Scheduling/Leveling Report - 09-Apr-15 - PM.

exe
===============================================
Default Project..................................................YWS
Projects:
YWS............................................................Y
ELLAMPALLY WATER SUPPLY
Scheduling/Leveling Settings:
----------------------------General
------Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............No
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Retaine
d Logic
Calculate start-to-start lag from ...............................Early S
tart
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish
Float
Calendar for scheduling Relationship Lag ........................Predece
ssor Activity Calendar
Advanced
-------Calculate multiple float paths...................................No
Statistics:
----------# Projects.......................................................1
# Activities.....................................................273
# Not Started....................................................273
# In Progress....................................................0
# Completed......................................................0
# Relationships..................................................442
# Activities with Constraint.....................................2
Project:
YWS
Activity:
A2030 CONCRETE MIX DES
IGN
Project:
YWS
Activity:
A2090 HAND RAILS
Errors:
------Warnings:
--------Activities without predecessors..................................2
Project:
YWS
Activity:
A1030 PROJECT START DA
TE
Project:
YWS
Activity:
A4000 RECIEVING DRAWIN
GS FROM CONSULTANT
Activities without successors....................................4
Project:
YWS
Activity:
A1300 HANDING OVER PRO

JECT
Project:

YWS

Activity:

A1340

PROJECT FINISH D

Project:

YWS

Activity:

A1940

HANDING OVER PRO

Project:

YWS

Activity:

A4060

PROJECT FINISH D

ATE
JECT
ATE
Out-of-sequence activities.......................................0
Activities with Actual Dates > Data Date.........................0
Milestone Activities with invalid relationships..................0
Scheduling/Leveling Results:
---------------------------# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................273
# Relationships with other projects..............................0
Data Date........................................................15-Oct12
Earliest Early Start Date........................................15-Oct12
Latest Early Finish Date.........................................08-Feb15
Exceptions:
----------Critical Activities..............................................42
Project:
YWS
Activity:
A1000 MOBILIZATION OF
CONTRACTOR
Project:
YWS
Activity:
A1020 RECIEVING DRAWIN
GS FROM CONSULTANT
Project:
YWS
Activity:
A1070 RCC FOR RAFT FO
OTING
Project:
YWS
Activity:
A1090 RCC GRADE SLAB
Project:
YWS
Activity:
A1120 DECKING & ROOF S
LAB & BEAMS
Project:
YWS
Activity:
A1130 CONCERETING & CU
RING FOR ROOF SLAB & BEAMS
Project:
YWS
Activity:
A1140 COMPLETION OF SL
AB WORK
Project:
YWS
Activity:
A1170 BACKFILLNG & COM
PACTION
Project:
YWS
Activity:
A1240 STEEL REINFORCEM
ENT
Project:
YWS
Activity:
A1270 TESTING & COMMIS
SIONING
Project:
YWS
Activity:
A1280 AS BUILT DRAWING
Project:
YWS
Activity:
A1300 HANDING OVER PRO
JECT
Project:
YWS
Activity:
A1310 SITE CLEARENCE
Project:
YWS
Activity:
A1320 SETTING OUT WORK
S
Project:
YWS
Activity:
A1450 SLAB WATER PROFF
ING
Project:
YWS
Activity:
A1610 APPLYING CORROSE
AL EPOXY RESIN BASED COAT
Project:
YWS
Activity:
A1870 EARTHWORK EXCAVA
TION & COMPACTON
Project:
YWS
Activity:
A1880 COLUMNS

Project:

YWS

Activity:

A1910

TESTING & COMMIS

Project:
Project:
Project:

YWS
YWS
YWS

Activity:
Activity:
Activity:

A1920
A1930
A1940

S BUILT DRAWING
SNAG LIST
HANDING OVER PRO

Project:

YWS

Activity:

A1950

CONCRETE MIX DES

Project:

YWS

Activity:

A2030

CONCRETE MIX DES

Project:

YWS

Activity:

A2050

ROOF SLAB & BEAM

Project:
Project:

YWS
YWS

Activity:
Activity:

A2090
A2280

HAND RAILS
RETAINING WALL U

Project:

YWS

Activity:

A2290

PCC FOR FOUNDATI

Project:
Project:

YWS
YWS

Activity:
Activity:

A2300
A2310

RCC PLINTH BEAM


RCC FOOTING & PE

Project:
Project:

YWS
YWS

Activity:
Activity:

A2360
A2380

SLAB ON GRADE
EXTERNIAL PLASTE

Project:
Project:
FOR DOORS & WINDOWS
Project:
F ROOF SLAB
Project:
Project:
LEVELS
Project:
Project:
BOVE GL
Project:
Project:
Project:
MS LADDER & PAINTING

YWS
YWS

Activity:
Activity:

A2400
A2410

PAINTING
FABRICATION WORK

YWS

Activity:

A2440

WATER PROFFING O

YWS
YWS

Activity:
Activity:

A2450
A2460

PARAPET WALL
ORIGINAL GROUND

YWS
YWS

Activity:
Activity:

A2470
A2480

PEG MARKING
RETAINING WALL A

YWS
YWS
YWS

Activity:
Activity:
Activity:

A2490
A2500
A2520

LAUNDER
STAIR CASE
INSTALLATION OF

SINING

JECT
IGN
IGN
S
PTO GL
ON
DESTRALS
RING

Activities with unsatisfied constraints..........................1


Project:
YWS
Activity:
A2090 HAND RAILS
Activities with unsatisfied relationships........................2
Project:
YWS
Activity:
A2030 CONCRETE MIX DES
IGN
Project:

YWS

Activity:

A2090

HAND RAILS

Activities with external dates...................................0