Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Eight years MoD various roles: Project Manager, Systems Engineer, Aircraft Trials and Certification
Three years PPM consulting: Defence and Aerospace roles
Key skills:
Project Management
Risk management & improvement
Quantitative Risk Analysis & decision support
Contents
1. Introduction to Schedule Risk Analysis
2. Case study project background
3. Analysis approach
Schedule logic
Task duration
uncertainty
Task A
Risk impact
Activity uncertainty
Task B
1000s of
iterations
30%
Task C
Planned
finish date
Completion
date
P10
P50
P90
Confidence
100%
90%
50%
10%
Completion
Date
00011 - Activity 3
00013 - Activity
00004 - Activity 14
00008 - Activity 12
00005 - Activity 47
00007 - Activity 2
00012 - Risk 2 30%
00009 - Risk 1 60%
00002 - Activity 45
00003 - Activity 16
55%
37%
22%
18%
16%
13%
10%
6%
4%
3%
Tornado
chart: identify
key activities
and risks
Stage 1
Design
Model
Production Model
Trials Model
Infrastructure
System A
System B
Unit 1
Sub-Unit i
10
Stage 2
Stage 3
11
3-point (triangular)
estimate
ML
min
max
Task A
Baseline duration
2-point (uniform)
estimate
min
Task A
Baseline duration
12
max
New risks
identified
during SRA
development
Schedule risks
Secondary benefits:
Quantified impact,
in-scope risks
Tailored risks
mapped against
SRA model
13
14
Distribution of
delay vs.
milestone /
project phase
80%
60%
40%
post-mit @ 50%
pre-mit @ 50%
20%
0%
-20%
Preliminary
Design
Definitive Design
Component
manufature
Production and
assembly
Factory testing
System trials
16
QUESTIONS?