Sei sulla pagina 1di 18

API 510 Pressure Vessel Inspector Preparatory Program

* Close Book *
API 510 CB Mockup 3 R0 26112010
1.

1.

The most extensively used NDT method for inspection of welds is:

1.
2.
3.
4.
2.

What is the maximum permissible period between two internal inspections of pressure vessels
that are in non-continuous service ( and protected properly) as per API 510.
1.
2.
3.
4.

3.

Visual Inspection
PT
Radiography
MT

10 Calendar years.
10 exposed years in service
5 Years
None of the above

What is the definition of SMAW?


1.
2.
3.
4.

An automatic welding process in shielding is provided with flux from the electrode.
A manual welding process in which shielding of the weld pool is provided by the flux
from the electrode.
An automatic process in which arc is maintained between two copper shoes.
A manual welding process in which shielding is provided with Argon gas.

4. A welding procedure is a detailed plan developed by whom to ensure sound welds.


945.
946.
947.
948.

API-510 Inspector
Welder
Quality Control Manager
Manufacturer/Fabricator

5. The maximum range of dial gauge pressure to be used in for hydro test application of a pressure
vessel.
1.
2.
3.
4.

3 times the test pressure.


2.5 times the test pressure.
2 times the test pressure.
4 times the test pressure.

6.
While placing the wire type IQI on welding for RT examination following is the acceptable
practice.
1.
2.
3.
4.
7.

Adjacent to the weld wires being parallel to weld.


Adjacent to the weld wires being perpendicular to weld.
On the weld - wires being perpendicular to weld.
On the weld - wires being parallel to weld.

When performing ultrasonic wall thickness checking, following technique will not be suitable.
1.
2.
3.
4.

Scanning with an angle probe.


A scan method.
Scan with a normal probe.
Scan with a twin probe.

API 510 CB Mockup 3 R0 26112010

8.

The maximum density permitted for Gamma ray RT on weld is 1.


2.
3.
4.

9.

2.0
3.0
4.0
3.5
When localized internal corrosion is expected in pressure vessel use the following NDT method.
1.
2.
3.
4.

10.

If a welder fails on a production weld joint when RT is done on 6 length, following should be
done to qualify the welder further.
1.
2.
3.
4.

11.

300 Deg. F
350 Deg. F.
175Deg F.
200 Deg. F

The MDMT+ correction temperature for hydro testing the pressure vessel as per API 510
is for thicknesses below 2 inch.
1.
2.
3.
4.

14.

Circumferential stress.
Longitudinal stress.
Both are same.
None of the above.

Minimum preheat temperature for weld deposition repair method as per API 510 shall be.
1.
2.
3.
4.

13.

Take further RT on 12 length on the same production weld to qualify him.


Ask him to weld two test coupon and go for bend test of the specimens to qualify the
welder.
Wait for six months to re-qualify the welder.
All of the above.

Following stress is more critical in a pressure vessel( wind load is not considered).:
1.
2.
3.
4.

12.

Scanning methods.
Profile Radiograpgy.
Acoustic emission.
Ultrasonic UT check at different points.

10 Deg. F
20 Deg F.
15 Deg. F
30 Deg. F

Which item below is not an organization permitted by the code to make repairs to pressure
vessels?
1.
2.
3.
4.

The holder of a valid U stamp certificate from ASME.


An owner or user of pressure vessels who repairs his own equipment in accordance
with this inspection code.
A contractor who was selected by the owner company.
An S stamp holder.
API 510 CB Mockup 3 R0 26112010

15.

At what places fatigue cracks usually initiate?


1.
2.
3.
4.

16.

The External inspection (of pressure vessel) report should always contain the following.
1.
2.
3.
4.

17.

339.5 - 360.5 psig


350 - 360.5 psig
339.5 - 350 psig
350 psig.

Eye test for an inspector for visual examination shall be done once in.
1.
2.
3.
4.

19.

Settlement survey.
UT thickness survey.
Insulation condition.
All of the above.

The acceptable popping range of a Relief valve whose set pressure is 350 psig.
1.
2.
3.
4.

18.

Internal surface
On the surface at notches
Openings
None of the above

12 months.
18 months.
24 months.
6 months.

A welder qualified on a plate groove weld will also be qualified for:


1.
2.
3.
4.

Some positions for fillet welding.


Pipe all position.
Plate welding all positions.
Fillet welding all positions.

20.

A plate having a carbon content of 0.35 % should 1.


Not be welded.
2.
Not be welded even though you have a WPS qualified for the P1 material with all
essential variables included.
3.
Be weldable if the Inspector allows.
4.
All of the above.

21.

Which material product form always requires a Material Test Repcrt.7


1.
2.
3.
4.

Bar
Pipe
Plate
Structural shapes

API 510 CB Mockup 3 R0 26112010

22.

Which welding process may not be used for qualifying a welder by radiography?
1.
2.
3.
4.

23.

Erosion and corrosion erosion is normally found at locations.


1.
2.
3.
4.

24

GMAW with short circuiting transfer


SAW
GTAW
SWAW

On surfaces perpendicular to the flow direction.


Parallel to the flow direction. Shiny smooth surfaces
Both A and B.
None of the above.

A pressure vessel has a nozzle with 10 size nozzle with reinforcement. Which following case
will not be an alteration.
1.
2.
3.
4.

Addition of 10 nozzle without reinforcement.


Addition of any size of nozzle below 10 size with or without
reinforcement.
12 nozzle with reinforcement.
None of the above.

25. A pressure vessel with Material A 387 Gr :22. class 1 of thickness 6.0 mm is being subjected
to weld repair. What is the best reason why PWHT is required in this case.?
1.
2.
3.
4.
26

The applicable material thickness calls for PWHT.


Material characteristics demands PWHT.
The thickness criteria.
Temper bead welding may be used to substitute for PWHT.

Prior authorization for repair work on a pressure vessel may be done by the Authorized
inspection where :
1.
2.
3.
4.

No hydro test is involved.


No RT is involved.
Both 1 and 2 are correct.
None of the above.

27. Notch toughness is checked by which of the following testing technique?


1.
2.
3.
4.

Hardness testing
Impact testing
Tensile testing
Fatigue testing

28. The best method for inspection of the defects in non metallic lining is
1.
2.
3.
4.

High voltage, low current Holiday Detector


Radiography.
Ultrasonic Testing
Eddy Current testing

API 510 CB Mockup 3 R0 26112010

29. A welding electrode packet is received from the supplier. Following is adequate for acceptance.
1.
2.
3.
4.

Partial marking on the box of the electrodes.


Delivery note / consignment note.
Electrode test certificate and AWS stenciling on each electrodes
Full description of the electrode type with brand name mentioned in delivery note

30. When two pressure parts were welded from different P No grouping and that require
PWHT, which statement from below is correct?
1
2
3
4

temperature shall be average of two temperatures


temperature shall be selected from lower of two temperatures
temperature shall be selected from higher of two temperatures
lower temperature shall be applied first followed by higher temperatures.

31. RT report need not include the following.


1.
2.
3.
4.

Source to object distance.


identification
Film brand .
Geometrical un-sharpness.

32. RT -4 according to Section VIII Div. 1 is carried out on a joint which is single V groove with
Backing strip in place. What is the efficiency of the weld joint.
1.
2.
3.
4.
33.

0.9
0.8
0.7
0.65.

The highest thickness of the cover for the given design conditions as per ASME section VIII
Div 1 will be for .
1.
2.
3.
4.

34.

Ellipsoidal dish end


Hemispherical dish head
Torispherical dish head
Flat head.

What is the disadvantage of the Stud Welding process?.


1.
2.
3.
4.

High productivity
All position process
Process is primarily suitable for Carbon and low ally steels
Process is suitable for all applications

35. If hydro test is impracticable what alternative you would recommend as an Authorized
Inspector.
1.
2.
3.
4.

Create the vacuum in the vessel so that the vessel will be tested with atmospheric
external pressure.
Go for Pneumatic Test with precautions given in Section VIII D1
Check all the welds with Careful VT.
Carry out any one of the above.

API 510 CB Mockup 3 R0 26112010

36. A piping is welded to a nozzle which is again welded to shell. ASME Section VIII D1 scope
ends at:
1.
2.
3.
4.

8 Distance from shell.


First circumferential weld.
Up to first isolation valve.
First elbow on line.

37.What is temper embrittlement?


1
2
3
4

Cracking resulting from exposure to hydrogen at elevated temperature and


pressures.
Surface initiated cracks caused by environmental cracking of 300 series
stainless and some nickel based alloys
loss of ductility and notch toughness of low alloy steels caused by prolonged
exposure to high temperatures.
Cracks developed under the combined effect of cyclic loading and corrosion.

38.Which of the following is/are not concerned with acceptance of bend test of weld as
per ASME Section IX?
1
2
3
4

Discontinuity opening in welds


Discontinuity opening in HAZ.
Bend diameter and angle of the bend
None of the above.

39.In pneumatic test, how many stages of pressurization are required?


1.
2.
3.
4.

4
5
6
1

40.Which technique out of the following from penetrant testing is the best suited for
detecting shallow pitting type of discontinuity in a pressure vessel in service during
shutdown?
1
2
3
4

solvent removable
water washable
post emulsifiable
needs more data

41.for volumetric examination and the equipment having accessibility only from one
side, which of the following NDT method is the most suitable?
1.
2.
3.
4.

radiography
Leak testing
ultrasonic testing
all of the above

42.The particles used for magnetic particle testing shall be used within:
1.

10

C to 52

C
API 510 CB Mockup 3 R0 26112010

2.
3.
4.

5 0 C to 52 0 C
15 0 C to 52 0 C
the temperature range limitations set by the manufacturer of the particles

43. Which of the following calibrated pressure gauges can be used to inspect hydro test
pressure of 50 psig ?
1.
2.
3.
4.

0-50 psig
0-100 psig
0-200 psig
B and C above

44. What is the area available inherent with the shell (A1) if the following data is given:
Data: Nozzle opening dia 300 mm. t required (tr) = 18.5 mm t specified (t) = 20
mm
Nozzle thickness (tn) = 12 mm, Nozzle required thickness (trn )= 6 mm
1.
2.
3.
4.

450 sq. mm
6000 sq. mm
5850 sq. mm
3600 sq. mm

45 What is objective to conduct impact test?


1
2
3
4

to know hardness
to estimate fracture toughness.
to estimate resistance to permanent deformation.
to estimate % Elongation

46 A welder is qualified to 3G position by using plate of 20 mm thickness on P 1 to P1


material. The process is FPW by GTAW root run and SMAW as a fill up runs. Which
of the following weld condition is unacceptable with respect to qualification ranges
qualified from above?
1
2
3
4
47

SA 106 to SA 106 piping of 4 NB in 1G rotated condition.


welder performing on 150 mm thickness weld by using another qualified
welding procedure in 3G position by double V and by back gouging.
1 NB piping of thickness 6.35 mm by use of 6G position by FPW
10 mm thicknesses SA 516 to SA 516 weld in 2F position welded only by
SMAW process.

The elevation of the bottom dish to shell joint is 5 ft. The total vessel height is 100
ft. The dish head is 2: 1 Ellipsoidal head. The vessel topmost point elevation is 100
ft. The ID is 56 inches and the flange (straight face) dimension of the head is 1.5
inches. What head (pressure) you will consider while designing the bottom dish
head?
1)
2)
3)
4)

41.694 lb
43.3 lb
20 lb
Data insufficient

48. What is the maximum period for which the Welder remains qualified after initial
qualification is over?
1.

6 months
API 510 CB Mockup 3 R0 26112010

2.
3.
4.

12 months
3 months
Unlimited

49. What is the length of simple beam impact test specimen used in ASME?
25 mm
10 mm
100 mm
5 mm

1.
2.
3.
4.

50. A repaired long seam of a pressure vessel is found to have a slag length of 9 mm in
radiographic film. The thickness of the plate was 25 mm with acceptable
reinforcement of 3 mm. The joint efficiency E = 1. What is your decision for
acceptance of this radiograph?
1.
2.
3.
4.

Not acceptable
Acceptable
Refer customer
Refer Level III

51. If the service conditions of the pressure vessel are changed what needs to be
done?
1.
2.
3.
4.

Check thickness readings again


Carry out RT again
The inspection intervals are to be established for new service
Do not do anything if the pressure vessel in not older than 10 years

Question no. 52,53 , 54 and 55 are to be sloved on the basis of the data given
below
A pressure vessel was put in service in 1992. The provided thickness was 25 mm with
the corrosion allowance considered as 3 mm. Required thickness is 21 mm
The first shutdown was taken in 2001 and the Thickness found was 23.65 mm. The
second shutdown was taken in 2010 and the thickness was found to be 22.75 mm.
52 What is the short term corrosion rate for the vessel?
1.
2.
3.
4.

0.1 mm per year


1.35 mm per year
1.5 mm per year
0.1 inch per year

53. What is the Remaining life of the vessel if the long term corrosion allowance is to be
considered for the calculations?
1.

17.5 years
API 510 CB Mockup 3 R0 26112010

2.
3.
4.

14 years
11.66 years
7 years

54. Considering the Long term corrosion allowance , what will be the next interval of
internal
inspection?
1.
2.
3.
4.

8.75 years
10 years
7 years
5.83 years

55. Considering the Long term corrosion rate what is the external inspection interval
required?
1.
2.
3.
4.

7 years
10 years
3.5 years
5 years

56 There were pits noticed having depth more than corrosion allowance and the details
are as given below:
Required thickness is 21 mm
The actual thickness measured was 21 mm
Corrosion allowance nil.
Depth of Pit A is 3 mm and diameter is inch
Depth of Pit B is 4 mm and dia is inch
Depth of pit C is 11 mm and diameter is 0.75 inch
Depth of pit D is 5 mm and diameter is 1 inch
All the pits are in the circle of 8 inch diameter.
No more than two pits are in one line
What is your decision on the acceptance of the pits and what is the reason?
1.
Pits are acceptable
2. Pits are rejected as the area is more than the allowed one in 8 inch diameter
circle
3. Pits are rejected as one of the pit is having depth more than that allowed by
the code
4.
pits are rejected because the length in one line exceeds 2 inches.
57 A vessel is having an inside diameter of 12 feet and was to be evaluated for a
locally
thinned area of corrosion. If circumferential stress is governing, what is the length
over
which you will average the thickness readings?
1.
2.
3.
4.

longitudinal length of 40 inches


longitufinal length of 50 inches
circumferential length of 50 inches
circumferential length of 50 inches

58 What is the major reason for the failure of the springs of the valves ?
1.
2.
3.

Corrosion
Errosion
creep
API 510 CB Mockup 3 R0 26112010

4.

Hidrogen blistering

59 There are specific lead letters kept along with the IQI to indicate that the IQI is placed
on
Film side or source side. What statement is correct as per ASME Section V?
1.
2.
3.
4.

Letter S for source side IQI and letter F for film side IQI
No Letter for source side IQI and letter F for film side IQI
Letter S for source side IQI and no letter for film side IQI
Such letters are not required as per ASME V

60 P numbers are assigned to the materials on the basis of


1.
2.
3.
4.

Comparable base material characteristics and the mechanical properties


Corrosion resistance
impact strength
usability characteristics

61 Which NDE examination cannot be sued for detecting subsurface flaws?


1.
2.
3.
4.

Radiographic testing
Ultrasonic Testing
Penetrant testing
Magnetic particle testing

62. A pressure vessel engineer means:


1.
2.
3.
4.

ASME employee giving these services


A person acceptable to owner/user who is knowledgeable and experienced
in engineering disciplines of pressure vessels integrity and reliability
corrosion specialist
NDE Level III

63. Which is not considered as testing in line with API 510 definition ?
1.
Hydro test
2.
Pneumatic test
3.
Charpy impact test
4.
Liquid Penetrant testing
64. P numbers are assigned to the materials for the purpose of reducing the
1.
Welding procedure Qualification requirements
2.
need for impact testing
3.
Welding Performance Qualification requirements
4.
requirements for the skill of the welders.

65.

The basic objective of the Welders Qualification is to


1.
2.
3.

to decide the procedure works well in the job


To determine the welders ability to deposit the sound weld metal
to find out corrosion resistance of weld metal
API 510 CB Mockup 3 R0 26112010

10

4.

To decide the welders salary

66. What is normally considered the essential variable for the welders performance
qualification?
1.
2.
3.
4.

Change of welding process


change of the welding machine
change of the room temperature from 20 deg C to 30 deg C
Change of electrode manufacturer keeping Electrode AWS number same

67. Which vessel is not coming under the scope of API 510?
1.
2.
3.
4.

Heat exchangers
Reboilers
Columns
Vessel for human occupancy

68. Proactive and retroactive PMI is the major action when the suspected damage is
due to
1.
2.
3.
4.

Sulfidation
Creep
Caustic corrosion
fatigue

69. When alteration of the pressure vessel is said to be completed?


1.
2.
3.
4.

When Radiography is over


When hydro test is over
When PMI is acceptable
The inspector witnesses the attachment of an additional nameplate or
additional stamping the required information

70. A CS pressure vessel was built in 2003 (ASME VIII D1 2001 Edition and add 2002 and
2003) and was repaired and given a re-hydro test in 2010. The Design pressure is
130 psi and MAWP is 150 psi , Allowable Stress at design temp 750 o F is 14800 psi
and Allowable stress at testing temp is 17500 psi, what is the hydro test pressure
to be given to the vessel? (MDMT is 20 o F and the required thickness is 1 inch)
1.
2.
3.
4.

230.57
199.83
142.9
164.9

psi
psi
psi
psi

71. What is the minimum temperature for the hydro test to be conducted in the vessel
with the data given in Question no 70?
1.
2.
3.
4.

30 def F
50 deg F
120 deg F
temperature is not important and not a code requirement

72. Where the erosion is commonly observed?


API 510 CB Mockup 3 R0 26112010

11

1.
2.
3.
4.

Downstream of orifices
impellers
agitators
all of the above

73. The external inspection of the pressure vessel should start with:
1.
2.
3.
4.

Thickness measurement
Insulation inspection
ladder, stairways, platforms and walkways connected to or bearing on
the vessel
Review of old documents

74. Which details are not required on the pressure vessel name plate?
1.
2.
3.
4.

Year built
pressure
Temperature
name of the authorized inspector

75. Authorized Inspection Agency is covering all but


1.
2.
3.
4.

Inspection organization of juridication


Inspection organization of owner user
inspection organization of the insurance company
Manufacturer

76. Fillet welded patches shall have rounded corners of minimum Radius of
1.
2.
3.
4.

25 mm
50 mm
75mm
3mm

77. Pressure vessel engineer has also to authorize the repair and alteration work when
1.
2.
3.
4.

Repair of ASME VIII D 2 Vessel and Alteration of ASME VIII D1 AND


D2 Vessels
Repair and alteration of ASME VIII D1 AND D2 Vessels
Repair and alteration of ASME VIII D2 vessels only
Engineer need not authorize if Authorized inspector is available.

78. MAWP of the vessel is 200 psi and the vessel height is 30 ft, what will be the
pressure on the bottom head?
1.
2.
3.
4.
79.

187 psi
213 psi
200 psi
depends on windload

What is the minimum temperature for welding if the ambient temperature is


between 0deg C to 20deg C ?
1.

20 deg C
API 510 CB Mockup 3 R0 26112010

12

2.
3.
4.

15 Deg C
30 deg C
0 deg C

80. Lap joint flanges shall be checked for


1.
2.
3.
4.

Corrosion between the flange and the pipe


erosion inside the pipe
cracks inside the pressure vessel
cracks in the grooves

81. The temperature range in between which the Carbon and low alloy steels the CUI is
prominent is
1.
2.
3.
4.

140 def F to 400 DEG f


10 def F to 350 Deg F
0 deg F to 100 deg F
Temperature is not important

82. Which standard covers the qualification and certification of NDT personnel?
1.
2.
3.
4.

ASNT-CP 189
ASNT- SNT-TC-1A
API 2201
MR 0123

83. Repairing a crack at a discontinuity ,where stress concentration are high should not
be attempted
1.
Without prior consultation with an engineer
2.
Without prior consultation with an inspector
3.
Without prior consultation with an owner/user
4.
Without prior consultation with an corrosion specialist
84. The appearance of Erosion, Erosion Corrosion will be
1.
2.
3.
4.

pits grooves gullies and waves in directional pattern


uniform thinning
pitting at random
craze pattern cracks

85. A pressure vessel having joint efficiency as 0.85 was found to be having corrosion
near the longitudinal weld joint. The thickness of pressure vessel was 25 mm . The
corrosion was found at a distance of 5 inches on one side and 6 inches on the other
side from the toe of the weld. How you will approach for analyzing the situation as
per API 510?
1.
2.
3.
4.

Calculate
Calculate
Calculate
Calculate

the
the
the
the

thickness required
required thickness
required thickness
required thickness

with
with
with
with

E
E
E
E

=
=
=
=

1 and proceed
0.85 and proceed
0.70 and proceed
0.65 and proceed

86. Identify correct statement


1.

Lamination run slant to the plate surface whereas cracks run at right
angle to the surface
API 510 CB Mockup 3 R0 26112010

13

2.
3.
4.
87. Hammer test
1.
2.
3.
4.

Lamination are right angle to the surface and the cracks are right
angle to the surface
laminations and cracks both are slant to the surface
lamination and cracks both are right angle to the surface
is not recommended for
piping upstream of a catalyst bed
Titanium piping
objects under pressure
1 and 3 are correct answers

88. Areas directly above and below the liquid levels in vessel with the process
containing acidic components may be subjected to
1.
2.
3.
4.
89.

erosion
hydrogen blistering
fatigue cracks
de-lamination

One method for location suspected deformation is to


1.
2.
3.
4.

Check with UT
CHECK with Fluorescent MT
check with profile RT
direct a flash light beam parallel to the surface and observe

90. To detect the metallurgical changes the common method uses is


1.
2.
3.
4.

UT
MT
eddy current testing
In-situ metallography ( replica transfer technique)

91. Cracks deeper than corrosion allowance or for which repairs are not made should be
evaluated by an engineer in accordance with
1.
2.
3.
4.

API 577
API 571
API579
API580

92. The basic reasons for pressure vessel inspection in service are:
1.
2.
3.
4.

safety, reliability and Regulatory requirements


safety , reducing shut down and economics
Safety , profitability and economy
profitability, controling oil cost,economy

93. Authorization for on stream repair must be given by


1.
2.
3.
4.

owner/user
pressure vessel engineer
Authorized inspector
juridction representative

94. Grounding connections recommended resistance is .... or less and resistance is not
to exceed ....
API 510 CB Mockup 3 R0 26112010

14

1.
2.
3.
4.

5 ohms and 25 ohms


25 ohms and 125 ohms
1 ohms and 5 ohms
20 ohms and 25 ohms

API 510 Pressure Vessel Inspector Preparatory Program


* Close Book *
API 510 CB Mockup 3 R0 26112010
Master
Q
1
2
3
4

Ref.
API 577
API 510
API 577
ASME Sect IX

1
2
2
4

ASME Sect VIII


D1
ASME Sect V

ASME Sect V

Clause
9.3.1
6.5.1
5.2
GENER
AL
Ug102

Page
26
6-2
9
GENER
AL
80

T 277.1
(d)
6.2

13

API 510 CB Mockup 3 R0 26112010

415l
15

8
9
10

3
1
1

ASME Sect V
API 510
ASME Sect IX

11

12

ASME Sect VIII


D1
API 510

13
14

1
4

15

API 510
ASME Sect VIII
D1
API 571

16
17

4
1

API 572
API576

18
19

1
1

ASME Sect V
ASME Sect IX

20
21

1
3

22

API 510
ASME Sect VIII
D1
ASME SECT IX

23

API 571

24
25

3
2

API 510
ASME Sect VIII
D1 and Sect IX

26
27
28
29

1
2
1
3

API
API
API
API

30

ASME Sect VIII


D1

510
577
572
577

282.1
5.6.2.3
321.3(b
)
Genera
l UW3
8.1.6.4.
2.2.2
5.8.6.2
GENER
AL
4.2.16.
3
9.3
6..2.15.
2
T923
QW
461.9
8.1.4
UG 93
(a) 1
QW
304
4.2.1.4.
5
3.2
UCS
56
QW422
8.1.1
10.4.4
9.4.8
7.4
AND
GENER
AL
UW408d

14
5-7
55
Gen
8-5
5-10
general
4-53
24
43
154
151
T ABLE
8-1
72
53
4-45
3-1
164,
AND 90
8-1
61
44
19

139

API 510 Pressure Vessel Inspector Preparatory Program


* Close Book *
API 510 CB Mockup 3 R0 26112010
Master
31

ASME V

32

ASME Sect VIII


D1
ASME Sect VIII
D1
API 577
API 510

33
34
35

4
3
2

T291/T
292
UW12

15

UG32 &
UG35
5.7.2
5.8.5

29,35

API 510 CB Mockup 3 R0 26112010

111

14
5.10
16

36

ASME Sect VIII


D1
API 510
ASME Sect IX

37
38

3
4

39

40

ASME Sect VIII


D1
ASME Section V

41

ASME Section V

42

ASME Section V

43

44

45

46

ASME
D1
ASME
D1
ASME
D1
ASME

47

48

49

50

51
52
53
54
55
56

3
1
2
3
4
3

Sect VIII
Sect VIII
Sect VIII
Sect IX

ASME Sect VIII


D1
ASME Sect IX
ASME Sect VIII
D1
ASME Sect VIII
D1
API 510
API 510
API 510
API 510
API 510
API 510

u-1(e)
(1)a
3.44
QW
163
UG 100

T651
and
general
SE797
&
general
T731
(c)
UG102

115

Fig. UG
37.1
UG 84

42

QW
461.9
table
UG 98

151

QW
322.1
(a)
Fig. UG
84
UW 51

55

7.1.1
7.2.1
6.5.1
6.4.1
7.4.3
7.4.3

7-1
7-1
6-2
6-1
7-3
7-3

3-3
6
75

414
122
80

65

73

64
141

API 510 Pressure Vessel Inspector Preparatory Program


* Close Book *
API 510 CB Mockup 3 R0 26112010
Master
57
58
59
60
61
62
63
64

1
1
2
1
3
2
4
1
API 510 CB

API 510
7.4.2.1
API 576
5.3.2
ASME V
T277.1b
ASME Sect IX
QW 420
ASME V
T620
API 510
3.48
API 510
3.61
ASME Sect IX
QW- 420
Mockup 3 R0 26112010

7-2
27
12
73
114
3-3
3-4
73
17

65

ASME Sect IX

66

ASME Sect IX

67
68
69
70
71
72

4
1
4
1
1
4

API
API
API
API
API
API

73
74

3
4

75
76

4
1

API 572
ASME Sect VIII
D1
API 510
API 510

77
78

1
2

79

80
81
82
83
84

1
2
1
1
1

API 510
ASME Sect VIII
D1
ASME Sect VIII
D1
API 572
API 510
API 510
API 510
API 571

85
86
87
88
89
90
91
92

1
1
4
2
4
4
3
1

API
API
API
API
API
API
API
API

93
94

1
1

API 510
API 510

510
571
510
510
510
571

510
572
572
572
572
572
572
572

QW
100.2
QW 350
GEN
B 10
4.4.2.7
8.2.2
5.8.2.1
5.8.6.2
4.2.14.4.
a
9.3.2
Fig UG
118
3.6
8.1.5.1.2
.3
8.1.1
UG98

UW 30

135

9.4.6
5.5.6.1
SECT 2
8.1.5.2.1
4.2.14.5
a
7.4.5
9.4.4.2
9.7.1.e
9.4.4.4
9.4.4.5
9.6
10.5
5.2,5.3,5
.4
GEN
9.3.10

42
5-6
2-1
8-3
4.45

API 510 CB Mockup 3 R0 26112010

56
A-1
4-110
8-8
5-9
5-10
4.44
24
85
3-1
8-2
8-1
73

7-3
37
47
38
40
46
52
15
GEN
29

18

Potrebbero piacerti anche