamp the bottles alongside the supplied serial number, manufacturer name and date of
manufacture. These stamps are required to enable refilling of the bottles in Algeria.
C. Fire Extinguishers (with parts having a capacity greater that five (5) liters) are within the
DPEM scope if the following two (2) conditions are simultaneously met: (Ref Decree 90245, Article 2, item 5)

Design pressure greater than 4 BarG

The product of the design pressure expressed in BarG, multiplied by the capacity
expressed in Liters, exceeds the number 80, or if the capacity is greater that one (1)
liter, the product is ten (10)

D. Fire & Gas Detection Equipment (in Plant Safety Dossier) gas, flame, smoke, cold
and heat detectors and alarms shall be subject to DPEM approval. Location
drawings and details of each detector type deployed shall be submitted.

The fire and gas system logic, panels, and data transmission is subject to DPEM
review.

6.2.18

DPEM shall attend functional tests of Fire and Gas Detection systems.

Sewage Networks (Ref: DPEM Circular No. 2, Plant Safety Dossier)


Sewage Networks shall be within DPEM scope. The following shall be subject to control
by DPEM:

6.2.19

A.

General map of sewage networks

B.

Construction of sumps and manholes

C.

Hydraulic guard against flame spread / propagation

D.

Calculation of sewage network flow rates

E.

Material used.

Pipelines associated with Hydrocarbons Productions (Ref: DPEM Circular No. 4,


Pipeline System Dossier, and Decree 88-35) See paragraph 7.8 for Table of Content
The following pipelines are considered as associated with hydrocarbons production:
A.

Flowline pipelines that connect either the wellhead to the center for hydrocarbon
gas processing or separation and processing centers to the re-injection facilities, or
the separation centers to the flow main centers (C.P.C).

B.

Service pipelines that connect the re-injection facilities to injection wellhead.

C. Sewers that connect either the processing centers to the main pipelines, or either
flowline main centers to main pipelines, processing and separation centers located
Page 14 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

in an exploration license area to a re-injection center in another exploration license


area.
6.2.21

For package units, skids and systems, the Supplier is to review the individual
components to see if they fall under DPEM regulations, if so, each individual item
requires a Dossier.
The Supplier shall supply KBR with a detailed list of each individual component and
their characteristics that relate to DPEM criteria for that type of equipment (ex.: design
temperature and pressure, flow rate, volume and size).

7.0

DOCUMENTATION SUBMITTALS
This Section details documents to be prepared and submitted by suppliers,
subcontractors and/or the contractor, and the general sequence of submittal. (See also
paragraph 10.0 and Attachment 5)

7.1

Suppliers Bid Inclusion (Pre-Award)


The Purchasers Requisition Form SDR will indicate the requirement to submit
Preliminary and Final Dossiers or Technical files for relevant items, parts and
appurtenances of the scope of supply that are to be involved with the DPEM based on
the criteria listed in Section 6.0.
The Supplier shall include within his quotation the relevant items/parts of the scope of
supply that are in accordance with the criteria.
The Supplier shall also confirm that his quotation includes all documentation and
submittals relative to DPEM involvement (Schedules, Preliminary Dossier, Final
Dossier, Technical Files and relevant Test Data) in accordance with this procedure and
SDR.
The Supplier shall be aware of the documentation requirements contained in this
procedure. It is incumbent on each Supplier to ensure that the necessary reviews and
approvals can be obtained in a timely manner such that there will be no slippages in
equipment deliveries.
Summarized ARA document submission and Inspection Notification Schedule etc, are
shown in the DPEM documentation and activities Coordination Schedule (see
Attachment 5 for reference).

7.2

Inspection Coordination Schedule


The Supplier is to prepare an overall schedule including shop fabrication, inspection
and testing activities and document submission that can be used by the Purchaser and
DPEM for planning inspection visits for the equipment, and to maintain the schedule
updated as required. The schedule is to be issued to Purchaser within the time after
Purchase Order commitment as indicated in the Purchase Order form SDR. Further
submissions shall be attached to the weekly/monthly report or made as required by the.
SDR.
Page 15 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE
7.3

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

Quality Control Plan (Inspection & Test Plan)


The Supplier is to submit a specific and unique Purchase Order Quality Control Plan
(Inspection & Test Plan) in accordance with project requirements (SDR) to cover all the
activities; Fabrication, Inspection & Test performed by the Supplier necessary to
provide the equipment (See Attachment 1, Document 8).
Purchaser Requisitioning Engineer, Quality Manager, and Project Procurement Quality
Control Manager will review the Suppliers Quality Control Plan (Inspection & Test Plan)
which must be tied together with the Suppliers Fabrication Schedule in the shop.
The DPEM Representative will be invited to witness the testing of equipment in
accordance with the criteria stated in paragraph 8.1 The Supplier is responsible for
indicating on the Quality Control Plan (Inspection & Test Plan) the required
Inspection/Testing activities of the DPEM in accordance with the criteria stated in
paragraph 8.1.

7.4

Preliminary Dossier
Supplier shall prepare Preliminary Dossier in accordance with this document and
submit to Purchaser. The Purchaser will check the Dossier and submit to DPEM for
approval.
Preliminary Dossier for items relevant to DPEM involvement is to be submitted to the
Purchaser preferably 6 weeks after purchase order / sub-order placement but no less
than 50 calendar days prior to commencement of fabrication of the relevant item.
Purchaser shall submit the Preliminary Dossier to the DPEM for approval on the
Suppliers behalf. Purchaser shall also expedite the required approval and inform the
Supplier when this has been obtained.
The Preliminary Dossier shall be composed of the documents mentioned below.
The Preliminary Dossiers shall be separate to the Final Dossier and shall be complete
with a cover sheet (per Attachment 1) and an index with clearly indicated section
dividers containing the relevant document number, indicating selected contents.
Provide a Table of Contents, (if more than one volume, each volume shall have Table
of Contents)
Section 1

A letter of request for approval of the Preliminary Dossiers (Attachment 1


Document 1). Supplier to complete and insert (2 originals in English &
French). Signed by the responsible Supplier Project Director or Manager.

Section 2

Certification by the local Chamber of Commerce of the Fabricators


Signatures and Algerian Consulate Stamp (Att 1, Doc 2) (2 originals in
English & French). It requires endorsement and stamping by Chamber of
Commerce or State Department & Algerian Consulate. This document is
the Suppliers responsibility for completion including the signature of the
local Chamber of Commerce and the stamp of the nearest Algerian
Consulate to the place of fabrication.
Page 16 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

Section 3

Certificate of Conformity and of Internal and External Inspections (Att 1,


Doc 3) (2 originals in English and French). Requires endorsement and
stamping by local Chamber of Commerce or State Dept. & Algerian
Consulate. This document is the suppliers responsibility for completion,
including the stamp of the nearest Algerian Consulate to the place of
fabrication.

Section 4

Equipment / Material description (Att. 1, Doc 4)

Section 5

Design Calculations (Att. 1, Doc 5)

Section 6

Drawings and Data Index listing the pertinent document numbers


applicable to the equipment (Att 1, Doc 6) include general arrangement
drawings other relevant detailed drawings and / or data sheets.

Section 7

Approved Welding Procedure Specifications (WPS) (signatures affixed)

Section 8

Quality Control Plan (Inspection and Test Plan) (Att 1, Doc 8).

The above Dossier, once completed per sample Attachment 1, shall be sent in
accordance with Purchase Order SDR to Purchasers Document Control Center, who
shall submit them to the relevant parties.
The Supplier shall not proceed with fabrication activities before obtaining DPEM
approval. Time frame for approval, including transmission period is 7 weeks after
receipt of the Preliminary Dossier by the Purchaser who checks it and sends it to
DPEM. After this period the Purchaser shall authorize the Supplier to commence
fabrication in the absence of a DPEM reply.
Notes:
1.

An advance Preliminary Dossier can be forwarded without the official Countrys


Chamber of Commence or State Department or equivalent entity and Algerian
Consulate stamping and signature for Section 2 and 3 in cases where these
documents would require a lot of time and cause a delay in the transmission of the
Preliminary Dossiers to the DPEM. In the Preliminary Dossier, Supplier shall state
that the Chamber of Commerce and Algerian Consulate stamping and signature is
being obtained and in progress. The outstanding stamped and endorsed
documents, sections 2 and 3 are to be transmitted by the Supplier to Purchaser
within 3 weeks of the Preliminary Dossier submittal.

2.

A series of identical equipment shall be grouped in one (1) single Preliminary


Dossier; however, this file must indicate each item number in the complete list. A
Final Dossier must be provided for each item.

3.

For equipment description (Section 4) for reactors, columns, heat exchangers, air
coolers exchangers, compressors, separators, filters, pressure vessels and tanks,
the DPEM model (Attachment 1, Document 4) shall be used.
For equipment description for other pressure devices (valves, pressure safety
valves), electrical equipment and material and for the overhead cranes, the DPEM
Page 17 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

model (Attachment 1, Document 4) shall be modified with regard to the specifics of


each kind of apparatus.
4.

The calculations (Attachment 1, Section 5), concerning the pressure devices


required in the Preliminary Dossier shall detail principally the thickness of the parts
under pressure (shells, heads, nozzles) and opening reinforcements.

5.

The Welding Procedure Specification (WPS) is required only for pressure devices,
tanks, valves and line pipes for pipeline.

6.

Number of copies required to be submitted are shown in Section 10 of this


procedure.

7.

The Table of Contents in Attachment 1 is mandatory for pressure equipment. If a


section is not relevant, please indicate Not Applicable.

8.

Purchaser recommends that documents 1, 2 & 3 (of Attachment 1) are produced


on relevant supplier / sub-supplier letter head paper.

9.

Supplier is required to retain a copy of each Preliminary Dossier (English and


French) for DPEM inspectors review during the shop visit.

10. The Preliminary Dossier is a separate document from the Final Dossier.
11. The Purchasers assigned inspector, where possible, will review and endorse the
Preliminary Dossier at the Supplier / Sub-supplier location to ensure correct
compilation prior to submittal to the Purchaser.
12. If changes to the work are made after approval of the Preliminary Dossier, for
example, item tagging, or instrument manufacturer or model number, a revised
dossier must be submitted in the same manner as the original.
13. The requirements for endorsement and stamping by the Chamber of Commerce,
Department of State or other such entity prior to stamping by the Algerian
Consulate vary from country to country. PURCHASER advises the Supplier to
verify the requirements in their country as soon as possible. In some areas the
Supplier may find a document authentication service provider to obtain the
endorsements and stamps.

7.5

Final Dossier
The Supplier shall prepare a Final Dossier in accordance with this procedure as per
Attachment 2. The Final Dossier is separate from the Preliminary Dossier and shall be
completed with a cover sheet (Attachment 2) and an index, with clearly indicated
section dividers containing the relevant document number, indicating section contents.
The Final Dossier for relevant items of DPEM involvement is to be submitted to the
Purchaser within 30 calendar days after successful completion of scheduled works and
prior to shipment.

Page 18 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

The Purchasers assigned inspector will review the Final Dossier at the Suppliers
location on successful completion of scheduled DPEM test activities to ensure correct
compilation prior to submittal to Purchaser.
Provide a Table of Contents (if more than one volume, each volume shall have Table of
Contents).
Section 10 Copy of DPEM letter of Preliminary Dossier approval (Att 2, Doc 10).
Section 11 Copy of letter or fax requesting the presence of DPEM Inspector (Att 2, Doc
11) (Purchaser will provide to Supplier).
Section 12 Copy of DPEM response to request (Att 2, Doc 12) (Purchaser will provide
to Supplier).
Section 13 Welding Procedure Qualification Record (PQR) (Att 2, Doc 13).
Section 14 Weld Maps, Welder Qualification Record and logs of welders who
performed on the equipment manufacture (Att 2, Doc 14).
Section 15 Material Test Certificates (MTRs): Legible certificates, identifying materials,
parts, components, including welding electrodes (Att 2, Doc 15).
Section 16 NDE reports (Att 2, Doc 16)
Section 17 Post Weld Heat Treatment chart, if applicable (Att 2, Doc 17)
Section 18 Internal & External Inspection certificate (Att 2, Doc 18) (2 originals in
English & French) signed by attending DPEM or his delegated
representative, Purchasers & Suppliers Inspector
Section 19 Hydrostatic Test Certificates (Att 2, Doc 19). (2 originals in English &
French) signed by attending DPEM or his delegated representative,
Purchasers & Supplier Inspector to also include Suppliers test certificates
or ASME U1A form or TEMA forms.
Section 20 Copy of DPEM Pro Forma nameplate (French) for Pressure Vessels, DPEM
Model 21, (Att 2, Doc 20) Note: only the French version is required to be
affixed to the pressure vessel.
Section 21 Test Certificate (Att 2, Doc 21) (2 originals in English and 1 French)
signed by attending DPEM or his delegated representative, Purchasers &
Suppliers Inspectors. For electrical equipment, identify the tests that were
conducted. (See paragraph 8.2.6) This form is Not Applicable if the only test
required for the equipment is a hydrostatic test which is evidenced by
Attachment 2 Document 19. (See paragraph 9.0)
Section 22 Copy of DPEM Pro Forma nameplate (French) for Heat Exchanger
equipment DPEM Model (Att 2, Doc 22) Note: only the French version is
required to be affixed to the heat exchanger.
Page 19 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

Section 23 Photocopy of DPEM French nameplate and other nameplates (i.e. ASME
Code Nameplate, TEMA nameplate, etc., if applicable).
Section 24 Copy of Supplier equipment Final/As-Built drawings. This shall include the
drawings in Section 6 of the Preliminary Dossier plus any other applicable
drawings.
7.6

Plant Safety Systems Dossier (Ref DPEM Circular No. 2)


A Plant Safety File dossier is a Purchaser/Contractor-compiled document for a site
installed system, and shall be submitted to DPEM by the Contractor prior to PreCommissioning. The files of the safety systems must be approved by DPEM, with
concurrent review by a designated Sonatrach Safety Manager. To this end, the
Supplier shall transmit to the Purchaser/Contractor (KBR) a Technical File covering his
scope of work, for the systems listed below; to enable the Purchaser to include the
data in the safety system file dossier.
A.

Emergency shutdown system

B.

Flare network

C. Fire, heat, cold, smoke and gas detection


D. Fire fighting systems (Network of fire water, CO 2 and chemical extinguishing
systems).

7.7

E.

Grounding network

F.

Lightning protection system

Technical File (For Safety System Components and certain other items as
indicated in 7.6 )
To facilitate approval, the Supplier shall prepare a Technical File containing the
documents listed below as appropriate, and send them to the Purchaser. All
documents must be provided in French & English.
Section A A letter of request for approval of the Technical File (Attachment 1
Document 1). Supplier to complete and insert (2 originals in English &
French).
Section B Certification by the Chamber of Commerce of the Fabricators or Stockists
Signatures and Algerian Consulate Stamp (Att 1, Doc 2) (2 originals in
English & French). Requires endorsement and stamping by Chamber of
Commerce or State Dept. & Algerian Consulate. This document is the
Suppliers responsibility for completion including the signature of the local
Chamber of Commerce and the stamp of the nearest Algerian Consulate to
the place of fabrication.
Section C Certificate of Conformity and of Internal and External Inspections (Att 1,
Doc 3) (2 originals in English and French). It requires endorsement and
stamping by Chamber of Commerce & Algerian Consulate. This document
Page 20 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

is the suppliers responsibility for completion, including the stamp of the


nearest Algerian Consulate to the place of fabrication.
Section D Equipment / Material description (Att 1, Doc 4).
Section E Copy of letter or fax requesting the presence of DPEM Inspector (Att 2, Doc
11). (Purchaser will provide to Supplier, as applicable).
Section F Internal & External Inspection certificate (Att 2, Doc 18) (2 originals in
English & French) signed by attending DPEM or his delegated
representative, Purchasers & Suppliers Inspectors.
Section G Hydrostatic Test Certificates (Att 2, Doc 19). (2 originals in English &
French), signed by attending DPEM or his delegate representative or
Purchasers & Suppliers Inspectors to include Suppliers test certificates or
ASME U1A form or TEMA forms.
Section H Material Test Certificates (MTRs): Legible certificates, identifying materials,
parts components, including welding electrodes (Att 2, Doc 15). NDE
reports (Att 2, Doc 16) if applicable.
Some equipment may require a different format for the technical file. The Supplier may
propose a format to Purchasers ARA Liaison coordinator for approval. The ARA Liaison
coordinator is identified at the Kickoff meeting or Pre-inspection meeting between the
Purchaser and Supplier.
The front cover for Technical File dossiers shall be modified to say Technical File (See
sample Dossier Cover page, Attachment 1 or 2).
The Technical Files shall be sent to Purchaser within 14 calendar days after issue of a
Purchasers Inspection Release Certificate. Purchaser will then forward to DPEM for
review and approval.
7.8

Pipeline System Dossier:


This portion of the Algerian Regulations is not applicable to this procedure for the
Skikda New LNG Train Project.

8.0

SCOPE OF DPEM INSPECTION (DPEM CIRCULAR 02 AND 04)


The list below summarizes typical Test and Inspection activities to be witnessed, and/or
documents to be reviewed, by the DPEM.

8.1

At Suppliers Shop

8.1.1

DPEM will witness testing including, but not limited to, tests listed here.
A.

Review of Material Test Certificates.

B.

Review of Test and Inspection Records previously conducted by Supplier.

C. Visual and Dimensional Check.


Page 21 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

D. Non Destructive Test Reports where applicable.


E.

All Hydrostatic Tests Pressures to be a minimum of one and a half (1.5X) times
the Design Pressure.

F.

Functional or Performance Test where applicable.

8.1.2

For all inspections, Supplier shall make available for Purchasers & DPEM inspection,
the complete inspection, test records and certificates, whether witness or nonwitnessed.

8.1.3

The Supplier shall also have available a copy of each approved Preliminary Dossier (for
the DPEM Inspector).

8.1.4

If the results of the test are satisfactory, DPEM Inspector (or his delegate) witnessing
the testing shall sign the test certificates (Document 18, 19 and/or 21), jointly with
representatives of Purchaser and the Supplier. The DPEM Inspector shall then stamp
the inspected equipment.

8.1.5

In the event or non-reply or non-arrival of DPEM Inspector to the location of tests, these
shall be carried out as scheduled in the presence of Purchaser and the agreed
assigned Suppliers Third Party Inspectors. The test results shall be submitted to
Purchaser then forwarded to DPEM for review and approval.

8.2

Typical Tests
Typical DPEM Tests carried out which fulfill the criteria indicated in this procedure are
as follows:

8.2.1

Pressure Retaining Equipment: Hydraulic or, where approved, pneumatic tests.

8.2.2

For Tanks: (shop and/or field tests)


A.

B.

Stationary Roof Tanks


Tank strength and tightness tests (hydrostatic, under and over pressure tests)
Floating Roof Tanks

Hydrostatic Test

Reports on other field or shop tests and inspections, signed by Engineer and
Client, shall be made available to DPEM representative.

8.2.3

Gas Compressors:
hydrostatic test).

8.2.4

Relief Valves: Verify the opening and closing pressures and seat tightness.

8.2.5

Pipelines: As noted above.

8.2.6

Hydraulic or, where approved, pneumatic tests (body/casing

Electrical Equipment rated 5.5kv or higher:


Page 22 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

A.

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

Motors 5.5 KV and above

In accordance with Project Specifications

Complete test for one motor of each group

Abbreviated test for motors not subject to Complete test

B.

Switchgear 5.5 kV and above

In accordance with Project Specifications

Power Frequency Voltage Test

Auxiliary circuit voltage test

Mechanical operation test

Check of wiring

C. Transformers 5.5 kV and above

In accordance with Project Specification

Wiring resistance measurement

Measurement of voltage ratio and check phase displacement

Measurement of short circuit impedance and load loss

Dielectric routine test

D. Generators 5.5 kV and above: In accordance with Project Specification.


E.

Cable 5.5Kv and above: In accordance with Project Specification

8.2.7

Hot Water System: Hydraulic or, where approved, pneumatic.

8.2.8

Mobile Equipment: Hydraulic or, where approved, pneumatic.

8.2.9

Fire Extinguishers: Hydraulic or, where approved, pneumatic.


Other tests, required by the standards and regulations in force, will be done in the
presence of Purchaser. All documentation and records from those tests will be given to
the DPEM inspectors upon their request.
The relevant Test Procedures for the equipment associated with DPEM / ONML
involvement must be submitted by the Supplier for Purchasers review within 2 (two)
weeks prior to the test date.

9.0

NAMEPLATES
Page 23 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

Supplier shall affix the Standard Code Stamped Nameplate for ASME or TEMA code
(as required). Additionally, Supplier is to affix a DPEM model Nameplate, in French, in
accordance with Attachment 2 Document 20 or 22 on all pressure-containing
equipment in accordance with the Purchase Order, and as follows:

10.0

Nameplate size: 160 x 200 mm.

Material: 7 mm Thick, 304 Stainless Steel.

Character and stamping to be preferably 6mm high but not less than 4mm high
with a depth of 0.5mm.

The Official DPEM Stamp is less than in diameter.

The DPEM Nameplate (French) is to be stamped by the DPEM, for equipment that
has been witnessed by DPEM.

Nameplates are to be supplied for pressure containing equipment only.

Electrical equipment > 5.5 kV that has been involved with the DPEM does not
require the French nameplates.

DOCUMENT QUANTITY & FORMAT


The DPEM requires English & French or bilingual documents (Doc 1 to 24 per
Attachment 1 and 2), as indicated in Attachment 3, which shall be used for official
submission. Each document shall be prepared in two (2) original copies (1 French & 1
English or 2 bilingual). Purchaser recommends the use of bilingual documents in both
English and French and has stated this option in the text of this procedure.

10.1

Quantities
Documents identified for submittal to the Algerian Regulatory Authorities shall be
submitted to Purchaser in the following quantities and format:

10.1.1

If dossiers are in both a French version and an English Version, the following quantities
are required:
Preliminary Dossiers

Final Dossiers & Technical Files

For DPEM

1 original French

1 original French

For Client

1 copy English + 1 copy French

1 copy English + 1 copy French

For Purchaser

original English & 2 copy French


(Note: 1 copy French to Site DC)

1 original + 1 copy French

Totals:

1 original French, 3 copies French


and 1 original English & 1 copy
English. One (1) electronic copy of
French and of English

1 original French & 2 copies French


and 1 original English & 1 copy
English. One (1) electronic copy of
French and of English

Page 24 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE
10.1.2

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

If bilingual dossiers are supplied then the following quantities are required:

Preliminary Dossiers

Final Dossiers & Technical Files

For DPEM

1 original

1 original

For Client

2 copies

2 copies

For Purchaser

1 original + 2 copies (Note: 1 copy to


Site DC)

1 original + & 1 copy

Totals:

2 originals, 4
electronic copy

2 originals + 3 copies
electronic copy

10.2

copies.

One

(1)

One

(1)

Format
The Preliminary Dossier, Final Dossier, Technical File and Safety Dossier are all
separate and shall be in hard cover 3 or 4 ring binders.
Provide a general Table of Contents. If more than one (1) volume, each volume shall
have a Table of Contents.
These Dossiers shall have section dividers and numbered accordingly. Each section
shall have a title page. If a section is not relevant to a particular item of material or
equipment, the divider shall be included and the title page shall be annotated Not
Applicable.

10.3

Front Cover & Spine


The front cover and spine of the Preliminary, Final or Technical Dossiers shall contain
information as shown in the attached sample pages, the first sheet each of Attachment
1 and Attachment 2.

11.0

NOTICE OF INSPECTION & TEST


When items, components and appurtenances subject to ARA involvement are agreed
between the supplier and the purchaser and ARA activities indicated on Suppliers
Quality Control Plan, Supplier shall notify the Purchaser of indicted ARA inspection
activities. The notification shall be sent to the Purchasers Project Procurement Quality
Control Manager and Purchasers ARA Liaison coordinator. This shall be sent by the
supplier at least forty five (45) calendar days before the expected date of test. The
defined date shall be confirmed by the Supplier as indicated above twenty-one (21)
calendar days before the test. Contact information for the ARA Liaison coordinator and
other Purchaser personnel will be provided at the Kickoff meeting or the Pre-inspection
meeting between the Purchaser and Supplier.

Page 25 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 5
17 APRIL 2008

The Purchasers ARA Liaison coordinator, on receipt of the notifications from the
Supplier, will forward to the relevant ARA the request for Inspection per Attachment 4.
The relevant ARA will confirm their intention on the indicated inspection at least
fourteen (14) calendar days prior to the defined inspection date, Purchasers ARA
Liaison coordinator will relay it to the Supplier at least seven (7) days prior to Defined
Inspection date with a copy to Purchasers Project Quality Control Manager.
In the event of a non attendance reply from the ARA, the Purchasers ARA Liaison
coordinator may instruct the Supplier to assign a third party inspector to perform
activities on behalf of ARA on the schedule date.
The PURCHASER assigned third party inspector will not stamp nameplate on behalf of
the ARA.
12.0

EQUIPMENT RELEASE CERTIFICATES


Final equipment release paperwork should describe the individual items which have
been DPEM witnessed, e.g. compressor fuel gas drums mounted on a skid with filter,
pump, etc., and indicate DPEM witness.
If not witnessed, the releases should also describe the individual items, and indicate
lack of DPEM witness.
Equipment which has not been stamped, but is subject to DPEM Inspection and Tests
in supplier shop, must be reported to the ARA with the Purchasers Inspection Report.
DPEM will review these dossiers in the field.

13.0

ATTACHMENTS
Attachment 1

Documents 1 8

Preliminary Design Dossier

Attachment 2

Documents 10 24

Final Dossier

Attachment 3

DPEM Document Translation Checklist

Attachment 4

DPEM Document Request for DPEM/ONML Inspector

Attachment 5

ARA Documentation & Activities Coordination Schedule

Attachment 6

Flowchart Preliminary Dossier

Attachment 7

Equipment Listing

Page 26 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

ATTACHMENT 1: PRELIMINARY DOSSIER FORMS, DOCUMENT 1 8


DOSSIER REGLEMENTAIRE / REGULATORY DOSSIER

DIRECTION DE LA PROTECTION DU PATRIMOINE


ENERGITIQUE ET MINIER
DIRECTION OF ENERGY AND MINE PATRIMONY PROTECTION
MINISTERE DE LENERGIE ET DES MINES
MINISTRY OF ENERGY AND MINES
PROJET DU NOUVEAU TRAIN DE GNL SKIKDA
SKIKDA NEW LNG TRAIN PROJECT

DESIGNATION DE LEQUIPEMENT / EQUIPMENT DESIGNATION

COMMANDE NO.. /
PURCHASE ORDER NO. _________________________
DOSSIER DETUDE PRELIMINAIRE
PRELIMINARY DESIGN DOSSIER

CONTRAT / CONTRACT
KBR
RAISON SOCIALE OU FOURNISSEUR / COMPANY OR VENDOR

Page 27 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

SOMMAIRE

TABLE OF CONTENTS

1. LETTRE DE DEMANDE DAPPROBATION

1. LETTER FOR APPROVAL REQUEST

2. CERTIFICATION PAR LA CHAMBRE DE


COMMERCE DES SIGNATURES DU FABRICANT
VISA DU CONSULAT ALGERIEN

2. CERTIFICATION BY THE CHAMBER OF


COMMERCE OF THE FABRICATOR SIGNATURES
ALGERIAN CONSULATE STAMP

3. CERTIFICAT DE CONFORMITE ET DE VISITES


INTERIEURES ET EXTERIEURES, ATTESTANT QUE
LEQUIPMENT EST DE CONSTRUCTION
CONFORME POUR UTILISATION DANS LE PAYS
DORIGINE

3. CERTIFICATE OF CONFORMITY AND OF


INTERNAL AND EXTERNAL INSPECTIONS,
ATTESTING THAT THE EQUIPMENT CONSTRUCTED
CONFORMS TO THE CONTRY OF ORIGIN

4. ETAT DESCRIPTIF

4. DESCRIPTION STATEMENT

5. NOTES DE CALCUL

5. DESIGN CALCULATIONS

6. PLANS DETAILLES AVEC INDEX

6. DETAILED DRAWINGS WITH INDEX

7. SPECIFICATIONS DE PROCEDURES DE
SOUDAGE (W.P.S)

7. WELDING PROCEDURE SPECIFICATIONS (WPS)

8. PLAN DE QUALITE DINSPECTION ET DESSAIS

8. QUALITY INSPECTION AND TESTING PLA N

(9 Not used)

( 9 Not used)

Page 28 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No 1

DOCUMENT No 1

LETTRE DE DEMANDE
DAPPROBATION

LETTER FOR APPROVAL REQUEST

MINISTERE DE LENERGIE

MINISTERE DE LENERGIE

Direction du Patrimoine Energtique et Minier

Direction du Patrimoine Energtique et Minier

80, Avenue Ahmed Ghermoul Alger

80, Avenue Ahmed Ghermoul Alger

A lAttention de Monsieur le Directeur

A lAttention de Monsieur le Directeur

N/Rf:

Our Ref :

V/Rf:

Your Ref :

OBJET : Projet de Dveloppement Skikda Projet

Subject : Skikda LNG Project

Dossier dEtude Prliminaire

Preliminary Design Dossier

Monsieur le Directeur,

Dear Sir,

Nous avons lhonneur de vous soumettre pour


approbation le prsent Dossier dEtude
Prliminaire
relatif

lquipement..
repre
n.., destin tre incorpor aux
installations des ouvrages concentrs du projet
dcrit ci-dessus.

Please find attached for your approval the


Preliminary Design Dossier related to the
equipment
..,
reference
No
, destined to be incorporated
into the facilities of the project work
described below.

Nous vous prions


Directeur, nos

dagrer,

Monsieur

le

salutations.
Yours faithfully,

Project Director

Directeur du Projet

Page 29 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No. 2

DOCUMENT No. 2

CERTIFICATION PAR LA CHAMBRE DE COMMERCE


DES SIGNATURES DU FABRICANT VISA DU
CONSULAT ALGERIEN

CERTIFICATION BY THE CHAMBER OF


COMMERCE OF THE FABRICATOR SIGNATURES
ALGERIAN CONSULATE STAMP

FABRICANT :

FABRICATOR :

NOM :

NAME :

CACHET DE LA SOCIETE:

COMPANY STAMP :

CHAMBRE DE COMMERCE LOCALE :

LOCAL CHAMBER OF COMMERCE :

Nom :

Name :

Signature :

Signature :

Nous certifions par la prsente que les signatures de :

We hereby certify that the signatures below of :

Nom :

Name :

Nom :

Name :

Nom :

Name :

Sont celles des signataires mandats de :

Are those of the signatories commissioned by :

Nom du Fabricant :

Fabricators Name :

Cachet :

Stamp :

CONSULAT ALGERIEN

ALGERIAN CONSULATE :

Date :

Date :

Signature :

Signature :

Timbres apposer

Stamp to be affixed

Page 30 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No 3

DOCUMENT No 3

CERTIFICAT DE CONFORMITE ET DE VISITES


INTERIEURES ET EXTERIEURES, ATTESTANT QUE
LEQUIPMENT EST DE CONSTRUCTION
CONFORME POUR UTILISATION DANS LE PAYS
DORIGINE

CERTIFICATE OF CONFORMITY AND OF INTERNAL


AND EXTERNAL INSPECTIONS, ATTESTING THAT
THE EQUIPMENT CONSTRUCTED CONFORMS TO
THE CONTRY OF ORIGIN

Je soussign :

I, the undersigned :

Nom :
Prnom :

First Name :
Last Name :

Directeur Gnral de la Socit :


(adresse exacte)

Managing Director of the Company


(exact address)

Certifie que lquipement (


no.
),
destin aux installations de
sera
conu et fabriqu conformment aux documents
soumis pour approbation la Direction du Patrimoine
Energtique et Minier, rpond en tous point au
rglement applicable en Algrie.

Certify
that
the
equipment
(
no.
), destined to the
installations of
will be designed and
fabricated in accordance with the documents submitted
to the Direction of Energy and Mines Patrimony
Protection (DPEM) and in strict conformance with the
regulations applicable in Algeria.

Cet quipement sera, avant de le prsenter lpreuve


rglementaire de la Direction du Patrimoine
Energtique et Minier, visit intrieurement et
extrieurement par un Technicien dsign par mes
soins. La vrification portera sur la conformit de la
pice de lquipement avec son plan de construction,
lexactitude des renseignements figurant sur ltat
descriptif, notamment en ce qui concerne les
paisseurs de tles, les caractristiques du mtal et les
modes dassemblage.

Prior to be presented for the regulatory testing by the


Direction of Energy and Mines Patrimony Protection,
this equipment will be internally and externally
inspected by a Technician, that I would personally
designate. The inspection will relate to the compliance
of the equipment with its construction drawing, the
accuracy of the information indicated on the
description statement, notably the thickness of the
metal sheet, the characteristics of the metal and the
methods of assembly.

Je certifie par ailleurs, que toutes les pices


dquipement prsentant un vice quelconque de
construction ne sera pas prsent lpreuve.

Furthermore, I certify that any part of the equipment


showing a fabrication defect of any type will not be
subject to testing.

In

Le,

on,

LE FABRICANT

FABRICATOR

CONSULAT ALGERIEN

ALGERIAN CONSULATE

Timbre apposer

Stamp to be affixed

Page 31 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No 4

DOCUMENT No 4

ETAT DESCRIPTIF

DESCRIPTION STATEMENT

Job No. : J6404


Client : SONATRACH

Job No. : J6404


Client : SONATRACH

Lieu :

Location : SKIKDA, ALGERIA

SKIKDA / ALGERIE

ETAT DESCRIPTIF

DESCRIPTION STATEMENT

Ordre dAchat No :
No Item (repre) :
No Fabrication :
Service
:
Nom et Adresse du Fabricant :
Anne de Construction:

Purchase Order No :
Item Number (reference) :
Fabrication No :
Service :
Fabricators Name and Address :
Year of Fabrication

CARACTERISTIQUES TECHNIQUES

TECHNICAL CHARACTERISTICS

Types : (rcipient, chaudire, changeur, four)

Dnomination de lappareil
Forme gnrale :
Fluide vhicul : hydrocarbure eau vapeur ou
autre
Pression de calcul :
Pression maximale de service :
Pression essai :
Temprature de calcul :
Temprature de service :
Temprature dessai :
Matriaux Utiliss :
Epaisseur(s) :
Charge limite de rupture :
Contrainte admissible :
Coefficient de joint :
Radiographie :
Traitement thermique :
Surpaisseur de corrosion :
Essais non destructifs :
Volume intrieur :

Page 32 of 59

Type of Equipment : (vessel, boiler, exchanger,


furnace)
Equipment Name :
General Shape :
Type of Fluid Carried : hydrocarbon water
steam or other
Design Pressure :
Maximum Service Pressure :
Test Pressure :
Design Temperature :
Service Temperature :
Test Temperature :
Materials Used :
Thickness (es) :
Breaking Point Load :
Permissible Stress :
Joint Coefficient :
Radiography :
Thermal Treatment :
Corrosion Allowance :
Non Destructive Examination :
Internal Volume :

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No. 5

DOCUMENT No. 5

NOTES DE CALCUL

DESIGN CALCULATIONS

Page 33 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No. 6

DOCUMENT No. 6

PLANS DETAILLES AVEC INDEX

DETAILED DRAWINGS WITH INDEX

Page 34 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE
DOCUMENT No. 7

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008
DOCUMENT No. 7

SPECIFICATIONS DE PROCEDURES DE SOUDAGE


(W.P.S)

Page 35 of 59

WELDING PROCEDURE SPECIFICATIONS


(WPS)

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No. 8

DOCUMENT No. 8

PLAN DE QUALITE DINSPECTION ET DESSAIS

QUALITY INSPECTION AND TESTING PLAN

Dcrire :

Describe :

Contrle visuel, dimensionnel

Visual and Dimensional Inspection :

Contrle U.S, Radiographie, Ressuage, MPT

Ultrasonic Testing, Radiography, Dye Penetrant,


Magnetic Particle Testing

lpreuve hydrostatique

Test activities:

Page 36 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

ATTACHMENT 2: FINAL DOSSIER FORMS, DOCUMENTS 10 24


DOSSIER REGLEMENTAIRE / REGULATORY DOSSIER

DIRECTION DE LA PROTECTION DU PATRIMOINE


ENERGITIQUE ET MINIER
DIRECTION OF ENERGY AND MINE PATRIMONY PROTECTION
MINISTERE DE LENERGIE ET DES MINES
MINISTRY OF ENERGY AND MINES

PROJET DU NOUVEAU TRAIN DE GNL SKIKDA


SKIKDA NEW LNG TRAIN PROJECT

DESIGNATION DE LEQUIPEMENT / EQUIPMENT DESIGNATION

COMMANDE No. /
PURCHASE ORDER No. _________________________

DOSSIER FINAL
FINAL DOSSIER
CONTRAT / CONTRACT

KBR

RAISON SOCIALE OU FOURNISSEUR / COMPANY OR VENDOR

Page 37 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

SOMMAIRE

TABLE OF CONTENTS

10. LETTRE

DAPPROBATON
DU
DOSSIER
DETUDE PRELIMINAIRE EMISE PAR DPEM

10. APPROVAL LETTER OF THE PRELIMINARY


DESIGN DOSSIER ISSUED BY DPEM

11. LETTRE

OU
TELEX
EMIS
PAR
LENTREPRENEUR DEMANDANT LA PRESENCE
DE
L INSPECTEUR
DPEM
POUR
LES
EPREUVES ET CONTROLES EN USINE

11. LETTER
OR
TELEX
ISSUED
BY
THE
CONTRACTOR REQUESTING THE PRESENCE
OF THE DPEM INSPECTOR FOR TESTS AND
INSPECTIONS AT THE FABRICATOR SHOP

12. REPONSE ECRITE DE DPEM CONFIRMANT OU

12. WRITTEN REPLY FROM DPEM CONFIRMING


WHETHER OR NOT THE PRESENCE OF ITS
REPRESENTATIVE OR ITS DELEGATE

NON LA PRESENCE DE SON REPRESENTANT


OU DE SON DELEGUE
13. CERTIFICAT
DHOMOLOGATION
PROCEDURES DE SOUDAGE (PQR)

DES

13. QUALIFICATION
CERTIFICATES
WELDING PROCEDURES (PQR)

OF

THE

14. ATTESTATION
DE
QUALIFICATION
DES
SOUDEURS ET OPERATEURS DE SOUDAGE
VALIDES A LA DATE DES OPERATIONS DE
SOUDAGE

14. QUALIFICATION CERTIFICATES OF WELDERS


OR WELDING OPERATORS (VALID AT THE
DATE OF THE WELDING OPERATIONS)

15. CERTIFICATS DES MATERIAUX AYANT SERVI


POUR LELABORATION DES PARTIES ET
PIECES DE LAPPAREIL (CARACTERISTIQUES
PHYSICO-CHIMIQUES) ET DES ELCTRODES.

15. CERTIFICATES OF THE MATERIALS USED FOR


THE FABRICATION OF THE PARTS AND
SECTIONS OF THE EQUIPMENT (PHYSICAL
AND CHEMICAL CHARACTERISTICS) AND
ELECTRODES

16. RAPPORT DETAILLE DES CONTROLES NON


DESTRUCTIFS
EFFECTUES
SUR
LES
SOUDURES OU SURFACE DES APPAREILS
OU/ET LEURS ELEMENTS ET LES RAPPORTS
DES CONTROLES DESTRUCTIFS EFFECTUES
LORS DE LA FABRICATION.

16. DETAILED
REPORTS
OF
THE
NON
DESTRUCTIVE EXAMINATION CARRIED OUT
ON EQUIPMENT WELDS OR SURFACES
AND/OR THEIR PARTS, PLUS REPORTS OF THE
DESTRUCTIVE TESTING PERFORMED DURING
THE FABRICATION.

17. DIAGRAMME DES TRAITEMENTS THERMIQUES

17. THERMAL TREATMENT CHARTS

18. CERTIFICAT DINSPECTION DE VISITES


INTERNES ET EXTERNES

18.

19. CERTIFCAT DEPREUVE HYDROSTATIQUE

19. HYDROTESTING CERTIFICATE

20. PLAQUE DIDENTIFICATION POUR APPAREIL A


PRESSION

20. NAME PLATE FOR PRESSURE EQUIPMENT

21. CERTIFICAT DESSAI

21. TEST CERTIFICATE

22. MODELE DE PLAQUE DIDENTIFICATION POUR


ECHANGEUR DE CHALEUR

22. PRO-FORMA
EXCHANGER

23. PHOTOCOPIE DU PLAQUE DIDENTIFICATION

23. PHOTOCOPY OF NAMEPLATE

24. PLAN FINAL, AS-BUILT PLANS FINAL

24 FINAL DRAWINGS/AS-BUILT DRAWINGS

Page 38 of 59

INTERNAL AND
CERTIFICATES

EXTERNAL

NAME

PLATE

INSPECTION

FOR

HEAT

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No 10

DOCUMENT No 10

LETTRE DAPPROBATION DU DOSSIER DETUDE


PRELIMINAIRE EMISE PAR DPEM

APPROVAL LETTER OF THE PRELIMINARY DESIGN


DOSSIER BY DPEM

Page 39 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No 11

DOCUMENT No 11

LETTRE OU TELECOPIE OU TELEX EMIS PAR


LENTREPRENEUR DEMANDANT LA PRESENCE DE
LINSPECTEUR DPEM POUR LES EPREUVES ET
CONTROLES EN USINE

LETTER OR FAX OR TELEX ISSUED BY THE


CONTRACTOR REQUESTING THE PRESENCE
OF THE DPEM INSPECTOR FOR TESTS AND
INSPECTIONS IN SHOP

MINISTERE DE LENERGIE

MINISTERE DE LENERGIE

A LATTENTION DE MONSIEUR LE DIRECTEUR DU


PATRIMOINE ENERGITIQUE ET MINIER
80, RUE AHMED GHERMOUL
ALGER

A LATTENTION DE MONSIEUR LE DIRECTEUR


DU PATRIMOINE ENERGITIQUE ET MINIER
80, RUE AHMED GHERMOUL
ALGER

N/REF :
OBJET : P.O #
No :
MATERIEL :
VALEUR DU MATERIEL :
COMMANDE No :

OUR REF. :
SUBJECT : P.O. NUMBER
No :
MATERIAL :
MATERIAL VALUE
ORDER No :

Suite votre tlex


du
, nous vous
informons que les essais sur la commande rfrence cidessus se drouleront le
. Nous vous
serions reconnaissants de nous faire parvenir votre
accord.

Pursuant to your telex


dated
, please be advised that the tests on the above
referenced order will be carried out on
.
Therefore, we would be obliged if you could confirm
your consent to the above.

Nom de la personne contacter :


Tel :
Fax :
Adresse :

Name of the contact person :


Telephone :
Fax :
Address :

Merci de bien vouloir conformer la prsence de votre


reprsentant ou la rfrence de laccord de drence de
laccord de dlgation.

Please
confirm
the
attendance
of
your
representative or advise of the reference of the
delegation approval.

Salutations respectueuses

Yours faithfully

Page 40 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No 12

DOCUMENT No 12

REPONSE ECRITE DE DPEM CONFIRMANT OU


NON LA PRESENCE DE SON REPRESENTANT OU
DELEGUE

WRITTEN REPLY FROM DPEM CONFIRMING THE


ATTENDANCE OF ITS REPRESENTATIVE OR
DELEGATE

Page 41 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No 13

DOCUMENT No 13

CERTIFICATS DHOMOLOGATION DES


PROCEDURES DE SOUDAGE (PQR)

QUALIFICATION CERTIFICATES OF WELDING


PROCEDURES (PQR)

Page 42 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No 14

DOCUMENT No 14

ATTESTATIONS DE QUALIFICATION DES


SOUDEURS ET OPERATEURS DE SOUDAGE

QUALIFICATION CERTIFICATES OF WELDERS AND


WELDING OPERATORS

Page 43 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No 15

DOCUMENT No 15

CERTIFICATS DES MATERIAUX AYANT SERVI


POUR LAPPROBATON DES PARTIES ET PIECES
DE LAPPAREIL ET DES ELECTRODES

CERTIFICATES OF MATERIALS USED, EQUIPMENT


PARTS AND COMPONENTS AND WELDING
ELECTRODES

Page 44 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No 16

DOCUMENT No 16

RAPPORT DETAILLE DES CONTROLES NON


DESTRUCTIFS EFFECTUES SUR LES SOUDURES
OU SURFACE DES APPAREILS OU/ET LEURS
ELEMENTS ET LES RAPPORTS DES CONTROLES
DESTRUCTIFS EFFECTUES LORS DE LA
FABRICATION.

DETAILED REPORTS OF THE NON DESTRUCTIVE


EXAMINATION CARRIED OUT ON EQUIPMENT
WELDS OR SURFACES AND/OR THEIR PARTS AND
REPORTS OF THE DESTRUCTIVE TESTING
PERFORMED DURING THE FABRICATION.

Page 45 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No 17

DOCUMENT No 17

DIAGRAME DES TRAITEMENTS THERMIQUES


(SIL Y A LIEU)

THERMAL (HEAT) TREATMENT CHARTS


(IF APPLICABLE)

Page 46 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No 18

DOCUMENT No 18

CERTIFICATS DINSPECTION DES VISITES


INTERNES ET EXTERNES

INTERNAL AND EXTERNAL INSPECTION


CERTIFICATES

Equipement :

Equipment :

Dsignation :

Designation :

No dItem :

Item No :

Service :

Service :

Fabricant : (Adresse exacte)

Fabricator :

Je certifie par la prsente que lquipement


susmentionn a t soumis une inspection
interne et externe et quil sest avr conforme
au :

I hereby certify that the above mentioned


equipment was subject to an internal and external
inspection and deemed to comply with :

Plan(s) No. :

Drawing(s) :

Fabricant :
Nom Signature :

Name Signature

Date :

Date :

Visiteur Dlgu :

Delegated Inspector :

Nom Signature :

Name Signature

Date :

Date :

Page 47 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No 19

DOCUMENT No 19

CERTIFICAT DEPREUVE HYDROSTATIQUE

HYDROSTATIC CERTIFICATE

Je certifie par la prsente que :

I hereby certify that :

Dsignation Equipement :

Equipment Designation :

No dItem :

Item No :

Service :

Service :

A t mis lpreuve dune manire satisfaisante

Has been successfully tested under a hydraulic

sous une pression hydraulique de :

pressure of :

Bar effectif :

Active Bar :

Dure :

Duration :

Fabricant :

Fabricator :

Nom Signature :

Name Signature :

Date :

Date :

Visiteur Dlgu :

Delegated Inspector :

Nom Signature :

Name Signature :

Date :

Date :

Page 48 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No 20

DOCUMENT No 20

MODELE DE PLAQUE DIDENTIFICATION


POUR APPAREIL SOUS PRESSION

PRO-FORMA NAME PLATE FOR


PRESSURE EQUIPMENT

No. de
fabrication/Item

Volume

Fabrication/Item
No.

Volume

Fluide

Poids vide

Type of Fluid

Empty Weight

Code Utilis

Surepaisseur de
Corrosion

Code Used

Corrosion
Allowance

Traitement
Thermique

Radiographie

Thermal
Treatment

Radiography

Press Max
Service

Temp Max Service

Max Service
Pressure

Max Service Temp.

Pression de
Calcul

Temperature de
Calcul

Design Pressure

Design
Temperature

Pression
dEpreuve
Hydrostatique

Date dEssai

Hydrotest Pressure

Test Date

Pour

For

Conu par

Designed by

Fabriqu par

Fabricated by

DOCUMENT No 21

DOCUMENT No 21

Page 49 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE
CERTIFICAT DESSAI
Je certifie par la prsente que :

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008
TEST CERTIFICATE
I hereby certify that :

Dsignation quipement :

Equipment Designation:

No Item :

Item No:

Service :

Service:

A t mis lpreuve dune manire satisfaisante


sous une pression hydrostatique de :

Has been successfully tested under a hydraulic


pressure of:

Bar effectif :

Active Bar:

Dure :

Duration:

(ou)

(or)

A t mis lpreuve dune manire satisfaisante :

Has been successfully tested:

Dsignation dessai :

Fabricant :

Fabricator:

Date :
Signature :

Visiteur Dlgu

Delegated Inspector:

Date :
Signature :

Signature:

Date :

Date:

Signature :
Date :

Date:

Signature :
Note : (*)
certificats dessais pour les quipements
lectriques et de levage seront prpars et contresigns

Note: Test certificates for electrical equipment shall be


prepared and countersigned.

Page 50 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No 22
MODELE DE PLAQUE DIDENTIFICATION POUR
ECHANGEUR DE CHALEUR
No dItem

NAME PLATE PRO-FORMA FOR HEAT


EXCHANGER
Item No

Calandre

Tube

Shell

Tube

Fluides
Press Max Service

Max Service Pressure

Press Calcul

Design Pressure

Temp. Max Service

Max Service
Temperature

Surpaisseur de Corrosion

Corrosion Allowance

Press Epreuve Hydrostatique

Hydrotest Pressure

Traitement
Thermique

Thermal Treatment

Radiographie

Radiography

Code de Calcul Utilis

Design Code Used

Volume

Volume

Surface

Surface

No

No

Date dessai

Test Date

Poids vide/faisceau

Empty weight/bundle

Pour

For

Conu par

Designed by

Fabriqu par

Fabricate by

Page 51 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

DOCUMENT No 23

DOCUMENT No 23

PHOTOCOPIE DU PLAQUE DIDENTIFICATION

PHOTOCOPY OF NAMEPLATES

DOCUMENT No 24

DOCUMENT No 24

PLANS FINAL, PLANS AS-BUILT

FINAL DRAWINGS / AS-BUILT DRAWINGS

Page 52 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

ATTACHMENT 3: DPEM DOCUMENTATION TRANSLATION CHECKLIST


Preliminary & Final Dossiers are separate documents and are not be to combined.

Page 53 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

The table below identifies the required documents required for the DPEM Preliminary Dossier
and necessary translations.

Doc No.

Description

1.

Letter of request for approval of the preliminary dossier.

2.

Certification of the fabricator signatures. (*) (**)

3.
4.

Certificates of conformance and internal and external


inspections. (*) (**)
Description Statement.

5.
6.
7.
8.
9.

Design Calculations.
Detailed drawings with index.
Welding procedure specifications (WPS)
Inspection and testing plans
Deleted

Language
Translation
English &
French
English &
French
English &
French
English &
French
English
English
English
English

The stamp of the nearest Algerian consulate of the fabrication place is required for all documents
marked by an asterisk (*). The stamp may be on the back of the form or on a separate page duly
referenced.
The stamp of the Fabricators local Chamber of Commerce is required for all documents marked **
(as applicable) The stamp may be on the back of the form or on a separate page duly referenced.
Required Documents for DPEM Final Dossier.

Doc No.

Description

10.
11.

Approval letter of the preliminary design dossier by DPEM.


Letter or telex issued by the contractor requesting the
presence of the DPEM inspector for tests and inspections at
the fabricator shop.
Written reply from DPEM confirming whether or not the
presence of its representative or its delegate. If nonattendance of DPEM, written instruction for Purchaser for
Supplier to assigned approved third party inspection agency.
Qualification certificates of the welding procedures (PQR).
Qualification certificates of welders or welding operations
(valid at the date of the welding operations).
Certificates of the materials used for the fabrication of the
parts and sections of the equipment (physical and chemical
characteristics) and electrodes.
Detailed reports of the non-destructive examination carried
out on equipment welds or surfaces and/or their parts, plus
reports of the destructive testing performed during the
fabrication.
Thermal treatment charts.
Internal and external inspection certificates.
Hydrostatic testing certificates.
Pro-forma Name plate for pressure equipment.
Test certificates.
Pro-forma name plate for Heat Exchangers.
Photocopy of Nameplates

12.

13.
14.
15.
16.

17.
18.
19.
20.
21.
22.
23.

Page 54 of 59

Language
Translation
French
English & French
French

English
English
English
English & / or
French
English
English & French ***
English & French ***
English & French
English & French ***
English & French
French for DPEM

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

Doc No.

Description

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

Language
Translation

nameplate, English
for manufacturers
nameplates
24
Final Drawings / As Built Drawings
English
(***) All documents marked by an asterisk are required to be signed by attending DPEM inspector or
his delegated representative (TPI), Purchaser and Suppliers Inspector.

Page 55 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

ATTACHMENT 4: FAX REQUEST FOR PRESENCE OF DPEM/ONML INSPECTOR


From:

_______________________________________________________________________
_______________________________________________________________________

To:

MINISTERE DE LENERGIE
Monsieur le Directeur
Direction de la Protection du Patrimoine
80, Avenue Ahmed Ghermoul, Alger.

VIA:

KBR

P.O. Number

________________________________________________________

Our References: Fax No.

_____________________on_________________________________

Subject:

REQUEST FOR DPEM / ONML INSPECTOR

WE REQUEST THE PRESENCE OF A DPEM/ONML INSPECTOR FOR TEST AT THE PLANT LISTED
BELOW.
DESIGNATION
ITEM NO.

EQUIPMENT

MANUFACTURER
FACILITY

TEST DATE

FACILITY
ADDRESS

FAX DE DEMANDE DE PRESENCE DINSPECTEUR DPEM/ONML


Expditeur::
: Ministre de lEnergie
Monsieur le Directeur
Direction de la Protection du Patrimoine
80, Avenue Ahmed Ghermoul, Alger.
VIA:

KBR

Commande No.
N/Rfrences:

_____________________________
FAX NO. ___________________ du __________________

Objet: CONTROLES REGLEMENTAIRES EN USINE


Nous avons lhonneur de vous demander de designer un inspecteur de votre societe pour assister aux tests
des equipements en Usine repris dans le programme ci dessous:
DESIGNATION
Article No.

Equipment

Fabrication

Date Essais

Lieu

ATTACHMENT 5: ARA / DPEM DOCUMENTATION & ACTIVITIES


Page 56 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

ACTIVITY

RESPONSIBILITY

TIME FRAME

PROVIDE DESIGN TO
SUPPLIER

PURCHASER (KBR)

WITHIN 14 CALENDAR DAYS AFTER


RECEIPT OF PO

SET UP INSPECTION
COORDINATION SCHEDULE

SUPPLIER

WITHIN 14 CALENDAR DAYS AFTER


RECEIPT OF PO

PREPARE PRELIMINARY
DOSSIER & SUBMIT TO
PURCHASER

SUPPLIER

TO ARRIVE 7 WEEKS PRIOR TO SUB


ORDERS OR FABRICATION START

PROVIDE PURCHASER
WITH STAMPED FORMS
FOR PRELIMINARY DOSSIER

SUPPLIER

4 WEEKS BEFORE START OF


FABRICATION

SUBMIT PRELIMINARY
DOSSIER TO DPEM FOR
APPROVAL

PURCHASER

IMMEDIATELY AFTER REVIEW

APPROVE / REJECT
PRELIMINARY DOSSIER, W/
NOTIFICATION BY FAX

DPEM

WITHIN 45 CALENDAR DAYS AFTER


RECEIPT

SEND PRELIMINARY NOTICE


OF INSPECTION TO
PURCHASER

SUPPLIER

45 CALENDAR DAYS PRIOR TO TEST

SEND PRELIMINARY NOTICE


OF INSPECTION TO DPEM

PURCHASER

45 CALENDAR DAYS PRIOR TO


SCHEDULED TEST

SEND FINAL NOTICE OF


INSPECTION TO
PURCHASER

SUPPLIER

21 CALENDAR DAYS PRIOR TO TEST

SEND FINAL NOTICE OF


INSPECTION TO DPEM

PURCHASER

14 CALENDAR DAYS PRIOR TO


SCHEDULED TEST

CONFIRM WITNESS OR NOT


WITNESS, TO PURCHASER

DPEM

7 DAYS PRIOR TO SCHEDULED TEST

CONFIRM WITNESS OR NOT


WITNESS, TO SUPPLIER

PURCHASER

5 DAYS PRIOR TO SCHEDULED TEST

SCHEDULE THIRD-PARTY
INSPECTION IF REQUIRED

PURCHASER

7 DAYS PRIOR TO SCHEDULED TEST

WITNESS TESTING

ALL PARTIES

SCHEDULED DATE, IF POSSIBLE

SUBMIT FINAL DOSSIER TO


PURCHASER

SUPPLIER

30 DAYS AFTER WORK


COMPLETION, PRIOR TO SHIPMENT

Page 57 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

ATTACHMENT 6: FLOWCHART PRELIMINARY DOSSIER

DPEM

PURCHASER (KBR-Houston)

PROJECT TEAM
(QA)

DCC
5

1
SUPPLIER

1.
2.
3.
4.
5.

Supplier will submit Preliminary Dossiers per paragraph 10.1.1 or 10.1.2 to the
Purchaser Document Control Center at least fifty (50) calendar days before
commencement of fabrication.
The Purchaser will transmit one French or one (1) bilingual original to DPEM for
approval at least forty five days before commencement of fabrication.
The Purchaser will retain one English or one (1) bilingual original and 2 French copies
for records, the Client will receive 1 English and 1 French or 2 bilingual copies via the
Purchaser.
DPEM will fax approval of the Preliminary Dossier to the Purchaser.
Purchaser will provide an electronic copy of the DPEM approval to the Supplier.

Page 58 of 59

KBR

SKIKDA LNG NEW TRAIN PROJECT


SKIKDA, ALGERIA
ARA REQUIREMENTS AND COORDINATION
PROCEDURE

DOCUMENT NO: PR101


REVISION 4
17 APRIL 2008

ATTACHMENT 7: EQUIPMENT LISTINGS

Item

PR 101 Article

Vessels

>4 Barg and if Barg x liters > 80

6.2.2

- other Gas Pressure


containers

>4 Barg and if Barg x liters > 80

6.2.2

CO2 & N2 Bottles

>4 Barg and if Barg x liters > 80

6.2.17

Exchangers

>4 Barg and if Barg x liters > 80

6.2.2

>10 Barg, Barg X m3/min >50 for non-hazardous or 20 for


hazardous

6.2.7

5.5 kV and above

6.2.11

Firewater distribution systems; foam, powder and inert gas


systems; fire extinguishers {5 liters>4 Barg, Barg X liters
>80 or 1 liter >4 Barg, Barg X liters > 10}; fire and gas
detection equipment [detectors and alarms]

6.2.17

Compressors
Generators

Fire Protection

Electrical

Pipe and Materials

Pumps
Valve Bodies

Requirements

All Valves
Control Valve Actuators
Tanks
Heaters and Furnaces
Lifting Device

5.5 kV and above


>3" and >10 Barg for non-hazardous gas and liquid (other
than steam or water) or >4 Barg for Explosive, flammable,
corrosive or toxic gas or liquid. Characteristic Number
(>1Barg, >80mm dia, >10 Barg max, dia in mm X Barg
>1500 for non-hazardous, 1000 for hazardous)
Firewater pumps or if pump has fabricated body and is >4
Barg, and if Barg x liters >80
PSV & non standard

6.2.9 & 6.2.11

6.2.13 & 6.2.15 & 6.2.16 &


6.2.19

6.2.5
6.2.12

4" and larger and 4 Barg and higher


All Accumulators

6.2.12

Firewater, hydrocarbon, and hazardous products (which


could be subject to pressure that the stress is equal to or
exceeds 5/8 of the elastic limit of the material being used

6.2.4

All

6.2.2

5T and larger

6.2.10

Page 59 of 59